NVPS Athletics (Balance) - Bid Clarification 02.pdf
PDF 3 MB Posted
- Solicitation number
- RFP NVP 260000002718 5
- Issued by
- Michigan
About this file
This is a Bid Clarification document issued by Northview Public Schools in Michigan regarding the Athletic Stadium Addition & Renovation project at Northview High School. The document addresses clarification questions submitted by bidders during the procurement process for this capital construction project. The clarification appears to focus on technical specifications, contract requirements, and project scope details relevant to the athletic stadium renovation work. Specific response dates, due dates for bids, site visit schedules, and bidders' meetings are not detailed in this summary document, as it functions primarily as a question-and-answer addendum to the original bid package.
Pricing terms, set-asides, and detailed funding information are not specified in this bid clarification document. The document serves as supplemental guidance to prospective bidders to ensure consistent understanding of project requirements and specifications across all bid submissions. No incumbent information, set-asides for small businesses or disadvantaged contractors, or specific funding amounts and sources are addressed in this clarification addendum.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
601 First Street NW Grand Rapids, Michigan 49504
(616) 285-6933 www.rockford.com
BID CLARIFICATION NO. 2
TO: All Subcontractors / Suppliers
FROM: Dan Korcek, Senior Project Manager; Morgan Gross, Assistant Project Manager
DATE: October 20, 2026
RE: NVPS Athletics Addition and Renovation
This Bid Clarification No. 2 is being sent to all bidders to address questions raised at bid time.
1. Bid RFIs have been generated; Responses are attached in files, with RFI Subjects shown below.
a. Bid RFI 09 – Signage Clarifications
b. Bid RFI 10 – Concession Stand Shutters Clarifications
c. Bid RFI 11 – Resinous Flooring Substitution Request
d. Bid RFI 12 – Door Design Questions
e. Bid RFI 13 – Plumbing/Flush Valve Clarifications
f. Bid RFI 14 – Overhead Door Substitution Request
g. Bid RFI 15 – Substitution Request; Zurn Plumbing Fixtures
h. Bid RFI 16 – Grade/Turf Clarifications – AWAITING RESPONSE
i. Bid RFI 17 – Concrete/Subbase Details Clarifications
j. Bid RFI 18 – Exterior Cement Board Siding and Paint Finish Clarifications – AWAITING
RESPONSE
k. Bid RFI 19 – Miscellaneous Civil, Turf, Exterior Improvements Clarifications – AWAITING
RESPONSE
l. Bid RFI 20 – Netting Foundation Clarifications
m. Bid RFI 21 – Additional Turf Clarifications – AWAITING RESPONSE
n. Bid RFI 22 – Turf Scope Clarifications
o. Bid RFI 23 - Additional Scope Clarifications Bid Category 32D
2. Scope Clarifications
a. Please reference the RFI List above to find scope changes relating to various different scopes of work.
b. Please note, Bid Forms have been updated on Procore to reflect these scope changes.
Ensure that you are working from the most up to date bid forms as you work to submit your bids.
3. Addendum #01
a. Addendum #01 is planned to be released to Rockford on Friday October 23, 2026. There will be an additional Bid Clarification #03 released early next week to address the Addendum release and any additional scope questions.
End of Clarification https://protect.checkpoint.com/v2/r01/___http:/www.rockford.com___.YzJ1OnJvY2tmb3JkMTpjOm9mZmljZTM2NV9lbWFpbHNfYXR0YWNobWVudDo5M2QwMjI2MWQxMmRhNzdlYmEzMzkzODgzYTMyNTAwMDo3OmE1OGI6NWEyYTg3YTcwZmI4OWM3M2VlNmEzNjAzOGZhZGM4YzE5NDE3ODNlY2Q3Y2YwOWZiNGUzYWY2Y2NiZmQ2YjRmOTpwOlQ6Rg
ROCKFORD CONSTRUCTION CO.
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger Grand Rapids, Michigan 49525
P: 616-327-9354
RFI #9: Bid RFI 09 - Signage Clarifications
Revision 0 Status Closed on 10/19/26
To Bill Zaske (Integrated Design Solutions) (Response Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 12, 2026 Due Date Oct 15, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Copies To Kala Slater (Rockford Construction), Dan Korcek (Rockford Construction)
Activity
Question Question from Morgan Gross Rockford Construction on Monday, Oct 12, 2026 at 09:35 AM EDT The following questions were brought about by an interested General Trades Bidder.
• What is the height of the aluminum dimensional letters for the "Wildcat Stadium" entry arch on A4.2?
• What is the desired thickness of all dimensional signage (9' 10" H Dimensional wall logo, 5' H dimensional wall logo, 14" H "Wildcat Walk" letters, "Wildcat Stadium" Letters). Details A4.1, A4.2, LD1.18.
• Please confirm that the "Wildcat Walk" arch and "Wildcat Stadium" east elevation north entry arch are to be built by others, and that our scope is just the dimensional letters. A4.2, LD1.18.
Official Response Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 11:04 AM EDT
- Height of "WILDCAT STADIUM" letters is 12"
- Thickness of all exterior signage to be 1"
- Please refer to Rockford Construction as to the scope of work.
All Replies Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 11:04 AM EDT
- Height of "WILDCAT STADIUM" letters is 12"
- Thickness of all exterior signage to be 1"
- Please refer to Rockford Construction as to the scope of work.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 19, 2026 01:57 PM EDT
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #10: Bid RFI 10 - Concession Stand Shutters Clarification
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 12, 2026 Due Date Oct 15, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Question Question from Morgan Gross Rockford Construction on Monday, Oct 12, 2026 at 10:10 AM EDT Counter Shutters Missing from Door Schedule. The Prints show rolling steel shutters on the 6 opening windows for concession 106, and are included in the specification document. Please confirm these should be included in the Door Schedule.
Attachments Bid RFI 10 - Consession Shutters.pdf
Official Response Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 09:53 AM EDT Correct there are counter shutters in the concession stand, please include in bids.
All Replies Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 09:53 AM EDT Correct there are counter shutters in the concession stand, please include in bids.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 19, 2026 01:58 PM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M4R74WY3C7G5R40PCVWREH2G?companyId=562949953513905&projectId=562949955315041&sig=6bc6cd51a4f6ef25cdb6e04ca899941a4663ce9653fc43c436db5cfedb67f353
00 63 13X RFI FORM (DURING BIDDING)
NVPS Athletics Stadium Addition & Renovation
4451 HUNSBERGER AVENUE NE
GRAND RAPIDS, MICHIGAN 49525
ROCKFORD CONSTRUCTION
BID REQUEST FOR INFORMATION
PROJECT: NVPS Athletics Stadium Addition & Reno R.F.I NO.: (RCCI USE ONLY)
TO: Dan Korcek, Rockford Construction EMAIL: dkorcek@rockfordconstruction.com
FROM: COMPANY:
DATE: SPEC. SHEET / DETAIL:
PROBLEM / CONFLICT:
SIGNED DATE _______ ______
TITLE
CM /
SIGNED DATE _______ ______
TITLE
Joel Russcher Compaan Door
10/9/2026
Counter Shutters missing from Door Schedule. The prints show rolling steel shutters on the 6 opening windows for Consession 106, and are included in the specification document.
Should these be included in our bid.
A5.2 - Detail 1, A8.1 - Detail 2, 3, 4
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #11: Bid RFI 11 - Resinous Flooring Substitution Request
Revision 0 Status Open
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 12, 2026 Due Date Oct 15, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Question Question from Morgan Gross Rockford Construction on Monday, Oct 12, 2026 at 11:51 AM EDT One interested bidder in the resinous flooring category has requested a substitution request to allow their products to be used on the project. Please see attached substitution request as well as their product documentation.
Xtreme Engineered Floor Systems - Substitution Request.pdf
Official Response Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 01:09 PM EDT The presented resinous flooring is not acceptable. The specified product is a district standard, that should be maintained consistent throughout the district.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 19, 2026 01:59 PM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M4RCWJWXJW4Z7EQQF3N6PBND?companyId=562949953513905&projectId=562949955315041&sig=00e526330b658e011da78a17f5dde8e861b1ffc76e8a408266df5fcb6d8c6fcf
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #12: Bid RFI 12 - Door Design Questions
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 12, 2026 Due Date Oct 15, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Question Question from Morgan Gross Rockford Construction on Monday, Oct 12, 2026 at 11:56 AM EDT Overhead Doors are marked with label "08 3613 OVERHEAD SECTIONAL DOOR WITH RIBBED PANELS, TYP" but
Sectional Door Sepcification (2.3 - A) calls for an Aluminum Sectional Door with Solid Aluminum Panels. (2.3 - D. 2).
This is for openings 107A, 107C, 108A, 108D.
Please clarify desired door design.
Bid RFI 12 - Door Design.pdf
Official Response Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 09:55 AM EDT Provide overhead doors as specified (Aluminum section door with solid Aluminum Panels)
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 19, 2026 02:00 PM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M4RD8SS7C97GJANH9A5X528G?companyId=562949953513905&projectId=562949955315041&sig=47a115974eaf74423d1178691354571e7d414354f2bb8dd4c50fd517501bfd55
00 63 13X RFI FORM (DURING BIDDING)
NVPS Athletics Stadium Addition & Renovation
4451 HUNSBERGER AVENUE NE
GRAND RAPIDS, MICHIGAN 49525
ROCKFORD CONSTRUCTION
BID REQUEST FOR INFORMATION
PROJECT: NVPS Athletics Stadium Addition & Reno R.F.I NO.: (RCCI USE ONLY)
TO: Dan Korcek, Rockford Construction EMAIL: dkorcek@rockfordconstruction.com
FROM: COMPANY:
DATE: SPEC. SHEET / DETAIL:
PROBLEM / CONFLICT:
SIGNED DATE _______ ______
TITLE
CM /
SIGNED DATE _______ ______
TITLE
Joel Russcher Compaan Door
10/9/2026 A4.1 - Detail 1 & 3
Overhead Doors are marked with label "08 3613 OVERHEAD SECTIONAL DOOR WITH RIBBED PANELS, TYP" but Sectional Door Specification (2.3 - A) calls for an Aluminum Sectional Door with Solid Aluminum Panels (2.3 - D. 2).
This is for openings 107A, 107C, 108A, 108D
Please clarify desired door design.
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #13: Bid RFI 13 - Plumbing/Flush Valve Clarifications
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 13, 2026 Due Date Oct 16, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Question Question from Morgan Gross Rockford Construction on Tuesday, Oct 13, 2026 at 09:55 AM EDT Two questions have been raised by an interested bidder for plumbing on the Athletics Project.
1. Flushometers for urinals & Toilets: electronic or manual?
2. Lavatory Faucets: battery powered or hardwired?
Please advise.
Official Response Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 04:54 PM EDT Provide U-FLV-3 for UR-1 and LF-2 for LAV-1, we will issue these changes in the future addendum.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 19, 2026 09:12 PM EDT
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #14: Bid RFI 14 - Overhead Door Substitution Request
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 13, 2026 Due Date Oct 16, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Copies To
Question Question from Morgan Gross Rockford Construction on Tuesday, Oct 13, 2026 at 10:05 AM EDT Interested bidder in the General Trades/Door Category is interested in an alternative door being approved via substitution request. Please see the attached information and provide a response if this is acceptable as a substitute or not.
Substitution request would allow the opportunity to source both coiling and sectional doors from a single source.
Bid RFI 14 - Overhead Door Substitution Request.pdf
Official Response Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 11:17 AM EDT The presented Raynor Overhead Door substitution is acceptable.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 19, 2026 02:01 PM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M4TS90D1HYY55DEWQ6ZWCJYA?companyId=562949953513905&projectId=562949955315041&sig=666c6e82f39d27eb68871d894686d4dda09195159d259b31f17b5715ee0764e1
01 2500.01
SUBSTITUTION REQUEST FORM
Substitution Request Number: _______________ Date Submitted: ___________________________________
IDS Project Number: _______ _______________
Project Name: ______________________________________________________________________________
SPECIFIED ITEM
Specification Title: _____________________________________________________________________________
Specification Section No.: _____________________ Specification Article / Paragraph: ____________________
Specified Item / Description: _____________________________________________________________________
Specified Manufacturer: _________________________ Specified Item / Model: __________________________
Reason for not providing specified item (If after Bidding): _______________________________________________
PROPOSED SUBSTITUTION
Proposed Substitution: _________________________________________________________________________
Proposed Manufacturer: __________________________ Proposed Item / Model: ________________________
Manufacturer’s Website: ________________________________________________________________________
Manufacturer’s Address: ________________________________________________________________________
Years manufacturer has been in business: __________ Years item / model has been manufactured: _________
Differences between proposed Substitution and specified item: __________________________________________
Will proposed Substitution affect other parts of work? ☐ No ☐ Yes
If Yes, provide explanation: ____________________________________________________________________
Benefit of proposed Substitution (If after Bidding): ☐ Cost savings ☐ Time savings ☐ Other
Provide explanation of Benefit: _________________________________________________________________
10/13/2026 25116-5000
NORTHVIEW PUBLIC SCHOOLS
ATHLETIC STADIUM
ADDITIONS AND RENOVATION
08 3323
Overhead Door
Obtain both coiling and sectional doors from single source.
Raynor raynor.com
1101 East River Road, Dixon IL
Single source both sectional and coiling doors from same manufacturer. Raynor is listed as a supplier for the sectional doors
Basis of Design Product
2.4, A
2.4 COUNTER DOOR ASSEMBLY – NON-RATED
Durashutter
Raynor product appears to meet specifications.
IDS Project Number: ______________________
01 2500.01
Provide the following information. Check box to indicate information has been attached. Substitution Requests without the following information will be rejected.
☐ Product data sheets.
☐ Point-by-point, comparative data.
Provide side-by-side, itemized, comparative data of specified product and proposed Substitution comparing essential attributes specified (gages, sizes, performance requirements, finishes, etc.). Alternatively provide annotated copy of applicable Specification Section indicating differences.
Indicate if any additional information is attached:
☐ Applicable certificates and test reports. ☐ List of References where proposed product is installed.
☐ Drawings. ☐ Samples. ☐ Other Items: __________________________________________________
SUBMITTED BY
The Undersigned certifies, except as otherwise indicated in Substitution Request:
• Substitution is equal or superior in all respects to specified product.
• Substitution complies with requirements in the Contract Documents, is compatible with related materials, and is appropriate for applications indicated.
• Same warranty will be provided for the Substitution as for the specified product.
• Same or equivalent maintenance service and source of replacement parts, as applicable, shall be available.
• Substitution will have no adverse effect on other trades and will not affect or delay project schedule.
• Substitution will not affect dimensions and functional clearances.
• Undersigned agrees to coordinate installation of the Substitution and any changes in the Work as necessary for installation of the Substitution.
• Costs for changes to the Work and any other costs caused by the Substitution; including, but not limited to, A/E design changes, detailing, and dimensioning, shall be paid by the undersigned.
• Undersigned waives claims for additional costs and time extensions that may subsequently become apparent after Substitution is approved.
Contractor / Company: _________________________________________________________________________
Signed By: __________________________________ Printed Name: __________________________________
Title: ______________________________________________________ Date: __________________________
Address: ____________________________________________________________________________________
Email: ____________________________________________ Phone: _________________________________
ARCHITECT’S RESPONSE
• During bidding, Architect will approve Substitution by issuing an Addendum, Substitutions not approved by addendum are rejected.
• During construction, Architect will notify Contractor in writing (see below) of decision to accept or reject a Substitution. Accepted Substitutions shall be incorporated into the Work by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments as provided for in the Conditions of the Contract.
☐ Substitution Approved - Provide submittals in accordance with Specification Section 01 3000 – Submittal
Procedures, as noted by Architect in Substitution Request, and in accordance with respective section for which substitution was made.
☐ Substitution Rejected - Provide specified materials.
Signed By: __________________________________ Printed Name: __________________________________
Architect’s Comments: __________________________________________________________________________
____________________________________________________________ Date: __________________________
Zylstra Company
Brett Zylstra
10/13/2026
7350 Broadmoor Ave SE Caledonia, MI 49316 brett@zylstracompany.com 616-698-7242
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #15: Bid RFI 15 - Substitution Request; Zurn Plumbing Fixtures
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 14, 2026 Due Date Oct 19, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Question Question from Morgan Gross Rockford Construction on Wednesday, Oct 14, 2026 at 10:35 AM EDT Interested Bidder has requested a substitution request for Zurn China Plumbing Fixtures ILO specified. Please confirm if this request is acceptable.
Zurn Substitution Request - Athletics.pdf
Official Response Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 04:55 PM EDT Zurn Plumbing fixtures are acceptable
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 19, 2026 09:14 PM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M4XD4QMDAZZT6CP3Z98X3DQR?companyId=562949953513905&projectId=562949955315041&sig=700cb8a245dfe1f36791f8004b652c6bf4ea9b9a86c62c2c2ea98cacee3b7425
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #17: Bid RFI 17 - Concrete/Subbase Details Clarifications
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 15, 2026 Due Date Oct 20, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number LD1.05 Reference
Linked Drawings
Received From
Question Question from Morgan Gross Rockford Construction on Thursday, Oct 15, 2026 at 08:34 AM EDT Sheet LD1.08 detail 2 is calling for 4" slab over 4" sand while detail 3 is calling for 6" reinforced concrete over 6" 21AA limestone base.
Please advise correct detail so bidders can supply an accurate price for this work.
Official Response Response from Bill Zaske Integrated Design Solutions on Monday, Oct 19, 2026 at 01:19 PM EDT This will be addressed in the upcoming Addendum.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 19, 2026 02:01 PM EDT
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #20: Bid RFI 20 - Netting Clarifications
To Morgan Gross (Rockford Construction) (Response Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 19, 2026 Due Date Oct 22, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Question Question from Morgan Gross Rockford Construction on Monday, Oct 19, 2026 at 03:44 PM EDT What Bid Category is responsible for Netting Post Foundations? It appears that they are currently included in Bid Category
#3: Cast In Place Concrete (items #47).
Suggested to Include netting post foundations in bid category #32C: Fencing/Protective Netting System.
Bid RFI 20 - NVPS.pdf
Official Response Response from Morgan Gross Rockford Construction on Monday, Oct 19, 2026 at 03:46 PM EDT BP 32C Shall be responsible for Delegated Design/Engineering and installation of foundations for fencing and netting. The exception is the concrete supply/form/installation of the foundations as identified in BP 3 Scope of Work inside of football and auxiliary field identified assuming they fit within the dimensions as identified. If not, BP 32C shall include allowance for difference.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 19, 2026 03:46 PM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M5AV2C4GXSVTB7FCMQ8GCDQ2?companyId=562949953513905&projectId=562949955315041&sig=33390f91983f26ab0ccbfcf40e7920cc6671cab3b6005053f2083754de5c7419
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #22: Bid RFI 22 - Turf Scope Clarifications (Not sent to Design Team)
Revision 0 Status Closed on 10/20/26
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 20, 2026 Due Date Oct 23, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
ROCKFORD CONSTRUCTION CO. Page 1 of 2 Printed On: Oct 20, 2026 09:54 AM EDT
Question Question from Morgan Gross Rockford Construction on Tuesday, Oct 20, 2026 at 09:53 AM EDT
1. Turf base responsibility: 32D includes base, flat drain and fines inside the anchor; BP 31 excludes them; 32D Alt 4 deducts it if "BP 31A" provides it. Confirm base is in our base bid and identify BP 31A. Disregard Alternate 4 language.
Follow Scope.
2. Existing stadium turf removal: Is removal/disposal in base bid or only 32D Alt 5 (also BP 2 Alt 3)? Alternate has been requested from BP 32D, BP 31, and BP 2. It will be assigned at award. The schedule shows turf removal Mar 22–Apr 2, 2027. Does the existing field have a shock pad? NO.
3. Existing stadium base rework: Who excavates ±2" of existing aggregate and salvages ±1" of fines (L1.1 Note 2, Detail 15 LD1.02)? How much new stone is assumed? Will the Owner test the reworked base? I have asked for clarification on this from IDS.
4. Wood nailer: The drawing asks for an allowance; the bid form asks for a $/LF unit price. Which governs, and what LF/allowance amount should all bidders carry? Provide cost per LF.
5. Missing specs: 03 3053 Concrete Turf Anchor and 27 5119 Field Utility Boxes are in the TOC but not in the spec book. Please issue them and confirm who furnishes boxes and turf-filled lids (32D lists 27 5119). Spec section 25 5119 has been requested. Per BP 32D Scope of work 27 5119, furnish and install all field utility boxes both inside and outside of turf areas.
6. Proposal exceptions: 32 1818 says exceptions go in the proposal, but the Procore form can't be qualified. How do we submit exceptions and voluntary alternates? Exceptions will be allowed. Voluntary alternates can be added to the voluntary alternate section of the bid form.
7. Batting cage: Architect Alt 5 (second bay) has no line on the 32D form — add one? The schedule installs batting cage turf Apr 21–22, 2027, before turf delivery May 11–14. Alternate Line is being added to the Bid Form.
8. Bullpen alternate: Confirm Alt 3 product (32 1809 coated-back bullpen turf), whether turf covers the mounds, and the area. Reference LD1.07 detail 7.
9. Testing costs: 32 1123 sieve analysis per 150 tons "administered through the project" — who pays? Above testing is provided by owner testing consultant and paid for by owner. Which compaction/permeability tests are by the Owner's agency? Permeability Testing is by BP 32D and witnessed by owners representatives.
10. Subgrade tolerance: BP 31 delivers ±0.05'; 32 1123 requires ±0.02'. Who corrects to ±0.02'? Per Common Scope of work BBB. All work shall be in strict accordance with the drawings and specifications; therefore All grading shall be +/-
0.02 foot. BP 31 shall meet the grading tolerance as specified in section 32 1123 as applicable per that section
11. Maintenance equipment: One set for the project or one per field? Provide per specification.
12. Staging: Where can we stage turf rolls and stockpile stone/infill, given the one-week-of-material limit? Reference
Logistics plan indicating Laydown area. Will track crossing mats support loaded turf trucks? Reference LD1.02 Detail 6.
This trade shall be responsible to not cause damage to adjacent work or existing surfaces.
13. Physical samples: Where and when should turf and pad samples and the sample insurance policy be delivered, since bids are electronic? Insurance can be uploaded with the bid along with affidavits. Samples will be reviewed as a part of the award.
Awaiting an Official Response
All Replies Response from Morgan Gross Rockford Construction on Tuesday, Oct 20, 2026 at 09:54 AM EDT Responses are provided in the body of the RFI. Yellow highlighting indicates responses.
RFI #22 - Bid RFI 22 - Turf Scope Clarifications (Not sent to Design Team) Project: NVPS - Northview Athletics Stadium Addition & Renovation
ROCKFORD CONSTRUCTION CO. Page 2 of 2 Printed On: Oct 20, 2026 09:54 AM EDT
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #23: Bid RFI 23 - Additional Scope Clarifications Bid Category 32D
Revision 0 Status Closed on 10/20/26
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Oct 20, 2026 Due Date Oct 25, 2026
Location Project Stage Bidding
Cost Impact No Schedule Impact No
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Question Question from Morgan Gross Rockford Construction on Tuesday, Oct 20, 2026 at 08:58 PM EDT Please see attached document showing questions and answers for several scope clarifications in the 32D Turf Bid Category.
Northview-32D-Bid-RFI.pdf
Official Response Response from Morgan Gross Rockford Construction on Tuesday, Oct 20, 2026 at 08:58 PM EDT Reference the attached PDF for questions and responses.
Northview-32D-Bid-RFI.pdf
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Oct 20, 2026 08:59 PM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M5DZDDYJPJ6QQGPWQ4BQAT5S?companyId=562949953513905&projectId=562949955315041&sig=3e330937d8789884ce41910daea363be6742dc66d3c0c50a1b7a592f60c60297 https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M5DZF3JVJND3WR4PW2Y69CJ7?companyId=562949953513905&projectId=562949955315041&sig=44bb2cb629de2e19f33fb59ee318d5ac3f4909de1dc5a217fc6b5f56e8c6a700
BID REQUEST FOR INFORMATION
Northview Public Schools | Athletics Stadium Additions & Renovations Bid Category #32D - Synthetic Turf and Base
To: Dan Korcek, Rockford Construction | dkorcek@rockfordconstruction.com
From: Ken Hutchinson | AstroTurf Great Lakes
Date: October 14, 2026 | RFI No.: RCCI to assign
Subject: Bid scope, document conflicts and pricing clarifications
Please provide written clarification of the following items by addendum or bid clarification so all bidders carry a consistent scope. References to manual/specification pages are original PDF page numbers. Drawing references use sheet/detail numbers.
1. Existing turf/infill removal and shock-pad clarification Manual p.23, Demolition Alternate 3; p.73, #32D Alternate 5; drawing L1.1 replacement notes.
Existing turf and infill must be removed. Please clarify whether the existing shock pad must also be removed and disposed of or is to be retained, and identify the affected fields/areas. Selective Demolition Alternate 3 and #32D Alternate 5 both carry existing turf/shock-pad removal. Identify the responsible contractor and confirm whether #32D carries this work in the base bid or as an additive alternate.
2. Stadium aggregate removal, salvage and adjustment L1.1 replacement note 4; LD1.02 detail 15; manual pp.60-62 and 71.
L1.1 requires excavation of approximately 2 inches of aggregate and salvage of approximately 1 inch of fines. Confirm who removes, stores, reuses and disposes of these materials; the required final aggregate elevations after the new pad is added; and the bid basis for supplemental stone or unsuitable existing material. Identify whether the indicated work is in #32D base or another category.
3. Band-field existing base removal alternate Manual p.62, Sitework Alternate 5; pp.70-73, #32D.
Sitework Alternate 5 prices complete removal of existing band-field base and drains, with disposal and access-road reuse options. Confirm the base-bid treatment of existing band-field base/drainage if that alternate is not accepted, and the demolition/reconstruction limits to be included by #32D.
4. Base/drainage transfer under #32D Alternate 4 Manual p.73, Alternate 4; Section 32 1123, 1.3.F and 3.1.
Define precisely what transfers to BP31A under Alternate 4: furnishing versus installation, stone/fines, geotextile, perimeter and flat drains, excavation/backfill, testing, survey/string checks and corrections. Confirm the work retained by #32D and the acceptance/warranty responsibilities for a base built by others.
DKorcek Text Box RFI was written several days ago requesting clarification on this item
DKorcek Text Box Clarification was requested if the entire base/drainage is to be removed. Currently, it is anticipated that the new storm drainage will be cutting through the existing Band field storm drainage and therefore could cause some settlement of base if washed into existing storm piping. Alternate is requested if Engineer advises that complete removal is not required. BP 32 D is to provide complete base/drainage layer system and drainage per scope of work.
DKorcek Text Box BP 32D shall disregard Alternate 4. BP 32D shall provide complete drainage per 32D scope of work.
DKorcek Text Box Existing Shock pad shall be removed and disposed of as a part of the alternate.
Alternate price is requested of both trades. It will be assigned the trade at award.
5. Subgrade handoff tolerance and deficient soils Manual p.60, Sitework item 20; p.71, Substrate items 1 and 5; Section 32 1123, 3.1.I.
Sitework hands over subgrade within +/-0.05 foot at every point; the aggregate specification requires +/-0.02 foot before the next layer. Confirm which trade brings subgrade to the tighter tolerance and performs the specified scarification/recompaction, proof-roll corrections and undercut/replacement before #32D acceptance. Define responsibility for later settlement caused by utility-trench backfill by other trades.
6. Drainage connection limits Manual p.61, Sitework item 47; p.71, Substrate item 3; p.73 exclusions; Section 33 4615.
Sitework extends storm drainage through the turf anchor a minimum of 5 feet, while #32D connects at the turf perimeter. Confirm the exact handoff locations and responsibility for the overlapping 5 feet, fittings, collector connections, trench excavation/backfill and testing. Confirm Section 33 4615 governs #32D interior drainage even though omitted from its listed sections.
7. Missing Field Utility Boxes section and scope split Manual p.70 lists 27 5119; specifications contents p.6; LD1.02 details 17-20; E7.1 detail 8.
Please issue Section 27 5119, which is listed but has no body in the supplied specifications. Identify who furnishes and installs outer field utility/communication boxes, goal-post access boxes, manhole covers and quick-coupler boxes, including supports, concrete backing, drainage connections and turf-covered lids. E7.1 assigns internal electrical components to electrical; confirm the outer-box quantities/models and #32D limits.
8. Concrete anchors and wood nailer allowance Manual pp.26 and 73; L1.1 replacement note 1; LD1.01 detail 19.
Concrete scope includes turf anchors and #32D excludes concrete, but #32D breakdowns group turf anchors with base/drainage. Confirm concrete is excluded from #32D pricing. L1.1 requests a nailer replacement allowance while #32D requests only a $/LF unit price. Provide the allowance quantity or dollar amount for the base bid and define measurement/payment for additional approved replacement.
9. Bullpen turf alternate assembly Manual p.73, #32D Alternate 3; LD1.07 details 7 and 8; Section 32 1123, 3.2.E.
The bullpen alternate shows 6 inches of aggregate while Section 32 1123 requires an 8-inch minimum full profile. Confirm the required base thickness, turf product/pile height, infill and pad requirements for both double bullpens, including mound transition limits. Confirm earthwork and concrete adjustments remain with their respective trades and are coordinated with this alternate.
10. Shock pad at stadium south D-zone and band field Manual p.71; LD1.01 detail 15 and auxiliary/band field details.
LD1.01 detail 15 labels the south D-zone pad optional while #32D includes a stadium pad. Confirm that the pad is included throughout the south D-zone. Auxiliary-only pad notes at the auxiliary/band details otherwise indicate no band-field pad; confirm this interpretation.
DKorcek Text Box Per Common Scope of work BBB. All work shall be in strict accordance with the drawings and specifications, therefore All grading shall be +/-0.02 foot. BP 31 shall meet the grading tolerance as specified in section 32 1123 as applicable per that section
DKorcek Text Box Supply and installation shall be provided per scopes of work. BP 32D shall cut off excess length of pipe provided by BP 31 and connect its storm system to it. Per Bid Clarification 1 BP 32D shall included specification section 33 4615.
DKorcek Text Box Per BP 32D Scope of work, Section 27 5119 is included in 32D. Specification section 27 5119 has been requested from IDS. BP 32D shall furnish and install all items in Section 27 5119 both in turf and outside of turf including complete installation. Electrical Components specified in electrical specifications are provided by BP 26.
DKorcek Text Box Per BP 3 Scope, Concrete curb is furnished for turf areas. BP 32D is responsible for Wood Turf anchor.
DKorcek Text Box RFI will be written
DKorcek Text Box RFI will be written
11. Maintenance equipment Manual p.72, Additional item 3 and stadium breakdown; Section 32 1818, 1.2.A.5, 1.6.B.6 and 3.5.B.
Is maintenance equipment required?
12. Field markings and flag football Section 32 1818, 2.2.C.8.e; LD1.11, LD1.12 and LD1.13.
The flag-football entry is blank. Confirm whether flag-football markings are required; if so, issue colors, widths, dimensions and applicable fields. Confirm the issued graphics sheets define the base-bid markings and provide editable logo/lettering artwork before shop drawing preparation.
13. Testing scope, payer and minimum locations Section 32 1123, 1.3.D-F, 1.5.D and 2.1.C; Section 32 1818, 1.4.E and 1.7; manual p.72.
Please identify who contracts and pays for subgrade/aggregate compaction, permeability, sieve tests and planarity/string checks, because the base sections refer to Owner-selected/provided testing while #32D includes testing. Confirm whether eight base permeability locations and ten turf G-max/HIC locations apply separately to each field, and identify any required warranty-period testing frequency and payer. Confirm HIC applies only to padded areas.
14. Performance acceptance criteria Section 32 1818, 1.7.F-G, 1.8.A.9-10 and 2.2.B.3; Section 32 1123, 2.1.B.
The turf section requires system infiltration greater than 16 inches/hour in testing but greater than 10 inches/hour in product requirements; the aggregate section references 14 inches/hour for the system including stone. Confirm the test method, assembly and governing threshold at each stage.
Also clarify initial padded-field G-max less than 120 versus the 80-165 warranty range and whether/when HIC must be retested during warranty.
15. Permits, inspection fees and delegated design Manual p.14, common scope J-M; p.70 General item 1; p.60 Sitework items 25-27.
Identify the permits, inspection/report requirements and fees specifically assigned to #32D, separate from Owner/sitework permits and the specified product/base testing. Confirm whether any signed/sealed engineering is required from #32D for turf/drainage/box work and identify the required deliverables. Confirm goal-post, net and concrete structural design remain with the assigned trades.
16. Turnover milestones and separate field acceptance Manual schedule pp.219-224; #32D multiple-mobilization requirement p.70.
The schedule lists fall sports beginning August 7, 2027 (TBD), first home game September 2, and stadium substantial completion September 8, with auxiliary substantial completion November 17.
Confirm mandatory playable-field turnover dates, field-specific base access/handoff dates, testing/training deadlines and whether early use initiates each field warranty separately. Identify required temporary protection and access maintained after each turnover.
DKorcek Text Box Per Specification 2.2E Maintenance Equipment shall be included in base bid.
DKorcek Text Box RFI will be written
DKorcek Text Box RFI will be written
DKorcek Text Box RFI will be written
DKorcek Text Box Each Bid Package is responsible for Common scope items as required. BP 32 will be responsible for signed/sealed engineering for their scope of work as per the Construction Documents.
DKorcek
Reference specific installation completion dates in the Construction Schedule. Warranty starts as per the substantial completion date in the schedule regardless of Manufactures. If their is a cost difference, a voluntary alternate can be provided.
17. Access protection and fencing responsibility L1.1 replacement notes; manual p.61 Sitework item 43; pp.68-69 fencing scope.
L1.1 assigns track protection and temporary fence removal/reinstallation within the turf replacement notes, while Sitework provides two track crossings. Confirm whether those crossings fulfill #32D requirements and identify who supplies, maintains and removes any additional protection and temporary fence openings needed for turf work.
DKorcek
Supply install and removal of the track protection as identified is by BP 31. Fence removal/reinstall as identified is by BP 32C. Any additional protection necessary to perform the work of this scope is the responsibility of BP 32D. All trades are responsible to protect existing work in place and the work of other trades.
| (616) 285-6933 |
| BID CLARIFICATION NO. 2 |
| FROM: Dan Korcek, Senior Project Manager; Morgan Gross, Assistant Project Manager |
File details come from the government source that posted it. Updated .