This document is a pavement segment description and schedule for a state and local contract opportunity in Ionia County, Michigan. The scope of work includes road repairs, pavement replacement, and trail construction across multiple segments of the park's main roads, beach area roads, campground roads, and various trails. The pavement segments range in size from 1,470 to 19,424 square yards, with varying pavement conditions and thicknesses. The schedule provides detailed cost estimates for heavy duty full replacement, standard duty full replacement, new pavement on existing gravel base, new pavement on pulverized existing, asphalt repair/chip seal, trail pavement, and concrete pavement as well as campground ADA improvements. The total recommended improvements sum to $4,035,595.87.
The pricing terms include unit costs per square yard for the different pavement treatments. There are no set-asides mentioned, and no information on incumbents or the current contracting environment. The funding source is indicated as ARPA (American Rescue Plan Act), though the specific amount and source are not provided. The contract term and any renewal options are also not specified in this document.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
Road Repairs
| PAVEMENT SEGMENT SCHEDULE | |||||||||||||||||||||
| KEY | PAVEMENT SEGMENT DESCRIPTION | PAVEMENT AREA SQUARE YARDS | MDNR CONDITION ASSESSMENT | GEOTECHNICAL ASSESSMENT | MDNR SEGMENT PRIORITY | HEAVY DUTY FULL REPLACEMENT $71.85 /SY | STANDARD DUTY FULL REPLACEMENT $63.05 /SY | NEW PAVEMENT ON EXIST. GRAVEL BASE $54.18 /SY | NEW PAVEMENT ON PULVERIZED EXISTING $39.55 /SY | ASPHALT REPAIR / CHIP SEAL $9.50 /SY | TRAIL PAVEMENT $79.22/SY | CONCRETE PAVEMENT $84.82 /SY | CAMPGROUND ADA IMPROVEMENTS $16,750.00 | ||||||||
| 1 | MAIN ROAD - Park Entrance to Beach Area Road | 4,638 | POOR | 1 1/2" HMA 8" Gravel | 1 | $ 71.85 | $ 333,240.30 | $ 63.05 | $ 292,425.90 | $ 54.18 | $ 251,286.84 | $ 39.55 | $ 183,432.90 | $ 9.50 | $ 44,061.00 | $ 84.82 | $ 393,395.16 | ||||
| 2 | MAIN ROAD - Beach Area Road to Visitor Center Road | 6,568 | POOR | 1 1/2" - 2" HMA 5 1/2" - 6" Gravel | 1 | $ 71.85 | $ 471,910.80 | $ 63.05 | $ 414,112.40 | $ 54.18 | $ 355,854.24 | $ 39.55 | $ 259,764.40 | $ 9.50 | $ 62,396.00 | $ 84.82 | $ 557,097.76 | ||||
| 3 | MAIN ROAD -Visitor Center Road to Picnic Shelter & Trailhead | 4,910 | POOR | 1" - 1 1/2" HMA 6 1/2" - 9" Gravel | 1 | $ 71.85 | $ 352,783.50 | $ 63.05 | $ 309,575.50 | $ 54.18 | $ 266,023.80 | $ 39.55 | $ 194,190.50 | $ 9.50 | $ 46,645.00 | $ 84.82 | $ 416,466.20 | ||||
| 4 | BEACH AREA ROAD - Main Road to Concession Building | 6,277 | MEDIUM | 1 1/4" - 2" HMA 5" - 13" Gravel | 1 | $ 71.85 | $ 451,002.45 | $ 63.05 | $ 395,764.85 | $ 54.18 | $ 340,087.86 | $ 39.55 | $ 248,255.35 | $ 9.50 | $ 59,631.50 | $ 84.82 | $ 532,415.14 | ||||
| 5 | BEACH AREA PARKING LOTS | 19,424 | MEDIUM | 1 1/2" - 2" HMA 6" - 15" Gravel | 3 | $ 71.85 | $ 1,395,614.40 | $ 63.05 | $ 1,224,683.20 | $ 54.18 | $ 1,052,392.32 | $ 39.55 | $ 768,219.20 | $ 9.50 | $ 184,528.00 | $ 84.82 | $ 1,647,543.68 | ||||
| 6 | ORGANIZATION CAMPGROUND ROADS | 2,580 | MEDIUM | 2" - 2 1/4" HMA 6" - 8" Gravel | 3 | $ 71.85 | $ 185,373.00 | $ 63.05 | $ 162,669.00 | $ 54.18 | $ 139,784.40 | $ 39.55 | $ 102,039.00 | $ 9.50 | $ 24,510.00 | $ 84.82 | $ 218,835.60 | ||||
| 7 | PICNIC AREA ROADS | 1,486 | MEDIUM | 2" - 2 1/4" HMA 6" - 8" Gravel | 3 | $ 71.85 | $ 106,769.10 | $ 63.05 | $ 93,692.30 | $ 54.18 | $ 80,511.48 | $ 39.55 | $ 58,771.30 | $ 9.50 | $ 14,117.00 | $ 84.82 | $ 126,042.52 | ||||
| 8 | VISITOR CENTER ROAD - Main Road to Visitor Center | 4,763 | POOR | 1 1/4" HMA 6 3/4" - 8" Gravel | 3 | $ 71.85 | $ 342,221.55 | $ 63.05 | $ 300,307.15 | $ 54.18 | $ 258,059.34 | $ 39.55 | $ 188,376.65 | $ 9.50 | $ 14,117.00 | $ 84.82 | $ 403,997.66 | ||||
| 9 | PARK HEADQUARTERS ROAD AND SERVICE AREA | UNKNOWN | 1 1/4" - 1 1/2" HMA 2 1/2" - 6" Gravel | 3 | $ 71.85 | $ 63.05 | $ 54.18 | $ 39.55 | $ 9.50 | $ 84.82 | |||||||||||
| 10 | CAMPGROUND ACCESS ROAD - Lake Harbor Road to Loops A-D | 9,522 | MEDIUM | 3/4" - 3" HMA 4" - 6" Gravel | 2 | $ 71.85 | $ 684,155.70 | $ 63.05 | $ 600,362.10 | $ 54.18 | $ 515,901.96 | $ 39.55 | $ 376,595.10 | $ 9.50 | $ 90,459.00 | $ 84.82 | $ 807,656.04 | ||||
| 11 | CAMPGROUND LOOP ROAD A | 3,028 | MEDIUM - POOR | 2 | $ 71.85 | $ 217,561.80 | $ 63.05 | $ 190,915.40 | $ 54.18 | $ 164,057.04 | $ 39.55 | $ 119,757.40 | $ 9.50 | $ 28,766.00 | $ 84.82 | $ 256,834.96 | |||||
| 12 | CAMPGROUND LOOP ROAD B | 2,839 | MEDIUM - POOR | 2" HMA Sand | 2 | $ 71.85 | $ 203,982.15 | $ 63.05 | $ 178,998.95 | $ 54.18 | $ 153,817.02 | $ 39.55 | $ 112,282.45 | $ 9.50 | $ 26,970.50 | $ 84.82 | $ 240,803.98 | ||||
| 13 | CAMPGROUND LOOP ROAD C | 2,125 | MEDIUM - POOR | 2 | $ 71.85 | $ 152,681.25 | $ 63.05 | $ 133,981.25 | $ 54.18 | $ 115,132.50 | $ 39.55 | $ 84,043.75 | $ 9.50 | $ 20,187.50 | $ 84.82 | $ 180,242.50 | |||||
| 14 | CAMPGROUND LOOP ROAD D | 6,341 | MEDIUM - POOR | 1" HMA 7" Gravel | 2 | $ 71.85 | $ 455,600.85 | $ 63.05 | $ 399,800.05 | $ 54.18 | $ 343,555.38 | $ 39.55 | $ 250,786.55 | $ 9.50 | $ 60,239.50 | $ 84.82 | $ 537,843.62 | ||||
| 15 | CAMPGROUND SITE ADA IMPROVEMENTS | 15 | $16,750.00 | $251,250.00 | |||||||||||||||||
| 16 | 10' WIDE NON - MOTORIZED TRAIL - Park Entrance to Campground, 1470 lf | 1,633 | N/A | $ 79.22 | $ 129,366.26 | ||||||||||||||||
| 1T | 10' WIDE NON - MOTORIZED TRAIL - Park Entrance to Beach Area Road, 1,700 lf | 1,888 | N/A | $ 79.22 | $ 149,567.36 | ||||||||||||||||
| 2T | 10' WIDE NON - MOTORIZED TRAIL - Beach Area Road to Visitor Center Road, 2,900 lf | 3,218 | N/A | $ 79.22 | $ 254,929.96 | ||||||||||||||||
| 3T | 10' WIDE NON - MOTORIZED TRAIL - Visitor Center Road to Picnic Shelter,620 lf | 688 | N/A | $ 79.22 | $ 54,503.36 | ||||||||||||||||
| 4T | 10' WIDE NON - MOTORIZED TRAIL - Beach Area Road Entrance to Concession Building, 2785 lf | 3,094 | N/A | $ 79.22 | $ 245,106.68 | ||||||||||||||||
| 8T | 10' WIDE NON - MOTORIZED TRAIL - Visitor Center Road Entrance to Visitor Center Parking, 1,224 lf | 1,360 | N/A | $ 79.22 | $ 107,739.20 | ||||||||||||||||
| RECOMMENDED IMPROVEMENTS | $ 1,616,475.90 | $ 1,003,502.15 | $ 223,155.00 | $ 941,212.82 | $ 251,250.00 | ||||||||||||||||
| TOTAL RECOMMENDED IMPROVEMENTS | $ 4,035,595.87 |