This document is a Procurement Justification Form from the State of Illinois Department of Innovation and Technology (DoIT) requesting the purchase of various tools to support the Wintel Infrastructure hardware team. The requested items include an aluminum folding hand truck, pliers, adjustable wrenches, screwdrivers, flashlights, a rubber mallet, a gyroscopic screwdriver, and a security bit set. The procurement is necessary as the current tools used by the infrastructure team are over 10 years old, broken, or at the end of their useful life, which impacts the team's ability to install and maintain servers across the state. The total quantity of items requested is 1 of each tool. This appears to be a new initiative rather than a renewal or replacement of an existing contract.

The economic justification indicates that using different procurement methods could result in higher costs, and there are no additional implementation, installation, or support costs associated with this procurement. The request is not subject to any special conditions such as brand name restrictions, emergencies, or the State Use program. Funding for this procurement will come from the DoIT's budget, though the specific amount is not provided.

View the file

Other files

File Type Posted
PRV - Infrastucture Tools.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CPO - General Services

Procurement Justification Form Procurement Justification Programmatic Objective

Describe what it is that you intend to procure (software, hardware, services, maintenance, etc.) including quantity if relevant. Describe business need for the procurement, and how the procurement will meet objectives of your agency and the State. Please make sure to spell out acronyms. Explain the potential consequences if this procurement is not approved. If other than one-time purchase, explain solicitation method, pricing structure (hourly, per item, not-to-exceed, etc.).

Economic Justification

Describe the economic benefit for the procurement approach selected and anticipated return on investment.

Describe consequences if different method is used to procure good or service. Indicate any additional procurement expenditures that will be processed separately in support of, or in conjunction with, this procurement including such items as implementation, installation, increased maintenance or support, etc. If method other than solicitation, indicate price breakout including hourly rate if applicable.

History/Background

State how business need is currently being met, if applicable. Indicate if this is a new initiative, replacement or expansion of existing system or contract, or a continued need which is procured yearly or quarterly, etc. If renewal or amendment, indicate Purchase Order # of previous procurement and contract term of existing contract. If replacing previous contract, explain if contract expired with no renewal options remaining, or choosing not to execute remaining renewal, and why. If bid in previous years, indicate the procurement approach used, any changes to previous solicitation requirements, and the results of previous bid (were there multiple bids?) Indicate if procurement is subject to Small Business Set-Aside, Business Enterprise Program or Veteran's Business Program and, if yes, whether a waiver will be sought.

Impact if Project is Not Completed

What Special Condition, if Any, is Applicable to Your Procurement?

What Special Condition, if Any, is Applicable to Your Procurement?

Provide the explicit rationale for brand name, (such as system compatibility, TCO maintenance costs, existing expertise). Detail emergency criteria permitted by the Illinois Procurement Code. Give detailed rationale for emergency procurement. Provide explicit rationale for no-bid award for the State Use program and detail cost differential for using State Use vendors for the life of the program. Be as specific as possible.

V.18.1

Procurement Justification

Text1: Quantity 1 - Aluminum folding hand truck Quantity 1 - Craftsman Evolv 5 piece Plier set Quantity 1 - Craftsman Evolv 3 piece adjustable wrench set Quantity 1 - Craftsman Slotted screwdriver set Quantity 1 - High Lumen LED flashlight set (2 pack) Quantity 1 - Rubber Mallet Quantity 1 - DEWALT DCF680N2 8V Max Gyroscopic screwdriver 2 battery kit Quantity 1 - 13-piece Tox Bit Socket set t8-T60 Quantity 1 - Bastex Tamper Proof Security screw hex bit head set

Text2: If these tools are not procured, the Infrastructure team will continue to use whatever means are found to install and support the servers across the state.
Text3: Currently the DoIT Infrastructure team is using tools that were procured over 10 years ago. Many of these tools are either broken or at the end of their useful life.
Text4: Many of the tools that the Infrastructure team use are either broken or at the end of life. These tools will help support the installation and maintenance of servers across the state.