This document provides information on a planned federal solicitation for bathroom renovation services. The Veterans Benefits Administration anticipates issuing a solicitation for renovation of ten restrooms in Building 46 at the St. Petersburg VARO. The solicitation will have an estimated value between $1,000,000 and $2,000,000. The scope of work involves providing all labor and materials to renovate each restroom in accordance with the statement of work. The acquisition has been set aside for total service-disabled veteran owned small businesses. The solicitation number is 36C10E20R0003 and is expected to be issued on August 10, 2020 with offers due within 30 days. The contract type will be firm-fixed-price and award will be based on price reasonableness and past performance. The period of performance is approximately 180 calendar days from notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C10E20R0003 0005.docx | DOCX document | |
| 36C10E20R0003 0004.docx | DOCX document | |
| 36C10E20R0003 0003.docx | DOCX document | |
| zS02 St Petersburg Restroom - PAST PERFORMANCE SURVEY.docx | DOCX document | |
| 36C10E20R0003 0002.docx | DOCX document | |
| S02 St Petersburg Restroom - 100_CD_Specifications.pdf | ||
| 100_CD_Drawings_05082020.pdf | ||
| 36C10E20R0003 0001.docx | DOCX document | |
| 36C10E20R0003_1.docx | DOCX document | |
| P07 St Petersburg Restroom - Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ST. PETERSBURG VA REGIONAL OFFICE
VA Project No: VB3210
VA Contract No: 36C10E18R0111
Bancroft-AE Project No: 18-114
Bathroom Renovation AE Services V2
ST. PETERSBURG VA REGIONAL OFFICE
100% CONSTRUCTION DOCUMENTS
May 08, 2020
BASIS OF DESIGN
St. Petersburg VA Regional Office Bathroom Renovation AE Services V2
VA Contract Number: 36C10E18D0017 Bancroft Project Number: 18-114
Issued For: User and VA approval
By:
Bancroft Architects + Engineers 700 Nicholas Blvd, Suite 300 Elk Grove Village, Illinois 60007
847.952.9362 | www.bancroft-ae.com
1. Executive Summary
2. Conceptual Design
3. Architectural Basis of Design
4. Mechanical Basis of Design
5. Plumbing Basis of Design
6. Fire Protection Basis of Design
7. Electrical Basis of Design
Appendix A - Meeting Minutes
Basis of Design Table of Contents
INTRODUCTION PROJECT SCOPE
Name Company Role
Dennis Ecord VHAUS Department of Veteran Affairs—VBA COR
Patricia Bailey Bancroft Architects + Engineers Project Manager
Connor Rollins Bancroft Architects + Engineers Project Architect
CJ Flask MES Group Mechanical Engineer
Lee HIll MES Group Electrical Engineer
Matthew St. Thomas VHAUS Department of Veteran Affairs—VBA CO
DESIGN TEAM
This document is a Conceptual Design Summary which will serve as the starting point for the Basis of De-sign (BOD), a living document that will evolve through the duration of this project. This document was cre-ated starting from the following key elements of developmental discovery:
• Pre-Contract Meeting June 17, 2019
• Kickoff Meeting September 26, 2019
• Investigative Services September 27, 2019
It is not the BOD’s function or intent to document every element of this entire process as it is developed;
rather it is to perform as an organized summary of the key developments of the project process. In addi-tion to the BOD, total documentation of the design process consists of project minutes of meetings, nu-merous design studies and options presented for consideration.
In 2019, Bancroft AE was contracted to provide Architectural/Engineering design services for the St.
Petersburg VA Regional Office in St. Petersburg, FL. The main project focus is the renovation of 10 bathroom suites in building 46. The intent is to provide complete reconfiguration of the existing bathrooms based on the specifications of the bathrooms at building 47. The scope of design services include Schematic Design, Design Development, and Construction Documents.
The optimal solution will update the existing bathrooms to today’s standards including ADA and the VA
Barrier Free Design Standard. In addition, updating finishes and fixtures as the existing finishes are original to the building. The design will also address the issue of backups that occur within the plumbing system during peak times of use.
Aerial view of St. Petersburg VA Regional Office
Executive Summary 1
APPLICABLE CODES
As of October, 2018 the following Codes and Standards have been adopted by the VA:
• VA Directives, Design Manuals, Master Specifications, VA National CAD Standard Application Guide, and other Guidance on the Technical Information Library (TIL) (http://www.cfm.va.gov/til/).
• International Building Code 2018 (IBC) (Only when specifically referenced in VA Design Documents)
• NFPA 101 Life Safety Code 2018
• NFPA National Fire Codes with the exception of NFPA 5000 and NFPA 900
• Occupational, Safety and Health Administration (OSHA) Standards.
• VA Seismic Design Requirements, H-18-8
• National Electrical Code (NEC)
• International Plumbing Code (IPC)
• Safety Code for Elevators and Escalators, American Society of Mechanical Engineers (ASME) A 17.1.
• ASME Boiler and Pressure Vessel Code
• ASME Code for Pressure Piping
• Architectural Barriers Act Accessibility Standards (ABAAS) including VA supplement, Barrier Free De-sign Guide (PG-18-13)
• Building Code Requirements for Reinforced Concrete, American Concrete Institute and Commentary
(ACI 318)
• Manual of Steel Construction, Load and Resistance Factor Design Specifications for Structural Steel Buildings, American Institute of Steel Construction (AISC)
• Energy policy Act of 2005 (EPAct)
• DOE Interim Final Rule: Energy Conservation Standards for New Federal, Commercial and Multi- Family High-Rise Residential Buildings and New Low-Rise Residential Buildings, 10 CFR Parts 433, 434 and 435.
• Federal Leadership in High Performance and Sustainable Buildings: Memorandum of Understanding
(MOU)
• Executive Order 13423: Strengthening Federal Environmental, Energy, and Transportation Manage-ment.
• The Provisions for Construction and Safety Signs. Stated in the General Requirements Section 01010 of the VA Master Construction Specification.
• Ventilation for Acceptable Indoor Air Quality – ASHRAE Standard 62.1- 2007.
• Safety Standard for Refrigeration Systems – ASHRAE Standard 15 – 2007.
• ASHRAE-110 F Velocity Measurement Procedures.
• Sheet Metal and Air Conditioning Contractors Associations (SMACNA)
• International Mechanical Code (IMC)
• Underwriter’s Laboratories (UL).
EXISTING CONDITIONS
In the wake of World War I, on January 5, 1929, Senator Duncan U. Fletcher introduced a bill that would appropriate funds for a Soldiers' Home to be constructed in Florida. Ultimately the bill’s word-ing was changed from "Florida" to "southeastern states," but it did pass and appropriate $2 million for a home.
Within Pinellas County, a campaign immediately began to rally support for construction in the area, namely at the Seminole Point site (although for some time Clearwater was also in the running). Semi-nole Point was chosen as the site on May 26, 1931 - an event which newspapers called the "glorious news" that will "bring Saint Petersburg back." However, only $900,000 in funds was appropriated, due to a decision to use the $2 million also to construct a hospital in Mississippi and an African-
American hospital in Tuskegee, Alabama.
Construction of the first three buildings (what are now buildings 1, 2, and 13), a gatehouse, and em-ployee living quarters (previously on the land given to St. Petersburg Junior College in 1973) were completed in 1933; the hospital by James I. Barnes Company from Indiana, and the living quarters by
J. M. Raymond Construction Company from Jacksonville. The main hospital, under the name
"National Home for Disabled Volunteer Soldiers," and the domiciliary unit opened on March 16, 1933.
Within days seventeen men joined the domiciliary, the first having been Pat Corr of St. Petersburg.
The hospital, however, did not treat its first patient, Charles Boone, the Veterans of Foreign Wars
State Commander from Miami, until March 19, 1933.
Construction continued, as plans were already in place for a Recreation Building (Building 20, com-pleted in 1935), an expanded domiciliary (completed in 1940), and convalescent homes, when the main building opened. Additionally, the VA Regional Office of Florida was moved to Bay Pines, which changed its name from Seminole Point in 1934, from Jacksonville, where they had been located in
1925. Until World War II, construction was non-stop: a 52-bed domiciliary for female veterans opened in 1937 (building 24), a new hospital wing increased bed capacity to 245, and a hydrotherapy treat-ment pavilion on Madeira Beach was constructed in 1934.
World War II brought a surge in patients for which initial construction could not have planned. To in-crease space, the Regional Offices were moved to the Don Ce-Sar, recently vacated by the Army Air
Corps., on Pass-a-Grille Beach and some offices, a brace shop, a chapel, and the library were moved to temporary Quonset-type huts.
But although building space was direly needed, Bay Pines had more than enough land and began to give away portions of the surplus land, beginning with 18 acres in 1955 for the construction of Madei-ra Beach School. Later issuances of land include 359 acres in 1966 to Pinellas County for War Me-morial Park, 60 acres in 1973 to St. Petersburg Junior College, and 17.6 acres in 1974 to the Florida
Department of Transportation.
Meanwhile, in September 1959, funds were approved for a much-needed 140 bed addition to be con-
Executive Summary 1 structed in 1963. Additionally a domiciliary building was converted to add 160 hospital beds, opening by October
8, 1961. The 1963 hospital, however, never surfaced: instead, a new VA Hospital was announced for Gainesville, Florida. Although the issue would resurface many times in the following 15 years, new hospital construction would not be announced again until the late 1970’s.
The next major construction project was the original Nursing Home Care Unit, opened in 1973. Then in 1976, fol-lowing the efforts of Congressman Bill Young and a visit by President Ford, $110 million in appropriations was announced for an addition to the Nursing Home Care Unit, a new domiciliary, the replacement hospital (Building
100) and renovations for Buildings 1 and 22. Prior to those projects, Building 23, the Clinical support Building opened on June 13, 1977.
The Nursing Home Care Unit addition and replacement Domiciliary were completed quickly - bids were accepted starting June 22, 1978 and both were dedicated October 21, 1980. The replacement hospital, however, was not completed until 1983 and dedicated on March 16, 1983. The restoration of Buildings 1 and 22 was not completed until July 1987.
In September 1998 the Regional Office returned to Bay Pines with the completion of a three-story, 125,000 square feet building on-site. Previously the Regional Office had moved from the Don Ce-Sar to a federal building on First Avenue in St. Petersburg in 1967.
Since its original construction in 1933, Bay Pines has continued to expand and adapt to meet the increasing needs of the veterans it serves.
EXISTING CONDITIONS—REVIEW OF AABAS COMPLIANCE
Each toilet room was reviewed for compliance with current AABAS standards as well as the VA Barrier Free Design
Standard Supplement.
Men’s Toilet Room 111: Meets current standards.
Women’s Toilet Room 110: Meets current standards.
Women’s Toilet Room 221: Meets current standards.
Men’s Toilet Room 219: Meets current standards.
Women’s Toilet Room 201: Meets current standards.
Men’s Toilet Room 202: Meets current standards.
Men’s Toilet Room 245: Stall depth does not meet required 6’-0” based on VA Barrier Free Design Standard.
Women’s Toilet Room 244: Stall depth does not meet required 6’-0” based on VA Barrier Free Design Standard.
Men’s Toilet Room 302: Meets current standards.
Women’s Toilet Room 303: Meets current standards.
Men’s Toilet Room 312: Meets current standards.
Women’s Toilet Room 311: Meets current standards.
HAC 115: Room too narrow to meet turning radius for wheelchair. Clear area not achievable.
CONSTRUCTION STRATEGIES
Renovating an existing structure while normal activity continues is a challenging task that must be met with advanced planning for phased implementation of the design during construction. The need for a multi-phased construction project becomes evident as clinical and facility operations must continue in existing occupied spaces during construction work without disruptions. During the early planning and design phases a process shall be developed to define the constructability from demolition to completion of construction with a compre-hensive look at the impact of each phase on the new and existing facility. To better anticipate difficulties be-fore plans are finalized and construction commences, project designers and hospital managers must carefully collaborate in developing drawings which document and detail each phase of the project. Several key goals to consider as follows:
1. Construction Phasing
• Project will be required to be phased as necessary to keep facility operational at all times.
• Refer to Phasing plans for outline of phases.
• Coordination with key personnel to develop a detailed phasing plan.
• Phasing to maximize efficiencies and minimize construction impact on the surrounding community.
• Determine construction phase activities that can potentially disrupt existing normal operations.
• Develop mitigation plan to allow operations to continue.
• Study the site and surrounding areas to designate lay-out areas and on-site trailer location.
• Define owner restrictions during construction.
2. Security
• Construction phasing plan to designate areas of construction isolated from secure perimeter of facility.
• Temporary construction fencing to be provided for safety and separation of construction site.
3. Utility Interruptions
• Determine any temporary utilities necessary for facility to remain operational at all times.
• Coordination required with facility management group to schedule any utility interruptions.
• Time and impact of any utility interruptions to be limited.
• Refer to Mechanical, Electrical and Plumbing Narratives contained in this document for additional de-tailed information regarding work related to required interruption of existing engineering systems.
Executive Summary 1
DEMOLITION
• The building shell and exterior windows will remain intact.
• All existing finishes shall be removed from existing bathrooms
• All existing plumbing fixtures to be removed from existing bathrooms.
• All existing toilet room accessories to be removed from existing bathrooms.
• Existing toilet partitions to be removed.
• Existing lavatory counters to be removed.
• All existing acoustic ceiling in bathrooms to be removed.
• All existing lighting fixtures in bathrooms to be removed.
Architectural Basis of Design3
1. Interior Partitions
a. Selective existing interior partition walls will be removed for new bathrooms layouts.
b. New gypsum wall boards with new finishes to be located at areas of existing toilet room wet walls.
c. New plumbing wall chases at back to back plumbing locations consisting of 5/8” moisture resistant board and 3 5/8” metal studs wall.
3. Sound Attenuation & Acoustical Privacy
a. All wall partitions to be full height with sound attenuating fiberglass batt insulation with STC 40 sound rating
b. Provide sound attenuating insulation around “noisy” spaces such as bathroom walls.
c. Provide new acoustical ceiling tile and grid system in all bathroom suites. New acoustical ceiling tile and grid system in corridors.
5. Doors
a. Bathroom doors to be solid core wood doors 1 ¾” throughout with painted hollow metal frames.
6. Finishes:
a. New floor finishes throughout bathrooms.
b. New wall finishes in all bathrooms.
c. New ceiling finishes in all bathrooms.
6. Life Safety
a. Provide UL rated construction where indicated on life safety drawings
b. Provide Fire Extinguisher cabinets as required by NFPA throughout space.
INTERIOR BUILDING SYSTEMS INTERIOR FINISHES
Interior finishes to match specifications for Building 47 renovation.
Finishes
Ceiling
All ceilings shall be of 2x2 acoustic tile construction.
Lighting
Lighting shall be LED type fixtures.
Flooring
All new flooring shall be 12x24 porcelain tile.
Walls
All walls shall receive moisture resistant gypsum wall board.
Any existing walls effected by renovations shall be patched to match existing.
Restroom wet walls shall receive 8x36 porcelain tile. All other walls shall receive 12x24
Porcelain tile.
Mechanical Basis of Design5
DESIGN CODES AND STANDARDS
The design of the HVAC systems shall be in accordance with the following codes and standards:
• International Building Code
• VA HVAC Design Manual 2011
• International Mechanical Code (IMC)
• ASHRAE Standard 170, Ventilation of Health Care Facilities
• VA Master Specifications (H-08-1)
• VA Standard Details (H-08-4)
• Applicable National Fire Protection Association (NFPA) codes including, but not limited to, NRPA 70-93 (National
Electric Code)
• Sheet Metal and Air Conditioning Contractors Association (SMACNA)
• Air Conditioning and Refrigeration Institute (ARI)
• Underwriter’s Laboratories (UL)
• National Electric Manufacturers Association (NEMA)
DESIGN CONDITIONS AND CRITERIA
Mechanical equipment functioning properly and shall remain. All toilet room diffusers and grilles are to be replaced and reinstalled in new ceiling grid. Ductwork will have to be adjusted as needed to accommodate new ceiling. All airflows shall remain. All added ductwork shall be supported properly according to specifications and SMACNA as required. Ductwork to have sealer applied as dictated by system duct pressure.
HVAC SYSTEM DESCRIPTION
• . All toilet rooms to have existing diffusers and grilles demolished and replaced with new
24”x24” lay-in diffusers and grilles, and adjusted to the new ceiling grid.
• All toilet room door undercuts to be verified as at least 1 inch.
Plumbing Basis of Design6
Plumbing lines will be modified as required to accommodate new floor plan. Sanitary, vent and domestic water lines that will no longer be in use will be demolished and removed in their entirety. Dead legs will not be allowed. Project specific toilets, sinks, etc. will be demolished and removed.
EXISTING CONDITIONS / DEMOLITION
PLUMBING SYSTEM DESCRIPTION
• All plumbing fixtures will be demolished and replaced with new in same location. Piping shall remain for installation of new fixtures.
• A new booster pump shall be installed in Mechanical Room 114 on the Ground floor of building 46 attached to the 3 inch domestic water line in the room.
• The lateral sanitary piping below Toilets 219 and 221 to be demolished and replaced with new like material piping.
• Sanitary and domestic water piping and associated fittings are to be installed to support addition of sink in Break Room P-3.
The design of the plumbing system will be in accordance with the latest editions of the following codes and standards:
• Underwriters Laboratory, Inc.
• American National Standards Institute (ANSI)
• American Society for Testing Materials (ASTM)
• American Water Works Association (AWWA)
• Cast-Iron Soil Pipe Institute (CISPI)
• International Plumbing Code, 2012 Edition
• VA Plumbing Design Manual 2014
DESIGN CODES AND STANDARDS
Fire Protection Basis of Design8
FIRE PROTECTION SYSTEM DESCRIPTION
• Existing sprinkler main will remain as is, whereas, the sprinkler head locations will be modified per the new reflected ceiling plans.
• Sprinkler heads in areas with ceiling modification should be changed out for upright heads or a fire watch be established during demolition.
• Existing recessed sprinkler heads shall be relocated to the middle of new ceiling tiles in areas of ceiling modifications.
The design of the fire protection system will be in accordance with the following codes and standards:
• NFPA-13 Installation of Sprinkler Systems
• NFPA-70 National Electric Code
• NFPA-72A Local Protective Signaling Systems
• NFPA-72E Automatic Fire Detectors
• NFPA 99 Health Care Facilities Code Book, 99B and 99C
• NRPA-101 Life Safety Code BOCA
• National Fire Protection Code
• Underwriters Laboratory, Inc. (UL)
• American National Standards Institute (ANSI)
Tests by independent agencies whose classifications and requirements have general acceptance as regulatory:
• Underwriters Laboratories, Inc. (UL)
• Factory Mutual
• Owner's Insurance Company
DESIGN CODES AND STANDARDS
Electrical Basis of Design9
ELECTRICAL SYSTEMS DESCRIPTION DESIGN CODES AND STANDARDS
The electrical design for this project is based on, but not limited to, the following publications, codes, specifica-tions, etc.:
• VA Electrical Design Manual 2015
• VA Electrical Design Manual 2015 (PG-18-10)
• VA Master Specification (PG-18-1)
• VA Design Guides (PG-18-12)
• National Fire Alarm Code – NFPA-72 , NFPA 99
• National Electrical Code (NEC) – NFPA-70
• Standard for Healthcare Facilities – NFPA-99
• ASHRAE Standard 90.1
• Illuminating Engineering Society of North America (IESNA)
• International Energy Conservation Code
DESIGN CRITERIA
Electrical Power:
• Power will be supplied to all new LED lighting fixtures.
• The addition of hand dryers will require new circuits be routed to each bathroom. Hand dryers have been assumed to be 120V. If the input voltage of the purchased hand dryers is not 120V then additional design will be necessary.
• Additionally, power will be provided to all existing outlets and layout may need to be reworked based on accessory locations.
• A new circuit will be provided to power the booster pump that will be installed in the ground floor mechanical room to provide a solution to plumbing backups within the building.
• Added two 60A, 208Y/120V 3-phase panels to accommodate power requirements for hand dryers in specific restrooms.
• Lighting System: The lighting design shall be practical, energy-efficient, easy to maintain, and ap-propriate for the intended function of the space. In general, the lighting design shall be based on the recommendations of the latest version of the IES lighting handbook and VA Design Manuals.
Interior and exterior lighting will utilize LED technology. Exit and emergency lighting will be provided per code and building design requirements.
Automatic lighting control will be provided by utilizing occupancy sensors for the interior lighting and astronomical timeclock controls for exterior lighting via a lighting control panel. Manual overrides will be provided for all automatic controls. Lights in dedicated electrical and mechanical areas will be manually controlled only for safety reasons.
Interior lighting fixtures will be LED, multi-volt rated 120/277V, 4100°K, 80+ CRI, 0-10V dimmable driver power supplies, be listed by a Nationally Recognized Testing Laboratory (NRTL), and meet the requirements of the Buy American Act.
The lighting system shall be commissioned per International Energy Conservation Code (2018). Pri-or to passing final inspection, a third-party contractor shall provide evidence that the lighting control systems have been tested to ensure that control hardware and software are calibrated, adjusted, programmed and in proper working condition in accordance with the construction documents and manufacturer's instructions. functional testing shall be in accordance with for the applicable control type.
Interior and Exterior lighting calculations will be performed using approved lighting calculation soft-ware and methods as described in the VA Lighting Design Manual paragraph 2.11.
• General Wiring Methods: Building wiring will be high conductivity copper, 600 volts, insulated.
Feeders and branch circuit ampacity shall be adequate to supply the load served in accordance with NEC requirements. Wire sizes may be increased for voltage drop, ambient temperature, num-ber of conductors in a raceway, etc. Wire size for voltage drop shall be designed to comply with NEC recommendations.
Conductors shall be copper unless noted otherwise. Conductors which serve HVAC equipment may be selected using the 75-degree column in the ampacity tale (NEC Table 310-16), as termina-tions on all such equipment are rated for 75-degrees. Conductor size less than or equal to 350 kcmil shall have THHN/THWN insulation. Conductor size greater than 350 kcmil shall have XHHW insulation.
Rigid Non-metallic conduit will not be allowed above grade. PVC raceways are allowed only on the service entrance, underground feeders, and site lighting branch circuit runs outside the building.
Electric Metallic Tubing (EMT) shall generally be used for interior installation throughout the facility.
Minimum raceway sizes shall be as follow:
1” for underground
1” for feeders
¾” for branch circuits
Safety disconnect switches shall be heavy duty, 600V rated, fused or non-fused as applicable, NEMA 1 (general purpose) or NEMA 3R (weatherproof) enclosure as required.
• Required Calculations: In order to provide a comprehensive design for the general secondary power system, the following calculation shall be performed.
Fault Calculations: Available short circuit current throughout the building electrical system shall be calculated down to a point where the available fault is below 10,000 amperes.
Voltage Drop Calculations: Voltage drop in AC circuits is a function of the load current, circuit impedance and power factor. Electrical loads will be evaluated and voltage drop limited to 2 percent for feeders and 3 percent for branch circuits. Electrical systems shall be designed such that the maximum voltage drop is less than 5% overall.