This is a Statement of Work (SOW) for the installation of Millipore pure and ultrapure water filtration systems at Brookhaven National Laboratory (BNL), a Department of Energy facility located in Upton, New York, managed by BrookhavenScience Associates. The work is specific to lab space 3LL07 at the National Synchrotron Light Source II (NSLSII).
The vendor is responsible for providing complete installation labor and parts, with all parts required to be new. Installation must be completed onsite the same day unless the BNL Technical Representative approves an extended timeline in advance. The vendor must adhere to all BNL work planning and control requirements, complete required training, and have the installation inspected by an authorized BNL Technical Representative before the job is marked complete. No after-hours or weekend work is permitted without prior approval from the Technical Representative. The vendor must supply their own tools, equipment, supplies, and personal protective equipment (PPE) based on equipment specifications and supplier operator manuals, while also complying with any additional PPE requirements identified by BNL.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ENCLOSURE A DRAFT PO 475362.pdf | ||
| BSA_Commercial_Product_Rev23.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P.O. Box 5000 Upton, NY 11973-5000 managed by Brookhaven Science Associates for the U.S. Department of Energy
Subject: Scope of Work for NSLSII lab Millipore pure & Ultrapure water filtration system Install
1. The vendor shall install Brookhaven National Laboratory (BNL) owned Millipore water filtration systems in the designated area of the specified lab space of 3LL07.
2. The vendor shall follow all BNL work planning and control requirements and complete all required training.
3. The installation shall be inspected by the BNL Technical Representative before the job is marked as complete. Authorized Technical Representatives will be identified in advance.
4. Vendor shall provide labor + parts. All parts will be new.
5. Pure & Ultrapure water filtration system installation shall be completed onsite.
6. The vendor will install Pure & Ultrapure water filtration system the same day, unless approved in advance by the Technical Representative for a longer turnaround time.
7. No after-hours or weekend work is expected or authorized under this statement of work, unless approved by BNL Technical Representative.
8. The vendor will provide their own tools, equipment, and any necessary supplies to complete the job.
9. The vendor will provide their own PPE based off their equipment, installation, and suppliers’ operator’s manual.
10. Vendor shall comply with any additional BNL identified PPE requirements.
Signature: