47PB0025R0007 Amendment 003.pdf

PDF 6 MB Posted

Attached to
LPOE Refresh Orient ME Federal contract opportunity
Solicitation number
47PB0025R0007
Issued by
General Services Administration Public Buildings Service Region 5

About this file

This is Amendment 003 to solicitation 47PB0025R0007 for the LPOE Refresh project at the Orient, ME border station. The amendment extends the proposal due date from January 31, 2025 to February 3, 2025 at 5PM Eastern Time and incorporates responses to contractor questions as well as an asbestos report for the facility.

The amendment includes clarifications through Q&A regarding repointing requirements, building closure during construction (facility will be closed), completion deadline of September 1, 2025 due to funding constraints, and various technical specifications about materials and installation requirements. The included 2012 asbestos survey report identified asbestos-containing materials in gray sink coating (5-10% chrysotile) and brown pebbled sheet flooring/mastic (5-10% chrysotile) in certain areas of the facility. The amendment requires contractors to sign and return the SF30 form with their proposals.

View the file

Other files for this federal contract opportunity

Other files attached to LPOE Refresh Orient ME, newest first.
File Type Posted
47PB0025R0007 Amendment 004.pdf PDF
47PB0025R0007 Amendment 002.pdf PDF
47PB0025R0007 Amendment 001.pdf PDF
Past Performance Questionnaire.pdf PDF
47PB0025R0007 1442.pdf PDF
Reps and Certs.pdf PDF
Wage Determination ME20230006.pdf PDF
GSA527-21.pdf PDF
47PB0025R0007 The Solicitation.pdf PDF
47PB0025R0007 The Agreement.pdf PDF
SF24.pdf PDF
Supplemental Information Form.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE

PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

See Attached.

Capital & Customer Projects Contracting Branch 230 S Dearborn St Chicago, IL 60604 USA

See box 6.

47PB0025R0007

01/27/2025

01/27/2025

INSTRUCTIONS

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Item 9, (Amendment of Solicitation No. - Dated), and 10, (Modification of Contract/Order No. - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries.

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 10-83) BACK

(1) Accounting classification Net increase $

RFP 47PB0025R0007

14. DESCRIPTION OF AMENDMENT/MODIFICATION

Amendment 003 is issued to make the following changes:

• The attached RFIs and Answers are incorporated. Please note that the Answers provided in the attached supersede any inconsistent provisions contained in the solicitation.

• Include the Orient LPOE Asbestos Report.

• Extend the proposal due date from 1/31/25 to 2/3/25 at 5PM Eastern Time.

All other solicitation terms and conditions remain unchanged.

PLEASE NOTE – YOU MUST SIGN THE SF30 INCORPORATING THIS

AMENDMENT IN BOX 15A AND RETURN THE SIGNED FORM ALONG

WITH YOUR PROPOSAL.

RFIs and Responses

RFP No. 47PB0025R0007

LPOE Refresh Orient ME

Questions: Answers:

1.

Can you please verify the Liquidated Damages for this project? The Agreement I.F. Contract Liquidated Damages Rate page 6 show $0.00.

LDs are not part of the project.

2.

On page 6 of the specification (page 1 of 011000 – Summary) Item1.1 D. states: Project Delivery Method: Traditional design/bid/build.

Just want to confirm that we do not have to bring in another designer to finalize or redesign the project. We are just bidding the already completed design and will be required to construct that design.

Correct.

3.

Missing the BC (branch connector) detail on page M-1-101

Manufacturers installation instructions to be followed if Branch Connectors are to be used.

4.

What is the electrical scope for the pointing and patching of the exterior masonry?

Means and methods, if something is deemed needed to be removed to properly pointing and patching then include it.

5.

Will there need to be temp relocations or replacement of the exterior conduits?

Unclear what this is referring to.

6.

Please advise if the building will be closed during construction?

Yes, the port will be closed for the duration of the project. Dates will be established as soon as possible

7.

Does a temporary facility need to be provided during construction?

No

8.

Does any temp power need to be provided? Means and methods, If the contractor can do the work without having to shut down power then no temp power is required

9.

In option 1 is the intent to repoint the whole building?

Repoint and patch where needed, if deemed the whole building needs repointing then propose it.

10.

Please clarify what is meant by “repair”. noun:

the action of fixing or mending something.

11.

Please provide the sign in sheet. The sign-in sheet is posted to SAM in

Amendment 002..

12.

Please provide specifications for structural steel columns and beam.

See ‘Structural Steel Notes’ sheet S-1-111

13.

There are no fire-rated walls. Please confirm requirements for firestopping.

There is no fire-rated wall construction. Provide solid 2x fire blocking at the top of all stud cavities where the wall partition intersects the ceiling.

14.

There is a specification for access doors and panels (08-3100), however, none are shown on drawings. Please confirm the quantity and locations for these access doors and panels.

No access doors are required for the HVAC system design.

15.

There is a specification for 09-6700 Fluid Applied Flooring, however, we do not see this denoted in the drawings. Please confirm if fluid-applied flooring is applicable and if so, provide locations and details for this system.

Specification Section 096700 Resinous Flooring refer to Note P18 on sheet A-1-111

16.

Who is responsible for furnishing and installing the lockers?

Contractors are responsible for furnishing and installing lockers, specs are on prints PG 16 of 52.

17.

On Amendment 002, it denotes under Item 3 Effective Date that this amendment is effective as of "01/07/2025," which is the same as Amendment 001. Please confirm which effective date should be utilized for Amendment 002 on the SF1442.

Please use 1/15/25.

18.

Solicitation reads:

Option 1 includes 100% repointing and Crack repair. But SOW states:

• Base Bid Work includes, but is not limited to the following:

1. Exterior Bid Work (Base Bid): includes the 100% repointing of the joints and any cracks discovered on the building's North, South, East and West Facades. This area covers the entire elevation/facade from the Ground Floor to the Roof:

B. Masonry Restoration: Repoint all brick joints and

Repointing the brick is part of the option. 100 percent repoint / patch building where needed, if the contractor deems doing the entire building is a better means and methods then present that in their proposal.

repair all cracks on the east & west facades

Can you quantify or differentiate whether repointing and crack repair is an option or should be included in the base bid ?

19.

At Some Mortar locations to 100% repoint will affect the roof and flashing which appears to be adhered to the brick and roof. Should we include in our price the associated repairs for the roof and flashing or assume we will not disturb the Brick's and mortar locations that would create additional work?

If Brick / mason joints need repair in those locations then pull back roofing, point / patch reflash.

20.

For Crack repair - Should we assume removal of cracked bricks and tooth in new to closely match existing?

Yes

Pg5 of "The Agreement - Can you Confirm The building will be unoccupied during this renovation?

See response to question 6.

Are any As-builts or existing framing plans available?

No

Do we know when the building was built? 1937

Is a mortar analysis required? No

Pg 040115-6 Para. 2.4 A. calls for lead T-caps, are lead t-caps required on this project? if so please quantify

If it calls for it then it is needed.

On Drawing A-1-131 plan note P11 is remove and replace existing gutters and Down spouts - During the sight visit the gutters and down spouts appeared to be intact but in some locations the Eaves, Eaves Drip, Facia, Soffit and Frieze Board appeared to be rotted. Can we assume this work if needed to replace the Gutters will be deemed an existing condition and not part of the project or scope?

Price replacing gutter and downspout and during install if deemed necessary to replace facia, and soffit we will address at that time.

Is there currently an existing Access control System and if so whom is the current service tech or provider? HIRSCH IDENTIV?

No existing access control.

Is there currently an existing Security and Monitoring System and if so whom is the current

Currently monitored via video feeds to the Houlton CBP Area Security Center (CASC). No

Service tech or provider? HIRSCH IDENTIV? IDS services/monitoring at this time.

For access controls and security is the facility currently using a vendor with proprietary software?

No existing access control or IDS.

Please provide Hazardous material report per specification 01 73 20 1.5.F

Uploaded with amendment 3

On Sheet A-1-131, Note P11 delineates, "Remove and replace all existing gutters and downspouts. Provide gutters and downspouts to match existing color, size and profile." We do not see a corresponding specification that notes the existing color, size and profile. Please provide this specification.

Provide architectural grade, pre-finished, 0.040 inch thick aluminum K-style gutters, pre-finished 2” x 3” x 0.040 inch thick ribbed aluminum downspouts, with concealed mill finish aluminum gutter hangers and downspout hangers.

Is there an asbestos report available? Please verify no hazmat, asbestos, lead, PCB etc removal required in scope of work

The asbestos report will be uploaded to SAM.gov with the responses to this form.

Please confirm load out path. Is there a location to leave a dumpster and parking location?

LPOE will be shutdown

For the demo/ project will there be any phasing requirements?

LPOE will be shutdown

Will off hours work be required for the demo/noisy work on this project?- I see working hours 7-4 but wasn’t sure about noisy work.

LPOE will be shutdown

Are there any CAD drawings for this project? Not at this time. All available drawings have been posted on SAM.gov.

Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

There are no guarantees of an extension. As noted during the pre-proposal, we need to complete by September 1, 2025 due to funding constraints, so it is critical to order materials asap. We will do what we can to ensure a successful project. Note that the option, if exercised, would not be subject to this same deadline.

What documentation will need to be submitted for closeout approval?

Standard close out procedures

Will the building be occupied during construction?

No

What specific standards or guidelines from the National Register of Historic Places (NRHP) must be adhered to during renovation?

Follow plans and specs

Are there approved vendors or materials for historic preservation work?

No approved vendors, follow plans and specs

Will utility disruptions (e.g., HVAC, plumbing, electrical) be allowed during the renovation, and what is the notification procedure?

The port will be closed, Contractor will be responsible for providing utilities to contractors, means and methods.

Are there any as-built drawings or surveys available for confirming existing structural conditions?

No

What precautions should be taken when working near historically significant elements?

See SECTION 013510 - HISTORIC BUILDING

TREATMENT PROCEDURES.

Are there any environmental considerations (e.g., wildlife, hazardous materials) that could impact construction?

See asbestos report.

the SOW on the repointing and it is calling out that you must have 5 years’ experience ( 1.3 Quality Assurance A )? as it will require bringing in specialists from away.

Perform the work to the trade standard, and meet local and regional building codes.

Is there an existing post to be removed and install new? the post is shown on the Structural foundation plan (S-1-101) but does not indicate removal of existing

See Attached

Vestibule 103 -Will there be flooring to be installed where the foundation and eye wash are to be removed as well as the remove the existing gwb and install new for the entire east wall? The Finish Schedule A-6-104 Note #2 remove finishes and provide new gwb painted and wood base at east weall.

See Attached

Electrical Demo plan Note # D5 & D6 e lighting is to remain i and there are notes for remove all existing lighting in entirety as well as note up to GC to remove all.

See Attached

Where there are 8" oval ducts up and down the walls, (3-1/4" wide ) is 3-5/8" stud enough to clear the duct?

See Attached

Cased opening at the Office 109-North Elevation (5/A-6-101) Please confirm the dimension of the wall and trim to be installed,The left side of the wall is this trim 5" or no trim on the left side of the opening?

See Attached

Door # X01 on the Door schedule refers to Card reader. Please confirm where the card readers are located and on the Electrical plans.

See Attached

Wall type # 2 What type of GWB is to be installed in the Kitchen

See Attached

North wall of Office: Wall Tag note # 5: Please confirm the 2-1/2" stud limits, the wall thickness looks larger then 2-1/2" stud Mechanical has a 8" oval duct running the wall ( 3-1/4" wide )

See Attached

Elevation 14 & 17 /A-6-101- The The millwork is flipped from what is on the plan.

See Attached

North Elevation is not tagged on the plan : 1/A6-

See Attached

( finish schedule A-6-104 note #2) remove finishes and provide with new painted gwb and wood base at the East wall, will there be flooring for the demo of the water fountain and the eye wash?

See Attached

Partition type 2 : sheet A-3-101 the description on the partition type calls out for sound attenuation blanket and is 2x wood framing, the wall type 2 description on the floor plan sheets does not call the insulation and states either wood or metal stud framing

See Attached

Door # 103 -Is the sill to remain existing or install new door

See Attached

Partition type #6 in the LAN 108 has 3/4" A/C plywood from floor to ceiling, Sheet ES1-101 has key note # 1 that has 4'- H x 3/4 thick fire rated plywood horizontally on the entire length of the wall as indicated on the plan Please confirm the Type of plywood and all walls are to receive from floor to ceiling in this room

Wall types: What sides of the wall get the 2 layers of 5/8" GWB

Call out 2/A-2-101.Please confirm this enlarged plan location there is no sheet provided A-2-101 or any other sheets have an enlarged restroom plan.

See Attached

What size farming is to be used this only leaves 3/16" either side for the duct to clear 3-5/8" stud wall framing and the duct?

See Attached

What is the locker enclosure soffit detail See Attached

Nurses Room Counter and Sink: Please confirm the Section 4/A-6-103 tagged on elevation 13/A- 6-102. Is this the correct section the counter depth is only( 1'-9") 1-'10" with back splash The Plan looks to be 2'-1" counter. There is an under counter fridge to be installed, will this need power under the counter?

See Attached

General demolition notes # 3 At first and second floor remove all existing ceilings and light in entirety. On the RCP plan there is a note for second floor: Patch and repair existing ceiling at removed partition and new mechanical and electrical work. At contractors option the existing ceiling may be removed and replaced in its entirety. Please confirm this scope, is this a bid alternate?

See Attached

-Basement- GC to provide coordination drawings showing all mechanical and proposed location and mounting hts for light fixtures?-is this typical

See Attached

Please confirm the lighting fixture schedule vs the description the rcp are different, and to refer to the electrical for fixture model numbers and correct sizes of the fixture Example: Processing

(101) sheet A-1-211 has symbol and description of 1'-04' surface mounted LED light fixture and the electrical has type A which is 8" x 4' Surface mounted linear LED light fixture Kitchen (107) 14" square LED and Type C on the electrical lighting is 1x1 slim mounted fixture for am location The exterior and interior lights are the same size and model # for type "C" but called out different on the architectural Type V on electrical Vanity light is 2' wall mounted linear light and arch rcp has this to be is 4' x 14" wall mounted light.

Door # 109 Hardware set # 3 is listed on the schedule. In the specifications Set 3.0 is not used. Please confirm the hardware set

See Attached

Door # 110 Pair of doors at the closet 110-have to fit door trim then size the opening to fit the doors.

See Attached

Please confirm the location of partition type "3A" See Attached

Door # 110-Would this door need a lock if the owner provided gun safe will be stored in this closet?

See Attached

Door # 203A & 201A - There is a note door with lever and slide latch is noted on the elevation(8 & 4/A-6-102) the hardware set has privacy lock surface closer and 3 hinge.

See Attached

Elev. 12/A-6-101 Lunch Counter Section 7/A-6- 103 has the top of the counter at 3'-"6'

See Attached

Kitchen 107- Elevations-10 & 11/A-6-101- Plastic Laminate soffit closure , The sections 1 &2 /A-6-103- calls out for PL-3 the elevation has

PL-1

See Attached

Office counter Elevations: 6 & 7/A-6-101 .

Please confirm if the counter is SS-3 or plastic Laminate PL-3 as shown in the sections 5 & 6 - A-106

See Attached

Elevation 15/A-6-101 has SS-3 at the counter,There are conflicts in the sections vs the elevations.

See Attached

WC # 201A- (elevation 1-A-6-102) The window existing to remain, the plan vs the elevation show different size windows. Please confirm scope

See Attached

At the lockers : Please confirm the gwb enclosure ht and construction detail. The elevations show two different paints PT-2 then PT-1 is there a step in the enclosure soffit?

Wall Heater North Elevation The WH- is on the west wall per mechanical

See Attached

Section 8 thru 12 /A-6-103 Solid Surface SS-3 is called out on the sections and on the elevation 17/A-6-101- it is called out as SS-1.

See Attached

A-6-102 : INTERIOR ELEVATIONS - BB-1 is missing from the elevation

See Attached

Section 8 thru 12 /A-6-103 Solid Surface SS-3 is called out on the sections and on the elevation 17/A-6-101- it is called out as SS-1.

Detail 4/A-6-103 Please confirm the heights and of the counters is to be 3'-0" ? and the depth of the counter is 1'-9" clear for space? Do these need to be at ada ht of 2'-10" aff and have counter depth of 2'-0" ?

See Attached

The Microwave Stove vent please confirm where this is connected to on the MEP and Roof plans

See Attached

Thermostat controlled cabinet fan. Who furnishes and installs the cabinet fans? Are there specifications and detail for install, Mechanical and Electrical do not have this

See Attached

Section 8/A-6-103 Please confirm the tel data is to run in the cabinet or in the wall? sections 9- 10-11-12 show this behind the base of the cabinet

See Attached

CWT-1 is on the schedule and elevations have WT-1, is there a difference, See Attached

Vestibule 103-Please confirm what walls will get paint, trim and base-The east wall is noted to have new gyp and paint and not shown on the finish schedule, only the West wall ?

See Attached

Women and men's locker room have PT-1 & PT-2 on the North walls only PT-1 is shown in the schedule

See Attached

8" OVAL up located in the north west corner.Please confirm where this goes to

See Attached

Please confirm where the BC-1 & BC-2 are located on the equipment schedules.

Please confirm where EDH-1 is located on the Schedules

See Attached

Diffuser Grill Schedule: please confirm where type B-D-E are located

Second Floor (W.C 201 A)- There is a note for 7" oval duct from basement, On the Basement Mechanical sheet (M1-01) there is a note 8" oval up. Please confirm

See Attached

In closet 202A- Is this light fixture to be new or replace existing? The lighting plan shows type D fixture as new

See Attached

In closet 202A- Is this light fixture to be new or replace existing? The lights are not dashed

See Attached

Basement Demolition Plan What does the hatched area represent? It is difficult to read the text

See Attached

Kitchen 107-Lunch Counter outlet- Should this be installed above the counter? This does not have the dot per the legend

See Attached

Kitchen # 107- at the stove/Oven the circuit is not shown on the plan CKT# 24/26. There is a microwave above please confirm the power locations/type/ckt # for the stove and microwave

See Attached

EX1 led exit sign is this new or existing to be removed and install new at same location? ( Vestibule 103 at door # 103)

See Attached

Kitchen 107 Please confirm the under cabinet lighting, it is shown on elevation 1 11-A-6-101 section 1/A-6-103 and not shown on the electrical lighting plan. Please confirm what cabinets will get the under cabinet lighting there are two cabinets next to the refrigerator

See Attached

Processing 101- Please confirm key note # 6 for Call Button, Is this Call Button at the mill work the Door # 103. Is this to be a DS - Door Release? at the mill work?

See Attached

Please confirm the manufacture an d model # for light fixture "E" SCA-4-0/0-45L3 5K-DCC- DV-1-1-LE2 ( Kennell)

CKT # 8 is shown in The office 105 or Interview holding, the schedule calls this out to be receptacle for agent restroom lighting ?

See Attached

The hatched are is this part of the area shown not in scope?This is not on the legend.

See Attached

Sink in Nursing , are the lines in the wall? the note points to the sink

See Attached

Demo Note 8 refers to “interior wall finish,” but describes the wall being on a masonry wall. Is this a paint finish or more of a framed/gwb system in front of the CMU walls that needs to be demolished? Please confirm.

See Attached

Has the insulation in the wall cavities been tested for vermiculite?

Orient LPOE _RFI REVIEW SUMMARY

Page Label: G-0-101 : GENERAL INFORMATION Page Index: 1 Subject: # of sheets Layer: BID RFI COMMENT

Cover Sheet - Document List:There are 52 provided -shows 53

1 (2)

Page Label: G-0-101 : GENERAL INFORMATION Page Index: 1 Subject: Specification: Elevator:

Layer: BID RFI COMMENT

Specifications: Selective Demolition: Elevator?

Page 112 - 3.5 -B

Page Label: AD-1-101 : BASEMENT DEMOLITION PLAN Page Index: 3 Subject: Existing Post in basement Layer: BID RFI COMMENT

Is there an existing post to be removed and install new? the post is shown on the Structural foundation plan (S-1-101) but does not indicate removal of existing

3 (1)

G-0-101

SEQUENCESHEET TYPE

OF 5301

08.03.21 Cover Sheet - Document List:There are 52 provided -shows 53

Specifications: Selective Demolition: Elevator?

Page 112 - 3.5 -B

Is there an existing post to be removed and install new? the post is shown on the Structural foundation plan (S-1-101) but does not indicate removal of existing

THERE IS NO EXISTING POST TO BE

REMOVED

SHEET 3 OF 53 WAS DELETED

THERE IS NO EXISTING ELEVATOR -

DELETE SPEC SECTION 017320

PARAGRAPH 3.5

Page Label: AD-1-111 : FIRST FLOOR DEMOLITION PLAN Page Index: 4 Subject: Vesibule 103 Scope of Work Finishes Layer: BID RFI COMMENT

Vestibule 103 -Will there be flooring to be installed where the foundation and eye wash are to be removed as well as the remove the existing gwb and install new for the entire east wall? The Finish Schedule A-6-104 Note #2 remove finishes and provide new gwb painted and wood base at east weall.

4 (2)

Page Label: AD-1-111 : FIRST FLOOR DEMOLITION PLAN Page Index: 4 Subject: Removal of Existing Lighting Layer: BID RFI COMMENT

Electrical Demo plan Note # D5 & D6 e lighting is to remain i and there are notes for remove all existing lighting in entirety as well as note up to GC to remove all.

Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject:

Layer: BID RFI COMMENT

Where there are 8" oval ducts up and down the walls, (3-1/4" wide ) is 3-5/8" stud enough to clear the duct?

7 (12)

Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject: Cased opening Office 109 Layer: BID RFI COMMENT

Cased opening at the Office 109-North Elevation (5/A-6-101) Please confirm the dimension of the wall and trim to be installed,The left side of the wall is this trim 5" or no trim on the left side of the opening?

RA

MP

U P

Vestibule 103 -Will there be flooring to be installed where the foundation and eye wash are to be removed as well as the remove the existing gwb and install new for the entire east wall? The Finish Schedule A-6-104 Note #2 remove finishes and provide new gwb painted and wood base at east weall.

Electrical Demo plan Note # D5 & D6 e lighting is to remain i and there are notes for remove all existing lighting in entirety as well as note up to GC to remove all.

RA

MP

U P

UP

DN

Where there are 8" oval ducts up and down the walls, (3-1/4" wide ) is 3-5/8" stud enough to clear the duct?

UP

archite

Cased opening at the Office 109-North Elevation (5/A-6-101) Please confirm the dimension of the wall and trim to be installed,The left side of the wall is this trim 5" or no trim on the left side of the opening?

THE EYE WASH STATION AND DRINKING

FOUNTAIN ARE WALL MOUNTED THEIR

REMOVAL DOES NOT AFFECT THE EXISTING

FLOOR FINISH

FOUNTAIN?

YES, IF PROPERLY INSTALLED.

SEE ALSO MECHANICAL RFI

RESPONSE RE: 7" / 8" OVAL

DUCT

SEE ELEVATION 5/ A-6-101 -

THE TRIM ON THE LEFT OF THE

OPENING IS TRIMMED TO FIT

D5 and D6 are Keyed notes. Keyed notes refer to particular room or area as described in the note. This does not affect the general comment of removing fixtures other than that particular area. Please read the note

Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject: Door X01 Card reader Layer: BID RFI COMMENT

Door # X01 on the Door schedule refers to Card reader. Please confirm where the card readers are located and on the Electrical plans.

Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject: Wall Type 2 Layer: BID RFI COMMENT

Wall type # 2 What type of GWB is to be installed in the Kitchen, Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject: Wall Type #5 at Office 109 North Wall

North wall of Office:

Wall Tag note # 5:

Please confirm the 2-1/2" stud limits, the wall thickness looks larger then 2-1/2" stud Mechanical has a 8" oval duct running the wall ( 3-1/4" wide )

Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject: Elevations at Processing Millwork Layer: BID RFI COMMENT

Elevation 14 & 17 /A-6-101- The The millwork is flipped from what is on the plan.

Door # X01 on the Door schedule refers to Card reader. Please confirm where the card readers are located and on the Electrical plans.

pes:

Wall type # 2 What type of GWB is to be installed in the Kitchen, UP

NS

North wall of Office:

Wall Tag note # 5:

Please confirm the 2-1/2" stud limits, the wall thickness looks larger then 2-1/2" stud Mechanical has a 8" oval duct running the wall ( 3-1/4" wide )

RA

MP

U P

Elevation 14 & 17 /A-6-101- The The millwork is flipped from what is on the plan.

STANDARD GYPSUM BOARD -

SEE SPEC SECTION 095200

PARAGRAPH 3.3

REFER TO FLOOR PLAN AND WALL TYPE 5 -

FACE OF WALL IS FLUSH WITH EXISTING

WALL AT LAN ROOM 108

THE PLAN AND ELEVATIONS ARE

SHOWN CORRECTLY

All new access control devices with the exception the call button and electric strike inbathroom vestibule of the was removed from project during a revision.

Subject: Exterior Elevation Tag Layer: BID RFI COMMENT

North Elevation is not tagged on the plan : 1/A6-101

Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject: HK NOTE Layer: HK QUESTION

( finish schedule A-6-104 note #2) remove finishes and provide with new painted gwb and wood base at the East wall, will there be flooring for the demo of the water fountain and the eye wash?

Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject: Partition Type 2 Layer: BID RFI COMMENT

Partition type 2 : sheet A-3-101 the description on the partition type calls out for sound attenuation blanket and is 2x wood framing, the wall type 2 description on the floor plan sheets does not call the insulation and states either wood or metal stud framing.

Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject: RFI COMMENT-BID Layer: BID RFI COMMENT

Door # 103 Is the sill to remain existing or install new door

North Elevation is not tagged on the plan : 1/A6-101

( finish schedule A-6-104 note #2) remove finishes and provide with new painted gwb and wood base at the East wall, will there be flooring for the demo of the water fountain and the eye wash?

Partition type 2 : sheet A-3-101 the description on the partition type calls out for sound attenuation blanket and is 2x wood framing, the wall type 2 description on the floor plan sheets does not call the insulation and states either wood or metal stud framing.

RA

MP

U P

Door # 103 Is the sill to remain existing or install new door

OK

SEE PREVIOUS RESPONSE

PARTITION TYPE 2 IS TO MATCH EXISTING WALL THICKNESS

AS SHOWN IN PLAN AND IN THE PARTITON TYPES. WOOD OR

METAL FRAMING IS AT CONTRACTOR'S OPTION TO ACHEIVE

THE APPROPRIATE WALL THICKNESS. PROVIDE SOUND

ATTENTUATION AS NOTED

PROVIDE NEW DOOR AND SILL

AS INDICATED ON THE DOOR

SCHEDULE

Subject: RFI COMMENT-BID Layer: BID RFI COMMENT

Partition type #6 in the LAN 108 has 3/4" A/C plywood from floor to ceiling, Sheet ES1-101 has key note # 1 that has 4'- H x 3/4 thick fire rated plywood horizontally on the entire length of the wall as indicated on the plan

Please confirm the Type of plywood and all walls are to receive from floor to ceiling in this room

Page Label: A-1-111 : FIRST FLOOR PLAN Page Index: 7 Subject: Wall Type: Layers of GWB Side Layer: BID RFI COMMENT

Wall types: What sides of the wall get the 2 layers of 5/8" GWB

Page Label: A-1-121 : SECOND FLOOR PLAN Page Index: 8 Subject: Recessed Paper Towel holder

HK Note Recessed paper towel dispenser in exterior wall

8 (6)

Page Label: A-1-121 : SECOND FLOOR PLAN Page Index: 8 Subject: Recessed paper towel holder in exterior wall

HK Note Recessed paper towel dispenser in exterior wall

Partition type #6 in the LAN 108 has 3/4" A/C plywood from floor to ceiling, Sheet ES1-101 has key note # 1 that has 4'- H x 3/4 thick fire rated plywood horizontally on the entire length of the wall as indicated on the plan

Please confirm the Type of plywood and all walls are to receive from floor to ceiling in this room

Wall types: What sides of the wall get the 2 layers of 5/8" GWB

HK Note Recessed paper towel dispenser in exterior wall

HK Note Recessed paper towel dispenser in exterior wall

PROVIDE 3/4" PLYWOOD FROM FLOOR TO CEILING AS

REQUIRED BY THE PARTITION TYPES. PLYWOOD TYPE AS

REQUIRED BY SPEC SETION 061053 PARAGRAPH 2.5

CONTRACTOR'S OPTION

YES, DOES NOT FIT

ON INTERIOR WALLS

YES, DOES NOT FIT

ON INTERIOR WALLS

Page Label: A-1-121 : SECOND FLOOR PLAN Page Index: 8 Subject: Sheet A-2-101 Layer: BID RFI COMMENT

Call out 2/A-2-101.Please confirm this enlarged plan location there is no sheet provided A-2-101 or any other sheets have an enlarged restroom plan.

Page Label: A-1-121 : SECOND FLOOR PLAN Page Index: 8 Subject: Framing vs Duct in wall

HK QUESTION:

what size farming is to be used this only leaves 3/16" either side for the duct to clear 3-5/8" stud wall framing and the duct?

Page Label: A-1-121 : SECOND FLOOR PLAN Page Index: 8 Subject: LOCKER SOFFIT DETAIL

HK Question: What is the locker enclosure soffit detail

Page Label: A-1-121 : SECOND FLOOR PLAN Page Index: 8 Subject: Nurses Counter /Sink/ Ref.

Layer: BID RFI COMMENT

Nurses Room Counter and Sink: Please confirm the Section 4/A-6-103 tagged on elevation 13/A-6-102. Is this the correct section the counter depth is only( 1'-9") 1-'10" with back splash The Plan looks to be 2'-1" counter.

There is an under counter fridge to be installed, will this need power under the counter?

Call out 2/A-2-101.Please confirm this enlarged plan location there is no sheet provided A-2-101 or any other sheets have an enlarged restroom plan.

HK QUESTION:

what size farming is to be used this only leaves 3/16" either side for the duct to clear 3-5/8" stud wall framing and the duct?

HK Question:

What is the locker enclosure soffit detail

Nurses Room Counter and Sink: Please confirm the Section 4/A-6-103 tagged on elevation 13/A-6-102. Is this the correct section the counter depth is only( 1'-9") 1-'10" with back splash The Plan looks to be 2'-1" counter.

There is an under counter fridge to be installed, will this need power under the counter?

PLEASE DELETE CALL OUT

2/A-2-101

THIS IS THE SAME

CONDITION AS 1ST FLOOR -

PLEASE SEE PREVIOUS

RESPONSE

P

PT

PT-1

SEE ELEVATION 1 & 7/ A-6-102.

GYPSUM BOARD ON FRAMING

NURSING

THE DIMENSIONS ON DETAIL 4/ A-6-103 ARE CORRECT.

THE UCR IS PROVIDED BY OWNER AS SHOWN ON

ELEVATION 13/ A-6-103. THE POWER FOR THE UCR IS

SHOWN ON SHEET EP-1-102

EXISTING SLOPING CEILING

Page Label: A-1-201 : BASEMENT REFLECTED CEILING

PLAN

Page Index: 10 Subject: 2nd floor Clg Removal and install Layer: BID RFI COMMENT

General demolition notes # 3 At first and second floor remove all existing ceilings and light in entirety. On the RCP plan there is a note for second floor:

Patch and repair existing ceiling at removed partition and new mechanical and electrical work. At contractors option the existing ceiling may be removed and replaced in its entirety. Please confirm this scope, is this a bid alternate?

10 (3)

Page Label: A-1-201 : BASEMENT REFLECTED CEILING

PLAN

Page Index: 10 Subject: GC TO PROVIDE MOUNTING HT AND LOCATIONS

HK QUESTION? scope of work note: Note # -Basement- GC to provide coordination drawings showing all mechanical and proposed location and mounting hts for light fixtures?-is this typical

Page Label: A-1-201 : BASEMENT REFLECTED CEILING

PLAN

Page Index: 10 Subject: Lighting Fixtures` Layer: BID RFI COMMENT

Please confirm the lighting fixture schedule vs the description the rcp are different, and to refer to the electrical for fixture model numbers and correct sizes of the fixture Example: Processing (101) sheet A-1-211 has symbol and description of 1'-04' surface mounted LED light fixture and the electrical has type A which is 8" x 4' Surface mounted linear LED light fixture

Kitchen (107) 14" square LED and Type C on the electrical lighting is 1x1 slim mounted fixture for am location The exterior and interior lights are the same size and model # for type "C" but called out different on the architectural

Type V on electrical Vanity light is 2' wall mounted linear light and arch rcp has this to be is 4' x 14" wall mounted ligh

General demolition notes # 3 At first and second floor remove all existing ceilings and light in entirety. On the RCP plan there is a note for second floor: Patch and repair existing ceiling at removed partition and new mechanical and electrical work. At contractors option the existing ceiling may be removed and replaced in its entirety. Please confirm this scope, is this a bid alternate?

HK QUESTION? scope of work note: Note # -Basement- GC to provide coordination drawings showing all mechanical and proposed location and mounting hts for light fixtures?-is this typical

Please confirm the lighting fixture schedule vs the description the rcp are different, and to refer to the electrical for fixture model numbers and correct sizes of the fixture Example: Processing (101) sheet A-1-211 has symbol and description of 1'-04' surface mounted LED light fixture and the electrical has type A which is 8" x 4' Surface mounted linear LED light fixture

Kitchen (107) 14" square LED and Type C on the electrical lighting is 1x1 slim mounted fixture for am location The exterior and interior lights are the same size and model # for type "C" but called out different on the architectural

Type V on electrical Vanity light is 2' wall mounted linear light and arch rcp has this to be is 4' x 14" wall mounted ligh

THIS NOT A BID ALTERNATE. EXTENT OF

REMOVAL IS AT THE CONTRACTOR'S

DISCRETION FOR EFFICIENCY OF WORK

REFLECTED CEILING PLAN NOTES

INDICATE THAT THIS IS FOR THE

BASEMENT ONLY

PROVIDE FIXTURES AS SHOWN /

REQUIRED BY ELECTRICAL DRAWINGS

Page Label: A-3-101 : DOOR SCHEDULE, WALL TYPES &

MISC. DETAILS

Page Index: 13 Subject: Door Schedule: Door # 109 Hardware Layer: BID RFI COMMENT

Door # 109 Hardware set # 3 is listed on the schedule. In the specifications Set 3.0 is not used. Please confirm the hardware set

13 (5)

Page Label: A-3-101 : DOOR SCHEDULE, WALL TYPES &

MISC. DETAILS

Page Index: 13 Subject: door size 110

(HK Question) Door # 110 Pair of doors at the closet 110- have to fit door trim then size the opening to fit the doors.

Page Label: A-3-101 : DOOR SCHEDULE, WALL TYPES &

MISC. DETAILS

Page Index: 13 Subject: Partition type 3A Layer: BID RFI COMMENT

Please confirm the location of partition type "3A"

Page Label: A-3-101 : DOOR SCHEDULE, WALL TYPES &

MISC. DETAILS

Page Index: 13 Subject: Door Schedule Door # 110 Layer: BID RFI COMMENT

Door # 110-Would this door need a lock if the owner provided gun safe will be stored in this closet?

Door # 109 Hardware set # 3 is listed on the schedule. In the specifications Set 3.0 is not used.

Please confirm the hardware set

(HK Question) Door # 110 Pair of doors at the closet 110-have to fit door trim then size the opening to fit the doors.

3A Please confirm the location of partition type "3A"

Door # 110-Would this door need a lock if the owner provided gun safe will be stored in this closet?

YES, PROVIDE 5" TRIM EACH SIDE

AND THEN FIT REMAINING OPENING

AS SHOWN ON ELEVATION 8/ 6-101

3A

WALL TYPE 3A OCCURS

AT OFFICE 105. SEE ALSO

DETAIL 2/ A-3-101

DOOR LOCK NOT REQUIRED, THE GUN

SAFE WILL BE LOCKED.

PLEASE REVISE DOOR 109 TO HARDWARE

SET 2.0

Page Label: A-3-101 : DOOR SCHEDULE, WALL TYPES &

MISC. DETAILS

Page Index: 13 Subject: Door Schedule: Door # 203A & 201A Layer: BID RFI COMMENT

Door # 203A & 201A - There is a note door with lever and slide latch is noted on the elevation(8 & 4/A-6-102) the hardware set has privacy lock surface closer and 3 hinge.

Page Label: A-6-101 : INTERIOR ELEVATIONS Page Index: 15 Subject: Lunch Counter Ht Layer: BID RFI COMMENT

Elev. 12/A-6-101 Lunch Counter Section 7/A-6-103 has the top of the counter at 3'-"6'

15 (4)

Page Label: A-6-101 : INTERIOR ELEVATIONS Page Index: 15 Subject: Kitchen 107 Laminate Layer: BID RFI COMMENT

Kitchen 107- Elevations-10 & 11/A-6-101-Plastic Laminate soffit closure , The sections 1 &2 /A-6-103- calls out for PL-3 the elevation has PL-1

Page Label: A-6-101 : INTERIOR ELEVATIONS Page Index: 15 Subject: Offfice Counter Finish Layer: BID RFI COMMENT

Office counter Elevations: 6 & 7/A-6-101 . Please confirm if the counter is SS-3 or plastic Laminate PL-3 as shown in the sections 5 & 6 -A-106

Door # 203A & 201A - There is a note door with lever and slide latch is noted on the elevation(8 & 4/A-6-102) the hardware set has privacy lock surface closer and 3 hinge.

T-4

T-4

KE

Y

PL

AN

Elev.

12/A-6-101 Lunch Counter Section 7/A-6-103 has the top of the counter at 3'-"6'

PL-1

PL-1

SS-1

PL-1

1/4" = 1'-0" office- south elevation7

Kitchen 107- Elevations-10 & 11/A-6-101-Plastic Laminate soffit closure , The sections 1 &2 /A-6-103- calls out for PL-3 the elevation has PL-1

PT-1

SS-3

WB-1

PR-1

PT-1A

SS-3

PT-1A

Office counter Elevations: 6 & 7/A-6-101 . Please confirm if the counter is SS-3 or plastic Laminate PL-3 as shown in the sections 5 & 6 -A-106

PLEASE PROVIDE HARDWARE AS

INDICATED ON ELEVATIONS 4&8/

A-6-102

PLEASE PROVIDE TOP OF

COUNTER AT 3'-6"

THE ELEVATIONS ARE CORRECT - PLEASE

PROVIDE LAMINATE TYPE PL-1

THE SECTIONS ARE CORRECT - PLEASE

PROVIDE PL-3

Page Label: A-6-101 : INTERIOR ELEVATIONS Page Index: 15 Subject: Solid Surface Layer: BID RFI COMMENT

Elevation 15/A-6-101 has SS-3 at the counter,There are conflicts in the sections vs the elevations.

Page Label: A-6-102 : INTERIOR ELEVATIONS Page Index: 16 Subject: Existing Window Layer: BID RFI COMMENT

WC # 201A- (elevation 1-A-6-102) The window existing to remain, the plan vs the elevation show different size windows. Please confirm scope

16 (4)

Page Label: A-6-102 : INTERIOR ELEVATIONS Page Index: 16 Subject: Locker Soffit Layer: BID RFI COMMENT

At the lockers : Please confirm the gwb enclosure ht and construction detail.

The elevations show two different paints PT-2 then PT-1 is there a step in the enclosure soffit?

Page Label: A-6-102 : INTERIOR ELEVATIONS Page Index: 16 Subject: Wall Heater location Layer: BID RFI COMMENT

Wall Heater North Elevation The WH- is on the west wall per mechanical

SS-3

PT-1

PT-1A

Elevation 15/A-6-101 has SS-3 at the counter,There are conflicts in the sections vs the elevations.

PT-1

PT-1A

WC # 201A- (elevation 1-A-6-102) The window existing to remain, the plan vs the elevation show different size windows. Please confirm scope

At the lockers : Please confirm the gwb enclosure ht and construction detail. The elevations show two different paints PT-2 then PT-1 is there a step in the enclosure soffit?

PT-1

PT-1

WB-1

r room- north elevation

Wall Heater North Elevation The WH- is on the west wall per mechanical

THE SECTIONS ON A-6-103 ARE CORRECT.

PLEASE PROVIDE SS-3

THE SCOPE OF WORK IS TO PAINT THE

EXISTING WINDOW AND FRAME AS

INDICATED IN THE ELEVATIONS

PT-1

PT-2

PT-1

PT-1 REFERS TO THE GYP. BD.

FASCIA, PT-2 IS REFERRING TO

THE SLOPED CEILING.

CONSTRUCTION IS A PREVIOUSLY

INDICATED

WH-6 TO BE LOCATED AS

SHOWN THE ARCHITECTURAL

DRAWINGS ELEVATION

8/A-6-102

SLOPING

CEILING

Page Label: A-6-102 : INTERIOR ELEVATIONS Page Index: 16 Subject: BB-1 Location Layer: BID RFI COMMENT

BB-1 is missing from the elevation

Page Label: A-6-103 : MILLWORK DETAILS Page Index: 17 Subject: SS-3 vs SS-1 Solid Surface Layer: BID RFI COMMENT

Section 8 thru 12 /A-6-103 Solid Surface SS-3 is called out on the sections and on the elevation 17/A-6-101- it is called out as SS-1.

17 (5)

Page Label: A-6-103 : MILLWORK DETAILS Page Index: 17 Subject: Counter Ht Layer: BID RFI COMMENT

Detail 4/A-6-103 Please confirm the hts and of the counters is to be 3'-0" ? and the depth of the counter is 1'-9" clear for space?

Do these need to be at ada ht of 2'-10" aff and have counter depth of 2'-0" ?

Page Label: A-6-103 : MILLWORK DETAILS Page Index: 17 Subject: Microwave vent Layer: BID RFI COMMENT

The Microwave Stove vent please confirm where this is connected to on the MEP and Roof plans

WB-1

PT-1

room- north elevation

BB-1 is missing from the elevation

1 1/2" = 1'-0" millwork detail- processing desk8

Section 8 thru 12 /A-6-103 Solid Surface SS-3 is called out on the sections and on the elevation 17/A-6-101- it is called out as SS-1.

tail- locker room sink

Detail 4/A-6-103 Please confirm the hts and of the counters is to be 3'-0" ? and the depth of the counter is 1'-9" clear for space?

Do these need to be at ada ht of 2'-10" aff and have counter depth of 2'-0" ?

The Microwave Stove vent please confirm where this is connected to on the MEP and Roof plans

BB-1 & BB-2 NOT SHOWN ON

ARCHITECTURAL DRAWINGS FOR

CLARITY OF WALL BASE

REQUIREMENTS

SEE PREVIOUS COMMENTS -

THE SECTION IS CORRECT

INDICATING SS-3

THE DIMENSIONS SHOWN ON

THE DRAWINGS ARE CORRECT

CONTRACTOR TO FIELD

DETERMINE HOOD VENTING

Page Label: A-6-103 : MILLWORK DETAILS Page Index: 17 Subject: RFI COMMENT-BID Layer: BID RFI COMMENT

Thermostat controlled cabinet fan. Who furnishes and installs the cabinet fans? Are there specifications and detail for install, Mechanical and Electrical do not have this

Page Label: A-6-103 : MILLWORK DETAILS Page Index: 17 Subject: tel data location in millwork Layer: BID RFI COMMENT

Section 8/A-6-103 Please confirm the tel data is to run in the cabinet or in the wall? sections 9-10-11-12 show this behind the base of the cabinet

Page Label: A-6-104 : ROOM FINISH SCHEDULE Page Index: 18 Subject: CWT vs WT finish Layer: BID RFI COMMENT

CWT-1 is on the schedule and elevations have WT-1, is there a difference, 18 (3)

Page Label: A-6-104 : ROOM FINISH SCHEDULE Page Index: 18 Subject: Vestibule 103 Finish Scope Layer: BID RFI COMMENT

Vestibule 103-Please confirm what walls will get paint, trim and base-The east wall is noted to have new gyp and paint and not shown on the finish schedule, only West wall ?

millwork detail- processing d8

Thermostat controlled cabinet fan. Who furnishes and installs the cabinet fans? Are there specifications and detail for install, Mechanical and Electrical do not have this

-0" ork detail- processing desk

Section 8/A-6-103 Please confirm the tel data is to run in the cabinet or in the wall?

sections 9-10-11-12 show this behind the base of the cabinet

CWT-1 is on the schedule and elevations have WT-1, is there a difference, finis

Vestibule 103-Please confirm what walls will get paint, trim and base-The east wall is noted to have new gyp and paint and not shown on the finish schedule, only West wall ?

THERE ARE A NUMBER OF MANUFACTURERS FOR THESE

FANS - THE MILLWORK CONTRACTOR SHOULD PROVIDE

A FAN APPROPRIATE FOR THE CABINET CONSTRUCTION.

(INTERNET SEARCH - 'THERMOSTATIC COMPUTER

CABINET FANS')

TEL/DATA IS RUN IN WALLS AS SHOWN ON

THE ELECTRICAL DRAWINGS AND FED THRU

DESK WIREWAY AS REQUIRED TO FEED

DEVICES/COMPUTERS

CWT AND WT ARE THE SAME

PLEASE REVISE THE FINISH SCHEDULE

TO PROVIDE PAINT AND BASE ON THE

EAST WALL.

THE NORTH, SOUTH AND WEST WALLS

ARE REMAIN AS EXISTING

EAST

WALL

Page Label: A-6-104 : ROOM FINISH SCHEDULE Page Index: 18 Subject: Womens and Mens Locker Room Paint Layer: BID RFI COMMENT

Women and mens locker room have PT-1 & PT-2 on the North walls only PT-1 is shown in the schedule

Page Label: M-1-101 : BASEMENT HVAC INSTALLATION

PLAN

Page Index: 27 Subject: 8" oval duct Layer: BID RFI COMMENT

8" OVAL up located in the north west corner.Please confirm where this goes to

27 (3)

Please confirm where the BC-1 & BC-2 are located on the equipment scheudles.

Please confirm where EDH-1 is located on the Schedules

Women and mens locker room have PT-1 & PT-2 on the North walls…