PDB-OTA Process Overview Placemat.pdf

PDF 332 KB Posted

Attached to
SOURCES SOUGHT ANNOUNCEMENT / INDUSTRY DAY FOR SENTINEL UTILITY CORRIDOR AT MALMSTROM AIR FORCE BASE, MONTANA
Solicitation number
W9128F26SM024
Issued by

About this file

This document is a process flowchart and explanatory guide for Progressive Design-Build (PDB) projects utilizing Other Transaction (OT) agreements under federal contracting authority (10 U.S.C. § 2808a) for Military Construction (MILCON) projects managed by the U.S. Army Corps of Engineers.

The PDB-OT process consists of two phases executed through OT agreements. Phase 1 (Design & Preconstruction Services) uses MILCON design funds and includes eight pre-agreement steps: project requirements definition, Request for Qualifications (RFQ), Statement of Qualifications (SOQ) submission, government down-selection of qualified offerors, pitch presentations, qualifications-based selection (QBS), negotiation of OT Phase 1 services, and award of the OT Phase 1 agreement. Phase 1 execution encompasses kickoff and alignment, schematic design, budget lock, design development, and preconstruction readiness activities, culminating in a government decision gateway to authorize Phase 2 when cost, scope, schedule, and risk are acceptable. Phase 2 (Final Design & Construction) uses MILCON construction funds and executes concurrent final design and construction activities in work packages, including long-lead procurement, foundations, structure, building systems, site utilities, commissioning, beneficial occupancy, and project closeout. The process emphasizes early alignment of government and industry goals, open-book cost collaboration, iterative problem-solving, off-ramp decision points protecting the government at key milestones, and overlapped design-construction execution to optimize delivery timelines and reduce overall project risk while improving cost and schedule confidence. The document includes a target completion date of 30 June 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROGRESSIVE DESIGN-BUILD (PDB) WITH OT

End-to-End Process for MILCON Projects

Right Authority.

Right Collaboration.

Right Outcome.

OT STATUTORY

AUTHORITY:

10 U.S.C. § 2808a, Facility Construction or Repair:

Transactions Other Than Contracts and

Grants

AGREEMENT PHASE 1 – DESIGN & PRECONSTRUCTION SERVICES (OT Agreement using MILCON Design Funds)

EARLY ALIGNMENT

Aligns Government & Industry Goals Early

OPEN BOOK COLLABORATION

Transparency in estimating drives informed decisions

ITERATIVE & FLEXIBLE

Evolves Strategy & Solves Challenges Early

OFF RAMP PROTECTION

Exit points protect Government at key milestones

OVERLAPPED EXECUTION

Design and Construction Optimized

BETTER OUTCOMES

Deliver facilities with more cost and schedule confidence

AGREEMENT PHASE 2 – FINAL DESIGN & CONSTRUCTION (OT Agreement using MILCON Construction Funds)

KICKOFF & ALIGNMENT SCHEMATIC DESIGN BUDGET LOCK DESIGN DEVELOPMENT DECISION GATEWAY TO

PHASE 2

PRECONSTRUCTION

READINESS

Outcome: Government Authorizes Phase 2 Construction when Cost, Scope, Schedule and Risk are Acceptable

Risk Informed Project Alignment Meeting

• Goals & Objectives

• Risk Workshop

• Success Metrics

• Communication Plan

Concept Solutions

• Further Alternatives

• Innovation Opportunities

• Risk Reduction

Schematic Design Development

• Develop Design

Concepts

• Evaluate Systems

• Confirm Approach

Budget Estimate Submission

• Level 3 Cost Estimate

• Cost Confidence Package

• Scope/Schedule Validation

Advance Design (Technical Development)

• Tailored Design

• Engineer Analysis

• Constructability Reviews

Integrated Schedule Development

• Long Lead Item Identification

• Resource Planning

Execution-Ready Integrated Solution

• Coordinate Estimate

• Constructability

• Risk Mitigation

Government Decision

• Scope Confirmed

• Cost Validated

• Risk Accepted

• Negotiate Phase 2:

Construction

Pre-Construction Work

• BCOES

• Permitting

• Early Submittals

• Site Readiness

Open Book Estimate / Revised GECWE / Open Book Estimate / IGE

Switch to Fixed Price

1. Project Requirements

• Mission Need

• Performance Objectives

• Industry Outreach /

Market Intelligence

• SCO OTA Approval

AUTHORIZE PHASE

2 CONSTRUCTION

FINAL DESIGN / CONSTRUCTION DOCUMENTS

(OVERLAPPING)

CONSTRUCTION (OVERLAPPING w/ DESIGN) REDZONE / BENEFICIAL OCCUPANCY TURNOVER /

CONSTRUCTION

COMPLETE

LONG LEAD / EARLY

WORK

• Early Site Acquisition

• Site Access

• Site Preparation

• Early Package

• Execute Construction in Work Packages

• Foundations / Structure

• Building / Systems

• Interior / Exterior

• Site Utilities

• Continuous Quality & Safety Reviews

• Punchlist

• Red Zone Commissioning

• Joint Occupancy (if needed)

• Beneficial Occupancy

• Base Certification

• Turnover / Construction Complete

• Close Out

• Success Letter, if applicable

• Mission Complete!

• Complete Construction Documents

• Permitting & Submittals

• Ongoing Design Development

• Submittals & Coordination

• Receive MILCON Construction Funding

• Issue Modification to Agreement

• Obligate Funding

• Decision Milestones

• Green Light Long Lead Item Procurement Construction Continues

2. Request for Qualifications

(RFQ)

3. Statement of Qualifications

(SOQs)

• Industry Submits SOQs

• Government Evaluation

4. Down-Select •Government

Selects Best Qualified Offers

•Invite Firms to Pitch Presentations

5. Pitch Presentations

6. Qualifications Based Selection

(QBS)

• Government Selects

Best Qualified Offeror

7. Negotiate OT (Phase 1) Services

• Scope of Ph 1 Design/ Preconstruction Services

• Performance Metrics

8. Award OT (Phase 1)

Agreement

• Award Other

Transaction Agreement

GOVERNANCE

& OVERSIGHT

• Tailored Oversight

• Periodic Reporting

• Cost, Schedule, Performance Reviews

• Risk Management

Why PDB with

OT?

PRE-AGREEMENT: PLANNING, SOLICITATION, & AWARD

OFF RAMP

DECISION POINT

OFF RAMP

DECISION POINT

• Finalize Requirements Package

• Industry Day / Notice

• Publish Solicitation

• Offeror Presentations / Meetings / Interviews

• Q&A

• Site Visit, if applicable

30 JUN 2026

Slide Number 1