CADD Q and A.pdf

PDF 74 KB Posted

Attached to
Contested Aerial Delivery Development (CADD)
Solicitation number
PANAPG25P000000
Issued by

About this file

This document is a Questions and Answers (Q&A) file for the Contested Aerial Delivery Development (CADD) Request for Project Proposal (RPP) issued by the U.S. Army DEVCOM SC under BOTAA 22-01. The Q&A addresses three key inquiries from potential proposers, clarifying critical aspects of the solicitation: the RPP's relationship to the Joint Precision Aerial Delivery System (JPADS) Program of Record, absence of a specific target airspeed requirement, and launch modality expectations. The government specifically noted that the intended launch modality is Airdrop, and no special consideration will be given to alternative flight modalities such as Vertical Take-off and Landing (VTOL) or conventional take-off and landing.

The underlying solicitation seeks pre-proposals for developing a preliminary design for aerial delivery vehicles capable of operating in contested, Anti-aircraft/Area Denial (A2/AD) environments. The objective is to advance aerial delivery vehicle capabilities by increasing deployment range and improving sensor technology to mitigate electronic warfare threats. Proposers are invited to develop preliminary designs that may involve reusing, modifying, or enhancing existing designs, with the ultimate goal of supporting a prototype project for the Soldier Sustainment Directorate's Aerial Delivery Division.

View the file

Other files

File Type Posted
CADD Q and A.pdf PDF
Request for Project Proposal CADD.pdf PDF
RPP Attachment NTDC Certification CADD.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEVCOM SC-BOTAA 22-01

REQUEST FOR PROJECT PROPOSAL (RPP)

Area of Interest: Soldier Sustainment Directorate, Aerial Delivery Division

Prototype: Contested Aerial Delivery Development

QUESTIONS AND ANSWERS

QUESTION 1: Is the CADD RPP tied to the JPADS POR – or this is a new / separate requirement?

ANSWER: The CADD RPP includes work for the JPADS POR

QUESTION 2: In double-checking the RFP documentation I noticed there was no mention of a requirement tied to a target airspeed for the proposed aircraft; is there a target requirement? If so, what is the target airspeed for a proposed airframe?

ANSWER: No target requirement.

QUESTION 3: As far as a capability for this RFP, would a Vertical Take off and Landing (VTOL) aircraft be considered a plus? Or is the requirement independent of flight modality (Conventional Take-off and Landing, VTOL, Glider, etc).

ANSWER: The intended launch modality for this effort is Airdrop. No special consideration will be given for other launch modalities.