RFP P17PS01913 Fort Vancouver NHS Attachment 1: Statement of Work
FOVA Painting Page 1
STATEMENT OF WORK
Paint Exteriors of Historic Structures
Fort Vancouver National Historic Site
Vancouver, Washington
National Park Service July 2017
FOVA Painting Page 2
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
011100 Summary of Work 012700 Definition of Bid Items 013300 Submittals 013523 Safety Requirements 015300 Barriers 015100 Temporary Services 015700 Temporary Controls 017000 Project Closeout
DIVISION 2 – SITE CONSTRUCTION
028313.00 20 Lead in Construction
DIVISION 9- FINISHES
099113 Painting
FOVA Painting Page 3
SECTION 011100
SUMMARY OF WORK
PART 1: GENERAL
1-1 DESCRIPTION:
A. The work of this contract consists of the preparation, repair, priming, and painting of the exterior of various historic structures. Paint all exposed previously painted exterior sur-faces including doors and windows, trim and molding, siding/walls, fascia, overhangs, rafters and rafter tails, porch and deck vertical and horizontal surfaces, railings, stucco surfaces, foundation cover/skirting, metal work, gutters, downspouts, and stairs. Existing surfaces and coatings exhibit flaking, cracking, bubbling, missing layers of paint from many years of neglect that must be prepared and treated to achieve a satisfactory finish.
Coatings may include primers, lead control primers, oil base and latex paints, solid coat and semi-transparent stains, polyurethanes, and lacquers. Prior to painting, it may be necessary to repair some surfaces to an acceptable condition.
B. Park Description and Location: Fort Vancouver National Historic Site is a unit of the Na-tional Park Service located in Vancouver, WA.
C. Base items: This project includes preparation and painting exterior and associated fea-tures of one (1) building as a base item. See Attachment 2 for descriptions and pictures.
D. Optional items (should funds become available): Perform additional preparation and painting exterior and associated features on optional items/buildings. See Attachment 2 for descriptions and pictures of optional structures.
E. The buildings included in this contract are historic and may contain hazardous materials.
It is highly likely that exterior surfaces contain lead-based paint and should be treated ac-cordingly; refer to Sections 028313.00 20 and 099113, Lead in Construction and Paint-ing.
F. There may be asbestos-containing materials (ACM). NPS will provide lab analysis re-sults for window glazing putty prior to the proposal due date. Removal of any damaged siding or deteriorated/loose glazing putty shall be treated carefully and in accordance with results.
G. Work hours are between 7:00 a.m. and 5:30 p.m., Monday through Friday and no work may occur on Federal Holidays. Any changes to these days and timeframes must be pre-approved by the COR.
H. Maps and park information may be viewed at www.nps.gov/fova.
I. All work is to be performed under a single contract.
http://www.nps.gov/fova
FOVA Painting Page 4
1-2 LOCATION:
A. All buildings are located within Fort Vancouver area, in Vancouver, WA 98661. The administrative address is 612 E. Reserve St, Vancouver, WA 98661. The buildings are all within ½ square mile.
1-3 CONTRACTOR’S USE OF PREMISES:
A. Construction Camp: Establishment of a camp within the park will not be permitted.
B. Contractor shall at all times conduct their operations to ensure the least inconvenience to the public.
C. Materials storage: Storage of construction materials is allowed on-site, at a location des-ignated by the Contracting Officer's Representative. Storage of hazardous materials must meet all federal, state, and local guidelines and regulations. On-site storage of the Con-tractor’s materials does not imply acceptance or protection of them by the Government.
D. Preservation of natural features: Confine all operations to work limits of the project.
Prevent damage to natural surroundings. Provide temporary barriers to protect existing trees and plants and root zones. Restore damaged areas, by repairing or replacing dam-aged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval.
Consult with Contracting Officer and remove agree-on roots and branches that inter-fere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
E. Preservation of existing site/features: The work site is a highly sensitive archeological site. No ground disturbance activities are allowed without written approval of the Con-tracting Officer (CO). Requests to dig, excavate or disturb the ground shall require writ-ten approval from the Contracting Officer 7 days in advance of the proposed work period.
F. Existing Utilities: Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Govern-ment. Overhead power to buildings must be protected or removed and reinstalled as needed to facilitate work.
G. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
H. Contractor must not display signs or advertisements (except those specified herein) on the construction site except with prior approval of the Contracting Officer.
1-4 FIELD VERIFICATION: Field verify all new and existing conditions and dimensions af-fecting the work of this contract before ordering products.
FOVA Painting Page 5
1-5 PROJECT MEETINGS
A. Preconstruction Conference
Before the start of the project, the Contracting Officer will arrange a meeting with the Contractor to be held at NPS offices at Fort Vancouver National Historic Site, Vancou-ver, WA or by teleconference.
B. Progress Meetings
Contractor will convene, chair, and provide notes for bi-weekly progress meetings with
COR.
END
FOVA Painting Page 6
SECTION 012700
DEFINITION OF CONTRACT LINE ITEMS
PART 1 GENERAL
1.1 DESCRIPTION
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another be-gins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
C. For additional information refer to Attachment 2 for pictures, building size, building type, etc.
1.2 CONTRACT LINE ITEMS
CONTRACT LINE ITEM 1 (base) - Prepare and paint exterior surfaces and associated fea-tures of historic Building 786.
CONTRACT LINE ITEMS A through D (options) - Prepare and paint exterior surfaces and associated features of historic buildings shown below.
Option A Building 752 Option B Building 748 Option C Building 746 Option D Building 725
A. All items consist of preparing and painting the exposed previously-painted exterior fea-tures of the historic building, including but not limited to doors and windows, trim and molding, siding/walls, fascia, overhangs, rafters and rafter tails, porch and deck vertical and horizontal surfaces, railings, stucco surfaces, foundation cover/skirting, metal work, gutters, downspouts, and stairs.
B. Paint preparation or removal notes: Contractor will propose paint treatment and removal method(s) that will meet all requirements and minimize damage to the original historic fabric and create sound substrates.
C. Repair Notes: If any portion of the siding has severely deteriorated to the condition that it cannot be nailed, puttied, repaired with epoxy or other such industry standard repairs to bring into a sound condition for painting and must be replaced, the Contractor shall notify the CO immediately. The CO and contractor shall perform an inspection together to de-termine the extent of the deterioration for repair work. A primary goal of historic preser-vation is to retain as much original historic fabric as possible so that repairing rather than replacing is the preferred option. The repair shall match the historic fabrics and styles and be done to the CO’s satisfaction. Include in cost of line item an assumed average of 2%
FOVA Painting Page 7 of surface area of exterior wood components for the building will need repairs or re-placement prior to painting
D. Payment will be made at the contract lump sum price for this line item.
PART 2 PRODUCTS NOT USED.
PART 3 EXECUTION NOT USED.
END OF SECTION
FOVA Painting Page 8
SECTION 013300
SUBMITTALS
1-1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.
1-2 RELATED REQUIREMENTS: Closeout submittals – 01700.
1-3 REQUIRED SUBMITTALS:
A. No on-site work may occur before the COR approves all submittals.
B. All submittals become the property of the Government.
C. Contractor must submit the following to COR at least seven calendar days before the pre-construction meeting.
1. List of proposed subcontractors. If requesting a substitution from subcontractors identified in the accepted proposal, provide supporting documentation related to their qualifications and experience.
2. List of proposed products showing manufacturers’ recommendations for installation.
3. Initial Construction Progress Schedule (see construction project schedule below).
4. Accident Prevention Plan.
5. Lead-Based Paint Treatment Plan.
6. Before beginning work, report to Contracting Officer if any specification require-ments conflict with product manufacturer's warranty requirements.
D. Construction Project Schedule Development and Updates
1. General: The schedule shall include important milestones for achieving completion of the project and shall be in Adobe PDF file. The project schedule shall include sub-mission dates, mock-ups and review periods, and address each building individually through the period of performance. Fully develop the anticipated schedule and submit to the Contracting Officer within 10 days of the Preconstruction meeting.
2. Purpose: The purpose of the project schedule is to ensure coordination, scheduling, and adjustments to scheduling during the period of performance. The project schedule will assist the Contractor and the Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor’s monthly pro-gress payment requests
FOVA Painting Page 9
3. Schedule Development: The project schedule shall cover the entire contract period including showing staggered work at individual buildings over time. In developing the project schedule, the Contractor shall be responsible for ensuring that subcontrac-tor work at all tiers, as well as its own work, is included in the project schedule.
4. The project schedule shall show the sequence and interdependence of activities re-quired for complete performance of the work. Proposed durations assigned to each activity shall be the Contractor's best estimate of time required to complete the activi-ty.
5. Seasonal weather conditions shall be considered and included as best as possible in planning and scheduling the work. The project work is expected to progress in a log-ical manner; preparation and painting work should progress by building in accordance with the scope of work and agreed upon schedule.
6. At the end of any period of work, or if awaiting proper climatic conditions, the build-ing shall be either finished or covered and protected from the elements.
7. Project Schedule Updates: The Contractor shall update the project schedule monthly, coordinating with the COR for adjustments and local logistics/access.
8. Time Extensions: Weather delays shall not automatically mean that an extension of the contract time is warranted or due the Contractor. For time extension considera-tions, the Contractor and COR shall document conditions and causes, and the CO will determine the extent of equitable time adjustments if necessary. Refer to Section F of the contract clauses.
FOVA Painting Page 10
SECTION 013523
SAFETY REQUIREMENTS
1-1 DESCRIPTION: The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1-2 REQUIRED SUBMITTALS
Accident Prevention Plan: At or before the pre-construction conference, the Contractor must submit for approval of the Contracting Officer a written safety plan demonstrating compliance with all applicable federal and state safety regulations.
PART 2: PRODUCTS
2-1 ACCIDENT PREVENTION PLAN
The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable).
2-2 FIRST AID FACILITIES
Provide adequate facilities for the number of employees and the hazards associated with the types of ongoing construction work at the site.
2-3 PERSONNEL PROTECTIVE EQUIPMENT
Meet requirements of applicable ANSI standards.
PART 3: EXECUTION
3-1 The Contractor must comply with all OSHA federal regulations (29 CFR 1910) and
Washington state regulations governing the safety of workers performing the type of work described in this contract.
FOVA Painting Page 11
SECTION 015300
BARRIERS
1-1 DESCRIPTION: The work of this section consists of furnishing, installing, and main-taining barriers to protect existing facilities and the public from painting operations.
PART 2: PRODUCTS
2-1 GENERAL: Material may be new or used, but shall be suitable for intended purpose.
Fences and barriers shall be structurally adequate and neat in appearance.
2-2 BARRICADES AND SIGNS: ANSI D6. 1-78, “Manual if Uniform Traffic Control De-vice: (MUTCD), Part VI.
2-3 LUMBER: Free of nails, large knot holes, and splinters.
2-4 BARRIER TAPE: Banner Guard, imprinted with “CAUTION: CONSTRUCTION
AREA,” manufactured by Reef Industries, Inc., Houston, Texas, or approved equal.
3-1 PROTECTION OF PUBLIC:
A. Fence, barricade, or otherwise block off the immediate work area to prevent unauthor-ized entry to the work area.
B. Erect, and maintain barricades, lights, danger signals, and warning signs in accordance the ANSI D6. 1-78.
C. Cover pipes, hoses, and power lines crossing sidewalks and walkways with troughs using beveled edge boards.
3-2 BARRIER TAPE: Install where directed by COR.
3-3 REMOVAL: Completely remove barriers no longer needed and when approved by COR.
FOVA Painting Page 12
SECTION 015100
TEMPORARY SERVICES
1-1 DESCRIPTION: The work in this section consists of providing temporary services for
Contractor’s performance of the work of this Contract.
PART 2: PRODUCTS
2-1 GENERAL: Temporary material may be new or used, but must be adequate in capacity for the usage, must not create unsafe conditions, and must not violate requirements of ap-plicable codes and standards.
2-2 SANITARY FACILITIES: Contractor shall furnish adequate portable toilet and locate it in an area acceptable to the COR.
2-3 FIRE PROTECTION EQUIPMENT: UL Class2A, 2-1/2 gallon water type, stored-pressure extinguisher and UL Class 10, Type I, 15-pound B:C carbon dioxide extinguish-er.
3-1 ELECTRICAL AND TELEPHONE:
A. NPS will provide electrical service via 20-amp duplex outlet at each building included in this contract, as designated by the COR. The Contractor must use distribution materials provided at Contractor’s expense and installed/removed in a professional and safe man-ner. The Contractor and employees are expected to conserve energy.
B. Telephone: There are no public telephones available at this site. Contractor should rely on cellular phones at this site.
3-2 WATER: Nominal quantities of non-potable water are available on-site.
3-3 SANITARY FACILITIES: Contractor shall locate portable toilet in an area near each work site acceptable to the COR.
3-4 FIRE PREVENTION AND PROTECTION:
A. Hazard Control: The contractor must take all necessary precautions to prevent fire during construction. The Contractor must not store flammable or combustible liquids in non-approved containers. Provide adequate ventilation during use of volatile or noxious sub-stances.
FOVA Painting Page 13
B. The Contractor must provide all equipment and procedures for fire protection on site.
The Contractor must assign a capable and qualified person on site in charge of fire pro-tection at all times. The responsibilities include locating and maintaining fire protective equipment and establishing and maintaining safe working procedures.
C. Smoking: No smoking allowed inside federal buildings or within 25 feet of windows or doors.
FOVA Painting Page 14
SECTION 015700
TEMPORARY CONTROLS
1-1 DESCRIPTION: The work in this section consists of providing temporary controls.
PART 2: PRODUCTS – Not used.
3-1 HOUSEKEEPING:
A. Keep project neat, orderly, and in a safe condition at all times.
B. Provide enough refuse containers for collecting all construction debris.
C. Wet-down dry material and rubbish to prevent blowing dust.
D. Keep volatile wastes in covered containers.
3-2 DISPOSAL:
A. Unless otherwise specified, all salvaged materials become property of the Contractor and shall be disposed of outside the park.
B. Immediately remove hazardous rubbish from project site. Strictly adhere to all hazmat management, collection, storage, disposal and documentation requirements. Place other construction debris in refuse containers at least daily. Dispose of refuse at least biweek-ly, in a legal manner, at public or private dumping area outside the park.
FOVA Painting Page 15
SECTION 017000
PROJECT CLOSEOUT
1-1 DESCRIPTION: The work in this section consists of final cleanup, closeout submittals, and final inspection procedures.
PART 2: PRODUCTS
2-1 CLEANING MATERIALS: As recommended by the manufacturer of surface to be cleaned.
PART 3: EXECUTION
3-1 CLEANING: Remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces of existing facilities that are marred, scratched, or damaged due to the work of this contract to match original condition. Remove paint chips, grease, dirt, stains, foreign mate-rials, and labels from interior and exterior finished surfaces. Sweep paved areas; rake grounds.
At time of final inspection, project shall be thoroughly clean and ready for use.
3-2 CLOSEOUT SUBMITTALS: Submit before final inspection request.
A. Guarantees: As specified in individual sections.
B. Spare Materials: As specified in individual sections.
C. Completed and signed hazardous waste manifest (if any) from treatment and disposal fa-cility.
D. Monitoring results for personal air sampling, if applicable.
3-3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION: Submit written certifica-tion that project, or designated portion of project, is substantially complete, and request in writ-ing, a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.
A. When Contracting Officer determines that the work is substantially complete, they will prepare a list of deficiencies that need to be corrected before final acceptance and issue a Letter of Substantial Completion.
B. If Contracting Officer determines that the work is not substantially complete, they will immediately notify Contractor in writing, stating reasons. After completing work, Con-tractor shall resubmit certification and request a new final inspection.
3-4 ACCEPTANCE OF WORK: After all deficiencies have been corrected, a Letter of Ac-ceptance will be issued.
3-5 POST-CONSTRUCTION INSPECTION: Before expiration of warranty period, Con-tracting Officer will inspect project and notify Contractor in writing of all deficiencies.
FOVA Painting Page 16
SECTION 028313
LEAD IN CONSTRUCTION
05/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI Z88.2(1992) Respiratory Protection
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926.103 Respiratory Protection
29 CFR 1926.21 Safety Training and Education
29 CFR 1926.33 Access to Employee Exposure and Medical Records
29 CFR 1926.55 Gases, Vapors, Fumes, Dusts, and Mists
29 CFR 1926.59 Hazard Communication
29 CFR 1926.62 Lead
29 CFR 1926.65 Hazardous Waste Operations and Emergency Response
40 CFR 260 Hazardous Waste Management System: General
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 262 Standards Applicable to Generators of Hazardous Waste
40 CFR 263 Standards Applicable to Transporters of Hazardous Waste
40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 265 Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 268 Land Disposal Restrictions
FOVA Painting Page 17
40 CFR 745 Lead-Based Paint Poisoning Prevention in Certain Residential Structures
49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communica-tions, Emergency Response Information, and Training Requirements
49 CFR 178 Specifications for Packagings
UNDERWRITERS LABORATORIES (UL)
UL 586(2009) Standard for High-Efficiency Particulate, Air Filter Units
WASHINGTON STATE ADMINISTRATIVE CODES
Chapter 296-155 Safety Standard for Construction Work
Chapter 365-230 Accreditation of lead-based paint training programs and the certification of firms and individuals conducting lead-based paint activities and renovation
1.2 DEFINITIONS
1.2.1 Action Level
Employee exposure, without regard to use of respirators, to an airborne concentration of lead of 30 micrograms per cubic meter of air averaged over an 8 hour period.
1.2.2 Area Sampling
Sampling of lead concentrations within the lead control area and inside the physical boundaries which is representative of the airborne lead concentrations but is not collected in the breathing zone of personnel (approximately 5 to 6 feet above the floor).
1.2.3 Competent Person (CP)
As used in this section, refers to a person employed by the Contractor who is trained in the recognition and control of lead hazards in accordance with current federal, State, and local regu-lations and has the authority to take prompt corrective actions to control the lead hazard. A Certi-fied Industrial Hygienist (CIH) certified by the American Board of Industrial Hygiene or a Certi-fied Safety Professional (CSP) certified by the Board of Certified Safety Professionals is the best choice.
1.2.4 Contaminated Room
Refers to a room for removal of contaminated personal protective equipment (PPE).
1.2.5 Decontamination Shower Facility
FOVA Painting Page 18
That facility that encompasses a clean clothing storage room, and a contaminated clothing stor-age and disposal rooms, with a shower facility in between.
1.2.6 High Efficiency Particulate Arrestor (HEPA) Filter Equipment
HEPA filtered vacuuming equipment with a UL 586 filter system capable of collecting and re-taining lead-contaminated particulate. A high efficiency particulate filter demonstrates at least
99.97 percent efficiency against 0.3 micron or larger size particles.
1.2.7 Lead
Metallic lead, inorganic lead compounds, and organic lead soaps. Excludes other forms of organ-ic lead compounds.
1.2.8 Lead Control Area
A system of control methods to prevent the spread of lead dust, paint chips or debris to adjacent areas that may include temporary containment, floor or ground cover protection, physical bound-aries, and warning signs to prevent unauthorized entry of personnel. HEPA filtered local exhaust equipment may be used as engineering controls to further reduce personnel exposures or build-ing/outdoor environmental contamination.
1.2.9 Lead Permissible Exposure Limit (PEL)
Fifty micrograms per cubic meter of air as an 8 hour time weighted average as determined by 29 CFR 1926.62. If an employee is exposed for more than eight hours in a work day, the PEL shall be determined by the following formula:
PEL (micrograms/cubic meter of air) = 400/No. hrs. worked per day
1.2.10 Material Containing Lead/Paint with Lead (MCL/PWL)
Any material, including paint, which contains lead as determined by the testing laboratory using a valid test method. The requirements of this section does not apply if no detectable levels of lead are found using a quantitative method for analyzing paint or MCL using laboratory instru-ments with specified limits of detection (usually 0.01%). An X-Ray Fluorescence (XRF) in-strument is not considered a valid test method.
1.2.11 Personal Sampling
Sampling of airborne lead concentrations within the breathing zone of an employee to determine the 8 hour time weighted average concentration in accordance with 29 CFR 1926.62. Samples shall be representative of the employees' work tasks. Breathing zone shall be considered an area within a hemisphere, forward of the shoulders, with a radius of and centered at the nose or mouth of an employee.
1.2.12 Physical Boundary
FOVA Painting Page 19
Area physically roped or partitioned off around lead control area to limit unauthorized entry of personnel.
1.3 DESCRIPTION
1.3.1 Description of Work
Construction activities impacting PWL or material containing lead which are covered by this specification include the removal of lead based paint on all components of exterior siding, win-dows, doors, and loose/deteriorated glazing putty.
1.3.2 Coordination with Other Work
The contractor shall coordinate with work being performed in adjacent areas. Coordination pro-cedures shall be explained in the Plan and shall describe how the Contractor will prevent lead exposure to the public and Government personnel performing work unrelated to lead activities.
1.4 SUBMITTALS
SD-01 Preconstruction Submittals:
a) Occupational and Environmental Assessment Data Report (if objective data is used to justify excluding the initial occupational exposure assessment);
b) Lead Compliance Plan including CP approval (signature, date, and certification number);
c) Competent Person qualifications (submit with quote);
d) Training Certification of workers and supervisors;
e) Lead waste management plan;
f) Certification of Medical Examinations;
SD-06 Test Reports
a) Sampling results;
b) Occupational and Environmental Assessment Data Report;
SD-07 Certificates (submit with quote)
a) Testing laboratory qualifications;
b) Third party consultant qualifications;
FOVA Painting Page 20
SD-11 Closeout Submittals
a) Completed and signed hazardous waste manifest from treatment or disposal facility;
1.5 QUALITY ASSURANCE
1.5.1 Qualifications
1.5.1.1 Competent Person (CP)
Submit name, address, and telephone number of the CP selected to perform responsibilities spec-ified in paragraph entitled "Competent Person (CP) Responsibilities." Provide documented con-struction project-related experience with implementation of OSHA's Lead in Construction stand-ard (29 CFR 1926.62) which shows ability to assess occupational and environmental exposure to lead, experience with the use of respirators, personal protective equipment and other exposure reduction methods to protect employee health. Submit proper documentation that the CP is trained and certified in accordance with federal, State and local laws. The competent person shall be licensed lead-based paint abatement Supervisor/Project Designer in the State of Wash-ington.
1.5.1.2 Training Certification
Submit a certificate for each worker and supervisor, signed and dated by the accredited training provider, stating that the employee has received the required lead training specified in 29 CFR 1926.62(l)and is certified to perform or supervise deleading, lead removal or demolition activi-ties in the state of Washington.
1.5.1.3 Testing Laboratory
Submit the name, address, and telephone number of the testing laboratory selected to perform the air and wipe analysis, testing, and reporting of airborne concentrations of lead. Use a laboratory participating in the EPA National Lead Laboratory Accreditation Program (NLLAP) by being accredited by either the American Association for Laboratory Accreditation (A2LA) or the American Industrial Hygiene Association (AIHA) and that is successfully participating in the Environmental Lead Proficiency Analytical Testing (ELPAT) program to perform sample analysis. Laboratories selected to per-form blood lead analysis shall be OSHA approved.
1.5.1.4 Third Party Consultant Qualifications
Submit the name, address and telephone number of the third party consultant selected to perform the wipe sampling for determining concentrations of lead in dust. Submit proper documentation that the consultant is trained and certified as an inspector technician or inspector/risk assessor by the USEPA authorized State (or local) certification and accreditation program.
1.5.2 Requirements
FOVA Painting Page 21
1.5.2.1 Competent Person (CP) Responsibilities
a. Verify training meets all federal, State, and local requirements.
b. Review and approve Lead Compliance Plan for conformance to the applicable referenced standards.
c. Continuously inspect PWL or MCL work for conformance with the approved plan.
d. Perform (or oversee performance of) air sampling. Recommend upgrades or downgrades (whichever is appropriate based on exposure) on the use of PPE (respirators included) and en-gineering controls.
e. Ensure work is performed in strict accordance with specifications at all times.
f. Control work to prevent hazardous exposure to human beings and to the environment at all times.
g. Supervise final cleaning of the lead control area, take clearance wipe samples if necessary;
review clearance sample results and make recommendations for further cleaning.
h. Certify the conditions of the work as called for elsewhere in this specification.
1.5.2.2 Lead Compliance Plan
a. Submit with the proposed paint removal method, name and qualifications of the Competent Person, proposed worker’s exposure monitoring protocols (actual or objective data) with bid.
b. Submit at preconstruction meeting, a detailed job-specific plan of the work procedures to be used. The plan shall include a sketch showing the location, size, and details of lead control areas, critical barriers, physical boundaries, location and details of decontamination facilities, viewing ports, and mechanical ventilation system. Include a description of equipment and materials, work practices, controls and job responsibilities for each activity from which lead is emitted. Include in the plan, eating, drinking, smoking, hygiene facilities and sanitary procedures, interface of trades, sequencing of lead related work, collected waste water and dust containing lead and de-bris, air sampling, respirators, personal protective equipment, and a detailed description of the method of containment of the operation to ensure that lead is not released outside of the lead control area or into building interior. Include site preparation, cleanup and clearance procedures.
Include occupational and environmental sampling, training and strategy, sampling and analysis strategy and methodology, frequency of sampling, duration of sampling, and qualifications of sampling personnel in the air sampling portion of the plan.
1.5.2.3 Occupational and Environmental Assessment Data Report
FOVA Painting Page 22
If the Contractor elects to conduct initial monitoring, submit occupational and environmental sampling results to the Contracting Officer within three working days of collection, signed by the testing laboratory employee performing the analysis, the employee that performed the sampling, and the CP.
In order to reduce the full implementation of 29 CFR 1926.62, the Contractor shall provide doc-umentation. Submit a report that supports the determination to reduce full implementation of the requirements of 29 CFR 1926.62 and supporting the Lead Compliance Plan.
a. The initial monitoring shall represent each job classification, or if working conditions are similar to previous jobs by the same employer, provide previously collected exposure data that can be used to estimate worker exposures per 29 CFR 1926.62. The data shall represent the worker's regular daily exposure to lead for stated work.
b. Submit worker exposure data gathered during the task based trigger operations of 29 CFR
1926.62 with a complete process description. This includes manual demolition, manual and mechanical scraping and sanding, heat gun.
c. The initial assessment shall determine the requirement for further monitoring and the need to fully implement the control and protective requirements including the lead compliance plan per 29 CFR 1926.62.
1.5.2.4 Medical Examinations
Initial medical surveillance as required by 29 CFR 1926.62 shall be made available to all em-ployees exposed to lead at any time (1 day) above the action level. Full medical surveillance shall be made available to all employees on an annual basis who are or may be exposed to lead in excess of the action level for more than 30 days a year or as required by 29 CFR 1926.62. Ade-quate records shall show that employees meet the medical surveillance requirements of 29 CFR 1926.33, 29 CFR 1926.62 and 29 CFR 1926.103. Provide medical surveillance to all personnel exposed to lead as indicated in 29 CFR 1926.62. Maintain complete and accurate medical rec-ords of employees for the duration of employment plus 30 years.
1.5.2.5 Training
Train each employee performing work that disturbs lead, who performs MCL/PWL disposal, and air sampling operations prior to the time of initial job assignment and annually thereafter, in ac-cordance with 29 CFR 1926.21, 29 CFR 1926.62, and State and local regulation.
1.5.2.6 Respiratory Protection Program
a. Provide each employee required to wear a respirator a respirator fit test at the time of initial fitting and at least annually thereafter as required by 29 CFR 1926.62.
b. Establish and implement a respiratory protection program as required by ANSI Z88.2, 29 CFR 1926.103, 29 CFR 1926.62, and 29 CFR 1926.55.
FOVA Painting Page 23
1.5.2.7 Hazard Communication Program
Establish and implement a Hazard Communication Program as required by 29 CFR 1926.59.
1.5.2.8 Lead Waste Management
The Lead Waste Management Plan shall comply with applicable requirements of federal, State, and local hazardous waste regulations and address:
a. Identification and classification of wastes associated with the work.
b. Estimated quantities of wastes to be generated and disposed of.
c. Names and qualifications of each contractor that will be transporting, storing, treating, and disposing of the wastes. Include the facility location and operator and a 24-hour point of con-tact.
d. Names and qualifications (experience and training) of personnel who will be working on-site with hazardous wastes.
e. List of waste handling equipment to be used in performing the work, to include cleaning, volume reduction, and transport equipment.
f. Spill prevention, containment, and cleanup contingency measures including a health and safety plan to be implemented in accordance with 29 CFR 1926.65.
g. Work plan and schedule for waste containment, removal and disposal. Proper containment of the waste includes using acceptable waste containers (e.g., 55-gallon drums) as well as proper marking/labeling of the containers. Wastes shall be cleaned up and containerized dai-ly.
1.5.3 Pre-Construction Conference
Along with the CP, meet with the Contracting Officer to discuss in detail the Lead Waste Man-agement Plan and the Lead Compliance Plan, including procedures and precautions for the work.
1.6 EQUIPMENT
1.6.1 Respirators
Furnish appropriate respirators approved by the National Institute for Occupational Safety and Health (NIOSH), Department of Health and Human Services, for use in atmospheres containing lead dust, fume and mist. Respirators shall comply with the requirements of 29 CFR 1926.62.
1.6.2 Special Protective Clothing
FOVA Painting Page 24
Furnish personnel who will be exposed to lead-contaminated dust with proper disposable or un-contaminated, reusable protective whole body clothing, head covering, gloves, eye, and foot coverings as required by 29 CFR 1926.62. Furnish proper disposable plastic or rubber gloves to protect hands. Reduce the level of protection only after obtaining approval from the CP.
1.6.3 Rental Equipment Notification
If rental equipment is to be used during PWL or MCL handling and disposal, notify the rental agency in writing concerning the intended use of the equipment.
1.6.4 Vacuum Filters
UL 586 labeled HEPA filters.
1.7 PROJECT/SITE CONDITIONS
1.7.1 Protection of Existing Work to Remain
Perform work without damage or contamination of adjacent areas. Where existing work is dam-aged or contaminated, restore work to its original condition or better as determined by the Con-tracting Officer.
PART 2 PRODUCTS Not used.
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Lead Control Area
a. Physical Boundary - Provide physical boundaries around the lead control area by roping off the area designated in the work plan or providing curtains, portable partitions or other enclo-sures to ensure that lead will not escape outside of the lead control area.
b. Warning Signs - Provide warning signs at approaches to lead control areas. Locate signs at such a distance that personnel may read the sign and take the necessary precautions before en-tering the area. Signs shall comply with the requirements of 29 CFR 1926.62.
3.1.2 Decontamination Shower Facility
Provide clean and contaminated change rooms and shower facilities in accordance with this specification and 29 CFR 1926.62.
3.1.3 Eye Wash Station
Where eyes may be exposed to injurious corrosive materials, suitable facilities for quick drench-ing or flushing of the eyes shall be provided within the work area.
FOVA Painting Page 25
3.1.4 Mechanical Ventilation System
a. To the extent feasible, use local exhaust ventilation or other collection systems, approved by the CP. Local exhaust ventilation systems shall be evaluated and maintained in accordance with 29 CFR 1926.62.
b. Vent local exhaust outside the building and away from building entrance or ensure system is connected to HEPA filters.
c. Use locally exhausted, power actuated tools or manual hand tools.
3.1.5 Personnel Protection
Personnel shall wear and use protective clothing and equipment as specified herein. Eating, smoking, or drinking or application of cosmetics is not permitted in the lead control area. No one will be permitted in the lead control area unless they have been appropriately trained and provid-ed with protective equipment.
3.2 ERECTION
3.2.1 Lead Control Area Requirements
Establish a lead control area by completely establishing barriers and physical boundaries around the area or structure where PWL or MCL removal operations will be performed.
Full containment - if required by the CP, contain removal operations by the use of critical barri-ers and HEPA filtered exhaust, or a negative pressure enclosure system with decontamination facilities and with HEPA filtered exhaust.
3.3 APPLICATION
3.3.1 Lead Work
Perform lead work in accordance with approved Lead Compliance Plan.
3.3.2 Paint with Lead or Material Containing Lead Removal
Acceptable removal methods:
1. Low-heat stripping with heat guns or heat plates (less than 450° F, round-edge scraper).
2. Infrared heat and scraping (round-edge scraper).
4. Finish sanding using mechanical sanders with HEPA vacuum.
3.5 CLEANING AND DISPOSAL
3.5.1 Cleanup
FOVA Painting Page 26
Maintain surfaces of the lead control area free of accumulations of dust and debris. Restrict the spread of dust and debris; keep waste from being distributed over the work area. Do not dry sweep or use pressurized air to clean up the area. At the end of each shift, clean the controlled area of visible contamination by vacuuming with a HEPA filtered vacuum cleaner, wet mopping the area and wet wiping the area as indicated by the Lead Compliance Plan.
3.5.2 Disposal
a. All material, whether hazardous or non-hazardous shall be disposed in accordance with all laws and provisions and all federal, State or local regulations. Ensure all waste is properly characterized. The result of each waste characterization (TCLP for RCRA materials) will dic-tate disposal requirements.
b. Contractor is responsible for segregation of waste. Collect lead-contaminated waste, scrap, debris, bags, containers, equipment, and lead-contaminated clothing that may produce air-borne concentrations of lead particles. Label the containers in accordance with 29 CFR
1926.62 and 40 CFR 261.
c. Dispose of lead-contaminated material classified as hazardous waste at an EPA or State ap-proved hazardous waste treatment, storage, or disposal facility off Government property.
d. Store waste materials in U.S. Department of Transportation (49 CFR 178) approved 55 gal-lon drums. Properly label each drum to identify the type of waste (49 CFR 172) and the date the drum was filled. For hazardous waste, the collection drum requires marking/labeling in accordance with 40 CFR 262 during the accumulation/collection timeframe. The Contracting Officer or an authorized representative will assign an area for interim storage of waste-containing drums. Do not store hazardous waste drums in interim storage longer than 90 cal-endar days from the date affixed to each drum.
e. Handle, store, transport, and dispose lead or lead-contaminated waste in accordance with 40 CFR 260, 40 CFR 261, 40 CFR 262, 40 CFR 263, 40 CFR 264, and 40 CFR 265. Comply with land disposal restriction notification requirements as required by 40 CFR 268.
3.5.2.1 Disposal Documentation
Submit written evidence to demonstrate the hazardous waste treatment, storage, or disposal facil-ity (TSD) is approved for lead disposal by the EPA, State or local regulatory agencies. Submit one copy of the completed hazardous waste manifest, signed and dated by the initial transporter in accordance with 40 CFR 262. Contractor shall provide a certificate that the waste was accept-ed by the disposal facility.
3.5.2.2 Payment for Hazardous Waste
Payment for disposal of hazardous and non-hazardous waste will not be made until a signed copy of the manifest from the treatment or disposal facility certifying the amount of lead-containing
FOVA Painting Page 27 materials or non-hazardous waste delivered is returned and a copy is furnished to the Govern-ment.
FOVA Painting Page 28
SECTION 099113
EXTERIOR PAINTING
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes surface preparation and the application of paint systems on the following exterior substrates:
1. Concrete or other Cementous surfaces
2. Wood.
3. Metals of all types.
B. Paint all exposed surfaces whether or not colors are designated in schedules, except sandstone and masonry blocks. Where an item or surface is not specifically mentioned, paint the same as similar adjacent materials or surfaces. If color or finish is not designated, the COR will select from standard colors or finishes available.
C. Do not paint closed any operational/function window, door or equipment covers.
1.2 DEFINITIONS
A. Gloss Level 1 (matte or flat): Not more than 5 units at 60 degrees and 10 units at 85 degrees, according to ASTM D 523.
B. Gloss Level 2 (velvet): Not more than 10 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D 523.
C. Gloss Level 3 (eggshell): 10 to 25 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D 523.
D. Gloss Level 4 (satin): 20 to 35 units at 60 degrees and not less than 35 units at 85 degrees, according to ASTM D 523.
E. Gloss Level 5 (semi-gloss): 35 to 70 units at 60 degrees, according to ASTM D 523.
F. Gloss Level 6 (gloss): 70 to 85 units at 60 degrees, according to ASTM D 523.
G. Gloss Level 7 (high gloss): More than 85 units at 60 degrees, according to
ASTM D 523.
H. VOC Ranges: Ranges listed are as prescribed by Master Painters Institute (MPI), Architectural Painting Specification Manual as follows (in grams/liter):
1. VOC Range E3: < 51 g/l.
2. VOC Range E2: 51-100 g/l.
3. VOC Range E1: 101-200 g/l.
FOVA Painting Page 29
4. VOC Range E0: Outside range.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product. Include preparation requirements and application instructions.
B. Samples for Verification: For each type of paint system and each color and gloss of topcoat.
1. Submit Samples on rigid backing, 8 inches (200 mm) square.
2. Step coats on Samples to show each coat required for system.
3. Label each coat of each Sample.
4. Label each Sample for location and application area.
C. Product List: For each product indicated, include the following:
1. Cross-reference to paint system and locations of application areas. Use same designations indicated in schedules.
2. Printout of current "MPI Approved Products List" for each product category specified, with the proposed product highlighted.
3. VOC content.
1.4 MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.
1. Paint: 5 percent, but not less than 1 gal. (3.8 L) of each material and color applied.
1.5 QUALITY ASSURANCE
A. Single-Source Responsibility: Provide primers and undercoat paint produced by the same manufacturer as the finish coats.
B. Mockups: Create a mockup for each building under contract. The purpose of the mockups is to demonstrate aesthetic effects and execution of surface preparation, come to a mutual agreement of the level of surface preparation to be achieved and paint system performance. Mockups shall comply with the following requirements, using materials indicated for the completed Work:
1. Mockup to be 8-foot by 8-foot in area at each individual building. Contracting
Officer to select location.
2. Notify Contracting Officer seven days in advance of dates and times when mockups will be constructed.
3. Perform surface preparation on wood siding in location of heavily deteriorated paint. Demonstrate the proposed range of aesthetic effects and workmanship.
4. Obtain Contracting Officer's approval of mockups before starting surface preparation on remaining buildings.
FOVA Painting Page 30
5. Maintain mockup during construction in an undisturbed condition as a standard for judging the completed Work.
6. Approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45 deg F (7 deg C).
1. Maintain containers in clean condition, free of foreign materials and residue.
2. Remove rags and waste from storage areas daily.
1.7 FIELD CONDITIONS
A. Apply paints only when temperature of surfaces to be painted and ambient air temperatures are between 50 and 95 deg F (10 and 35 deg C).
B. Do not apply paints in snow, rain, fog, or mist; when relative humidity exceeds 85 percent; at temperatures less than 5 deg F (3 deg C) above the dew point; or to damp or wet surfaces.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:
1. Benjamin Moore (BM);
2. ICI Paint Stores, Inc. (ICI);
3. Sherwin Williams.
2.2 PAINT, GENERAL
A. MPI Standards: Provide products that comply with MPI standards indicated and that are listed in its "MPI Approved Products List."
B. Material Compatibility:
1. Provide materials for use within each paint system that are compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.
2. For each coat in a paint system, provide products recommended in writing by manufacturers of topcoat for use in paint system and on substrate indicated.
C. VOC Content: Provide materials that comply with VOC limits of authorities having jurisdiction.
FOVA Painting Page 31
2.3 BLOCK FILLERS
Block Filler, Latex, Interior/Exterior: MPI #4.
2.4 PRIMERS
A. Primers for wood substrate and stucco: water borne, exterior application, Sherwin Williams PrepRite ProBlock, Peel Bonding primer, or an approved equal. For other surfaces: alkyd enamel, Sherwin Williams A11 or an approved equal.
B. Primer alternative: “Ecobond”, a product manufactured by, MT2, LLC - Metals Treatment Technologies (14045 West 66th Avenue, Arvada, CO 80004; 888-435-6645 toll free, or an approved equivalent.
2.5 UNDERCOAT MATERIALS
Undercoat Materials: Provide factory-formulated latex undercoat materials that are compatible with the primer and finish coats indicated and by the same manufacturer.
2.6 EXTERIOR FINISH PAINT MATERIAL
A. Finish Paint for wood: Provide factory-formulated latex finish-coat materials that are compatible with the undercoats indicated.
VOC Content: E Range of E2-E3.
B. Exterior Acrylic Emulsion: Quick-drying, flat, acrylic paint.
C. Latex, Exterior Semi-Gloss (Gloss Level 5): MPI #11.
D. Other surfaces: alkyd enamel, Sherwin Williams A11 or an approved equal
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.
B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:
Wood: 15 percent.
Concrete: 12 percent.
C. Verify and document for COR suitability of substrates, including surface conditions and compatibility with existing finishes and primers.
FOVA Painting Page 32
D. Proceed with coating application only after unsatisfactory conditions have been corrected. Application of coating indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Comply with manufacturer's written instructions and recommendations in "MPI Manual" applicable to substrates and paint systems indicated.
B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.
After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection.
C. Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease, and incompatible paints and encapsulants.
D. Repair Notes: If any portion of the siding has severely deteriorated to the condition that it…