P001U VOL I Part 2 Final.pdf
PDF 2 MB Posted
- Attached to
- P001U Hazardous Storage Facility
- Solicitation number
- ACQR-6120122
About this file
This file is a comprehensive specification document for the P001U Hazardous Waste Storage Facility construction project at Joint Base Anacostia-Bolling, Washington, DC, issued under Naval Facilities Engineering Systems Command (NAVFAC) contract N4008020D0018/N4008024F4952, Work Order 1817027.
The document establishes detailed general requirements, administrative procedures, and technical specifications for a Design-Build construction contract. Key contractual requirements include: a designated Project Superintendent and Quality Control Manager meeting specified experience standards; submission of a Schedule of Prices within 15 days of award; a Baseline Network Analysis Schedule (NAS) using Oracle Primavera P6 software due at the Post-Award Kickoff meeting; and monthly NAS updates with cost-loaded activities and earned value reports. Critical submittals include preconstruction plans (safety, quality control, environmental protection, stormwater pollution prevention, construction waste management), design submittals at design development and final stages, and closeout documentation including as-built drawings, Operation and Maintenance Manuals, Facility Data Workbooks, and commissioning reports. The contractor must establish a three-phase quality control system (Preparatory, Initial, and Follow-Up phases) for each Definable Feature of Work, perform special inspections per ICC standards, implement comprehensive environmental controls and hazardous waste management procedures, achieve a minimum 60 percent construction waste diversion rate, and complete building commissioning for HVAC systems, lighting controls, metering systems, and building envelope performance. All work must comply with EM 385-1-1 safety requirements, maintain cybersecurity standards for temporary networks, and coordinate with Government Acceptance Testing Representatives for critical system verification. The contract requires training of Government personnel on facility operations and systems before beneficial occupancy, with supporting documentation including video recordings and attendance rosters.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P001U VOL II Part 3 - 5 Final.pdf | ||
| P001U Part 6 Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maximo NO. 23985706
WORK ORDER NO. 1817027
Contract NO. N4008020D0018 / N4008024F4952 Installation Project No. BXUR233001 APPROPRIATION: 057 3300- Military Construction, Air Force
FINAL SUBMITTAL
P001U Hazardous Waste Storage Joint Base Anacostia Bolling, Washington, DC
PREPARED BY:
Wiley|Wilson/Burns&McDonnell JV
2850 Eisenhower Avenue Suite 200
Alexandria, VA 22314
Architectural: Jessica Somgynari, AIA Mechanical: Scott Little, PE Interior: Tammy Farral CID Electrical: Charlie Richardson, PE Civil: Steve Schad, PE Fire Protection: Joe Rainey, PE Connor Leslie, EIT Cost Engineer: Kevin Waters, PE Structural: Drew Augustin, PE Geotechnical: Katie Cox, PE
Submitted By: Steve Schad, PE Date: 15 DEC 2025 AE Project Manager
Project Manager: Marcell Kennedy Date: 15 DEC 2025
Approved By: Christine Rutkowski Date: 15 DEC 2025 Design Production Director
P001U Hazardous Waste Storage Contract No.: N4008020D0018 / N4008024F4952 Joint Base Anacostia Bolling, Washington, DC Work Order Number: 1817027
1.0 Table of Contents (RFP Parts 2-6)
1. PART 2 – GENERAL REQUIREMENTS
01 14 00 WORK RESTRICTIONS
01 20 00 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 19.05 20 CONCEPT DESIGN WORKSHOP
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT
CONTRACT MANAGEMENT SYSTEM
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES
01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING
01 35 13 SPECIAL PROJECT PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 FACILITY DATA WORKBOOK (FDW)
01 91 00.15 BUILDING COMMISSIONING
01 91 19 BUILDING ENCLOSURE COMMISSIONING
2. PART 3 – PROJECT PROGRAM
CHAPTER 1 & 2. PROJECT DESCRIPTION AND PROJECT OBJECTIVES
CHAPTER 3. SITE ANALYSIS
CHAPTER 4. SPACE TABULATION FORM
CHAPTER 5. ROOM REQUIREMENTS
CHAPTER 6. ENGINEERING SYSTEMS REQUIREMENTS
3. PART 4 – PERFORMANCE TECHNICAL SPECIFICATIONS
A10 FOUNDATIONS
A20 BASEMENT CONSTRUCTION
B10 SUPERSTRUCTURE
B20 EXTERIOR ENCLOSURE
B30 ROOFING
C10 INTERIOR CONSTRUCTION
C30 INTERIOR FINISHES
D20 PLUMBING
D30 HVAC
D40 FIRE PROTECTION
D50 ELECTRICAL
E10 EQUIPMENT
E20 FURNISHINGS
F10 SPECIAL CONSTRUCTION
F20 SELECT BLDG DEMOLITION
G10 SITE PREPARATIONS
G20 SITE IMPROVEMENTS
G30 SITE CIVIL/MECHANICAL UTILITIES
G40 SITE ELECTRICAL UTILITIES
Z10 GENERAL PERFORMANCE TECHNICAL SPECIFICATION
4. PART 5 – PRESCRIPTIVE SPECIFICATIONS
[-- Not used --]
5. PART 6 – ATTACHMENTS
CONCEPT DRAWINGS
AIR FORCE SUSTAINABILTY REQUIREMENTS SCORE SHEET
GEOTECHNICAL REPORT AND MEMORANDUM
OWNERS PROJECT REQUIREMENTS
CONSTRUCTION SCHEDULE
eOMSI FACILITY DATA WORKBOOK
LCAA REPORT
LIST OF REQUIRED PERMITS
PERTINENT AIR FORCE CRITERIA
PART SIX - ATTACHMENTS - Page 1
PART SIX - ATTACHMENTS
General Requirements
FY25
Category Code 442-257
Joint Base Anacostia Boiling Washington DC
01 December 2025
PART TWO - GENERAL REQUIREMENTS - Page 2
THIS PAGE INTENTIONALLY LEFT BLANK
P001U Hazardous Waste Storage Work Order Number: 1817027
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 14 00 11/22, CHG 2: 05/24 WORK RESTRICTIONS
01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 3: 08/23 ADMINISTRATIVE REQUIREMENTS
01 31 19.05 20 02/21 CONCEPT DESIGN WORKSHOP (CDW)
01 31 23.13 20 08/23, CHG 1: 02/24 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
(eCMS)
01 32 17.00 20 05/25 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00.05 20 05/14, CHG 5: 03/23 CONSTRUCTION SUBMITTAL PROCEDURES
01 33 10.05 20 05/17, CHG 6: 03/23 DESIGN SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL
01 45 35 05/24 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 05/23, CHG 1: 11/23 FACILITY DATA WORKBOOK (FDW)
01 78 30.00 23 10/16 CADD DATA FOR GIS DELIVERABLES
01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING
01 91 19 05/2023 BUILDING ENCLOSURE COMMISSIONING
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 2: 05/24
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20 DESIGN SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
SD-07 Certificates
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Additional Personnel Requirements
1.2.1.2.1 General Construction and Finish Work
General construction and finish work of the controlled area must be performed by U.S. firms using U.S. citizens. General construction includes construction activities such as building sitework, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work. Finish Work includes construction activities such as insulation, floor, partition, and ceiling systems; cabinet work; conveyor systems; specialties; building furnishings, fixtures, and equipment; and mechanical and electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.
SECTION 01 14 00 Page 1
1.2.1.3 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.2.1.3.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.2.1.3.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.2.1.3.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
SECTION 01 14 00 Page 2
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.2.1.3.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.2.1.4 Additional Badge Requirements - NAS Patuxent River
Identification badges will be issued to the Contractor and his employees in accordance with the Naval Air Station Security Regulations. A copy of the security regulations may be obtained from the security office. All badges must be returned or accounted for to the department of Public Safety's Pass and Identification Office upon expiration of the badge or contract, or termination of the employee.
1.2.1.5 Employee List
The Contractor must provide to the Contracting officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract. The Contractor must adhere to the requirements of "Important Clarifications - Contractors - How to Gain Access," dated 31 October 1995, in obtaining access to the Naval Air Station complex for the life of the contract. A copy of these requirements will be provided at the preconstruction meeting.
1.2.1.6 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion.
1.2.1.7 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.2.2 Working Hours
Regular working hours will consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 3:30 p.m., Monday through Fridayand 7 a.m. to 3:30 p.m. on Saturday, excluding Government holidays.
SECTION 01 14 00 Page 3
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours.
During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.2.4 Occupied and Existing Buildings
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
1.2.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and are considered utility cutovers pursuant to the paragraph
WORK OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.3 SECURITY REQUIREMENTS
1.3.1 Joint Base Anacostia-Bolling (JBAB), Washington, DC
No employee or representative of the Contractor will be admitted to the work site unless he furnishes satisfactory proof that he is a citizen of the United States or is specifically authorized admittance by the OICC.
a. Personnel Information - All duty authorized non-military personnel utilizing the base are required to have in their possession at all times a Base Entry Pass. This pass is issued by the Visitors Control Center at the South Gate. Visitors Control is open Monday through Friday, 6:00 a.m. to 3:00 p.m. A minimum of 5 working days prior to start of work, the Contractor must furnish to the Joint Base Anacostia-Bolling (JBAB), Washington, DC, Security Department, via the Contracting Officer, the following information for Contractor and
SECTION 01 14 00 Page 4 subcontractor personnel required to enter the Station:
(1) Name of the company
(2) Name of the employee
(3) Social Security Number
(4) Proof of U.S. citizenship
(5) A completed Contractor/Vendor Criminal History Record Request
(6) A completed application for Base Entry Pass
b. Proof of Citizenship - Proof of citizenship will consist of copies of birth certificates, military dependent ID card, or naturalization papers, which will be returned once entered into the security computer system. The Security Department will run a criminal history check on Contractor employees and, as a condition of employment, each employee must willingly sign an authorization form allowing the Security Department to conduct the criminal history check. Subject authorization form will be maintained on file by the Security Officer. Based on proof of U.S. citizenship and the results of the criminal history check, the Security Officer will or will not grant entry to the Station. If entry is denied, the Contractor will be immediately notified.
c. Contractor Responsibility for Employees - The Contractor is responsible for employees under his employment. Ensure that employees are familiar with and obey station traffic, safety, and security regulations.
d. Motor Vehicle Operation - Ingress and egress of personnel will be subject to the security regulations of the Station.
(1) All personnel must be made aware of the base speed limits:
Housing areas 5 mph Parking areas 10 mph All other areas 25 mph (unless otherwise posted)
(2) Parking is in designed areas only, between two white lines. No parking is permitted in fire lanes, on seeded areas, in parking slots reserved for general officers and handicapped personnel.
(3) Traffic accidents should be reported immediately to the Security Police Law Enforcement Desk by calling 767-5000, 5001.
(4) All personnel entering the installation are subject to random vehicle inspections. The purpose of these inspections is to detect the theft of Government and private property, and to detect contraband or illegal drugs.
(5) Required Information on Privately Owned Vehicles - Advise company employees who desire to use their privately owned vehicles to personally bring the vehicle, vehicle registration, copy of vehicle insurance policy, valid state inspection documentation, and driver's license to the Visitor Control Center at the South Gate.
SECTION 01 14 00 Page 5
(6) Access to Restricted Areas - Base entry passes allow access to designated areas on the installation only. Entry into off limits areas is prohibited unless the contract requires it.
(7) Current Information - Contractors will be responsible for keeping the vehicle and employee lists current, and for securing and returning identification cards belonging to terminated employees to the Command Manager's Officer.
(8) Base Entry Passes - Contractor base entry passes will be valid for each entry aboard Joint Base Anacostia-Bolling (JBAB) from 6:00 a.m. to 6:00 p.m., Monday through Friday only, unless prior arrangements have been made with the Resident Officer in Charge of Construction, NDW, and the Base Security Officer, Joint Base Anacostia-Bolling (JBAB), has been notified. The passes are the property of the base and are to be returned to Visitors Control at the South Gate upon completion of the contract or termination of employment. Replacement passes must be requested in writing and be accomplished by written authorization from the Contracting Officer.
(9) Providing Information to Subcontractors - Prime Contractors are responsible for ensuring that subcontractors receive security information. Failure to comply with the specified requirements will result in prime contractors and subcontractors being denied access to the construction site.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 14 00 Page 6
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 3: 02/23
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and
01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices ; G
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 15 calendar days of Contract Award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction Contract) as directed by the Contracting Officer. Schedule of Prices must have cost summarized and totals provided for each construction category. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices. Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.
1.3.2 Payment Schedule Instructions
Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer. For design phase progress payment(s), the Schedule of Prices or Earned Value Report from the Cost Loaded CPM must include detailed design activities and general (summarized) approach for the construction phase(s) of the project. The Schedule of Prices or Earned Value Report must be fully developed with detailed construction line items as design progresses. The complete design and construction Schedule of Prices or Earned Value Report must be submitted and accepted prior to starting construction work.
For Fast-Tracked or Critical Path Submittals of construction projects, the
SECTION 01 20 00 Page 1
Schedule of Prices must include detailed design and construction line items for each fast-tracked/ critical path phase(s), submitted to and accepted by the Contracting Officer during the Post Award Kickoff Meetings and confirmed prior to starting construction work in that phase.
Additionally, the Schedule of Prices must be separated as follows:
a. Primary Facilities Cost Breakdown:
Defined as work on the primary facilities out to the 5 foot line.
Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 foot line.
b. Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 5 foot line.
1.3.3 Schedule Requirements for HVAC TAB
The field work requirements in Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC must be broken down in the Schedule of Prices and in the Construction Progress Documentation by separate line items which reflect measurable deliverables. The value for each pay item listed below will be established on a case by case basis for each Contract. The line items are as follows:
a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. Submit the resulting findings to the Government to allow correction of the design. The progress payment will not be issued until the report is reviewed and approved.
b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report must contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.
c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data must be collected for one seasonal condition (either summer or winter depending on project timing).
d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government. The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.
e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously
SECTION 01 20 00 Page 2 submitted Season I report.
f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. Compile this data into a report and submit to the Government. On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued. Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the
EP 1110-1-8 .
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.
b. The Estimate for Voucher/ Contract Performance Statement on NAVFAC Form 4330/54 furnished by the Government. Use NAVFAC Form 4330, unless otherwise directed by the Contracting Officer, on NAVFAC Contracts when a Monthly Estimate for Voucher is required.
c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.
d. Monthly Work-hour report.
e. Updated Construction Progress Schedule and tabular reports required by the contract.
f. Contractor Safety Self Evaluation Checklist.
g. Updated submittal register.
h. Solid Waste Disposal Report.
SECTION 01 20 00 Page 3
i. Certified payrolls.
j. Updated testing logs.
k. Other supporting documents as requested.
1.5.2 Submission of Invoices
Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR
32.103 Progress Payments Under Construction Contracts:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this Contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not
SECTION 01 20 00 Page 4 acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this Contract.
Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation must be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.
g. Materials in transit to the job site or storage site are not acceptable for payment.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 5
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 3: 08/23
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Health Requirements
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and
01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map
Progress and Completion Pictures
Design Submittal Packaging
Performance Assessment Plan (PAP)
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.
Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.
Include a date designator in file names. Photographs provided are for
SECTION 01 30 00 Page 1 unrestricted use by the Government.
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by law.
1.6 SUPERVISION
1.6.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.6.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.6.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION MEETING
Upon completion of design and design acceptance by the government, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The purpose of this meeting is to discuss and develop a mutual understanding
SECTION 01 30 00 Page 2 of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.7.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.8 POST AWARD KICKOFF (PAK) MEETING
Immediately after award, coordinate with the Contracting Officer a time and place for the PAK Meeting. The PAK meeting must be held within 35 calendar days after contract award and prior to commencing work. If mutually agreed upon by the Contractor and the Government, the PAK Meeting may be held concurrently with the Design Presentation/Design Development Meeting or Concept Design Workshop (CDW) whichever is required.
1.8.1 PAK Meeting Outcomes
a. Integrate the Contractor and all client representatives into the project team.
b. Achieve consensus from the project team on any issues and concerns with the Contractor's technical proposal and the User's functional requirements. Confirm the design is within the project budget.
c. Review the administrative requirements of the contract that are critical during the design phase.
d. Establish clear lines of communication and points of contact for Government and Contractor team members.
e. Obtain an acceptable conceptual design including floor and site plans, signed by the client, Contractor and other key team members.
f. Review the project design schedule and design package requirement, design submittal packaging , and preliminary construction schedule in accordance with Section 01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULE (NAS). Discuss design milestones and events that will be included in the Quality Control Communication Plan.
g. Establish clear expectations and schedules for facility turnover, providing DD Form 1354 asset management records, eOMSI submittals, Guiding Principle Validation, Third Party Certification (if applicable), and training of Government maintenance personnel.
h. Establish procedure for design packages reviews, Contractor's resolution to comments, and Government's role in review of packages.
i. Establish clear expectations for the Concept Design Workshop as established in UFGS 01 31 19.05 20 CONCEPT DESIGN WORKSHOP (CDW).
SECTION 01 30 00 Page 3
j. Establish clear expectations for Design Model presentations for projects implementing Building Information Management/Modeling (BIM).
1.8.2 PAK Meeting Contractor Attendees
The following Contractor personnel must attend the PAK meeting; Project Manager, Project Scheduler, Lead Designer-of-Record (DOR), Design Staff responsible for each architectural/engineering discipline when facility design is discussed, Superintendent, QC Manager, and the DQC Manager and the Commissioning Authority (CA). Optional attendees include: Principal, Assistant Project Manager, major subcontractors and specialized supplemental QC personnel.
1.9 DESIGN PRESENTATION/DEVELOPMENT (DP/D)
The Contractor must lead discussions to develop an understanding of the facility design that the accepted technical proposal represents with the Government users and maintainers of the facility. Develop site plans, floor plans, exterior finish materials, and building elevations to conduct working sessions with the Government meeting attendees. The purpose of the DP/D Meeting is to confirm the appropriateness of the facility design and develop acceptable alternatives if changes are needed. The Contractor must anticipate that Government Facility Users represented at the DP/D Meeting will provide additional functional information. Incorporate functional design changes into the facility design as required to meet the needs of the Users. At the end of the DP/D Meeting the Contractor must provide either assurance that the updated design can be built within the budget or identify potential cost modification items and establish a follow-on DP/D Meeting to finalize a design that will include trade-offs to bring the project within the budget. The following Contractor key personnel must attend the Design Presentation: Project Manager, Project Scheduler, Cost Estimator, Lead Designer of Record, Design Staff responsible for each architectural/engineering discipline when facility design is discussed, Major Subcontractors, and DQC.
Demonstrate ability to achieve identified Guiding Principle sustainability goals and also Third-Party Certification sustainability goals, if applicable. Provide Preliminary Sustainability Notebook, refer to Section 01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING for requirements.
1.10 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NAVFAC Red Zone Meetings beginning at approximately 75 percent of project completion. Include the following in the facility Turnover effort:
1.10.1 Red Zone Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.
b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The
SECTION 01 30 00 Page 4
Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.
1.10.2 Meetings
a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.
At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.
c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.
e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.
Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.
1.11 PARTNERING
To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, NAVFAC, PWD, FEAD/ROICC, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.
1.11.1 Team-Led (Informal) Partnering
a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.
b. The Initial Team-led Partnering session may be held concurrently with the Post-Award Kickoff meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.
c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.
d. The Partners will determine the frequency of the follow-on sessions.
SECTION 01 30 00 Page 5
e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.
1.12 PERFORMANCE ASSESSMENT PLAN (PAP)
The Performance Assessment Plan (PAP) will be used to document design innovation and budget management, provide performance feedback to the Contractor, and as a basis for interim and final evaluations in the Contractor Performance Appraisal Reporting System (CPARS) on-line database.
It is the intent of the Government to establish the PAP based on tangible, measurable indicators of outstanding contractor performance, and on commitments made in the Contractor's proposal. The initial PAP may be found on the NAVFAC Design-Build Request for Proposal Website in RFP PART 6 Attachments. Review and finalize the initial PAP during the Partnering Session. During the initial Partnering Session, the Government, the Contractor, the Designer-of-Record, and the Client will establish the PAP.
Following the establishment of the PAP, the Contractor will present it, with his input, for update and discussion at projects meetings which discuss project performance. Submit an updated PAP on a monthly basis with the invoice for that period as a minimum.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 6
SECTION 01 31 19.05 20
CONCEPT DESIGN WORKSHOP (CDW)
02/21
PART 1 GENERAL
1.1 SUMMARY
This document includes post-award requirements for the concept design workshop.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 REQUIREMENTS AND REPORTING. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20 DESIGN SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
CDW Facilitator Experience Resume ; G
CDW Preliminary Concept Design ; G
CDW Report ; G
1.3 CONCEPT DESIGN WORKSHOP (CDW)
Provide a CONCEPT DESIGN WORKSHOP that meets the following requirements:
1.3.1 CDW General Requirements
a. Methodology. Conduct a CDW for this project. This effort will examine programmatic functions, review project requirements, ensure life and operational safety requirements are met, analyze alternate design concepts, expose and resolve project issues, and develop the final conceptual design.
b. Facilitator. Provide a Facilitator who is experienced in conducting Concept Design Workshops. Submit a CDW Facilitator Experience Resume to the Contracting Officer describing experience with facilitation including a minimum of three examples. He or she will be responsible for leading the team in a timely manner, making sure issues are addressed and resolved during the CDW, documenting meetings held throughout the CDW, organizing concept design documents for on-site presentations and endorsement, and providing the Concept Design Workshop Report.
c. Contractor's Design Team. The primary functions of the Design Team will be to investigate, develop and present alternate design solutions. The entire Design Team must participate in all phases of the Concept Design Workshop and assist the Facilitator in developing the Concept Design Workshop Report.
SECTION 01 31 19.05 20 Page 1
d. Concept Design Workshop Report. Summarize the workshop including the various concepts developed and presented. Include a copy of the signature/endorsement sheet prepared and signed at the end of the on-site CDW.
e. Award Amount. Confirm the final concept is within the contract award amount.
1.3.2 CDW Procedures
a. Preliminary Work.
Complete the following prior to the on-site workshop:
(1) Review the contract documents and references explaining the project scope and history.
(2) Prepare and submit, at least 14 days in advance of the CDW, electronic copies and an agreed upon number of hard copies of a CDW Preliminary Concept Design (Concept #1) and a Basis of Design.
As a minimum, include the following in the CDW Preliminary Concept Design:
(a) Site Plan
(b) Building Floor Plans
(c) Building Elevations
(d) Mechanical Plans
(e) Electrical Plans
(3) Make arrangements for and provide an appropriately sized conference room convenient to the project site and Users for use by the Design Team and government participants during the workshop.
(4) Incorporate any government comments received prior to the CDW into a revised Concept #1 and provide at least 20 hard copies of the revised Concept #1 documents for distribution at the workshop. If there are no revisions to the CDW Preliminary Concept Design provide at least 20 hard copies of the original Concept #1 documents for distribution at the workshop.
(5) Facilitator conducts meeting with NAVFAC representatives before the CDW to review preparations, relationships, and the status of work to be accomplished.
b. On-Site Workshop.
On-site CDWs are typically conducted over three to five working days with minimal breaks throughout the workshop. The Design Team can expect longer than normal workdays. Accomplish the following during the on-site CDW.
(1) On the first day of the workshop, meet with the using activity, Station and other Government representatives. The Facilitator will describe the CDW process and review the workshop agenda. The User(s) may provide a functional presentation to review User(s) requirements to aid in further development of the conceptual design.
SECTION 01 31 19.05 20 Page 2
(2) Present the revised Concept #1 and respond to questions.
(3) (3) Conduct a comment/creative session to generate ideas to improve the conceptual design within the award amount. Document or request User and Government comments in writing so they may be considered, responded to, and presented at subsequent presentations.
(4) Develop a new concept design based on comments and feedback received from the Concept #1 presentation on the first day of the CDW. Include drawings, sketches, and other graphics as necessary to describe the concept design. Prepare at least 20 hard copies for distribution at all presentations.
(5) Repeat applicable steps as necessary. Three concepts are typically required.
(6) The final concept must include the following:
(a) Site Plan: Show the layout of the proposed facility in relation to major landmarks. Show all buildings, access roads, parking, pedestrian walkways, roads, sidewalks, landscaping, and major utilities. Indicate major dimensions and orientation.
Provide a building code analysis, relating the proposed building site, size, and construction type to maximum allowable limits of the…