S02 St Petersburg Restroom - 100_CD_Specifications.pdf
PDF 3 MB Posted
- Attached to
- Y1AZ--VB3210 Bathroom Renovation Federal contract opportunity
- Solicitation number
- 36C10E20R0003
About this file
This pre-solicitation notice provides details for an upcoming solicitation to renovate ten restrooms in Building 46 at the St. Petersburg VA Regional Office. The scope of work includes renovating each restroom in accordance with the statement of work. The solicitation number will be 36C10E20R0003 and is expected to be issued on or around August 10, 2020, with offers due within 30 days. The project value is estimated between $1,000,000 to $2,000,000. The government anticipates awarding a single firm-fixed price contract and will consider price and past performance in selecting the best value offer. This acquisition has been set aside for total service-disabled veteran owned small businesses. The NAICS code is 236220 for commercial and institutional building construction and the small business size standard is $39.5 million. The project completion timeline is expected to be approximately 180 calendar days following the notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C10E20R0003 0005.docx | DOCX document | |
| 36C10E20R0003 0004.docx | DOCX document | |
| 36C10E20R0003 0003.docx | DOCX document | |
| zS02 St Petersburg Restroom - PAST PERFORMANCE SURVEY.docx | DOCX document | |
| 36C10E20R0003 0002.docx | DOCX document | |
| 100_CD_Drawings_05082020.pdf | ||
| 36C10E20R0003 0001.docx | DOCX document | |
| P09 St Petersburg Restroom - SOW ATT 1.pdf | ||
| 36C10E20R0003_1.docx | DOCX document | |
| P07 St Petersburg Restroom - Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specifications
ST. PETERSBURG VA REGIONAL OFFICE
9500 Bay Pines Blvd., St. Petersburg, FL 33744
BATHROOM RENOVATION
AE SERVICES V2
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114
Divisions 00-26
100% Construction Documents Submission
May 08, 2020
DIVISION 00
SPECIAL SECTIONS
St. Petersburg VA Regional Office
St. Petersburg, FL 33744
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers
10-01-19
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 00 01 10-1 05/08/2020
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18
01 32 16.01 Architectural and Engineering CPM Schedules 01-11
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 09-19
01 45 00 Quality Control 03-19
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE (NOT USED)
DIVISION 04 – MASONRY (NOT USED)
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 16 63 Cementitious Sheathing 02-16
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 13 00 Sheet Waterproofing 04-13
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers
10-01-19
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 00 01 10-2 05/08/2020
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 06-18
09 30 13 Ceramic/Porcelain Tiling 09-15
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 02-16
09 65 19 Resilient Tile Flooring 05-18
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 21 13 Toilet Compartments 12-15
10 21 23 Cubicle Curtain Tracks 05-15
10 28 00 Toilet, Bath, and Laundry Accessories 02-16
DIVISION 11 – EQUIPMENT (NOT USED)
DIVISION 12 – FURNISHINGS
12 32 00 Manufactured Wood Casework 09-15
12 36 61.16 Solid Surface Counter
DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)
DIVISION 14– CONVEYING EQUIPEMENT (NOT USED)
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 07 11 Plumbing Insulation 09-19
22 11 00 Facility Water Distribution 09-15
22 11 23 Domestic Water Pumps 09-15
22 13 00 Facility Sanitary and Vent Piping 09-15
22 40 00 Plumbing Fixtures 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 08-17
23 37 00 Air Outlets and Inlets 02-15
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers
10-01-19
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 00 01 10-3 05/08/2020
DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 36 Wireways for Radiology Equipment 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 09 23 Lighting Controls 01-18
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS (NOT USED)
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY (NOT USED)
DIVISION 31 – EARTHWORK (NOT USED)
DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)
DIVISION 33 – UTILITIES (NOT USED)
DIVISION 34 – TRANSPORTATION (NOT USED)
DIVISION 48 – Electrical Power Generation (NOT USED)
St. Peterburg VA Regional Office
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 07-01-15
Bancroft-AE Project No. 18-114 00 01 15 - 1 05/08/2020
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
VAMC (NAME) (SPEC No.)
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI000 GENERAL – COVER SHEET
GI001 GENERAL – DRAWING INDEX
GI100 GENERAL – PROJECT NOTES
GI101 GENERAL – NOTES
GI102 GENERAL – NOTES
GI103 GENERAL – SYMBOLS, ABBREVIATIONS AND TYPICAL
MOUNTING HEIGHTS
GI301 GENERAL – INFECTION CONTROL DETAILS
GI400 GENERAL – FIRST FLOOR – LIFE SAFETY PLAN
GI401 GENERAL – SECOND FLOOR – LIFE SAFETY PLAN
GI402 GENERAL – THIRD FLOOR – LIFE SAFETY PLAN
GI410 GENERAL – FIRST AND SECOND FLOOR – INFECTION
CONTROL PLANS
GI411 GENERAL – THIRD FLOOR – INFECTION CONTROL PLAN
GI420 GENERAL – FIRST AND SECOND FLOOR – PHASING
PLANS
GI421 GENERAL – THIRD FLOOR – PHASING PLANS
ARCHITECTURAL
AD100 ARCHITECTURAL – FIRST AND SECOND FLOOR
DEMOLITION PLAN
AD101 ARCHITECTURAL – THIRD FLOOR DEMOLITION PLAN
ACD100 ARCHITECTURAL – FIRST AND SECOND FLOOR CEILING
DEMOLITION PLAN
Bancroft-AE Project No. 18-114 00 01 15 - 2 05/08/2020
ACD101 ARCHITECTURAL – THIRD FLOOR CEILING DEMOLITION
PLAN
AD200 ARCHITECTURAL – DEMOLITION ELEVATIONS
AD201 ARCHITECTURAL – DEMOLITION ELEVATIONS
AD202 ARCHITECTURAL – DEMOLITION ELEVATIONS
AD203 ARCHITECTURAL – DEMOLITION ELEVATIONS
A100 ARCHITECTURAL – FIRST AND SECOND FLOOR PLAN
A101 ARCHITECTURAL – THIRD FLOOR PLAN
AC100 ARCHITECTURAL – FIRST AND SECOND FLOOR CEILING
PLAN
AC101 ARCHITECTURAL – THIRD FLOOR CEILING PLAN
A200 ARCHITECUTRAL – INTERIOR ELEVATIONS
A201 ARCHITECTURAL – INTERIOR ELEVATIONS
A202 ARCHITECTURAL – INTERIOR ELEVATIONS
A501 ARCHITECTURAL – DETAILS
INTERIOR
IF100 INTERIORS – FIRST AND SECOND FLOOR FINISH PLANS
IF101 INTERIORS- THIRD FLOOR FINISH PLANS
IQ100 INTERIORS – FIRST AND SECOND FLOOR EQUIPMENT
PLANS
IQ101 INTERIORS – THIRD FLOOR EQUIPMENT PLANS
IF601 INTERIORS – FINISH LEGEND AND FINISH SCHEDULE
IQ611 INTERIORS – FIRST AND SECOND FLOOR – EQUIPMENT
SCHEDULES
IQ612 INTERIORS – THIRD FLOOR – EQUIPMENT SCHEDULES
FIRE PROTECTION
FP001 FIRE PROTECTION NOTES, ABBREVIATIONS, AND
LEGEND
FP101 FIRST FLOOR – FIRE PROTECTION
FP102 SECOND FLOOR – FIRE PROTECTION
FP103 THIRD FLOOR – FIRE PROTECTION
PLUMBING
P001 PLUMBING NOTES, LEGEND, SCHEDULE, &
ABBREVIATIONS
Bancroft-AE Project No. 18-114 00 01 15 - 3 05/08/2020
PD101 FIRST FLOOR PLAN – PLUMBING DEMOLITION
PL101 FIRST FLOOR PLAN – PLUMBING RENOVATION
PL102 SECOND FLOOR – PLUMBING
PL103 THIRD FLOOR – PLUMBING
PL401 ENLARGED PLAN – PLUMBING
PL402 ENLARGED PLAN – PLUMBING
MECHANICAL
M001 HVAC NOTES, SCHEDULE, LEGEND, & ABBREVIATIONS
MH101 FIRST FLOOR – HVAC
MH102 SECOND FLOOR – HVAC
MH103 THIRD FLOOR – HVAC
MH401 ENLARGED PLAN – HVAC
MH402 ENLARGED PLAN – HVAC
ELECTRICAL
E001 ELECTRICAL NOTES, LEGEND, & ABBREVIATIONS
E101 FIRST FLOOR – ELECTRICAL
E102 SECOND FLOOR – ELECTRICAL
E103 THIRD FLOOR – ELECTRICAL
EL401 ENLARGED PLAN – LIGHTING
EL402 ENLARGED PLAN – LIGHTING
EP401 ENLARGED PLAN – POWER
E501 ELECTRICAL ONE LINE DIAGRAM
- - - E N D - - -
DIVISION 01
GENERAL REQUIREMENTS
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 i 05/08/2020
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 WARRANTY MANAGEMENT
1.16 USE OF ROADWAYS
1.17 RESIDENT ENGINEER'S FIELD OFFICE
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.19 TEMPORARY USE OF EXISTING ELEVATORS
1.20 TEMPORARY USE OF NEW ELEVATORS
1.21 TEMPORARY TOILETS
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 ii 05/08/2020
1.23 NEW TELEPHONE EQUIPMENT
1.24 TESTS
1.25 INSTRUCTIONS
1.26 GOVERNMENT-FURNISHED PROPERTY
1.27 RELOCATED // EQUIPMENT // ITEMS //
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.29 CONSTRUCTION SIGN
1.30 SAFETY SIGN
1.31 PHOTOGRAPHIC DOCUMENTATION
1.32 FINAL ELEVATION Digital Images
1.33 HISTORIC PRESERVATION
1.34 VA TRIRIGA CPMS
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -1 05/08/2020
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the renovation of 12 bathrooms in building 46 of the St. Petersburg VA Regional Office in St.
Petersburg, FL. Additionally, the installation of a booster pump on the incoming domestic cold water line in the mechanical of building 46 as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
COR.
C. Offices of Bancroft Architects and Engineers, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the
Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -2 05/08/2020
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, //GENERAL CONSTRUCTION:// _______:// Work includes general construction, alterations, roads, walks, grading, drainage, //______// necessary removal of existing structures and construction and certain other items.
ITEM II, //Electrical Work:// _______:// Work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including….., , //______//.
ITEM III, //Mechanical Work:// _______:// Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project including….., , //______//.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense,.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -3 05/08/2020
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR)for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -4 05/08/2020 information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Bancroft-AE Project No. 18-114 01 00 00 -5 05/08/2020
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -6 05/08/2020
2. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to
Medical Center Director, COR and Contractor, as follows:
Phase I:
Phase II:
SPEC WRITER NOTE: Following sub-paragraphs H and H' shall be used where entire buildings are vacated. Coordinate with preceding phasing paragraph. Edit and use sub-paragraphs H and H' as indicated by project requirements. If the project includes NAS, the Project
Analysis Group should furnish information
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -7 05/08/2020 about which buildings or areas that cannot be vacated during construction.
H. // Building (s) No. (s) // Part of Bldg.// _____will be vacated by
Government in accordance with above phasing beginning immediately after date of receipt of Notice to Proceed and turned over to Contractor.
SPEC WRITER NOTE: Use the first sentence of Paragraph H', including material enclosed within " // ," only if all areas will be vacated by VA during the periods of alterations. Delete material within "
// " from first sentence and include subparagraph 1 and 2 if one or more areas will be occupied by VA during the periods of alterations.
H. Building(s) No.(s) 46 will be occupied during performance of work // .
// ; but immediate areas of alterations will be vacated.
1. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -8 05/08/2020
K. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days n advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -9 05/08/2020
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -10 05/08/2020
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -11 05/08/2020
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -12 05/08/2020 be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 PHYSICAL DATA (NOT USED)
1.12 PROFESSIONAL SURVEYING SERVICES (NOT USED)
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Bancroft-AE Project No. 18-114 01 00 00 -13 05/08/2020
1.13 LAYOUT OF WORK (NOT USED)
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one setof the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -14 05/08/2020 acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -15 05/08/2020
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance Bond: The Performance Bond must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -16 05/08/2020
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed necessary by the
Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
Following oral or written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -17 05/08/2020
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
Code 1-Life Safety Systems
a. Fire suppression systems.
b. Fire alarm system(s).
Code 1-Air Conditioning Systems
a. Air conditioning leak in part of the building, if causing damage.
b. Air conditioning system not cooling properly.
Code 1 Doors
a. Overhead doors not operational, causing a security, fire or safety problem.
b. Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
Code 3-Doors
a. Overhead doors not operational.
b. Interior/exterior personnel doors or hardware not functioning properly.
Code 1-Electrical
a. Power failure (entire area or any building operational after 1600 hours).
b. Security lights.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -18 05/08/2020
c. Smoke detectors.
Code 2-Electrical
a. Power failure (no power to a room or part of building).
b. Receptacles and lights not operational (in a room or part of building).
Code 3-Electrical
a. Exterior lights not operational.
Code 1-Gas
a. Leaks and pipeline breaks.
Code 1-Heat
a. Power failure affecting heat.
Code 1-Plumbing
a. Hot water heater failure.
b. Leaking water supply pipes.
Code 2-Plumbing
a. Flush valves not operating properly
b. Fixture drain, supply line or any water pipe leaking.
c. Toilet leaking at base.
Code 3- Plumbing
a. Leaky faucets.
Code 3-Interior
a. Floors damaged.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -19 05/08/2020
b. Paint chipping or peeling.
c. Casework damaged.
Code 1-Roof Leaks
a. Damage to property is occurring.
Code 2-Water (Exterior)
a. No water to facility.
Code 2-Water (Hot)
a. No hot water in portion of building listed.
Code 3
a. All work not listed above.
E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting
Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit tworecord copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Bancroft-AE Project No. 18-114 01 00 00 -20 05/08/2020
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -21 05/08/2020 leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.17 RESIDENT ENGINEER'S FIELD OFFICE (NOT USED)
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -22 05/08/2020 replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
SPEC WRITER NOTE: Use following Article whenever Contractor may or may not use existing elevators. Information must be secured from Medical Center as to whether elevator is for exclusive or temporary use of Contractor and between what hours it may be used by Contractor.
1.19 TEMPORARY USE OF EXISTING ELEVATORS
A*. Use of existing elevator for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators.
The COR will ascertain that elevators are in proper condition.
Contractor may use elevators Nos. _______ in Building Nos. 46 for daily use between the hours of ________. and for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of
Veterans Affairs.
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -23 05/08/2020
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractors expense.
1.20 TEMPORARY USE OF NEW ELEVATORS (NOT USED)
1.21 TEMPORARY TOILETS (NOT USED)
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and
BATHROOM RENOVATION AE SERVICES V2
Bancroft Architects + Engineers 03-01-20
Contract No. 36C10E18D0017
Station Project No. VB3210
Bancroft-AE Project No. 18-114 01 00 00 -24 05/08/2020 associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the…