P09 578-M25114 SOW Bldg 12 Exterior Stairs.pdf
PDF 173 KB Posted
- Attached to
- Z1DA--578-M25114 Building 12 Stairs Exterior Construction area for the exterior porch reconstruction
- Solicitation number
- 36C25225B0012
About this file
This Statement of Work (SOW) details exterior stairs and porch reconstruction at the Edward Hines Jr. VA Hospital in Hines, Illinois. The project involves comprehensive repair of the south entrance of Building 12, which currently has failing concrete stairs and structural integrity issues. The scope of work includes nine contract line items (CLINs) covering tasks such as securing the construction area, shoring the existing canopy, demolition operations, eliminating the existing crawl space, retrofitting columns, replacing the concrete porch, reconstructing stairs, installing new handrails and railings, and restoring brick veneer.
The project has a performance period not exceeding 100 days after Notice to Proceed, with actual onsite construction expected to take 50 days. Key requirements include maintaining patient care operations, following strict infection control protocols, obtaining necessary permits, and ensuring all work is performed by qualified personnel. Contractor qualifications include having an OSHA-certified site superintendent, providing documentation for specialized personnel, and adhering to VA technical standards. The solicitation (36C25225B0012) is issued by the Department of Veterans Affairs Veterans Health Administration for a critical infrastructure repair project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25225B0012 0004.docx | DOCX document | |
| 36C25225B0012 0003.docx | DOCX document | |
| 36C25225B0012 0002.docx | DOCX document | |
| 36C25225B0012 0001.docx | DOCX document | |
| 36C25225B0012_1.docx | DOCX document | |
| P07 Wage.Determination.578-M25114.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
578-M25114 Building 12 Exterior Stairs
1. Location of Service
The Contractor shall provide all labor, material, tools, travel, management, and equipment necessary for the repair of items described in this document at the Edward Hines Jr. VA Hospital (HINES VAH), 5000 South 5th Avenue, Hines, Illinois 60141.
2. Period of Performance The period of performance shall not exceed one hundred (100) days after Notice to Proceed. This period reflects the entire contract period to include wait time of materials, administrative time, and contract close out. Actual onsite construction time is not expected to exceed fifty (50) days from initial mobilization. A detailed schedule must be provided to the COR within 7 days after receiving the contract notice to proceed and prior to any onsite work.
3. Background/History/Current Conditions Hines VA is an active medical campus. The contractor must not interfere with patient care or VA staff unless given permission in writing from the COR/CO. Currently, building 12 is a patient care building. The exterior stairs on the south side of the building are failing along with the concrete slab supporting the columns supporting the exterior canopy. There is rebar sticking out and pieces of concrete falling off creating trip hazards on this fire exit route. The failing concrete slab is exposing the columns holding the roof of the exterior patio to the elements. With the weather changing and snow season setting in, it is possible the structural columns may fail causing the roof to collapse with the added weight.
4. Scope of Work Reconstruction of the existing porch and stairs located at the south entrance of Building 12. Complete the repairs and restore the function and safety of the exterior stairs on the main entrance of the east side of building 12, explicitly detailed in line 6 of this document.
5. Deliverables and Tasks
a. CLIN 1 – Secure construction area
i. Secure south building entrance to restrict pedestrians from accidentally entering construction.
ii. Provide temporary fencing around construction area to protect pedestrians from the hazards of ongoing demolition and construction operations.
b. CLIN 2 – Shore existing canopy.
i. Contractor shall install structural support system for existing canopy. Shoring to support roof girder beams to allow existing columns to be modified.
ii. Contractor shall install shoring beams bridging existing porch to NOT obstruct the reconstruction of the existing slab. Existing stairs shall be removed prior to shoring installation.
iii. Contractor shall install shoring on compacted gravel pads.
c. CLIN 3 – Demolition operations.
i. Contractor shall saw, break, and remove existing stairs. Existing stairs shall be removed prior to shoring installation.
ii. Contractor shall remove and dispose of AC and Electrical components in crawl space below patio.
iii. Contractor shall Remove existing iron fence and handrails.
iv. Contractor shall saw, break, and remove the deteriorating existing Portland
Cement Concrete porch.
v. Contractor shall clean and grade existing crawl space beneath the porch.
vi. Contractor shall clean all debris shall be removed from the site.
d. CLIN 4 – Eliminate Existing Crawl Space.
i. Contractor shall frame, set rebar, and pour new foundation wall and footing along entire perimeter of porch and building face. Roughly 80 feet.
ii. Contractor shall furnish and install CA7 aggregate in compacted lifts so new PCC porch can be constructed as a slab on grade. Roughly 100 tons of CA7 gravel.
e. CLIN 5 –Retrofit existing columns.
i. Contractor shall retrofit existing columns to slab on grade. Column will be set on
PCC pad 2-inch above new Portland Cement Concrete porch to deter moisture penetration. Post shall be plated and anchored to porch with galvanized anchors.
ii. Contractor shall trim existing columns to eliminate any impediment into the new PCC porch. Furnish and install new column trim if needed.
f. CLIN 6 – Replace Portland Concrete Cement porch.
i. Contractor shall furnish, frame, and set reinforcing rebar and dowels.
ii. Contractor shall purchase, place, and broom finish 4,000 psi Portland Cement Concrete (PCC) slab.
g. CLIN 7 – Reconstruct stairs.
i. Contractor shall reconstruct the stairs to the following specifications: Minimum
Tread Depth 12- inches, Maximum Riser Height 7.75-inches, Stairway Rise approximately 42-inches.
ii. Contractor shall install shoring on compacted gravel pads.
h. CLIN 8 – Fabricate and install new handrails and porch railing.
i. Contractor shall furnish and install two (2) railings and handrails for staircase.
ii. Contractor shall four (4) sections of deck railing between existing columns. All deck railing and handrail posts shall be surface mounted (i.e., no longer be impeded in porch slab). Post shall be welded to 3/8 x 6” x 6” galvanized steel base plates and anchored to the deck with 5/8” x 5” galvanized wedge anchors.
iii. Contractor shall furnish and install horizontal and vertical frames to be 1-1/2 inch square tube with 3/16-inch wall thickness.
iv. Contractor shall furnish and install vertical pickets to be ¾-inch 16-gauge square tubes.
v. Contractor shall furnish and apply black powder coat finish to all railing and handrails.
i. CLIN 9 – Brick veneer restoration.
i. Contractor shall grind and tuckpoint 100% of the existing brick masonry veneer below the concrete porch slab along all elevations.
ii. Contractor shall close existing crawl space vents with matching brick.
iii. Contractor shall furnish and install new bricks where needed.
6. Reports and Documentation
a. The contractor is responsible for submitting a schedule of sufficient detail for approval by the COR/CO.
i. Equipment Lead time. The contractor shall make an informed bid submission by working with suppliers and considering all potential long-lead items involved with the project reasonably known or considered to impact the start, performance, and completion of the project.
ii. The schedule shall be submitted within 7 days of the Contract Notice to Proceed and must be approved prior to any onsite work beginning.
iii. Work outside of the business hours of Monday-Friday 6:00am-5:00pm, or during federal holidays shall be confirmed and approved by COR.
iv. Utility shutdowns that would prevent patient care require minimum 16 calendar day notice.
v. The contractor shall complete the delivery on the specified above. If for any reason the scheduled time for a deliverable cannot be met, the contractor is required to explain why (include the original deliverable due date) in writing to the Contracting Officer (CO), including a firm commitment of when the work shall be completed. This notice to the CO shall cite the reasons for the delay, and the impact on the overall project. The CO will then review the facts and issue response in accordance with applicable regulations.
7. Contractor Qualification Criteria
a. Awarded Contractor is responsible for ensuring all work whether subcontracted or self-performed is done by professional, fully qualified personnel.
b. All work on building management system must be performed by a JCI Authorized Building Controls Specialist (ABCS) with documentation from JCI stating that they are in good standing at the time of this proposal. Proof of the Contractor being an ABCS must be provided with their response to this RFP.
c. Contractor shall provide certifications for all personnel performing any welding and shall certify all welds prior to the start-up of any of the units.
d. The Contractor shall have an OSHA certified site superintendent on site whenever any work is being performed.
8. Changes to the Statement of Work
a. Any changes to this SOW shall be authorized only through written correspondence from the Contracting Officer (CO). Costs incurred by the contractor through the actions of parties other than the CO shall be borne by the contractor.
9. General Requirements
a. Where a conflict exists between the Statement of Work (SOW) requirements and the requirements of other associated contract documents, the SOW requirements shall prevail.
b. This SOW presumes the Contractor will not need access to the Hines LAN or any VA Sensitive Information to execute the contract.
c. The awarded Contractor will adhere to all codes, standards, guidelines, and design requirements found in the VA’s Technical Information Library (TIL) https://www.cfm.va.gov/til/index.asp.
d. Pre-bid site visit: A site walk is encouraged and should be coordinated by the CO. The intent of this walkthrough is to give the Contractor access to the project site so that an accurate evaluation of the project requirements and site assessment can be made.
e. Infection Control Barrier (ICB): To protect the patients and VA staff, any work performed onsite must follow the Infection Control Risk Assessment (ICRA) and the Preconstruction Risk Assessment (PCRA) when applicable. See attachments for details on these requirements.
i. The Contractor shall provide and install a rigid infection control panel system manufactured by Edge Guard out of Bement, Illinois or an approved equal.
http://www.edge-guard.com/home.html. Salient details of the infection control barrier are:
ii. Temporary construction partitions shall be smoke-tight and built of noncombustible materials that will not contribute to the development or spread of fire.
iii. Barriers shall not obstruct access to emergency services and for fire, police, and other emergency forces.
iv. The barrier must be water resistant; capable of being cleaned and sanitized.
v. Fire-resistant plastic sheeting may be used to supplement the rigid infection control panel system. COR approval is required.
vi. The Contractor shall submit an RFI requesting approval during the bid period.
f. Wood studs, plywood, OSB, particle board, pressboard, or other flammable materials are not allowed at Hines.
g. Cover all sprinkler heads (daily), signs, data transmitters, and light fixtures. Contractor must prevent the spread of dust and fumes to other areas outside the work zone.
h. The Contractor shall post and maintain the final signed PCRA, ICRA, ILSM and Emergency Contact Information (when issued) at the entrance to the jobsite for the duration of the project. See Attachments for the details of these forms. The Contractor will update the postings when new documents are issued.
i. Hines VA Local Permits: Unless otherwise stated the Contractor shall submit for all required permits fourteen (14) calendar days prior to the event based on the approved project schedule with the COR.
i. Permits include: Crane work, Underground Dig Permit, Above Ceiling Work Permit, Hot Work-Burn Permit https://www.cfm.va.gov/til/index.asp http://www.edge-guard.com/home.html
j. Project Pay Applications: Contractor shall email the COR a pdf of the intended invoice and/or pay application prior to uploading to Tungsten/OB10 electronic payment system.
The COR must preapprove or payment shall be subject to rejection. All submitted project pay applications require certified payroll and waste report documents to be current with each pay submission.
k. Submittals and Shop Drawings: Unless otherwise stated the Contractor shall provide shop drawings and submittals of all material or equipment being installed for review and approval by the COR a minimum of fourteen (14) calendar days prior to the start of construction.
10. Identification Badging Requirements
a. All personnel who perform work onsite for this contract shall be required to wear a VA issued identification badge and are subject to fingerprinting and background investigations. Badge types include, Daily/Temporary, and Contractor Flash Pass, and shall be applied for as contractor determines necessary through their means and methods. The badging process requires significant time to complete and failure to precisely follow the instructions could lead to delays.
i. Contractor shall fill out a “Fingerprint Request Form”.
ii. Contractor shall coordinate with COR and bring “Fingerprint Request
Form” to Mikel Jones (Bldg 2, Rm 119) to coordinate for fingerprints (Ph: 708 202-8387, ext. 21322; Email: mikel.jones@va.gov).
iii. Once approved by Mikel Jones, contractors shall take copies of forms to Human Resources located in Building 17 for fingerprinting (It takes a minimum of 3-5 days for fingerprints clear).
iv. Upon verification the fingerprints have been cleared, the contractor can be sponsored.
At any time if the Contractor or their subcontractors are found working without proper badging, they are subject to immediate removal from the Hines Campus and any costs or work delays shall be the responsibility of the contractor.