This Statement of Work (SOW) details a gas pressure regulator valve service contract for the Rocky Mountain Regional VA Medical Center (RMR VAMC). The project involves assessing and replacing gas pressure regulator valves on four Cleaver Brooks boiler systems, with specific requirements including a minimum five-year experience in gas pressure systems maintenance, ability to provide original manufacturer parts, and compliance with VA Directive 1810 and safety standards.
The solicitation (RFQ #36C25926Q0021) is a 100% small business set-aside with a NAICS code of 238220 and a small business size standard of $19M. Quotes are due by 2:00 PM Mountain Time on 10/30/2025, to be submitted via email to natasha.holland@va.gov and thaddeus.gray@va.gov. The government anticipates awarding a firm-fixed price contract, with work to be completed within 30 days of contract award. Key tasks include inspecting valves, performing replacements, conducting system commissioning, cleaning up the work area, and training facility staff, with all work to be performed during normal business hours and minimal disruption to medical center operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P09_SOW Gas Regulator Valve_11.7.doc | DOC document | |
| 36C25926Q0021 0003.docx | DOCX document | |
| 36C25926Q0021 0002.docx | DOCX document | |
| 36C25926Q0021 0001.docx | DOCX document | |
| SAM Wage Determination.pdf | ||
| 36C25926Q0021.docx | DOCX document | |
| Past Performance Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RMRVAMC Gas Pressure Regulator Valve Service Contract
I. SCOPE
The Rocky Mountain Regional VA Medical Center (RMR VAMC) operates four (4) Cleaver Brooks boiler systems which require the assessment and replacement of the gas pressure regulator valves to ensure safe and efficient operations. This SOW outlines the requirements for the contractor to perform this work.
a. SITE SPECIFIC EQUIPMENT INFORMATION
i. Boiler #1: Cleaver Brooks; Model No. 4WI-200-700-200ST; Serial No. T3786-1-1
ii. Boiler #2: Cleaver Brooks; Model No. 4WI-200-700-200ST; Serial No. T3786-1-2
iii. Boiler #3: Cleaver Brooks; Model No. 4WI-200-700-200ST; Serial No. T3786-1-3
iv. Boiler #4: Cleaver Brooks; Model No. 4WI-200-700-200ST; Serial No. T3786-1-4
b. CONTRACTOR REQUIREMENTS AND CREDENTIALS
Minimum five (5) years of experience in gas pressure systems maintenance and repair.
Minimum five (5) years of experience with Cleaver Brooks Boiler Systems.
Ability to provide replacement parts from the original manufacturer.
c. TASKS Tasks identified shall be completed during normal working hours, Monday through Friday from 7:30am to 4:00pm MST. A service report describing tasks performed and hours worked shall be submitted to the POC within 24 hours of work completion. The Contractor shall provide hourly rates for normal hours of maintenance and repairs. All parts, labor and materials shall be provided by the contractor. Due to potential weather conditions, only one (1) boiler can be down at one time. Each gas pressure regulator valve needs to be completely re-installed and tested prior to bringing down the next boiler for replacement.
Replacements must be in accordance with VA Directive 1810 and all industry safety standards:
· Inspect and assess all gas pressure regulator valves on the four (4) Cleaver Brooks Boilers and identify any issues that might prevent the replacement or cause additional costs.
· Utilize lockout tagout procedures while conducting work.
· Remove old gas pressure regulator valves and replace with compatible gas regulator valves.
· Start up and commission of gas pressure regulating system on each boiler after replacement to ensure operational status prior to working on the next boiler.
· Report any conditions found outside normal operating standards immediately to POC.
These include but are not limited to incorrect pressure ratings, leaks, inoperative components, physical damage, sticking valve, noisy operation, pilot light issues, carbon monoxide emissions, etc.
· Clean-Up: Clean the work area and dispose of any debris, old valves, and materials in accordance with local regulations. Ensure that the boiler system is left in a clean and operational state.
· The contractor shall adhere to all VA safety protocols and OSHA regulations during the performance of this work.
· Personal protective equipment (PPE) must be worn by all personnel on site
· Properly dispose of all removed valves and other waste materials in accordance with federal, state, and local regulations.
· Train facility staff (up to 14 operators) on new gas pressure regulating valve system.
· Provide service reports including description of work performed and hours spent on each task.
II. PERIOD OF PERFORMANCE
Removal and installation of gas pressure regulator valves shall take place within 30 days of the contract award. The contract is not complete until documented tested according to VA Directive 1810 and BEI specifications are provided to facilities POC: Malcolm Wilkinson, 720-857-5555.
III. HOURS OF WORK AND SCHEDULING
The majority of the work will be performed during normal working hours (Monday through Friday from 7:30am to 4:00pm). Contractor shall ensure the work will have minimal impact on the operation of the VA Medical Center. Any potential disruption to ongoing medical center operations shall be coordinated 2 weeks in advance and shall be subject to review and approval by the Contracting Officer Representative (COR). Any other disruption of operations in any building shall be scheduled at least one week in advance with the COR. Work shall be scheduled to allow continuous operation of all facilities to the greatest extent possible.
IV. COMPLIANCE
The Contractor shall be fully responsible for compliance with all VA, local, state, and Federal environmental/occupational safety laws, rules, and regulations. The Contractor shall follow life and safety codes and take necessary actions to avoid conditions that may be hazardous to the health and safety of hospital personnel and patients. The Contractor is responsible for meeting all applicable OSHA and VA guidelines for safe working processes; example: lockout/tagout. All work for the duration of the contract shall be performed by trained technicians. All safety measures shall be approved as adequate by the safety officer in advance.
V. POINT OF CONTRACT (POC) CHECK-IN
All Contractor personnel working onsite at the VA facility shall check in and out with the POC located in Building L (ENC). Access to work areas and performance monitoring will be provided by the POC. In all cases, the POC shall be notified of any changes which may affect the response time of vital equipment.
VI. CONTRACT ADMINISTRATION DATA
The following Federal legal holidays are observed by this facility and no work shall be completed on these days:
New Year’s Day - January 1
Martin Luther King, Jr. Day - Third Monday in January
Presidents' Day (Washington's Birthday) - Third Monday in February
Memorial Day - Last Monday in May
Juneteenth National Independence Day - June 19
Independence Day - July 4
Labor Day - First Monday in September
Columbus Day - Second Monday in October
Veterans Day - November 11
Thanksgiving Day - Fourth Thursday in November
Christmas Day - December 25