This document is a Notice to Proceed letter from the Oregon Department of Fish and Wildlife (ODFW) to Molecular, Inc. for Contract 835-384-22 Oxbow Hatchery Rearing Pond Repairs. The project involves performing repairs to the rearing ponds at the Oxbow hatchery by injecting an expanding chemical soil grout to waterproof and seal the underside of ponds 1-3. The project start date is 7 calendar days from issuance of the Notice to Proceed, with a Substantial Completion date of no later than November 18, 2022 and Final Completion date of no later than November 30, 2022. All contract activities are to be coordinated with the ODFW Project Engineer, Charles Matteson.
The contract is specific to the Oxbow Hatchery located in Hood River County and Carlton City, Oregon. The Notice to Proceed indicates that ODFW's solicitation, evaluation, and approval processes have been satisfied, and Molecular, Inc. is authorized to proceed with the contract terms. The contract pricing and any set-aside requirements are not included in this document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 01 22 00 MEASUREMENT AND PAYMENT - Updated 10-25-22.pdf | ||
| ITB.pdf | ||
| Oxbow Hatchery Pricing Submittal Sheet REV 10-25-22.docx | DOCX document | |
| Oxbow Rearing Pond Repairs Attachment B Plans Drawings REV 10 25 22 .pdf | ||
| Bid Tally sheet~1.pdf | ||
| Prebid attendee list.pdf | ||
| TERMS AND CONDITIONS - All Other Federal~2.docx | DOCX document | |
| Oxbow Soilgrout Injection Compressed.pdf | ||
| Technical Specifications.pdf | ||
| ITA~10.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Fish and Wildlife
Fish Division 4034 Fairview Industrial Dr SE Salem, OR 97302
(503) 947-6201
FAX (503) 947-6202
www.dfw.state.or.us/
Chris Siegrist and Courtney Rawson Molecular, Inc.
157 McMillan Dr Longview, WA 98632 Re:
NOTICE TO PROCEED; Contract 835-384-22
Oxbow Hatchery Rearing Pond Repairs Chris and Courtney, ODFW’s solicitation, evaluation, and approval processes have been satisfied and we have received the required documents for the above referenced project. This letter serves as ODFW’s final Contract award.
Molecular, Inc. is authorized to proceed in strict accordance with the terms of the Contract. Included with this letter is a copy of the executed Contract/ Project Manual for your records.
All Contract activities shall be coordinated with Charles Matteson, ODFW Project Engineer (503) 947-6239 or charles.r.matteson@odfw.oregon.gov.
Project dates are as follows:
PROJECT START DATE: 7 calendar days from issuance of Notice to Proceed.
SUBSTANTIAL COMPLETION: No later than November 18, 2022 FINAL COMPLETION: No later than November 30,2022
Sincerely, Kathy Blehm Kathy Blehm, OPBC Procurement Contract Specialist II