CADD Q and A.pdf
PDF 74 KB Posted
- Attached to
- Contested Aerial Delivery Development (CADD)
- Solicitation number
- PANAPG25P000000
About this file
This document is a Questions and Answers (Q&A) file for the Contested Aerial Delivery Development (CADD) Request for Project Proposal (RPP) issued by the U.S. Army DEVCOM SC under BOTAA 22-01. The Q&A addresses three key inquiries from potential proposers, clarifying critical aspects of the solicitation: the RPP's relationship to the Joint Precision Aerial Delivery System (JPADS) Program of Record, absence of a specific target airspeed requirement, and launch modality expectations. The government specifically noted that the intended launch modality is Airdrop, and no special consideration will be given to alternative flight modalities such as Vertical Take-off and Landing (VTOL) or conventional take-off and landing.
The underlying solicitation seeks pre-proposals for developing a preliminary design for aerial delivery vehicles capable of operating in contested, Anti-aircraft/Area Denial (A2/AD) environments. The objective is to advance aerial delivery vehicle capabilities by increasing deployment range and improving sensor technology to mitigate electronic warfare threats. Proposers are invited to develop preliminary designs that may involve reusing, modifying, or enhancing existing designs, with the ultimate goal of supporting a prototype project for the Soldier Sustainment Directorate's Aerial Delivery Division.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CADD Q and A.pdf | ||
| Request for Project Proposal CADD.pdf | ||
| RPP Attachment NTDC Certification CADD.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEVCOM SC-BOTAA 22-01
REQUEST FOR PROJECT PROPOSAL (RPP)
Area of Interest: Soldier Sustainment Directorate, Aerial Delivery Division
Prototype: Contested Aerial Delivery Development
QUESTIONS AND ANSWERS
QUESTION 1: Is the CADD RPP tied to the JPADS POR – or this is a new / separate requirement?
ANSWER: The CADD RPP includes work for the JPADS POR
QUESTION 2: In double-checking the RFP documentation I noticed there was no mention of a requirement tied to a target airspeed for the proposed aircraft; is there a target requirement? If so, what is the target airspeed for a proposed airframe?
ANSWER: No target requirement.
QUESTION 3: As far as a capability for this RFP, would a Vertical Take off and Landing (VTOL) aircraft be considered a plus? Or is the requirement independent of flight modality (Conventional Take-off and Landing, VTOL, Glider, etc).
ANSWER: The intended launch modality for this effort is Airdrop. No special consideration will be given for other launch modalities.