About this file
MOD to address additional questions to solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Responses_to_RFIs_(2nd_Set_CLARIFICATION)_Related_to_NRC-R1-91-14-Q-0005.docx | DOCX document | |
| Responses_to_RFIs_Related_to_NRC-R1-91-14-Q-0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Additional responses to questions that have arisen regarding solicitation NRC-R1-91-14-Q- 0005:
14) Are additional strips of UL Level III ballistic panels required to be overlaid along seams? No.
15) Is UL Level III ballistic protection also required behind wall outlets and switches? Yes.