Oregon Project Broad Scope Requirements.pdf
PDF 705 KB Posted
- Attached to
- Over the Horizon Radar Sources Sought
- Solicitation number
- W912DQ26RA092
About this file
This document is a Scope Requirements briefing for the Oregon Project Broad, a Military Construction (MilCon) program managed by the U.S. Army Corps of Engineers, Kansas City District. The project involves construction of radar facilities at two remote sites in Oregon separated by approximately 125 miles, with driving times of 3-4 hours to major metropolitan areas. The total program budget is approximately $250-500 million, with target dates for advertising qualifications in FY27Q2, construction contract award in FY27Q4, and project completion in FY29Q1.
Site 1, located approximately 2.5 hours southwest of Boise, Idaho, requires extensive civil work including grading and earthworks (891,722 cubic yards of cut and 776,234 cubic yards of fill), five antenna rows each 9,000 feet long and 800 feet wide, and construction of an Operations Facility (10,787 SF), Water Treatment Building (1,323 SF), Vehicle Maintenance Shelter (1,600 SF), Vehicle Storage Shelter (2,450 SF), Security Building (387 SF), fueling station, and power area with fuel storage. Site 2, located approximately 250 miles northwest of Site 1, requires similar facilities with a larger Operations Facility (13,288 SF), minimal cut and fill (9,489 cubic yards cut and 7,808 cubic yards fill), a Substation, and a Helicopter Landing Area. Both sites require utility infrastructure including paving, water treatment systems, and fencing. Construction must occur concurrently at both sites but is not sequential. The RFP will detail phasing requirements and coordination requirements with the radar system integrator. Key project challenges include remote locations with minimal local workforce availability, logistical and material supply chain constraints, limited utilities availability, and multiple Joint Use Dates and Beneficial Occupancy Dates that will drive construction scheduling.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PLA Survey.pdf | ||
| Industry Feedback Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OREGON PROJECT BROAD
SCOPE REQUIREMENTS
Northwestern Division
US Army Corps of Engineers
USACE, Kansas City District
Michael France – Contracting Officer michael.g.france@usace.army.mil
Jeri Halterman – Contracting Specialist jeri.l.Halterman@usace.army.mil
SCOPE & SCHEDULE
Total MilCon Program Amount: ~$250M
-500M
Remote Locations:
Transmit (Tx) and Receive (Rx) Sites are in separate remote sites approximately 125 miles straight line distance apart.
Driving times to major metropolitan areas are 3-4 hours.
Program Scope: Schedule: These are target dates only
• Advertise for Qualifications (Step-1)
• Construction Contract Award
• Project Complete
FY27Q2
FY27Q4
FY29Q1
OREGON
Facilities at each site may include:
• Operations Facilities
• Antenna Foundations and Support Structures (Multiple and differing types)
• Power and Fueling Areas at each site
• Water Treatment at each site
• Vehicle Maintenance/Storage Facilities and others (Multiple Buildings)
• Fencing (multiple types)
Not included in this is the project is the design and installation of the radar system (antennas, associated cables, and electronic operations equipment). However, close coordination with the radar installer is required as once facilities are available for radar install, the installer will be working on site while facilities construction is ongoing. There are multiple Joint Use Dates (JUD) and Beneficial Occupancy Dates (BOD) associated with this project to facilitate radar installation. The JUDs and BODs will drive your schedule.
PLANNED CONSTRUCTION OVERVIEW
Construction at Tx and Rx must be concurrent but not sequential. They do not have to finish on the same date.
SITE Civil Work associated with this project will include:
• Paving
• Fuel Storage
• Water Storage
• Utility Infrastructure
• Large scale grading/earthworks
• Footings for antenna arrays
• Fencing
Some phasing of construction efforts and coordination with system integrator during construction will be required, phasing requirements will be outlined in the
RFP.
CONSTRUCTION SITE CIVIL WORK
The following information is for information purposes to provide responses to the questionnaire.
Site 1 – Located approx. 2.5 hrs SW of Boise, ID
Cut and Fill Quantities (All Rows) Cut (CY) Fill (CY) NET (CY)
891,722 776,234 115,488
Red: Cut, ~891,700 CY
Green: Fill, ~ 776,200 CY
• 5 rows, each row ~9,000’ long (1.7mi), ~ 800’ wide
• Rows 1 and 2 are first priority
• Clearing required:
o low-lying sage and brush, no trees o along the perimeter fence line (for fence installation) + 20 feet (to account for loop perimeter road, which is outside the fence line);
perimeter fence runs around all 5 rows.
o the ~800’ x 9000’ area for each antenna row, 5 rows total (see row detail below) o Grading will be only along the rows (~800’ wide per row) o Fine grading includes +/- 6 inches within each row o Assume cut material will be used as fill, no extra fill needed o Extra cut material will be placed on site within ½ mile of row area
Site 1 - Individual Row Detail (area to be cleared)
1 lane gravel Access Road, 10’ behind back of shelters
Shelters
Transformer
22’ 40’ 44’
Screen Area
Leveled +/- 6”
Screen Area
Leveled +/- 6”
88’ 568’
Forward Plain Area
Terrain shall not exceed 2 degrees of elevation fall, Shelters
38’
Access Area (includes road)
Forward Plain Area does not require clearing, to be left natural, assume terrain is within 2 degrees of elevation
Site 2 – Located approx. 250 miles Northwest of Site 1
• Cut and fill occurs only within the red/green areas identified above. The remaining area is generally flat and only requires masticating
• Area within the 1.5 x 0.58 mile
• The landscape is sage and brush, no trees or very few small scrub trees are present
CONSTRUCTION FACILITIES
Site 1
• Operations Facility, Pre-Engineered Building (PEB) on slab, 10,787 SF o Server Room, workshop, office area, restroom, comm room, break room, logistics room, mechanical room, electrical room o EMI shielding in comm room, EMI shielding for UPS (located in electrical room) o 160 SF UPS Battery Shelter o Electric, comm, water, sewer (septic system) utilities
• Water Treatment Building, PEB on slab, 1,323 SF o Fire water storage tank required, commercial off the shelf o Potable water storage tank required, commercial off the shelf o Connect to water well (well installed by others) o Treatment system for potable water
• Vehicle Maintenance Shelter, PEB on slab, 1,600 SF o One 12’x12’ garage door o No heating o Electric and water utilities
• Vehicle Storage Shelter, PEB on slab, 2,450 SF o Electric utilities only, no heating o Drive through Overhead Doors o Workbench areas
• Power Area o Gravel area with all equipment and fuel storage on concrete pads o Houses transformers, backup generator system (2 generators, government furnished), 14.4KV load bank (government furnished), 80,000 gal generator fuel storage (double walled), switchgear integrated with SCDA, Network, and Metering System.
• Fueling station (gasoline and diesel dispensing) with minimum 500 gal storage for diesel and 500 gal storage for gasoline
• Security Building, PEB on slab, 387 SF o Electric gate arm, lighting, fencing o Comms
Site 2
• Operations Facility, Pre-Engineered Building (PEB) on slab, 13,288 SF o Equipment Room, workshop, 1 office (open classified storage), Secure comms closet, Server room, restrooms, break room, logistics, fire/mechanical room, comm room, and electric room o Utilizes Fluid Cooling units on 8’x30’ concrete pad outside of facility o Specialized cable entry ports o Electric, comm, water, sewer (septic system) utilities
• Water Treatment Building, PEB on slab, 1,323 SF o Fire water storage tank required, commercial off the shelf o Potable water storage tank required, commercial off the shelf o Connect to water well (well installed by others) o Treatment system for potable water
• Vehicle Maintenance Shelter, PEB on slab, 1,600 SF o One 12’x12’ garage door o No heating o Electric and water utilities
• Vehicle Storage Shelter, PEB on slab, 2,450 SF o Electric utilities only, no heating o Drive through Overhead Doors o Workbench areas
• Power Area o Gravel area with all equipment and fuel storage on concrete pads o Houses transformers, backup generator system (2 generators, government furnished), 14.4KV load bank (government furnished), (4) 60,000 gal generator fuel storage (double walled), switchgear integrated with SCDA, Network, and Metering System.
• Fueling station (gasoline and diesel dispensing) with minimum 500 gal storage for diesel and 500 gal storage for gasoline
• Security Building, PEB on slab, 387 SF o Electric gate arm, lighting, fencing
Site 2 Continued
• Substation – serves as electrical utility interconnect and site distribution substation, includes enclosure for control shelter (with heating and cooling), fence, power distribution
• Helicopter Landing Area, 100’ x 100’, minimal earthwork required.
1) Remote Site locations
1) Two sites within the project separated by over one hundred miles with concurrent construction
2) Minimal to no local workforce availability
3) Logistical/material supply chain challenges
a) Limited local sustainment/material/utilities availability
b) Long travel distances from nearest major city
c) Waste disposal
4) JUDs/BODs which will drive construction scheduling
KNOWN CHALLENGES/RISKS FOR THIS PROJECT
| Slide 1: OREGON PROJECT BROAD SCOPE REQUIREMENTS |
| Slide 2: SCOPE & SCHEDULE |
| Slide 3: PLANNED CONSTRUCTION OVERVIEW |
| Slide 4: CONSTRUCTION SITE CIVIL WORK |
| Slide 5: CONSTRUCTION SITE CIVIL WORK |
| Slide 6: CONSTRUCTION SITE CIVIL WORK |
| Slide 7: CONSTRUCTION SITE CIVIL WORK |
| Slide 8: CONSTRUCTION SITE CIVIL WORK |
| Slide 9: CONSTRUCTION FACILITIES |
| Slide 10: CONSTRUCTION FACILITIES |
| Slide 11: CONSTRUCTION FACILITIES |
| Slide 12: KNOWN CHALLENGES/RISKS FOR THIS PROJECT |