Text version
(x)
P15PS00175
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
MM1
Springfield IL 62701-1905 413 S. Eighth Street DOI, NPS, MWR - Missouri MABO-LIHO
PMM
St Louis MO 63102 11 North 4th Street NPS, MWR - Missouri MABO
01/22/2015000002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
12/30/2014
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
RFQ P15PS00175 - COMBINED SYNOPSIS SOLICITATION
REPRODUCTION DRAPERIES FOR LINCOLN HOME
AMENDMENT 0002:
The purpose of this amendment is to provide the Government's responses to various questions received from interested contractors, and to inform quoters of changes and information added to the solicitation by the Government.
Should any of the information contained in this Amendment 0002 or its attachments contradict, change, add, or delete any work, specifications, or instructions described in
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
KATHRYN LOGSDON
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
the original solicitation, the information contained in this Amendment 0002 and its attachments is deemed to take precedence and will supersede that specific information found to be contrary to, or lacking from the original solicitation, except when a subsequent amendment has been issued for clarification or correction.
Other exceptions include apparent clerical errors, and minor informalities or irregularities that are merely a matter of form and not of substance.
As per Amendment 0001, the closing date and time for submission of quotes was amended from
Thursday, January 22, 2015 at 2:00 p.m. central time to FRIDAY, FEBRUARY 6, 2015 AT 2:00 P.M.
CENTRAL TIME.
AI = ADDITIONAL INFORMATION BY GOVERNMENT
Q = QUESTION FROM CONTRACTOR
R = GOVERNMENT'S RESPONSE TO CONTRACTOR'S
QUESTION
AI-1. For clarification:
a. Sitting and Dining Room Draperies. The green moire taffeta, embossed watered pattern fabric that is specified in Attachment 1
(Specifications and Scope of Work) is that which was used in the fabrication of the drapes currently hanging in the Lincoln Home Sitting
Room and Dining Room. It was purchased in 1988 from the source identified in Attachment 10
(Drapery Sources - 1988). The green moire taffeta may or may not be historically accurate as there are no photos or information on record which indicate such. The only information known by the Lincoln Home Curator that exists, is the black and white drawing, Attachment 3
(Illustration of Lincoln Home Sitting Room -
1860). The Park is seeking a fabric and color, in appearance, to those drapes pictured in the
Sitting and Dining Rooms' photos in Attachment 7.
If this can be accomplished with an alternative fabric which is less expensive than the moire taffeta fabric, but same in color; that will be acceptable. Note: Park will make final selection based on samples provided by the contractor to
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
3 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
whom the contract is awarded. The Additional
Requirements found in Attachment 1, Section III, still apply.
b. 2nd Floor Bedrooms, Front and Back Hall.
The sheer dimity fabric in white that is specified in Attachment 1 (Specifications and
Scope of Work) is that which was used in the fabrication of the window coverings currently hanging in those areas of the Lincoln Home. It was purchased from the source identified in
Attachment 10 (Drapery Sources - 1988). This dimity fabric may or may not be historically accurate as there are no photos or information on record which indicate such. The only information known by the Lincoln Home Curator that exists, are the black and white drawings, Attachments 4 and 5 (Illustration of 2nd floor bedroom curtain style, and Illustration of simple 19th century curtain style). The Park is seeking a sheer dimity fabric in white to that which is pictured in Attachment 7 for the 2nd Floor Bedrooms and
Front and Back Hall. For this fabric, Attachment
1 states, a subtle white on white pattern is acceptable, preferably with a thin stripe. Note:
Park will make final selection based on samples provided by the contractor to whom the contract is awarded. The Additional Requirements found in Attachment 1, Section III, still apply.
c. Kitchen: The sheer batiste fabric that is identifed in Attachment 10 (Drapery Sources -
1988) is that which was used in the fabrication of the window coverings currently hanging in the kitchen. The sheer batiste fabric is not specified for this kitchen curtain requirement.
Rather, as specified in Attachment 1
(Specification and Scope of Work), the curtains for the kitchen will be of the same fabric as that used in the fabrication of the curtains for the 2nd floor bedrooms, and front and back hall.
The Additional Requirements found in Attachment
1, Section III, still apply.
d. Front and Rear Parlors: The wool and silk damask that is specified in Attachment 1
(Specifications and Scope of Work) is that which was used in the fabrication of the window coverings currently hanging in the Front and Rear
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
4 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
Parlors of the Lincoln Home. It was purchased from the source identified in Attachment 10
(Drapery Sources - 1988). It is known that this damask is historically accurate. The Park is seeking a reproduction of that fabric in the fabrication of the draperies. However, because of the expense of that fabric, at one time
(several years ago) Scalamandre, who was the source of that fabric, suggested a fabric that would replicate the look, but it would substitute the silk with an alternative material as a cost-cutting measure. It is not known if that is still a possibility; therefore, it is encouraged that contractors submit two quotes; that is, one quote that includes the utilization of the exact wool and silk damask fabric as specified, and one quote that includes the alternative material, if possible. The Additional Requirements found in
Attachment 1, Section III, still apply.
AI-2. Although the measurements' information provided by the Government in the solicitation and in the below Government's Responses, the
Contractor is responsible for securing correct measurements needed to fabricate the window coverings. The Contractor awarded the contract should anticipate at least two site visits to
Lincoln Home; one for verification of measurements and site visit, and one for installation of completed window treatments.
Travel costs and arrangements are the responsibility of the Contractor and should be calculated into the Contractor's quote.
AI-3. Attachment 11 (Contractor's Proposed
Milestone Dates) has been revised, and is an attachment to this Amendment. Contractor is to complete the Revised Attachment 11 and submit with their quote.
AI-4. Attachment 12 (Quotation Submittal and
Instructions) has been revised, and Addendum A to
Attachment 12 has been added. Both are attached to this Amendment. Contractor is to complete the revised Attachment 12 and Addendum A and submit with their quote.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
5 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
AI-5. The Combined Synopsis/Solicitation document has been revised to identify the
Attachments that were revised and documents added by this Amendment. FAR Clause 52.212-2, Evaluation Factors for Award, has also been amended to show the priorities for evaluated pricing as detailed in Q-15. and R-15. below.
AI-6. Should you require clarification of any of the information contained within this
Amendment or its Attachments, or have additional questions, please submit them via e-mail to kathryn_logsdon@nps.gov no later than 4:30 p.m.
central time on Thursday, January 29, 2015.
Q-1. What is the floor to ceiling height where curtains are going?
R-1. Floor to ceiling heights are as follows:
Front & Rear Parlors: 9'
Dining Room: 9'
Sitting Room: 9'
Upstairs Front Hall: 11' 1 1/2"
Lincoln's Bedroom: 11' 1 1/2"
Mary's Bedroom: 8' 9 1/4"
Boys' Bedroom: 8' 9 1/4"
Upstairs Back Hall: 8' 9 1/4"
Kitchen not included in these measurements
Q-2. What are the distances between the top of the window frames and the ceilings?
R-2. The distances are as follows:
Front Parlor: 3" for both windows
Rear Parlor: 9 1/2" (western-most), 10¿ (eastern)
Dining Room: 19 3/4"
Sitting Room: 2 3/4"
Upstairs Front Hall: 27 1/4"
Lincoln's Bedroom: 26 7/8" (west facing), 27
1/4" (north facing)
Mary's Bedroom: 17 1/4"
Boys' Bedroom: 17 1/4"
Upstairs Back Hall: 17 1/8"
Kitchen not included in these measurements
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
6 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
Q-3. As per Page 4, Part C from the specifications: For the Front and Rear Parlor window coverings, Contractor is encouraged to submit two quotes; one that copies the original silk and wool material, and one that would substitute alternative materials for the silk as a cost-cutting measure. Is this fabric alternative supposed to be selected by the
Government or is the contractor to find one from
Scalamandre?
R-3. The contractor is asked to determine the possibility or availability of an alternative fabric and submit a second quote, if possible, which includes the utilization of the alternative fabric. See AI-1.d. above.
Q-4. What is the sheer batiste for kitchen and pantry from the Vermont Country Store on
Attachment 10 (Drapery Sources - 1988). I thought the kitchen had the Brunshwig white fabric. Is the pantry window the only window then getting sheer batiste from the Vermont
Store? Can this window have the same fabric as the kitchen window?
R-4. Disregard the sheer batiste for kitchen and pantry. The fabric for the kitchen window is to be the same as that used for the 2nd floor bedrooms, and front and back hall. See AI-1.c.
above. Also, the pantry window covering is not being replaced and is not included in this requirement. Only the kitchen window covering will be replaced in this room.
Q-5. Some sources may require a minimum order of 100 to 120 yards for the damask in the
Parlors, and the same for the moire taffeta for the Sitting and Dining Rooms.
R-5. If that is the minimum order required, the contractor will then provide the excess yardage of material to the Park. If you find from your source the minimum order exceeds more than 120 yards, please notify me so that I may consult with the Lincoln Home Curator for further instructions.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
7 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
Q-6. Do we need to provide rods for Mr. and
Mrs. Lincoln's Bedrooms, Upstairs Hall, Boys' room and flat rod for the kitchen as well, or just the S. hooks and rings?
R-6. Contractor will not need to provide any rods; the existing rods on all windows in all rooms will be reused. For the S hooks and rings, the specifications state the hooks and rings are to be provided by contractor; however, I have since discussed this with the Curator, and this requirement is amended to inform contractors that the existing S hooks and rings can be utilized;
however, they would have to be sewn on the window coverings by the contractor at the time of installation since the only S hooks and rings available are those that are on the existing window coverings. Existing window coverings cannot be taken down until the day prior to, or the day of, the new window coverings being installed.
Q-7. Does contractor take down the existing drapes and will the contractor need to dispose of them?
R-7. The Park Curator will be responsible for taking down the existing drapes. The existing drapes will remain the property of Lincoln Home and the National Park Service.
Q-8. Is the fabric amount for the required tiebacks included in the total yardage of the fabrics?
R-8. Yes
Q-9. Is there a preference for hand-made versus machine-made? Handmade will be more in the tradition of the building but will increase costs.
R-9. Window coverings shall be machine-made.
Q-10. Would there be a ladder available that the contractor can use?
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
8 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
R-10. A ladder can be made available by the
Park. If utilized by the contractor, the government property clauses will be added to the contract; that is FAR 52.245-1, 52.245-2, and
52-245-9. Full text of the referenced clauses may be accessed electronically at https:/www.acquisition.gov/far.
Q-11. For the lining, is this to be plain off white cotton lining fabric, or is it be interlining?
R-11. It is to be off white cotton lining fabric.
Q-12. Do the metal valances on the Sitting
Room, Dining Room, and Front and Rear Parlor windows need removed?
R-12. The valances will not be removed for installation. The rods are accessible and new window coverings can be installed without removal of the valances.
Q-13. It was stated by an interested Contractor that it would not be possible to get the fabrication and installation of the drapes for the Front and Rear Parlors completed within six
(6) months or even nine (9) months from the date of award. Will their quote still be considered if their completed milestones goes beyond nine months?
R-13. The Government refers to the evaluation criteria found on Page 4 of 8 in the Revised
Combined Synopsis/Solicitation document whereby it states:
Delivery / Completion Time - Quoter is to complete the Revised Attachment 11 (Contractor¿s
Proposed Milestone Dates). It is the
Government's preference that all window coverings be provided, installed, and all deliverables received within six (6) months from the date of award, but not later than nine (9) months from the date of award. A delivery/completion date of
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
9 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
1 to 4 months will be rated Excellent, 5 to 6 months will be rated Above Average, 7 to 9 months will be rated Satisfactory, 10 months will be rated Below Average, and a delivery date of over
10 months will be rated Unsatisfactory. (Note:
The Contracting Officer may find it necessary to adjust the range of the above ratings for the delivery dates. This will be contingent upon the average delivery / completion time of all quotes received. For example: If the average delivery/completion time of all quotes received is 11 to 12 months, all ranges could be adjusted accordingly and a 12-month delivery/completion time could be rated as Satisfactory.)
Q-14. What if all curtains, with the EXCEPTION of the Front and Rear Parlor drapes can be completed in six to nine months, but the Front and Rear Parlor drapes cannot be completed for a year or longer; and to save on installation costs, can the window coverings for the Bedrooms, Front and Back Hall, Kitchen, and Sitting and
Dining Rooms be sent to the Park as soon as they are completed for the Park to install themselves, and then when the Front and Rear Parlor drapes are completed at a later time, the Contractor travel to Lincoln Home to install those?
R-14. If all curtains, with the EXCEPTION of the Front and Rear Parlor drapes, can be completed in six to nine months, but the Front and Rear Parlor drapes cannot be completed for a year or longer, the Contractor would then be expected to make two trips for installation. One trip to install the window coverings for the
Bedrooms, Front and Back Hall, Kitchen, and
Sitting and Dining Rooms as soon as their fabrication is completed, and another trip later to install the Front and Rear Parlor window coverings when their fabrication is completed.
Q-15. What is the total dollar amount the
Government is making available for this award?
R-15. This information cannot be conveyed;
however, after discussing with the Park's
Curator, should the funds allocated for this project not be adequate to cover the entire price
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
10 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
to have the window coverings fabricated and installed for ALL the rooms within the Lincoln
Home, then award may only be made for the amount of funds available. With that being the case;
the Government has prioritized their requirement for window coverings based on the condition and wear and tear of the existing window coverings.
Those priorities are as follows:
Priority #1: 2nd Floor Bedrooms, Front and Back
Hall, and Kitchen (highest priority for replacement)
Priority #2: Sitting and Dining Room (middle priority for replacement)
Priority #3: Front and Rear Parlors (lowest priority for replacement)
- If funds are only available to fund all of Priority #1 and part of Priority #2, then only
Priority #1 will be procured.
- If funds are only available for all of Priority #1, all of Priority #2, and part of Priority #3, then only Priorities #1 and #2 will be procured.
- If funds are available for all of Priority #1, Priority #2 and Priority #3, then all three priorities will be procured.
See Clause 52.212 Evaluation Factors for Award, paragraph (c) which states, "Before the quoter's specified expiration time of quote, the
Government may accept a quote (OR PART OF A
QUOTE), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award."
Addendum A to Attachment 12 is added for contractors to complete for submission of their pricing.
Q-16. Is the payment schedule of 25% / 75% as described in Attachment 1, Section V, firm?
R-16. Yes, unless an award is made under the conditions described in Q-14 and R-14 above. In that case, it would still remain at 25% / 75% as indicated in Attachment 1, Section V; but the 25%
/ 75% would be calculated on the price of the first window coverings fabricated and delivered
(installed), and then 25% / 75% would be
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
11 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
calculated on the price of the second window coverings fabricated and delivered (installed).
Q-17. Does Springfield, Illinois have an airport?
R-17. Yes. Commercial car rental services are also located at the Springfield, IL airport.
Q-18. If flying into Chicago, IL airport, what is the driving distance from Chicago to Springfield, Illinois?
R-18. Approximately 200 miles.
Q-19. If flying into St. Louis, MO airport, what is the driving distance from St. Louis to
Springfield, Illinois?
R-19. Approximately 110 miles.
LIST OF CHANGES:
CHANGES FOR LINE ITEM NUMBER: 10
REVISED RFQ P15PS00175 COMBINED SYNOPSIS AND
SOLICITATION, consisting of 8 pages
Revised Attachment 11, consisting of 1 page Contractor's Proposed Milestone Dates
Revised Attachment 12, consisting of 3 pages Quotation Submittal and Instructions
Addendum A to Attachment 12, consisting of 1 page
Contractor's Price(s)
///////END of AMENDMENT 0002/////
Point of Contact for this Amendment is:
Kathryn M. Logsdon
(217) 391-3225
E-mail: kathryn_logsdon@nps.gov
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
12 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
00010 REPRODUCTION DRAPERIES/CURTAIN FOR LINCOLN HOME.
Contractor is to provide all qualified labor, supervision, materials, supplies, tools, equipment, services, facilities, travel and transportation to provide, fabricate, and install window coverings (draperies/curtains/tiebacks) for nineteen (19) windows throughout the historic
Lincoln Home, located at the Lincoln Home
National Historic Site, 430 S. 8th Street, Springfield, IL. Also included, is the requirement to provide and attach curtain/drapery rings to the window coverings. The following documents comprise this Solicitation:
REVISED RFQ P15PS00175 COMBINED SYNOPSIS AND
SOLICITATION, consisting of 8 pages
Attachment 1, consisting of 8 pages
Specifications and Scope of Work
Attachment 2, consisting of 1 page Illustration of Lincoln Home Front Parlor, 1860, showing draperies from Frank Leslie's Illustrated
Newspaper. Lincoln Home NHS collection.
Attachment 3, consisting of 1 page Illustration of Lincoln Home Sitting Room, 1860, showing draperies from Frank Leslie's Illustrated
Newspaper. Lincoln Home NHS collection.
Attachment 4, consisting of 1 page Illustration of 2nd floor bedroom curtain style, as seen in a watercolor by M. Sekim, 1841. Reprinted in Gere, Charlotte, Nineteenth-Century Decoration: The Art of the Interior (New York: Harry N. Abrams, Inc., 1989), pg. 192.
Attachment 5, consisting of 1 page Illustration of simple Nineteenth-Century window hangings, originally from J.C. Loudon, An Encyclopedia of
Cottage, Farm, and Villa Architecture and
Furniture (London: Longman, Rees, Orme, 1833),
pp. 338-39. From Internet Archive:
https://archive.org/stream/encyclopdiaofc00loud#pa ge/338/mode/2up (accessed 1/31/2014).
Attachment 6, consisting of 1 page Illustration Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
13 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
P15PS00175/000002
of kitchen curtain style, as seen in William
Rothenstein, Hampstead Interior, 1903. Reprinted in Gere, Charlotte, Nineteenth-Century
Decoration: The Art of the Interior (New York:
Harry N. Abrams, Inc., 1989), pg. 335.
Attachment 7, consisting of 11 pages Present day photographs of Lincoln Home 1st and 2nd floor window coverings.
Attachment 8, consisting of 9 pages Photographs of tiebacks.
Attachment 9, consisting of 10 pages Photographs of drapery/curtain rings.
Attachment 10, consisting of 1 page Drapery Sources - 1988
Revised Attachment 11, consisting of 1 page Contractor's Proposed Milestone Dates
Revised Attachment 12, consisting of 3 pages Quotation Submittal and Instructions
Addendum A to Attachment 12, consisting of 1 page
Contractor's Price(s)
Amendments issued against the solicitation.
IT Approval Num: N
Requisition No: 0040173659
FOB: Destination
Point of Contact for this combined synopsis/solicitation is:
Kathryn M. Logsdon, Contracting Officer
Phone: (217) 391-3225
E-mail: kathryn_logsdon@nps.gov
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)