PINNACLE HILL RT Power Construction SOW Ver A 08-23-2022.pdf

PDF 296 KB Posted

Attached to
Electrical Infrastructure Installation Federal contract opportunity
Solicitation number
00595
Issued by
Department of Transportation Federal Aviation Administration Franchise Acquisition Services

View the file

Other files for this federal contract opportunity

Other files attached to Electrical Infrastructure Installation, newest first.
File Type Posted
Appendix A_Construction Drawings_SWB-RIB-002B_30PCT_PINNACLE B_ELECTRICAL_REVISION_A.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work FAALC Upton Road SCP Electrical Service

FAALC/CBP

For Official Use Only (FOUO)

Federal Aviation Administration U.S. Customs and Border Protection

Pinnacle Hill Relocatable Tower

Electrical Infrastructure Installation

Published: November 3, 2022

Support Agency:

Federal Aviation Administration (FAA) FAA Logistics Center 6500 S. MacArthur Blvd Oklahoma City, OK 73069

Distribution Statement: Distribution authorized to the U.S. Customs and Border Protection Agency and Federal Aviation Administration Logistics Center and their Contractors. This document contains non-technical data for administrative use. Requests for this document must be referred to FAALC

FAALC/CBP

FAALC/CBP P a g e | iii

Table of Contents

1.0 Background

2.0 Scope

3.0 Requirements

4.0 Schedule

5.0 Deliverables

FAALC/CBP P a g e | iv For Official Use Only (FOUO)

Change History

Derived from/Original File Name Effective Date Original Repository Author/Editor

Rev # Effective

Date Sections Affected

Description of Change Author/Editor

Draft 08/23/2022 All Initial Draft Greg Barker

Approvals on file: Reference SCM/Harvest for Approval Date:

Management Approval

Reference SCM/Harvest for Process Owner Date:

Process Owner

FAALC Derringer Tower Maintenance

FAALC/CBP P a g e | 1 For Official Use Only (FOUO)

Background The Customs and Border Protection (CBP) for the Swanton Sector is installing an electrical service for a Relocatable Tower (RT) located at 45.015441, -72.700404 (Richmond, VT). The RT is expected to be deployed in November 2022. The electrical service needs to be installed prior to the start of deployment of the RT.

2.0 Scope

The contractor must provide all labor, tools, material, transportation, inspections, and any other incidentals required to install the electrical infrastructure needed for the RT.

The intent of the SOW is to define the electrical installation, installation of the electrical H-Frame and removal of all trees and shrubs as described in this SOW. This SOW does not encompass the fixed tower construction. This is a new electrical service for the RT.

3.0 Requirements

Contractor must install infrastructure required to support the deployment of a RT. The contractor must follow all rules and regulations required by Vermont Electrical Corporation (VEC). If instructions from this SOW contradicts the rules and regulations of VEC, the contractor must follow the rules and regulations of VEC. These requirements will refer back to the construction drawings, “Appendix A_Construction Drawings_SWB-RIB-002B_30PCT_PINNACLE B_ELECTRICAL_REVISION_A.pdf”. Note: In this drawing set FAA/Others refers to the Vendor in this solicitation.

3.1 Removal of Trees and Shrubs.

• Remove all trees and shrubs as defined in sheet SWB-RIB-002B-C003. Follow guidelines on sheet SWB-RIB-001-G003, notes “Clearing and Grubbing”.

• All debris from clearing must be removed from the facility and disposed of in accordance with local regulations.

3.2 Install new secondary service from the VEC utility transformer located on the North side of the Pinnacle Hill Port of Entry, see sheet SWB-RIB-002B-G004.

• Install a Stub Pole for the electrical meter to the north of the VEC utility transformer.

• Install the secondary service underground from the meter to the location of the H-Frame. Utilize the Primary Conduit guidelines for the underground infrastructure.

• Terminate the secondary service into the H-frame in accordance with sheet

SWB-NVB-001-E603.

3.3 Install the H-Frame and all equipment as described in sheet SWB-NVB-001-E601 and

SWB-NVB-001-E603.

• References to equipment external to the H-frame should not be constructed.

• The meter will not be mounted on the H-frame, it will be mounted north of the Port of Entry on a stub pole.

• Underground conduit from the breaker panel will not be installed, sheet SWB-

NVB-001-E601.

• The UPS will not be installed during this installation, sheet SWB-NVB-001- E601.

FAALC Derringer Tower Maintenance

FAALC/CBP P a g e | 2

3.4 Install underground conduit for the Fiber connection.

• Install 1” conduit between the nearest vault located to the west of the H-frame to within five feet of the H-Frame. Camera pole to the west of the RT has an underground conduit with vault periodically placed. This conduit runs between the camera pole and the POE. The conduit run will be between 100’ and 125’ to the vault.

• Stub the conduit near the H-Frame two feet above ground level. Seal the stub.

4.0 Schedule

The contractor must perform the work describe in this SOW as soon as practical, based on ground conditions, after the contract has been awarded.

5.0 Deliverables

• H-Frame

• Conduit runs

• Cabling inside and to the H-Frame from the Utility

1.0 Background
2.0 Scope
3.0 Requirements
3.1 Removal of Trees and Shrubs.
3.2 Install new secondary service from the VEC utility transformer located on the North side of the Pinnacle Hill Port of Entry, see sheet SWB-RIB-002B-G004.
3.3 Install the H-Frame and all equipment as described in sheet SWB-NVB-001-E601 and SWB-NVB-001-E603.
3.4 Install underground conduit for the Fiber connection.
4.0 Schedule
5.0 Deliverables