P02. 656-25-910 - Replace Water Softeners - Drawings.pdf
PDF 5 MB Posted
- Solicitation number
- 36C26325Q0755
About this file
These are architectural and engineering drawings for replacing water softeners at the St. Cloud VA Hospital, dated January 28, 2025. The documents include a one-line water supply and distribution diagram (PS-00), a site photo plan sheet (PS-1), a control valve photo plan sheet (PS-2), a detailed drain line flow device photo (PS-3), and a gage/sample-meter piping photo plan sheet (PS-4).
The project involves removing and disposing of three existing water softener units, including tanks, bases, resin, drain lines, and accessories. Key requirements include installing new softener tanks in the same locations, modifying piping, installing new copper drain lines, new ball valves, flow control valves, and isolation valves, and adding new gages and sample piping. The contractor must provide new control units with cord connections to existing 120-volt outlets, remove existing CAT 5 control wiring, and ensure the replacement can be completed with minimal disruption to the VA hospital's water supply.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 36C26325Q0755 0001.pdf | ||
| S02. RFQ 36C26325Q0755.pdf | ||
| S02. Contract Opportunities 36C26325Q0755_1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VHASTCPfeniM Text Box St. Cloud VA Hospital Replace Water Softeners 2025 January 28, 2025
VHASTCPfeniM Text Box
PS-00
Existing Conditions Plan Sheet
Plan Notes
7. New softeners control units to provide a cord allowing connection to the existing 120 volt outlets.
8. Contractor to remove and dispose of existing CAT 5 control wiring that is currently running between the softeners. This contractor is to furnish and install new control wiring as required for the new softener units.
9. The Replacement of Softeners work shall be scheduled and sequenced so two softeners will remain in service supplying water to the VA water tower at all times, except while replacing isolation valves, where softening system shutdown shall not exceed four hours. This contractor is responsible for all temporary piping and unit programming to accommodate.
VHASTCPfeniM Callout Drain Line Flow Control
VHASTCPfeniM Text Box Plan Notes
1. Remove and dispose of the three water softener units. Include the tanks, bases, resin, drain line, flexible connectors, control valve and all appurtenances.
2. Install new softener tanks in the same locations as removed tanks. Level tanks as necessary per the manufacturers instructions. Leveling material, if necessary, must be of a durable material able to withstand salt and moisture with out degrading.
3. Modify piping to connect and accommodate contractor provided braided stainless steel flexible connections, control valve and existing CPVC brine piping. Install new CPVC isolation valve on the brine line for each softener.
4. Furnish and install new type L copper drain line. Provide new drain flow control as necessary. Provide new ball valves for drain line isolation of each softener. Fabricate and install a floor mounted galvanized uni-strut pipe support for the vertical section of drain line. Install additional hangers per code requirements.
5. Install new gages and gage/sample piping. Piping detail of this assembly is to be same as the existing. See plan photo PS-4. Fabricate and install a galvanized uni-strut pipe support for the vertical section of the gage sample pipes.
6. Insulate inlet and outlet piping, including flexible connectors, up to the softener control valve. New insulation is to be equal to the existing insulation. Modify hangers as necessary to accommodate insulation.
St. Cloud VA Hospital Replace Water Softeners 2025 January 28, 2025
PS-1
Site Photo Plan Sheet
Callout Provide all new drain line pipe. Include a new isolation ball valve at each softener.
VHASTCPfeniM Text Box St. Cloud VA Hospital Replace Water Softeners 2025 January 28, 2025
VHASTCPfeniM Text Box
PS-2
Control Valve Photo Plan Sheet
VHASTCPfeniM Callout Softener specific flow meter (Typ.). Replace each with new meter.
VHASTCPfeniM Callout Provide Dialectric Fitting at each control valve connection
VHASTCPfeniM Line
VHASTCPfeniM Line
VHASTCPfeniM Callout Remove Isolation ball valve (typical)
VHASTCPfeniM Callout Replace isolation valves. (typical)
Line
Callout Drain Line Flow Device. Replace as required.
VHASTCPfeniM Text Box St. Cloud VA Hospital Replace Water Softeners 2025 January 28, 2025
VHASTCPfeniM
PS-3
Plan Notes
1. Install new gages and gage/sample piping. Piping detail of this assembly is to be same as the existing. See plan photo. Fabricate and install a galvanized uni-strut pipe support for the vertical section of the gage sample pipes. Softener tank is not to be used as a support anchor point.
2. Softener specific flow meter (Typ) Replace the three meters with new.
VHASTCPfeniM Text Box
PS-4
Gage/Sample-Meter Piping Photo Plan Sheet
VHASTCPfeniM Text Box St. Cloud VA Hospital Replace Water Softeners 2025 January 28, 2025
VHASTCPfeniM Text Box Note #1: Gages and Gage Sample Piping
VHASTCPfeniM
Note #2: Typical Softener Flow Meter
| PS00_Existing Condition |
| PS01_Three Tanks with margin |
| PS02_Head with margin |
| PS03_Drain Device with Margin |
| PS04_Gage Meter Lines with Margins |