Pendleton - 2025 Res Coatings Project_Addendum 2_2025-11-05.pdf
PDF 968 KB Posted
- Attached to
- 2025 Reservoir Coatings Project
- Solicitation number
- S-KN0040-00015178
- Issued by
- Union County, Oregon
About this file
This is Addendum No. 2 to the contract documents for the 2025 Reservoir Coatings Project issued by the City of Pendleton, Oregon, through Consor North America, Inc., the owner's design consultant. The addendum modifies the original contract documents effective November 5, 2025, and establishes bidder qualification requirements for specialty contractors. Bidders must submit Statements of Qualifications for two categories of specialty contractors: Tank Painting Contractors and Tank Contractors selected from Consor's prequalified lists or submitted with the bid for review. The prequalified Tank Painting Contractors include Coatings Unlimited, Inc., F.D. Thomas, Long Painting Company, National Industrial Painting, Inc., Purcell Painting & Coatings, Columbia Industrial Coatings, and Hancock Sandblast & Paint. Prequalified Tank Contractors include CB&I Storage Solutions, T Bailey, Inc., and Paso Robles Tank, Inc. Statement of Qualifications Forms must be submitted by 5:00 pm local time on Monday, November 3, 2025, to taylor.spencer@consoreng.com, with an addendum listing all prequalified contractors issued by 5:00 pm local time on Wednesday, November 5, 2025. Sealed bids remain due on November 13, 2025, at 2:00 pm local time.
The addendum also clarifies technical specifications by deleting the original project description that incorrectly referenced street and infrastructure construction work, replacing it with language specific to water storage tank rehabilitation. Modifications to Technical Specifications Section 05 50 00 eliminate shop painting of metal fabrications, while revisions to Section 09 97 13.25 regarding existing steel water storage tank painting require the contractor to provide all access equipment during warranty inspections. All bids submitted without notation of prequalified specialty contractors will be deemed non-responsive and rejected. Bidders must include references to both required specialty contractors on the bid proposal form to be considered responsive.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 2 W241261OR Page 1 of 2
ADDENDUM NO. 2
TO THE
CONTRACT DOCUMENTS
FOR
WATER FILTRATION PLANT CLEARWELL AND
SOUTHWEST RESERVOIR REHABILITATION PROJECT
FOR
CITY OF PENDLETON, OREGON
THIS ADDENDUM IS HEREBY MADE A PART OF THE CONTRACT DOCUMENTS TO THE SAME EXTENT AS
THOUGH IT WERE ORIGINALLY INCLUDED THEREIN.
BIDDERS MUST ACKNOWLEDGE RECEIPT OF ALL ADDENDA ON THE BID PROPOSAL FORM. BID
PROPOSALS THAT FAIL TO ACKNOWLEDGE ALL ADDENDA MAY BE CONSIDERED IRREGULAR AND MAY BE
REJECTED.
ISSUED THIS 5TH DAY OF NOVEMBER 2025.
Consor North America, Inc.
One SW Columbia Street, Suite 1700
Portland, OR 97204
(503) 225-9010
Addendum No. 2 W241261OR Page 2 of 2
ITEM NO. 1 - INFORMATION FOR BIDDERS, SECTION 4, BIDDER’S QUALIFICATIONS
A. Delete Section 4, Bidder’s Qualifications, in its entirety and REPLACE with the attached copy.
ITEM NO. 2 - INFORMATION FOR BIDDERS, SECTION 14, SPECIAL SPECIFICATIONS
A. In Section 14, Special Specifications, page 1 of 8, DELETE the following:
“DESCRIPTION OF WORK
This Project consists of the following work for the 2025 Reservoir Coatings Project:
1. Construct curb, gutter, sidewalks, ADA ramps, asphalt street, and side street approaches as called for in the Plans.
2. Install catch basins and storm sewer pipe as called for in the Plans.
3. Install sanitary sewer pipe as called for in the Plans.
4. Install water pipe and pressure reducing valve vault as called for in the Plans.
5. Install electrical conduits, vaults, and street light bases.
6. Construct storm detention ponds as called for in the Plans.
7. Perform additional and incidental work as called for in the Specifications and Plans.”
ITEM NO. 3 – TECHNICAL SPECIFICATIONS, SECTION 05 50 00, METAL FABRICATIONS
A. On page 05 50 00-10, subsection 2.6 C, Shop Painting, DELETE paragraphs 2.6 C(1) through (5) in their entirety and REPLACE with the following:
“1. Shop painting of metal fabrications will not be allowed.”
ITEM NO. 4 – TECHNICAL SPECIFICATIONS, SECTION 05 50 00A, SUPPLEMENT A RAFTER SUPPORT
DETAIL
A. DELETE Section 05 50 00A, Supplement A, Rafter Support Detail, in its entirety and REPLACE with the attached copy of Section 05 50 00A, Supplement A, Rafter Support Detail.
ITEM NO. 5 – TECHNICAL SPECIFICATIONS, SECTION 09 97 13.25, EXISTING STEEL WATER STORAGE
TANK PAINTING
A. On page 09 97 13.25-10, subsection 1.12, Warranty, ADD the following:
“D. The Contractor shall provide all access equipment (lifts, scaffolding, ladders, etc) as requested by the Owner at the time of the warranty inspection.”
4.00
BIDDER’S QUALIFICATIONS
(To be submitted with Bid)
Bidders shall complete this Bidder’s Qualifications Document and submit it with their Bids, along with Statements of Qualifications (SOQ) Forms for the following specialty contractors: 1) Tank Painting Contractor and 2) Tank Contractor found in this Section. Additional pages may be provided, but this form shall be filled out completely.
Consor is the owner’s design consultant for this project. Below is a list of Consor’s prequalified Tank Painting Contractors and Tank Contractors for this project. These companies have all completed Consor’s SOQ review and approval process and/or have successfully completed at least one Consor-designed project to make this list.
Tank Painting Contractors:
1. Coatings Unlimited, Inc., Kent, WA
2. F.D.Thomas, Central Point, OR
3. Long Painting Company, Portland, OR
4. National Industrial Painting, Inc, University Place, WA
5. Purcell Painting & Coatings, Vancouver, WA
6. Columbia Industrial Coatings, Richland, WA
7. Hancock Sandblast & Paint, Pasco, WA
Tank Contractors:
1. CB&I Storage Solutions, Everett, WA
2. T Bailey, Inc., Anacortes, WA
3. Paso Robles Tank, Inc., Paso Robles, CA
For prequalification approval, Consor will review Statement of Qualification Forms, included in this Section, to be submitted on or before 5:00 pm local time Monday, November 3, 2025.
Completed SOQ Forms can be submitted by PDF via email to the Consor Project Manager, Taylor Spencer, at this email address: taylor.spencer@consoreng.com
An addendum listing all prequalified contractors will be issued by 5:00 PM local time on Wednesday, November 5, 2025 for 1) Tank Painting Contractors and 2) Tank Contractors.
ALL BIDS MUST BE SUBMITTED WITH PREQUALIFIED SPECIALTY CONTRACTORS NOTED ON
THE BID PROPOSAL FORM. If a prequalified specialty contractor is not noted in the Addendum issuance, Bidder must submit a Statement of Qualifications for the specialty contractor with their bid and it will be assessed as part of the Proposal. (See attached forms.)
IF A BID IS SUBMITTED WITHOUT NOTING PREQUALIFIED SPECIALTY CONTRACTORS, that bid will be deemed NON-RESPONSIVE and be REJECTED. In the absence of a specialty contractor not being listed in the Addendum issuance, a Statement of Qualification must also be submitted with the Bid for the specialty contractor consideration and will be reviewed with the Bid Proposal and Bidder’s Qualifications. ALL BIDS MUST INCLUDE REFERENCE TO THE TWO SPECIALTY CONTRACTORS
TO BE DEEMED RESPONSIVE AND NOT BE REJECTED.