P16PS00262_Amendment_3.pdf

PDF 93 KB Posted

Attached to
Mariposa Grove Restoration Phase 5, Yosemite National Park, YOSE 206431
Solicitation number
P16PS00262
Issued by

About this file

Amendment Three

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

P16PS00262

x x

3 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

YOSE 20643104/28/2016000003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/04/2016

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Yosemite National Park - YOSE 206431

Mariposa Grove Restoration Phase 5

Mariposa County, CA

This amendment clarifies brand name items, answers questions received, and extends the due date for questions and proposals. See attached.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Sarah Mcmahon

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

P16PS00262

Amendment Three

In order to clarify brand name items and answer questions received, the above numbered solicitation is hereby amended as follows:

1. Throughout the specifications and drawings for this project, there are references to specific brand name standard products and/or services. This amendment clarifies that an equal product or service can be submitted as a substitution for any stated brand name. However, the substitute products or services need to be requested with the offeror’s proposal (see the form included in the proposal submission package) with the supporting data in accordance with specification section 01 33 23, 1.3E “Submittal Procedures--Approved Equals" and FAR 52.211-6. Any questions regarding the salient characteristics of any listed brand name product or service must be submitted by 5 May 2016.

2. The following questions have been received and answers provided.

Q6: SECTION 01 55 26 - TRAFFIC CONTROL, Under 2.2 Other Traffic Control Devices calls to use a paint that is no longer used in California. Please advise.

A6. Revise Specification Section 01 55 26 - Traffic Control, Road Striping Paint 2.2D-1 to say:

"1. Paint shall meet Federal Specifications TT-P-1952E, Type 2, white, yellow or blue traffic rated paint."

Q7: The minimum binder content for asphalt concrete at 5.8% seems extremely high and will cause flushing. Can you reduce the requirement to at least at 5.3% for 1/2 mix, and 5.0% for a 3/4? This is compatible to local DOT specifications.

Also, will a liquid Antistrip be allowed instead of lime marination to mitigate for any stripping?

A7: No. A good mix design with the 5.85 oil content will not flush and the higher oil content and lime treatment have performed better in Yosemite.

Q8: Per Section 31 10 00, Paragraph 3.6 C, Duff and Topsoil Stripping, topsoil is to be stripped 6-12 inches which conflicts with Sheets C5.01 to C5.04 which call out a minimum of 12 inches. What is the correct stripping depth and can the Contractor reduce the depth of stripping shown on the plan sheets to the lesser dimension? Also the designated top soil stockpiles have space limitations and will not accommodate the 10,000 CY of stripping at 12” or even 6” in depth if limited to a height to 72 inches, will the Government provide additional stockpile locations within the Contractors work area since by Paragraph 1.6A , Material Ownership, the stripped topsoil remains the property of the Government.

A8: The depth varies from 6" to 12", so you can reduce the minimum amount of top soil stripping to 6", but the maximum amount will still remain at 12". The Government will provide additional stockpile locations within 6 miles of the Contractor's work area.

3. The due date for questions has been extended until 5 May 2016.

4. The due date for proposals has been extended until 1400 MT on 12 May 2016.

5. All other terms and conditions remain unchanged.