OMB-MC3804000164-AD 1.pdf
PDF 2 MB Posted
- Solicitation number
- OMB-MC3804000164
- Issued by
- Sussex County, Delaware
About this file
This Pre-Bid Meeting Minutes and Addendum No. 1 document pertains to the Delaware Department of Correction's request for sealed bids for the SCI Maintenance/SVOP Generator & ATS Replacement project at Sussex Correctional Institution, located at 23203 DuPont Boulevard, Georgetown, Delaware. The project scope involves replacing two diesel-fired emergency/standby generators (a 100 kW unit at the SCI Maintenance Building and a 200 kW unit at the SVOP Center) with natural gas units integrated into existing electrical distribution systems, along with replacement of Automatic Transfer Switches at both facilities. The mandatory pre-bid meeting was held on October 13, 2026, at 10:00 AM at the Haslet Armory in Dover, and attendance was limited to prime bidders. Sealed bids are due by 1:00 PM on November 12, 2026, via the Bonfire Portal or in-person delivery at 122 Martin Luther King Jr. Boulevard South, Dover, Delaware 19901, with bid opening and reading scheduled for 2:00 PM the same day. A site review is scheduled for 10:00 AM on October 20, 2026, limited to a maximum of three representatives per registered contractor and requiring background clearance approval. Contract award is anticipated within 30 days of bid opening, with project completion measured in calendar days from Purchase Order receipt to Substantial Completion. The contractor must provide a phasing plan due to ongoing facility operations restrictions and will be required to maintain temporary or roll-up generators during construction.
The base bid includes all work shown in the contract documents with two allowances: $50,000 for unforeseen system modifications and $25,000 for utility company costs. A bid bond or certified check equal to 10 percent of the bid amount is required; the successful contractor must post performance and payment bonds each equal to 100 percent of the contract price. Delaware prevailing wage rates for Sussex County Building Construction classification, effective March 15, 2026, apply to this project, and both the prime contractor and all listed subcontractors must have drug testing programs in place. Subcontractors must be identified in three categories: Electrical, Mechanical, and Concrete, with any additional third-tier subcontractors listed under the appropriate category. The contract requires a two-year warranty on work and materials beginning on the date of substantial completion. The facility operates as a correctional institution with 24/7/365 restricted access; all on-site personnel must receive DOC background clearance approval, work only with a DOC escort, maintain proper identification, and adhere to strict work hour restrictions of 7:00 AM to 3:00 PM, Monday through Friday. Contractor-initiated equipment shutdowns must be performed after normal working hours or on weekends and require advance DOC coordination. The facility is tobacco-free, and the contractor is responsible for all permits, licenses, required inspections, and fees.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OMB-MC3804000164-wages.pdf | ||
| OMB-MC3804000164-rfp.pdf | ||
| OMB-MC3804000164-spec.pdf | ||
| OMB-MC3804000164-Exemption From Plan Publication.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-BID MEETING MINUTES-ADDENDUM NO. 1
SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT
DELAWARE DEPARTMENT OF CORRECTION
SUSSEX CORRECTIONAL INSTITUTION
23203 DUPONT BLVD, GEORGETOWN, DE 19947
OMB/DFM PROJECT #: MC3804000164
A Mandatory Pre-Bid Meeting was held at the Haslet Armory Building, Main Conference Room on Tuesday, October 13, 2026 at 10:00 AM. Those in attendance were:
Michael Bailey OMB/Division of Facilities Management Jon Pugh Fidelity Power Systems TJ Hartley Diamond Electric Teagan DiRusso Filec Services Thomas O’Flynn Superior Electric Josh Morris B.W. Electric, Inc.
Chris Hyatt Electrical Integrity Fred Fisher First State Electric Company Rich Arndt H&A Electric Joe Waski H&A Electric Matt Bailey Power Plus Electrical Contracting, Inc.
Heather Fayda Fayda Engineering & Energy Solutions, LLC Matthew Galinskie, AEE Fayda Engineering & Energy Solutions, LLC
Date of Report: October 19, 2026 FE&ES Comm. No.: 25-1643C
Items of Discussion:
1.0 These Pre-Bid Meeting Minutes, Addendum No. 1, shall be made part of the Project Manual and
Drawings dated September 2026 for “SCI Maintenance/SVOP Generator & ATS Replacement” at Sussex Correctional Institution, 23203 Dupont Blvd, Georgetown, DE 19947.
2.0 Sealed bids for OMB/DFM Contract No. MC3804000164 Project Name: SCI Maintenance/SVOP
Generator & ATS Replacement will be received by the State of Delaware, Office of Management and Budget, Division of Facilities Management, by way of the Bonfire Portal at https://DFM.bonfirehub.com until 1:00 PM local time on November 12, 2026. Bids may also be delivered in person to 122 Martin Luther King Jr BLVD S Dover DE 19901 no later than the date and time indicated above. Bidder bears the risk of late submission.
Bids will be opened and read aloud at 2:00PM local time on November 12, 2026 at the Haslet
Armory, 122 Martin Luther King Jr. Blvd. S., Dover, DE 19901.
3.0 This is a mandatory pre-bid meeting and only Prime Bidders are limited to those in attendance.
Pre-Bid Meeting Minutes & Addendum No. 1 SCI Maintenance/SVOP Generator & ATS Replacement Sussex Correctional Institution
4.0 For further bidding information relating to the Project Manual and Drawings, the contractors are directed to contact Matthew Galinskie, AEE at Fayda Engineering & Energy Solutions, LLC at telephone: 302-999-1060. Contractor Requests for Substitution, Clarification or Interpretation shall be delivered electronically (by email) to mgalinskie@faydaees.com, with CC to efayda@faydaees.com. Ensure the project title, contractor’s name and RFI # are in the subject line. (Example: SCI Maintenance/SVOP Generator & ATS Replacement “Contractor Name”- RFI #1)
5.0 The wage rates for this Project are Delaware Department of Labor and Division of Industrial Affairs for Sussex County, Building Construction Classification, effective 3/15/26. A certified copy of the prevailing wage rates and Debarred list of contractors for this specific project is included in the Project Manual. This approved scale of wages must be posted by the Contractor in a prominent and easily accessible place at the work site.
6.0 Contractors are to contact the Department of Labor if they have any questions with regard to the State Prevailing Wage Law or clarifications on payroll reporting. Telephone number is 302-451- 3423.
7.0 Contractors are reminded that if they are a recognized contractor that customarily performs the work of a given subcontractor classification; that they can list themselves on the line for that particular subcontractor category. DO NOT LEAVE ANY BLANKS ON THE BID FORM. DO NOT ADD
ANY ADDITIONAL VERBIAGE OTHER THAN WHAT IS REQUESTED. FAILURE TO DO SO MAY
DISQUALIFY YOUR BID. As an example, if you are an electrical contractor that will self-perform the electrical work, that you list your company on the Electrical Subcontractor line on the bid form. Ensure your address, business license, etc. is also included on the bid form.
8.0 The prime contractor and all listed subcontractors must have a drug testing program in place.
There is an Affidavit located with the Bid Form.
9.0 Project Summary
Project scope: The SVOP and SCI Maintenance Buildings both maintain a 200kW diesel fired emergency/standby generator. This project will replace both with a Natural Gas unit and integrated into the existing building electrical distribution system. At both buildings, the existing Automatic Transfer Switches will be replaced.
Base Bid: All work shown on the Contract Documents
Alternates: There are no Alternates
Unit Prices: There are no Unit Prices
Allowances:
ALLOWANCE #1: $50,000.00 for “Unforeseen system modifications”.
ALLOWANCE #2: $25,000.00 for “Utility Company Costs”.
Sussex Correctional Institution
10.0 Contractor must be a registered plan holder in order to submit a bid. One complete Bid Form shall be submitted. Only Addendum #1 will be sent out to all attendees of the Pre-bid meeting.
All other addenda will be sent out to the registered plan holders via email. Contractors are encouraged to monitor their email accounts during the Bidding period for such updates.
11.0 Bidders shall verify that their Sub-bidders are in full receipt of the information contained herein.
12.0 A two (2) year warranty is required on work and materials beginning on the date of substantial completion.
13.0 One of the purposes of the pre bid is to establish a list of subcontractors. A revised list is included with the attached Bid Form. They are:
1. Electrical
2. Mechanical
3. Concrete
Any subcontractors used but not specifically named must also be listed as a 3rd tier subcontractor under the listed subcontractor category. The omission of a required 3rd tier subcontractor may render your bid non-responsive. When in doubt, list it.
14.0 In completing the Bid Form, contractors shall identify the # of calendar days to complete the project beginning on the date that their PO is received and completed on the Date of Substantial Completion.
15.0 The following sections of the specifications were reviewed:
Section Article Title ------ Advertisement for Bids 00 21 15 3.3 Instructions to Bidders 00 26 00 ------ Procurement Substitution Procedures & Forms 00 10 00 1.03 Project Summary 00 81 16.1 ------ DOC Security Form #1 00 81 16.2 ------ Security Clearance Application 26 32 13 1.5 Engine Generators
16.0 The drawings were generally reviewed to present the intent of the contract documents.
1. The project must be internally phased due to restrictions that may affect ongoing operations.
2. A proposed phasing plan has been provided; however, since this is a Means & Methods issue, the successful contractor shall provide their own phasing plan. It should not be submitted with your bid.
3. Temporary/Roll Up generators will be required. Duration and quantity are a Means &
Methods issue; however, the shorter the rental, the lower the cost.
Sussex Correctional Institution
17.0 The following items were discussed in detail:
A. Work Restrictions
1. This is a Correctional Facility. Restricted access is required 24/7/365. Work shall only be performed with a DOC escort.
2. Only staff that have submitted and received approval of a background check will be permitted on site. This includes the contractor’s walkthrough and construction.
3. Access to the Facility:
a. Contractors shall check in daily with the DOC provided escort at the exterior of
Facility. In general, access through the main building entrance will not be required.
b. Proper ID is required at all times by all on site personnel.
c. Cell phones and cameras will be permitted outside secure fencing areas only. Use of cell phone or camera within the Facility must be pre-approved during construction.
d. Contractor will be permitted to park company vehicles at the Maintenance
Building and SVOP parking lots. Contractor vehicles will be subjected to daily tool inventory and security checks while working at the SVOP Facility only. Tool inventory will not be required for work being performed at the SCI Maintenance
Facility.
e. A tool inventory log will be required at the beginning and end of each work day while working at the SVOP Facility only. Tool inventory will not be required for work being performed at the SCI Maintenance Facility. Tools shall not be left unattended.
4. An exterior lockable job box may be staged at the existing generator location, or in a Mechanical Room during construction.
5. Equipment may remain on site after working hours provided all equipment is properly locked and secured, and located outside of the secure fence.
6. Vehicles & other equipment shall not be left unattended and shall be secured at all times. All construction materials & tools must be secured or removed from the site when contractors are not actively working in a designated area.
7. On-Site Work Hours: Working hours will be 7:00 a.m. to 3:00 p.m.; Monday thru Friday. Any shutdowns to existing equipment must be performed after normal working hours, or on weekends, and shall be coordinated and approved by DOC in advance.
B. There is a short window to get your background checks in and approved before the walkthrough. Contractors shall expedite submission of all security clearance forms directly to Steven Brown at Steven.Brown@delaware.gov
Sussex Correctional Institution
C. Substitution Requests: A standard of design is identified in the specifications along with pre-approved equals. Any manufacturer other than the Standard of Design will be required to submit a complete submission for review for acceptance and posting via Addendum. The deadline for substitution requests is 10 days prior to bid opening, or 1:00 PM on Monday, November 2, 2026.
Instructions for requesting substitutions are very specific and are contained in the project manual. If the contractor does not follow the process, it is automatic grounds for rejection.
D. All questions should be directed in writing to the Engineer. Contractors are encouraged to submit questions as soon as possible. All answers to questions not in addendum format will not be binding. In the case of a conflict between the specifications and drawings or within each not answered by addendum, the greater quantity or better quality shall be provided. The deadline for questions shall be or 1:00 PM on Friday, November 6, 2026.
E. Billing for stored material will not be paid unless the material is on the jobsite and in a secure location under the contractor’s control.
F. Contractor shall provide a lockable portable toilet for the duration of on-site construction.
G. The facility is tobacco free. No form of tobacco is permitted on site; including e-cigarettes, vape, etc.
H. Contractor will be responsible for all permits, licenses, required inspections and fees for this project.
I. Contractors are reminded that it will be unlikely that the bid due date will change.
18.0 A site review of the project site is scheduled for 10:00 AM, Thursday, October 20, 2026 for all registered attendees. A maximum of 3 representatives will be permitted for each registered contractor. In order to attend this site review, a background check is required. A copy is included with the pre-bid meeting minutes.
Contact Matt Galinskie at the Engineer’s office at 302-999-1060 to register for the walk-thru. If no one registers, the walk through will be cancelled.
19.0 The successful contractor shall designate one job foreman who will remain as the main point of contact throughout the duration of the project. This foreman must be on-site whenever any sub-contractors are on-site
20.0 Reminder: For your bid to be deemed responsive, you need to include:
1. Bid Form- One (1) Original, no blanks use the latest version published by Addenda.
2. Bid Bond or Certified check in the amount of 10% of your bid.
3. Drug Testing Affidavit for Prime Contractor.
4. Affidavit of Contractor Qualifications.
Sussex Correctional Institution
21.0 Changes to Specifications
21.1 Section 00 41 13 Bid Form: Replace current Bid Form with the one attached that includes subcontractor listing.
21.2 Delete two (2) duplicate Sections 26 32 13.2 “Engine Generators – SCI Maintenance” in their entirety.
21.3 Delete Section 26 32 13.2 “Engine Generators – SVOP” in its entirety.
21.4 Add new Section 26 32 13.1 “Engine Generators – SCI Maintenance” in its entirety.
21.5 Add new Section 26 32 13.2 “Engine Generators – SVOP” in its entirety.
22.0 Changes to Drawings
22.1 No changes to Drawings.
23.0 Questions/Clarifications
23.1 No Questions or Clarifications.
Original Signature on File
Matthew Galinskie, AEE MG/mg 25-1643C Addendum #1- Pre-Bid Meeting Minutes #1
Attachments: Sign-in Sheet 00 41 13 Bid Form 00 81 16.2 Security Clearance Application 26 32 13.1 Engine Generators – SCI Maintenance 26 32 13.2 Engine Generators – SCI Maintenance cc: All in Attendance All Registered Plan Holders P-File
4FAYDA ENGINEERING&
• ENERGY SOLUTIONS, LLC
Pre-Bid Sign-In Log
PLEASE FILL OUT COMPLETELY AND LEGIBLY
Tuesday, October 13, 2026 PROJECT NAME: SCI Maintenance/SVOP Generator & ATS Replacement
Sussex Correctional Institution I3203 DuYont Blvd., Georgetown. DE 19947
FE&ES COMM. NO.: 25-1643C
OMB/DFM PROJECT NO.: MC3804000164
PRE-BID MEETING: Tuesday, October 13, 2026@ 10:00am BIDS DUE: Thursday, November 12. 2026@ 1:00pm (elec. via Bonfire) BID OPENING: Thursday, November 12, 2026@ 2:00pm
MEETING START: MEETING END: ____ _ Main Lobby; Haslet Armory 122 Martin Luther King Jr. Blvd. South, Dover DE 19901
Company Name Representative Address Phone & Fax Email Arrival Time
Fayda Engineering & Matthew Galinskie, AEE
801 W. Newport Pike, 302-999-1060 mgalinskie@faydaees.com ?·~() Energy Solutions, LLC Wilmington DE 19804 302-999-1053
Fayda Engineering & Heather Fayda
801 W. Newport Pike, 302-999-1060 hfayda@faydaees.com f/: t/D
Energy Solutions, LLC Wilmington DE 19804 302-999-1053 fidv1 ~r J:>-JVu:J'-" 4-!; Loie..~ c.vck- 'ii 0-1-=J--I - j l>'-t) lt\ ~~doJ .~ -~ 94.r S\..\ ,~A\J ~~, t--Av Zt\ ~Z.. q400 C,./J(""
J 1J -H"'r+I e V JS bb fc,,o-d--1rc-c... r.,r, "5oz. b0/"7 }Z°'.'1 A ~.,(/eJS @d: ... roac,-' D{P/WJND J;.{c!-W ··C qys-17,s:, <n1/( Vl.., ~o I elwf,--;·c. O(d
,,-;- 55 77 (/ tJ po" -( H1.1y )o l - 72a -71 tJ (5f,' 1'14 f t'llj@(/{tt >trvl(t).OA 5avt'Ct) I ea9411
Fi(tC (li'!ivJJ" I f"yr114. () E 19911 j:l(o
$u.~0C- ~~~~ g'2 C,, ~I' ./"t<'<-~ 0 1 302- '3 3 -z-9 3,l(t( +-\Ao,..."'$ @ £- <-'.-fv, ~ r- - 10 :00 [/c,d·-r I(... o ·At1vvv- u :,.M :"'6to"', (}E 1rao<f cl~c/-rlc. , b, r.
Pre-Bid Meeting Minutes-Addendum #1 SCI Maint/SVOP Generator Replacement
V
, f:
- V
C l n 0 3 "C
D J z D
J 3 (1
(1
"C .... (1
V
(1
, -DJ - <' (1
a a . ro V
V j
0 ::
(1 ) 12
"T
D
X m
3 D
Pre-Bid Meeting Minutes-Addendum #1
.:c i, I
B
-:1 7 ~
-:s
A e.
L
I( b' b-
¾
(0 f
"t :s - -l
.r
:z t\
- I';
\ 0, <">
~ ~ " C C n1 "fi
\ ~J
0'
/ r
Vi l\ _, ~
I>' 1\
~'t i.
J\
Cl ' :i::
$ 0 0 u n 0 3 "C
Il z Il l 3 rD
"C
, .... Il l .... <' a a "' "' " :::r 0 ::
) Ro ..., Il
X
3 Il
Pre-Bid Meeting Minutes-Addendum #1
BID FORM
SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT
SUSSEX CORRECTIONAL INSTITUTION
OMB/DFM PROJECT: MC3804000164
FAYDA ENGINEERING & ENERGY SOLUTIONS BID FORM
FE&ES Comm.: 25-1643C 00 41 13-1
For Bids Due: 1:00 PM; Thursday, November 12, 2026 To: Mr. Michael Bailey, Construction Project Manager OMB/Division of Facilities Management Haslet Armory Building 122 Martin Luther King Jr. Blvd-South Dover, DE 19901
Name of Bidder:
Delaware Business License No.: Taxpayer ID No.:
(Other License Nos.):
Phone No.: ( ) - Fax No.: ( ) -
The undersigned, representing that he has read and understands the Bidding Documents and that this bid is made in accordance therewith, that he has visited the site and has familiarized himself with the local conditions under which the Work is to be performed, and that his bid is based upon the materials, systems and equipment described in the Bidding Documents without exception, hereby proposes and agrees to provide all labor, materials, plant, equipment, supplies, transport and other facilities required to execute the work described by the aforesaid documents for the lump sum itemized below:
BASE BID: PROVIDE ALL WORK SHOWN ON THE CONTRACT DOCUMENTS.
Amount: ($ )
ALTERNATES
There are No Alternates
ALLOWANCES:
ALLOWANCE #1: We have included an allowance amount equal to $50,000 in the Base Bid for miscellaneous costs not identified on the bid documents. I/We have reviewed and familiarized ourselves with the requirements contained in Specification Section 01 21 00 Allowances.
Acknowledged by: __________________________________________________
ALLOWANCE #2: We have included an allowance amount equal to $25,000.00 in the Base Bid for Utility Company Costs. I/We have reviewed and familiarized ourselves with the requirements contained in Specification Section 01 21 00 Allowances.
Acknowledged by: __________________________________________________
UNIT PRICES:
There are no Unit Prices.
Pre-Bid Meeting Minutes-Addendum #1 SCI Maint/SVOP Generator & ATS Replacement
DELAWARE DEPARTMENT OF CORRECTION
SUSSEX CORRECTIONAL INSTITUTION
BID FORM
SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT
SUSSEX CORRECTIONAL INSTITUTION
OMB/DFM PROJECT: MC3804000164
BID FORM FAYDA ENGINEERING & ENERGY SOLUTIONS
00 41 13-2 FE&ES Comm.: 25-1643C
I/We acknowledge Addendums numbered and the price(s) submitted include any cost/schedule impact they may have.
This bid shall remain valid and cannot be withdrawn for thirty (30) days from the date of opening of bids (60 days for School Districts and Department of Education), and the undersigned shall abide by the Bid Security forfeiture provisions. Bid Security is attached to this Bid.
The Owner shall have the right to reject any or all bids, and to waive any informality or irregularity in any bid received.
This bid is based upon work being accomplished by the Sub-Contractors named on the list attached to this bid.
Should I/We be awarded this contract, I/We pledge to achieve substantial completion of all the work within calendar days of the Notice to Proceed.
The undersigned represents and warrants that he has complied and shall comply with all requirements of local, state, and national laws;
that no legal requirement has been or shall be violated in making or accepting this bid, in awarding the contract to him or in the prosecution of the work required; that the bid is legal and firm; that he has not, directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken action in restraint of free competitive bidding.
Upon receipt of written notice of the acceptance of this Bid, the Bidder shall, within twenty (20) calendar days, execute the agreement in the required form and deliver the Contract Bonds, and Insurance Certificates, required by the Contract Documents.
I am / We are an Individual / a Partnership / a Corporation
By Trading as (Individual’s / General Partner’s / Corporate Name)
(State of Corporation)
Business Address:
Witness: By:
(Authorized Signature)
(SEAL)
(Title)
Date:
ATTACHMENTS
Sub-Contractor List Non-Collusion Statement
Affidavit of Employee Drug Testing Program Affidavit of Contractor Qualifications
Bid Security (Others as Required by Project Manuals)
Pre-Bid Meeting Minutes-Addendum #1 SCI Maint/SVOP Generator & ATS Replacement
BID FORM
SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT
SUSSEX CORRECTIONAL INSTITUTION
OMB/DFM PROJECT: MC3804000164
FAYDA ENGINEERING & ENERGY SOLUTIONS BID FORM
FE&ES Comm.: 25-1643C 00 41 13-3
SUBCONTRACTOR LIST
In accordance with Title 29, Chapter 69, Section 6962(d)(10)b of the Delaware Code, the following subcontractor listing must accompany any bid submittal. The bidder must list in each category the full name and address (City & State) of the sub-contractor that the bidder will be using to perform the work and provide material for that subcontractor category. Should the bidder’s listed subcontractor intend to provide any of their subcontractor category of work through a third-tier contractor, the bidder shall list that third-tier contractor’s full name and address (City & State). If the bidder intends to perform any category of work itself, it must list its full name and address. For clarification, if the bidder intends to perform the work themselves, the bidder may not insert “not applicable”, “N/A”, “self” or anything other than its own full name and address (City & State). To do so shall cause the bid to be rejected. In addition, the failure to produce a completed subcontractor list with the bid submittal shall cause the bid to be rejected. If you have more than three (3) third-tier contractors to report in any subcontractor category, print out additional page(s) containing the appropriate category, complete the rest of your list of third-tier contractors for that category, notate the addition in parentheses as (CONTINUATION) next to the subcontractor category and an asterisk (*) next to any additional third-tier contractors, and submit it with your bid.
Subcontractor Category Subcontractor Address (City & State) Subcontractors tax-payer ID # or Delaware Business license #
1. Electrical
A.
B.
C.
2. Mechanical
A.
B.
C.
Pre-Bid Meeting Minutes-Addendum #1 SCI Maint/SVOP Generator & ATS Replacement
BID FORM
SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT
SUSSEX CORRECTIONAL INSTITUTION
OMB/DFM PROJECT: MC3804000164
BID FORM FAYDA ENGINEERING & ENERGY SOLUTIONS
00 41 13-4 FE&ES Comm.: 25-1643C
3. Concrete
A.
B.
C.
Pre-Bid Meeting Minutes-Addendum #1 SCI Maint/SVOP Generator Replacement
BID FORM
SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT
SUSSEX CORRECTIONAL INSTITUTION
OMB/DFM PROJECT: MC3804000164
FAYDA ENGINEERING & ENERGY SOLUTIONS BID FORM
FE&ES Comm.: 25-1643C 00 41 13-5
NON-COLLUSION STATEMENT
This is to certify that the undersigned bidder has neither directly nor indirectly, entered into any agreement, participated in any collusion or otherwise taken any action in restraint of free competitive bidding in connection with this proposal submitted this date (to the Office of Management and Budget, Division of Facilities Management).
All the terms and conditions of (OMB/DFM PROJECT: MC3804000164) have been thoroughly examined and are understood.
NAME OF BIDDER:
AUTHORIZED REPRESENTATIVE
(TYPED):
AUTHORIZED REPRESENTATIVE
(SIGNATURE):
TITLE:
ADDRESS OF BIDDER:
E-MAIL: ______________________________________________________________
PHONE NUMBER:
Sworn to and Subscribed before me this day of 20 .
My Commission expires . NOTARY PUBLIC .
THIS PAGE MUST BE SIGNED AND NOTARIZED FOR YOUR BID TO BE CONSIDERED.
Pre-Bid Meeting Minutes-Addendum #1 SCI Maint/SVOP Generator & ATS Replacement
BID FORM
SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT
SUSSEX CORRECTIONAL INSTITUTION
OMB/DFM PROJECT: MC3804000164
BID FORM FAYDA ENGINEERING & ENERGY SOLUTIONS
00 41 13-6 FE&ES Comm.: 25-1643C
AFFIDAVIT
OF
EMPLOYEE DRUG TESTING PROGRAM
4104 Regulations for the Drug Testing of Contractor and Subcontractor Employees Working on Large Public Works Projects requires that Contractors and Subcontractors implement a program of mandatory drug testing for Employees who work on Large Public Works Contracts funded all or in part with public funds.
We hereby certify that we have in place or will implement during the entire term of the contract a Mandatory Drug Testing Program for our employees on the jobsite, including subcontractors, that complies with this regulation:
Contractor/Subcontractor Name:
Contractor/Subcontractor Address:
Authorized Representative (typed or printed):
Authorized Representative (signature):
Title:
Sworn to and Subscribed before me this day of 20 .
My Commission expires . NOTARY PUBLIC .
THIS PAGE MUST BE SIGNED AND NOTARIZED FOR YOUR BID TO BE CONSIDERED.
Pre-Bid Meeting Minutes-Addendum #1 SCI Maint/SVOP Generator & ATS Replacement
BID FORM
SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT
SUSSEX CORRECTIONAL INSTITUTION
OMB/DFM PROJECT: MC3804000164
FAYDA ENGINEERING & ENERGY SOLUTIONS BID FORM
FE&ES Comm.: 25-1643C 00 41 13-7
AFFIDAVIT
OF
CONTRACTOR QUALIFICATIONS
We hereby certify that we will abide by the contractor’s qualifications outlined in the construction bid specifications for the duration of the contract term.
In accordance with Title 29, Chapter 69, Section 6962(d)(10)b.3 of the Delaware Code, after a contract has been awarded the successful bidder shall not substitute another subcontractor whose name was submitted on the Subcontractor Form except for the reasons in the statute and not without written consent from the awarding agency. Failure to utilize the subcontractors on the list will subject the successful bidder to penalties as outlined in the General Requirements Section 5.2 of the contract.
Contractor Name:
Contractor Address:
Authorized Representative (typed or printed):
Authorized Representative (signature):
Title:
Sworn to and Subscribed before me this day of 20 .
My Commission expires . NOTARY PUBLIC .
THIS PAGE MUST BE SIGNED AND NOTARIZED FOR YOUR BID TO BE CONSIDERED.
Pre-Bid Meeting Minutes-Addendum #1 SCI Maint/SVOP Generator & ATS Replacement
SCI Maint/SVOP Generator & ATS Replacement
DELAWARE DEPARTMENT OF CORRECTION SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT
SUSSEX CORRECTIONAL INSTITUTION OMB/DFM PROJECT #: MC3804000164
FAYDA ENGINEERING & ENERGY SOLUTIONS ENGINE GENERATORS - MAINTENANCE
FE&ES Comm.: 25-1643C 26 32 13.1-1
SECTION 26 32 13.1
ENGINE GENERATORS - SCI MAINTENANCE
PART 1 GENERAL
1.1 GENERAL PROVISIONS
A. Applicable provisions of the entire specifications, including Addenda, shall govern this section as fully as if repeated herein.
B. Refer specifically to the technical provisions of the 26 04 99 “Common Work Results for Electrical”.
1.2 RELATED DOCUMENTS
A. The work covered by this section of the specifications includes the furnishing of all labor, material, equipment and performance of all operations in connection with furnishing a new Emergency/Standby generator and an automatic transfer switch as indicated on the drawings and as specified herein.
B. The requirements of the conditions of the contract, Supplementary Conditions and General Requirements, apply to the work specified in this section.
C. The complete installation shall conform to the applicable sections of the latest edition of the National Electrical Code, Local Authorities having jurisdiction and the local utility serving the premises.
D. The work covered by this section of the specifications shall be coordinated with the related work.
1.3 SCOPE
A. This specification covers requirements for providing a factory built, prototype tested, production tested, field tested, complete and operable emergency/standby electric generating system, including all devices and equipment specified herein, shown on the drawings, and/or as required for the service. Materials and equipment shall be new and current, delivered to the site completely wired, tested, and ready for installation. This system shall include the following:
1. One (1) Engine-generator set rated 100kW/125kVA at 80% P.F., reach-in, Level 1 sound attenuated enclosure with 130⁰C Rise alternator.
2. Mounted and loose accessories, parts, tests, documents, and services, as needed to meet the performance requirements of this specification.
B. Provide complete factory assembled generator set equipment with digital (microprocessor-based) electronic generator set controls, digital governor, and digital voltage regulator.
C. Provide factory test, startup by a supplier authorized by the equipment manufacturer(s), and on-site testing of the system.
Pre-Bid Meeting Minutes-Addendum #1
SCI MAINTENANCE/SVOP GENERATOR & ATS REPLACEMENT DELAWARE DEPARTMENT OF CORRECTION
OMB/DFM PROJECT #: MC3804000164 SUSSEX CORRECTIONAL INSTITUTION
ENGINE GENERATORS - MAINTENANCE FAYDA ENGINEERING & ENERGY SOLUTIONS
26 32 13.1-2 FE&ES Comm.: 25-1643C
D. The generator set manufacturer shall warrant all equipment provided under this section, whether or not is manufactured by the generator set manufacturer, so that there is one source for warranty and product service for a period of five (5) years. Technicians specifically trained and certified by the manufacturer to support the product and employed by the generator set supplier shall service the generator sets.
1.4 CODES AND STANDARDS
A. The generator set and its installation and on-site testing shall conform to the requirements of the following codes and standards:
1. EN50082-2, Electromagnetic Compatibility – Generic Immunity Requirements, Part 2: Industrial.
2. EN55011, Limits and Methods of Measurement of Radio Interference Characteristics of Industrial, Scientific and Medical Equipment.
3. FCC Part 15, Subpart B.
4. IEC8528 part 4. Control Systems for Generator Sets
5. IEC Std 801.2, 801.3, and 801.5 for susceptibility, conducted, and radiated electromagnetic emissions.
6. IEEE446 – Recommended Practice for Emergency and Standby Power Systems for Commercial and Industrial Applications
7. IEEE587 for voltage surge resistance.
8. Mil Std 461D –1993. Military Standard, Electromagnetic Interference Characteristics.
9. Mil Std 462D - 1993. Military Standard, Measurement of Electromagnetic Interference Characteristics.
10. NEMA ICS10-1993 – AC Generator sets.
11. NFPA70 – National Electrical Code. Equipment shall be suitable for use in systems in compliance to Article 700, 701, and 702.
12. NFPA110 – Emergency and Standby Power Systems. The generator set shall meet all requirements for Level 1 systems. Level 1prototype tests required by this standard shall have been performed on a complete and functional unit, component level type tests will not substitute for this requirement.
13. UL508. The entire control system of the generator set shall be UL508 listed and labeled.
Pre-Bid Meeting Minutes-Addendum #1
FAYDA ENGINEERING & ENERGY SOLUTIONS ENGINE GENERATORS - MAINTENANCE
FE&ES Comm.: 25-1643C 26 32 13.1-3
14. UL2200. The genset shall be listed to UL2200 or submit to an independent third party certification process to verify compliance as installed.
15. EPA Compliant Engine Certified to current EPA emission standards for units of this size and fuel source.
B. The generator set manufacturer shall be certified to ISO 9001 International Quality Standard and shall have third party certification verifying quality assurance in design/development, production, installation, and service, in accordance with ISO 9001.
1.5 ACCEPTABLE MANUFACTURERS
A. Only approved bidders shall supply equipment provided under this contract. Standard of Design & Construction is by Rehlko with microprocessor-based controls or Approved Equal. Refer to Specification Section 00 21 13 and 00 26 00 for Additional Substitution Requirements.
B. Approved manufacturers subject to the requirements of this entire specification being met are:
1. Cummins
2. Caterpillar
C. The manufacturers identified above offer products similar in type, style and features.
Listing does not indicate their product meets the requirements of this specification. It is the vendor and contractor’s responsibility to ensure full compliance subject to the terms of these specifications. In the event that a listed approved manufacturer does not meet the specifications during the submittal phase of the project, the contractor shall provide one that does at no additional cost to the owner.
1.6 SUBMITTALS
A. Within ten (10) days after award of contract, provide one (1) electronic submission of the following information for review:
1. Manufacturer’s product literature and performance data, sufficient to verify compliance to specification requirements.
2. A paragraph-by-paragraph specification compliance statement, describing the differences between the specified and the proposed equipment.
3. Manufacturer's certification of prototype testing.
4. Manufacturer's published warranty documents.
5. Shop drawings showing plan and elevation views with certified overall dimensions, as well as wiring interconnection details.
6. Interconnection wiring diagrams showing all external connections required; with field wiring terminals marked in a consistent point-to-point manner.
7. Manufacturer's installation instructions.
8. Upon final approval of the submission, provide five (5) bound copies for record purposes.
Pre-Bid Meeting Minutes-Addendum #1
ENGINE GENERATORS - MAINTENANCE FAYDA ENGINEERING & ENERGY SOLUTIONS
26 32 13.1-4 FE&ES Comm.: 25-1643C
1.7 LITERATURE
A. The manufacturer shall have printed literature and brochures describing the standard series specified (not a one-of-a-kind fabrication). Unless specified otherwise herein, all performance data and other information shall be as on the manufacturer's printed literature.
Performance data shall be the result of test procedures in accordance with nationally recognized standards, plus such other procedures that are judged necessary by the manufacturer to insure maximum service reliability by the Engineer upon request.
1.8 SEQUENCE OF OPERATION
A. Generator set shall start on receipt of a start signal from remote equipment. The start signal shall be via hardwired connection to the generator set control and a redundant signal over the required network connection.
B. The generator set shall complete a time delay start period as programmed into the control.
C. The generator set control shall initiate the starting sequence for the generator set. The starting sequence shall include the following functions:
1. The control system shall verify that the engine is rotating when the starter is signaled to operate. If the engine does not rotate after two attempts, the control system shall shut down and lock out the generator set, and indicate “fail to crank” shutdown.
2. The engine shall fire and accelerate as quickly as practical to start disconnect speed. If the engine does not start, it shall complete a cycle cranking process as described elsewhere in this specification. If the engine has not started by the completion of the cycle cranking sequence, it shall be shut down and locked out, and the control system shall indicate “fail to start”.
3. The engine shall accelerate to rated speed and the alternator to rated voltage.
Excitation shall be disabled until the engine has exceeded programmed idle speed, and regulated to prevent over voltage conditions and oscillation as the engine accelerates and the alternator builds to rated voltage.
4. On reaching rated speed and voltage, the generator set shall operate as dictated by the control system in isochronous state.
5. When all start signals have been removed from the generator set, it shall complete a time delay stop sequence. The duration of the time delay stop period shall be adjustable by the operator.
6. On completion of the time delay stop period, the generator set control shall switch off the excitation system and shall shut down.
7. Any start signal received after the time stop sequence has begun shall immediately terminate the stopping sequence and return the generator set to isochronous operation.
Pre-Bid Meeting Minutes-Addendum #1
FAYDA ENGINEERING & ENERGY SOLUTIONS ENGINE GENERATORS - MAINTENANCE
FE&ES Comm.: 25-1643C 26 32 13.1-5
PART 2 PRODUCTS
2.1 GENERATOR SET
A. Ratings
1. The generator set shall be Rehlko Model KG100 and operate at 1800 rpm and at a voltage of: 208Y/120VAC, three phase, 4-wire, 60 hertz.
2. The generator set shall be rated at 100 kW/125 kVA at 0.8 PF, Standby rating, based on site conditions of: Altitude 100 feet (30.5 meters), ambient temperatures up to 122°F (50°C).
3. The generator set rating shall be based on emergency/standby service.
4. Fuel source shall be Natural Gas.
B. Performance
1. Voltage regulation shall be plus or minus 0.5 percent for any constant load between no load and rated load. Random voltage variation with any steady load from no load to full load shall not exceed plus or minus 0.5 percent.
2. Frequency regulation shall be isochronous from steady state no load to steady state rated load. Random frequency variation with any steady load from no load to full load shall not exceed plus or minus 0.5%.
3. The natural gas engine-generator set shall accept a single step load of 100% nameplate kW and power factor, less applicable derating factors, with the engine-generator set at operating temperature.
4. Motor starting capability shall be a minimum of 448kVA. The generator set shall be capable of recovering to a minimum of 90% of rated no load voltage following the application of the specified kVA load at near zero power factor applied to the generator set. Maximum voltage dip on application of this load, considering both alternator performance and engine speed changes shall not exceed 25%.
5. The alternator shall produce a clean AC voltage waveform, with not more than 5% total harmonic distortion at full linear load, when measured from line to neutral, and with not more than 3% in any single harmonic, and no 3rd order harmonics or their multiples. Telephone influence factor shall be less than 40.
6. The generator set shall be certified by the engine manufacturer to be suitable for use at the installed location and rating, and shall meet all applicable exhaust emission requirements at the time of commissioning.
Pre-Bid Meeting Minutes-Addendum #1
ENGINE GENERATORS - MAINTENANCE FAYDA ENGINEERING & ENERGY SOLUTIONS
26 32 13.1-6 FE&ES Comm.: 25-1643C
C. Construction
1. The engine-generator set shall be mounted on a heavy-duty steel base to maintain alignment between components. The base shall incorporate a battery tray with hold-down clamps within the rails.
2. All switches, lamps, and meters in the control system shall be oil-tight and dust-tight. All active control components shall be installed within a UL/NEMA 3R enclosure. There shall be no exposed points in the control (with the door open) that operate in excess of 50 volts.
D. Connections
1. The generator set load connections shall be composed of silver or tin plated copper bus bars, drilled to accept mechanical or compression terminations of the number and type as shown on the drawings. Sufficient lug space shall be provided for use with cables of the number and size as shown on the drawings.
2. Power connections to auxiliary devices shall be made at the devices, with required protection located at a wall-mounted common distribution panel.
3. Generator set control interfaces to other system components shall be made on a permanently labeled terminal block assembly. Labels describing connection point functions shall be provided.
2.2 ENGINE AND ENGINE EQUIPMENT
A. The engine shall be natural gas, EPA Certified for standby applications, 4 cycle, naturally aspirated. Minimum displacement shall be 378 cubic inches (6.2 Liter), with 8 cylinders.
The horsepower rating of the engine at its minimum tolerance level shall be sufficient to drive the alternator and all connected accessories. Two cycle engines are not acceptable.
Engine accessories and features shall include:
1. An electronic governor system shall provide automatic isochronous frequency regulation. The governing system dynamic capabilities shall be controlled as a function of engine coolant temperature to provide fast, stable operation at varying engine operating temperature conditions. The control system shall actively control the fuel rate and excitation as appropriate to the state of the generator set. Fuel rate shall be regulated as a function of starting, accelerating to start disconnect speed, accelerating to rated speed. The governing system shall include a programmable warm up at idle and cooldown at idle function. While operating in idle state, the control system shall disable the alternator excitation system.
2. Skid-mounted radiator and cooling system rated for full load operation in 122°F (50°C) ambient as measured at the alternator air inlet. Radiator fan shall be suitable for use in a system with 0.5 in H2O restriction. Radiator shall be sized based on a core temperature that is 20°F higher than the rated operation temperature, or prototype tested to verify cooling performance of the engine/radiator/fan operation in a controlled environment. Radiator shall be provided with a duct adapter flange.
The equipment manufacturer shall fill the cooling system with a 50/50-ethylene
Pre-Bid Meeting Minutes-Addendum #1
FAYDA ENGINEERING & ENERGY SOLUTIONS ENGINE GENERATORS - MAINTENANCE
FE&ES Comm.: 25-1643C 26 32 13.1-7 glycol/water mixture prior to shipping. Rotating parts shall be guarded against accidental contact.
3. Electric starter(s) capable of three complete cranking cycles without overheating.
4. Positive displacement, mechanical, full pressure, lubrication oil pump.
5. Full flow lubrication oil filters with replaceable spin-on canister elements and dipstick oil level indicator.
6. Natural Gas regulator, solenoid and wired controls.
7. Replaceable dry element air cleaner with restriction indicator.
8. Flexible supply and return fuel lines.
9. Provide fully regulated, constant voltage, current limited, and battery charger for each battery bank. The chargers shall be designed for heavy-duty industrial service, primarily to quickly recharge and maintain batteries that start internal combustion engines. Charger shall be rated a minimum of 10 amps, and be capable of operating in parallel with another like charger for reliability and added charging capacity.
10. Provide LED indication of general charger condition, including charging, fault, and equalize. Provide a 2 line LCD display to indicate charge rate, battery voltage, faults, and provide for charger set up.
11. The charger shall be compliant to the same RFI/EMI and voltage surge performance as are specified for the genset control.
B. Coolant heater
1. Engine-mounted, thermostatically controlled, coolant heater(s) for each engine.
Heater voltage shall be as shown on the project drawings. The coolant heater shall be UL 499 listed and labeled.
2. The coolant heater shall be installed on the engine with silicone hose connections.
Steel tubing shall be used for connections into the engine coolant system wherever the length of pipe run exceeds 12 inches. The coolant heater installation shall be specifically designed to provide proper venting of the system. The coolant heaters shall provisions to isolate the heater for replacement of the heater element without draining the coolant from the generator set. The quick disconnect/automatic sealing couplers shall allow the heater element to be replaced without draining the engine cooling system or significant coolant loss.
3. The 120V, 1 phase coolant heater shall be provided with a 120VAC or 240VAC thermostat, installed at the engine thermostat housing. An AC power connection box shall be provided for a single AC power connection to the coolant heater system.
Pre-Bid Meeting Minutes-Addendum #1
ENGINE GENERATORS - MAINTENANCE FAYDA ENGINEERING & ENERGY SOLUTIONS
26 32 13.1-8 FE&ES Comm.: 25-1643C
4. The coolant heater(s) shall be sized as recommended by the engine manufacturer to warm the engine to a minimum of 104°F (40°C) in a 40°F (4°C) ambient, in compliance with NFPA 110 requirements, or the temperature required for starting and load pickup requirements of this specification.
C. Internal vibration absorbers, integral to the generator set frame, as recommended by the generator set manufacturer, shall be provided.
D. Starting and Control Batteries shall be calcium/lead antimony type, 24 volt DC, sized as recommended by the engine manufacturer, complete with battery cables and connectors.
The batteries shall be capable of a minimum of three complete 15-second cranking cycles at 40°F ambient temperature when fully charged.
E. Provide critical exhaust silencer(s) for each engine of size and type as recommended by the generator set manufacturer and approved by the engine manufacturer. The mufflers shall be critical grade. Exhaust system shall be installed according to the engine manufacturer’s recommendations and applicable codes and standards. For housed units, the silencer must be mounted within the genset enclosure.
2.3 AC ALTERNATOR
A. The AC alternator shall be; synchronous, four pole, 2/3 pitch, revolving field, drip-proof construction, single pre-lubricated sealed bearing, air cooled by a direct drive centrifugal blower fan, and directly connected to the engine with flexible drive disc. All insulation system components shall meet NEMA MG1 temperature limits for Class H insulation system and shall be UL 1446 listed. Actual temperature rise measured by resistance method at full load shall not exceed 80°C.
B. The generator shall be capable of delivering rated output (kVA) at rated frequency and power factor, at any voltage not more than 5% above or below rated voltage.
C. A permanent magnet generator (PMG) shall be included to provide a reliable source of excitation power for optimum motor starting and short circuit performance. The PMG and controls shall be capable of sustaining and regulating current supplied to a single phase or three phase fault at approximately 300% of rated current for not more than 10 seconds.
D. The sub-transient reactance of the alternator shall not exceed 12%, based on the standby rating of the generator set.
2.4 GENERATOR SET CONTROL AND PROTECTION
A. The generator set shall be provided with a microprocessor-based control system that is designed to provide automatic starting, monitoring, protection and control functions for the generator set. The control system shall also be designed to allow local monitoring and control of the generator set, and remote monitoring and control as described in this specification.
B. The control shall be mounted on the generator set, or may be mounted in a free-standing panel next to the generator set if adequate space and accessibility is available. The control
Pre-Bid Meeting Minutes-Addendum #1
FAYDA ENGINEERING & ENERGY SOLUTIONS ENGINE GENERATORS - MAINTENANCE
FE&ES Comm.: 25-1643C 26 32 13.1-9 shall be vibration isolated and prototype tested to verify the durability of all components in the system under the vibration conditions encountered.
2.5 CONTROL FEATURES AND FUNCTIONS
A. Control Switches
1. Mode Select Switch. The mode select switch shall initiate the following control modes. When in the RUN or MANUAL position the generator set shall start, and accelerate to rated speed and voltage as directed by the operator. A separate push-button to initiate starting is acceptable. In the OFF position the generator set shall immediately stop, bypassing all time delays. In the AUTO position the generator set shall be ready to accept a signal from a remote device to start and accelerate to rated speed and voltage.
2. EMERGENCY STOP switch. Switch shall be Red "mushroom-head" push-button. Depressing the emergency stop switch shall cause the generator set to immediately shut down, and be locked out from automatic restarting.
3. RESET switch. The RESET switch shall be used to clear a fault and allow restarting the generator set after it has shut down for any fault condition.
4. PANEL LAMP switch. Depressing the panel lamp switch shall cause the entire panel to be lighted with DC control power. The panel lamps shall automatically be switched off 10 minutes after the switch is depressed, or after the switch is depressed a second time.
B. Generator Set AC Output Metering. The generator set shall be provided with a metering set including the following features and functions:
1. Digital metering set, 1% accuracy, to indicate generator RMS voltage and current, frequency, output current, output KW, KW-hours, and power factor. Generator output voltage shall be available in line-to-line and line-to-neutral voltages, and shall display all three-phase voltages (line to neutral or line to line) simultaneously.
2. Analog voltmeter, ammeter, frequency meter, power factor meter, and kilowatt (kW) meter. Voltmeter and ammeter shall display all three phases. Meter scales shall be color coded in the following fashion: green shall indicate normal operating condition, amber shall indicate operation in ranges that indicate potential failure, and red shall indicate failure impending. Metering accuracy shall be within 1% at rated output. Both analog and digital metering are required.
3. The control system shall monitor the total load on the generator set, and maintain data logs of total operating hours at specific load levels ranging from 0 to 110% of rated load, in 10% increments. The control shall display hours of operation at less than 30% load and total hours of operation at more than 90% of rated load.
4. The control system shall log total number of operating hours, total kWH, and total control on hours, as well as total values since reset.
Pre-Bid Meeting Minutes-Addendum #1
ENGINE GENERATORS - MAINTENANCE FAYDA ENGINEERING & ENERGY SOLUTIONS
26 32 13.1-10 FE&ES Comm.: 25-1643C
C. Generator Set Alarm and Status Display
1. The generator set control shall include LED alarm and status indication lamps. The lamps shall be high-intensity LED type. The lamp condition shall be clearly apparent under bright room lighting conditions. Functions indicated by the lamps shall include:
a. The control shall include five configurable alarm-indicating lamps. The lamps shall be field adjustable for any status, warning, or shutdown function monitored by the genset. They shall also be configurable for color, and control action (status, warning, or shutdown).
b. The control shall include green lamps to indicate that the generator set is running at rated frequency and voltage, and that a remote start signal has been received at the generator set. The running signal shall be based on actual sensed voltage and frequency on the output terminals of the generator set.
c. The control shall include a flashing red lamp to indicate that the control is not in automatic state, and red common shutdown lamp.
d. The control shall include an amber common warning indication lamp.
2. The generator set control shall indicate the existence of the warning and shutdown conditions on the control panel. All conditions indicated below for warning shall be field-configurable for shutdown. Conditions required to be annunciated shall include:
a. low oil pressure (warning)
b. low oil pressure (shutdown)
c. oil pressure sender failure (warning)
d. low coolant temperature (warning)
e. high coolant temperature (warning)
f. high coolant temperature (shutdown)
g. high oil temperature (warning)
h. engine temperature sender failure (warning)
i. low coolant level (warning)
j. fail to crank (shutdown)
k. fail to…