Performance Time Rpr Afld Parking Ramp PH3.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- Repair Airfield Parking Ramp PH III
- Solicitation number
- FA441825R0003
About this file
This is a Performance Time tabulation spreadsheet for project DKFX 1093395 "Repair Aircraft Parking Ramp - Phase 3" at Joint Base Charleston. The document outlines the project timeline and weather impact calculations.
The contract schedule shows a Notice to Proceed date of August 4, 2025, with 60 days allocated for mobilization and submittal preparation. Construction is planned to start October 3, 2025, with 39 construction days and 11 inclement weather days built into the schedule. The construction completion date is set for November 21, 2025, followed by a 30-day closeout period, for a total contract duration of 140 days ending December 21, 2025. The spreadsheet includes detailed monthly weather impact calculations, focusing particularly on August-September 2025 when the majority of construction work is scheduled, with 87% and 40% of those months respectively allocated for construction activities.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Time Performance Time Tabulation Form
| DKFX 1093395, Repair Aircraft Parking Ramp - Phase 3 |
| 14-Jan-25 |
| Instructions: | ||
| 1 | Insert Project Number and Title (data linked to Liquidated Damages tab). | |
| 2 | Insert current date (data linked to Liquidated Damages tab). | |
| 3 | Insert estimated Construction Start Date. | |
| 4 | Insert number of Mobilization & Submittal Preparation days you are allowing. | |
| 5 | Insert number of days for any Special Order Materials Lead Time you are allowing. | |
| 6 | Insert the Number of Construction Days/Month for each month without consideration of inclement weather days. | |
| 7 | Insert the % of Month Impacted by Inclement Weather | |
| 8 | Total number of Contract Days is displayed below. | |
| 9 | Construction Complete Date is displayed below. | |
| 10 | Performance Time tab data is linked to the Liquidated Damages tab. Coordinate current LD rates with Contracting. |
| Notice to Proceed | 4-Aug-25 | |
| Mobilization & Submittal Preparation: | 60 | |
| Special Order Materials Lead Time: | NA | |
| Construction Start Date: | 3-Oct-25 | |
| Number of Construction Days: | 39 | |
| Number of Inclement Weather Days: | 11 | |
| Construction Complete | 21-Nov-25 | |
| Number of Closeout Days: | 30 | |
| Total Contract Days: | 140 | |
| Contract Complete: | 21-Dec-25 |
| Month | Days In Month | Average Inclement Weather Days/Month | Number of Construction Days/Month | % of Days of Month Construction | Possible Inclement Weather Days Per Month | % of Month Impacted by Inclement Weather | Allowed Inclement Weather Days Per Month |
| March 2008 | 31 | 11 | 0 | 0% | 0 | 0% | 0 |
| April 2008 | 30 | 7 | 0 | 0% | 0 | 0% | 0 |
| May 2008 | 31 | 9 | 0 | 0% | 0 | 0% | 0 |
| June 2008 | 30 | 11 | 0 | 0% | 0 | 0% | 0 |
| July 2008 | 31 | 14 | 0 | 0% | 0 | 0% | 0 |
| August 2008 | 31 | 11 | 0 | 0% | 0 | 0% | 0 |
| September 2008 | 30 | 9 | 0 | 0% | 0 | 0% | 0 |
| October 2008 | 31 | 6 | 0 | 0% | 0 | 0% | 0 |
| November 2008 | 30 | 7 | 0 | 0% | 0 | 0% | 0 |
| December 2008 | 31 | 8 | 0 | 0% | 0 | 0% | 0 |
| January 2009 | 31 | 10 | 0 | 0% | 0 | 0% | 0 |
| February 2009 | 28 | 9 | 0 | 0% | 0 | 0% | 0 |
| March 2009 | 31 | 11 | 0 | 0% | 0 | 0% | 0 |
| April 2009 | 30 | 7 | 0 | 0% | 0 | 0% | 0 |
| May 2009 | 31 | 9 | 0 | 0% | 0 | 0% | 0 |
| June 2009 | 30 | 11 | 0 | 0% | 0 | 0% | 0 |
| July 2009 | 31 | 14 | 0 | 0% | 0 | 0% | 0 |
| August 2009 | 31 | 11 | 0 | 0% | 0 | 0% | 0 |
| Jan 2025 | 31 | 6 | 0 | 0% | 0 | 100% | 0 |
| Feb 2025 | 28 | 5 | 0 | 0% | 0 | 100% | 0 |
| Mar 2025 | 31 | 5 | 0 | 0% | 0 | 100% | 0 |
| Apr 2025 | 30 | 5 | 0 | 0% | 0 | 100% | 0 |
| May 2025 | 31 | 5 | 0 | 0% | 0 | 100% | 0 |
| Jun 2025 | 30 | 8 | 0 | 0% | 0 | 100% | 0 |
| Jul 2025 | 31 | 9 | 0 | 0% | 0 | 100% | 0 |
| Aug 2025 | 31 | 9 | 27 | 87% | 8 | 100% | 8 |
| Sep 2025 | 30 | 7 | 12 | 40% | 3 | 100% | 3 |
| Oct 2025 | 31 | 5 | 0 | 0% | 0 | 100% | 0 |
| Nov 2025 | 30 | 4 | 0 | 0% | 0 | 100% | 0 |
| Dec 2025 | 31 | 6 | 0 | 0% | 0 | 100% | 0 |
| Jan 2026 | 31 | 6 | 0 | 0% | 0 | 100% | 0 |
| Feb 2026 | 28 | 5 | 0 | 0% | 0 | 100% | 0 |
| Mar 2026 | 31 | 5 | 0 | 0% | 0 | 100% | 0 |
| Apr 2026 | 30 | 5 | 0 | 0% | 0 | 100% | 0 |
| May 2026 | 31 | 5 | 0 | 0% | 0 | 100% | 0 |
| February 2011 | 28 | 9 | 0 | 0% | 0 | 0% | 0 |
| March 2011 | 31 | 11 | 0 | 0% | 0 | 0% | 0 |
| April 2011 | 30 | 7 | 0 | 0% | 0 | 0% | 0 |
| May 2011 | 31 | 9 | 0 | 0% | 0 | 0% | 0 |
| June 2011 | 30 | 11 | 0 | 0% | 0 | 0% | 0 |
| July 2011 | 31 | 14 | 0 | 0% | 0 | 0% | 0 |
| August 2011 | 31 | 11 | 0 | 0% | 0 | 0% | 0 |
| September 2011 | 30 | 9 | 0 | 0% | 0 | 0% | 0 |
| October 2011 | 31 | 6 | 0 | 0% | 0 | 0% | 0 |
| November 2011 | 30 | 7 | 0 | 0% | 0 | 0% | 0 |
| December 2011 | 31 | 8 | 0 | 0% | 0 | 0% | 0 |
| Total: | 39 | Total: | 11 | ||||
| TOTAL Construction + Weather = | 50 | ||||||
| Note: We have to clearly convey to the contractor that his construction time does not include the 60 for | |||||||
| mobilization and submittals. Once work begins, the balance of the 60 days go away. Also need to | |||||||
| Convey that LDs will be charged starting at the end of Final Inspection/Constr. Complete and not at | |||||||
| the end of closeout period. |