About this file

This is a Past Performance Questionnaire (PPQ) template issued by the GSA Public Buildings Service for solicitation number 47PB0025R0007 related to the LPOE Refresh Orient ME project. The questionnaire must be submitted by January 31, 2025 to GSA contracting officials Neal Deodhar and Justin Baysore.

The PPQ includes detailed rating criteria across seven major evaluation areas: Quality, Schedule/Timeliness of Performance, Customer Satisfaction, Management/Personnel/Labor, Cost/Financial Management, Safety/Security, and General Performance. It uses a six-point rating scale from Exceptional (E) to Unsatisfactory (U), with specific definitions provided for each rating level. The form requires client points of contact to evaluate contractors on specific aspects within each area, such as technical performance, problem resolution, schedule compliance, workforce management, cost control, and safety adherence. Additional sections address sustainability practices and whether the client would work with the contractor again. The template includes space for narrative comments on contractor strengths, weaknesses, and other performance risk factors.

View the file

Other files for this federal contract opportunity

Other files attached to LPOE Refresh Orient ME, newest first.
File Type Posted
47PB0025R0007 Amendment 004.pdf PDF
47PB0025R0007 Amendment 003.pdf PDF
47PB0025R0007 Amendment 002.pdf PDF
47PB0025R0007 Amendment 001.pdf PDF
47PB0025R0007 1442.pdf PDF
Reps and Certs.pdf PDF
Wage Determination ME20230006.pdf PDF
GSA527-21.pdf PDF
47PB0025R0007 The Solicitation.pdf PDF
47PB0025R0007 The Agreement.pdf PDF
SF24.pdf PDF
Supplemental Information Form.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions for Past Performance Questionnaire

Dear Respondent, The United States General Services Administration would like to thank you for taking the time to assist us in the selection of a Contractor for our Project. Please complete the questionnaire to the best of your ability. We ask that you keep your responses to this questionnaire confidential.

The information you provide on this questionnaire will not be shared with the Offeror.

When completed, please send a scanned or electronic copy of the questionnaire to the following e-mail addresses: neal.deodhar@gsa.gov and justin.baysore@gsa.gov. We ask you to include the following information in the subject line of the e-mail: Solicitation No. 47PB0025R0007.

The questionnaire must be returned ON or BEFORE January 31, 2025.

We appreciate your time and efforts in assisting us in serving the American public.

mailto:neal.deodhar@gsa.gov

PBS Past Performance Questionnaire July 2014

PBS PAST PERFORMANCE QUESTIONNAIRE

CONTRACT INFORMATION (Contractor/Offeror to complete Blocks 1-4)

1. CONTRACTOR/OFFEROR INFORMATION

Firm Name:

Address:

Phone Number: SAM UEI:

Contact Name

Email Address: : Contact Phone Number:

2. GENERAL WORK INFORMATION

Work performed as: Prime Contractor Sub Contractor Joint Venture Other (Please explain):

Percent (%) of project work performed:

If a subcontractor, who was the prime (Name/Phone #):

3. CONTRACT INFORMATION

Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please explain)

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. PROJECT DESCRIPTION

Complexity of Work: High Med Routine

How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

INSTRUCTIONS FOR CLIENTS COMPLETING THIS QUESTIONNAIRE: PBS requests that the client completes this questionnaire and submits it directly back to the offeror. The offeror will submit the completed questionnaire to PBS with their proposal, and may duplicate this questionnaire for future submission on PBS solicitations. Clients are highly encouraged to submit questionnaires directly to the offeror. However, questionnaires may be submitted directly to PBS. Please contact the offeror for PBS POC information. The government reserves the right to verify any and all information on this form.

Use the following adjective ratings and definitions in your evaluation of the Contractor’s performance.

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable No information or did not apply to your contract Rating will be neither positive nor negative.

TO BE COMPLETED BY CLIENT

CLIENT INFORMATION

Client Point of Contact Information

Name:

Title:

Phone Number:

Email Address:

Project Information

Contract Type:

Contract Title:

Contract Location:

Describe your role in the project:

Date Questionnaire was completed (mm/dd/yy):

Client’s Signature:

Instructions: Please select the adjective rating that best reflects your evaluation of the contractor’s performance.

1. QUALITY: E VG S M U N

(a) Quality of technical data/report preparation efforts.

(b) Ability to meet quality standards specified for technical performance.

(c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance.

(d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance).

2. SCHEDULE/TIMELINESS OF PERFORMANCE: E VG S M U N

(a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below.)

(b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract.

3. CUSTOMER SATISFACTION: E VG S M U N

(a) To what extent were the end users satisfied with the project?

(b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication).

(c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?

(d) Overall customer satisfaction.

4. MANAGEMENT/ PERSONNEL/LABOR E VG S M U N

(a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?

(b) Ability to hire, apply, and retain a qualified workforce to this effort.

4. MANAGEMENT/ PERSONNEL/LABOR - Continued E VG S M U N

(c) Government Property Control.

(d) Knowledge/expertise demonstrated by contractor personnel.

(e) Utilization of Small Business concerns.

(f) Ability to simultaneously manage multiple projects with multiple disciplines.

(g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes.

(h) Effectiveness of overall management (including ability to effectively lead, manage and control the program).

5. COST/FINANCIAL MANAGEMENT E VG S M U N

(a) Ability to meet the terms and conditions within the contractually agreed price(s)?

(b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client.

(c) If this is/was a Government cost type contract, or a CMc/CMc at Risk Contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns).

(d) Is the Contractor’s accounting system adequate for management and tracking of costs? (If no, please explain in comment section below.)

Yes No

(e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? (Indicate if show cause or cure notices were issued, or any default action in comment section below.)

Yes No

(f) Have there been any indications that the contractor has had any financial problems? (If yes, please explain in the comment section below.)

Yes No

6. SAFETY/SECURITY E VG S M U N

(a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?

(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.).

(b) Contractor complied with all security requirements for the project and personnel security requirements.

7. GENERAL E VG S M U N

(a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

(b) Compliance with contractual terms/provisions (If there were specific issues, please explain in the comments sections below

(c) In summary, provide an overall rating for the work performed by this contractor.

8. SUSTAINABILITY

Did this project include sustainable methods, materials, processes or certifications? (See Whole Building Design Guide for acceptable requirements. Link to guide WBDG Green Building Standards and Certification Systems.) (If yes, please explain in the comments section below.)

Yes No

9. SUMMARY

Would you hire or work with this firm again? (If no, please explain in the comments section below.)

Yes No

COMMENTS SECTION

Please provide additional information below, and attach additional pages if necessary.

Please provide responses to the above questions (if applicable) and/or additional remarks. Also please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):

http://www.wbdg.org/resources/gbs.php#rcas http://www.wbdg.org/resources/gbs.php#rcas

File details come from the government source that posted it. Updated .