This performance work statement outlines the requirements for water treatment services for nine cooling tower systems at the Beltsville Agricultural Research Center. The contractor will perform monthly service visits during the cooling season from April through November to handle and apply necessary treatment chemicals, adjust chemical feeding equipment, obtain and analyze water samples, and provide a detailed service report with test results to the government point of contact. Additionally, the contractor will test twice yearly in June and August for Legionella bacteria. The period of performance for the base year is estimated to be from April 1, 2024 through March 31, 2025, with four optional one-year periods of performance.

The related federal contract opportunity is solicitation number 12305B24Q0011 for water treatment services for cooling towers from the Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Northeast Area.

View the file

Other files

File Type Posted
Performance Work Statement- UPDATE 12122023.docx DOCX document
Questions and Answers for SAM- 3.docx DOCX document
Performance Work Statement- UPDATE 12062023.docx DOCX document
Questions and Answers for SAM- 2.docx DOCX document
Questions and Answers for SAM- 1.docx DOCX document
Contract Terms and Conditions.docx DOCX document
Wage Determination Prince George MD WD 2015-4281.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Performance Work Statement – Log Lodge Grounds Maintenance

Performance Work Statement Prepared By U.S. Department of Agriculture (USDA), Agricultural Research Service (ARS), Beltsville Agricultural Research Center (BARC), Operations and Maintenance Unit 10300 Baltimore Avenue, Building 436A, BARC-East Beltsville, MD 20705-2350 For Service Agreement for all BARC Cooling Systems Beltsville Agricultural Research Center

Date November 3, 2023

SECTION 1 GENERAL INFORMATION

1.0 Background & Description of Requirement

Beltsville Agricultural Research Center (BARC) has a total of nine cooling tower systems. They are located at buildings 001, 004, 007, 010A, 010B, 306, 307, 307B and 307D. This performance work statement is for the service and upkeep of these nine cooling towers.

1.2 Performance Work Statement

The contractor will make monthly service visits during the cooling season (April through November) for the cooling towers and quarterly service visits to closed loop systems. The contractor shall handle and apply all necessary treatment chemicals including two alternating micro biocides, adjust chemical feeding equipment to ensure proper treatment levels, obtain and analyze water samples from each system and provide government technical point of contact a detailed service report with test results and service protocols.

The contractor shall test twice yearly in June and August for the presence and concentration of Legionella bacteria and the report shall be sent to the government point of contact.

Beltsville Buildings and Systems

Building
Systems
Months Of Operation
Building 001
640 Ton Cooling Tower Chilled Water

Hot Water Heating April through November April through November October through April

Building 004
826 Ton Cooling Tower Chilled Water

Hot Water Heating April through November April through November October through April

Building 007
400 Ton Cooling Tower Chilled Water

Hot Water Heating April through November April through November October through April

Building 010A
600 Ton Cooling Tower Chilled Water

Hot Water Heating April through November January through December January through December

Building 010B
540 Ton Cooling Tower Chilled Water

Hot Water Heating April through November January through December January through December

Building 306
Chilled Water

Hot Water Heating January through December January through December

Building 307
Chilled Water

Hot Water Heating (Glycol) January through December January through December

Building 307B
300 Ton Cooling Tower Chilled Water

Hot Water Heating April through November April through November October through April

Building 307C
300 Ton Cooling Tower Chilled Water

Hot Water Heating April through November April through November October through April

1.3 Period of Performance

Final dates will be determined at time of award.

Base Year estimated to start April 1, 2024 through March 31, 2025.

If exercised, the period of performance for the following option years are as follows:

Option Year IApril 1, 2025 through March 31, 2026
Option Year IIApril 1, 2026 through March 31, 2027
Option Year IIIApril 1, 2027 through March 31, 2028
Option Year IVApril 1, 2028 through March 31, 2029