PIKE_SOW.docx

DOCX document 29 KB Posted

Attached to
52000QR260028280-CGC PIKE Fire System Inspection
Solicitation number
52000QR260028280
Issued by

About this file

This is a Statement of Work (SOW) for fire system inspection services on the USCG Cutter (CGC) PIKE. The contractor must inspect, test, and recertify the installed Engine Room CO2 and Galley Aqueous Film-Forming Foam (APC) Systems in accordance with Coast Guard specification MPC N33005.D, and clean the Galley Hood vent system by removing all grease, oil, and debris buildup from the ducting. Contractor personnel must be trained and qualified to perform these services. The work location is onboard CGC PIKE at USCG Base Ketchikan, 1300 Stedman Street, Ketchikan, Alaska 99901, with the primary point of contact being EMC Jeremy Gager (Work: 415-933-0214; Email: Jeremy.W.Gager@uscg.mil) and the Contracting Officer Technical Representative being Tanner Miller (Cell: 307-371-8435; Office: 571-610-4597; Email: Tanner.M.Miller@uscg.mil).

The period of performance must not exceed five (5) consecutive days, with all work completed no later than 30 September 2026, within the availability window of 21-30 September 2026. Upon contract award, the contractor must contact the CGC PIKE Point of Contact within two business days to coordinate final performance dates. All contractor personnel requiring base access must possess a valid state-issued REAL ID-compliant driver's license or acceptable Department of Homeland Security alternative identification, and the contractor is solely responsible for ensuring personnel are properly credentialed; failure to comply with access requirements may result in performance delays that will not constitute an excusable delay.

View the file

Other files

File Type Posted
PIKE_SOW_Revised.docx DOCX document
Smart Matrix Acquisition.GOV.pdf PDF
N33005.D_Maintenance Procedure Card.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

CGC PIKE Fire System Inspection 52000PR260028280

1. BACKGROUND

CGC PIKE requires inspection and hydrostatic testing of the installed Engine Room CO2 & Galley APC Systems

2. REFERENCE

MPC N33005.D

3. REQUIREMENTS

Entity completing the work will have trained personnel. Contractor must inspect, test and recertify the installed Engine Room CO2 and Galley APC systems IAW CG MPC N33005.D. The contractor must also clean the Galley Hood vent system, removing all grease/oil/debris buildup from ducting.

4. PERIOD OF PERFORMANCE

Upon contract award, the Contractor shall contact the CGC PIKE Point of Contact (POC) within two (2) business days to coordinate and confirm final performance dates. Once a start date is set and the Contractor is prepared to conduct services, the actual period of performance shall not exceed a total of five (5) days. All work shall fall within the window of availability between 21 September 2026 and 30 September 2026, with all services completed no later than (NLT) 30 September 2026.

5. PLACE OF PERFORMANCE

The primary place of performance shall be onboard CGC PIKE located at below address:

USCG Base Ketchikan 1300 Stedman St Ketchikan, AK 99901

Cutter Point of Contact:

EMC Jeremy Gager, Engineer Petty Officer Work: (415) 933-0214 Email: Jeremy.W.Gager@uscg.mil

Contracting Officer Technical Representative (COR):

Tanner Miller Cell: (307) 371-8435 Office: (571) 610-4597 Email: Tanner.M.Miller@uscg.mil

6. Security Requirements

All contractor personnel requiring access to the place of performance in order to perform work under this contract must possess a valid-state issued REAL ID-compliant driver’s license or identification card, or an acceptable alternative form of identification as defined by the Department of Homeland Security (DHS) [https://www.dhs.gov/real-id]. It is the contractor’s responsibility to ensure that all personnel are properly credentialed to gain base access. Failure to comply with access requirements may result in delays to performance and will not constitute an excusable delay.