This is a Bid Clarification document issued by Rockford Construction Company for the Northview High School Athletic Stadium Addition & Renovation project located in Grand Rapids, Michigan. The clarification, dated September 9, 2026, addresses five Requests for Information (RFIs) submitted by bidders and subcontractors during the bidding phase. The document provides scope clarifications regarding lighting fixtures beneath bleachers, concrete foundations and flatwork requirements, aluminum facade specifications, auxiliary angle frame bleacher finishes, and tread plank finishing standards. Contact information for local excavation contractors (John W. Potter and Dykema Excavators) and concrete contractors (Choice Concrete Construction, Schepers Concrete Construction, and Prime Construction Co.) is provided to assist bidders in obtaining local pricing for these services.
The RFI responses clarify several key scope elements for Bid Category 13: lighting fixtures for walkways beneath bleachers have been removed from the bleacher contractor's scope and will be included in the overall electrical scope provided by others; all concrete required for foundations and flatwork for bleachers, grandstand, and press box, including 21AA aggregate base materials, falls under Bid Category 13; black vinyl chainlink fence (per sheet LD5.02 details) applies to the elevated walkway and stair areas rather than colored aluminum facade; auxiliary angle frame bleacher risers shall be finished with clear anodized aluminum rather than color-coated aluminum; and tread planks shall remain mill finish despite industry concerns regarding oxidation and staining of uncoated aluminum surfaces. The project manager and assistant project manager from Rockford Construction coordinated these clarifications with design firm Integrated Design Solutions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
601 First Street NW Grand Rapids, Michigan 49504
(616) 285-6933 www.rockford.com
BID CLARIFICATION NO. 1
TO: All Subcontractors / Suppliers
FROM: Dan Korcek, Senior Project Manager; Morgan Gross, Assistant Project Manager
DATE: September 09, 2026
RE: NVPS Athletics Improvements – Bleachers
This Bid Clarification No.1 is being sent to all bidders to address questions raised at bid time.
1. Requests for Information (RFIs) Documents attached. Refer to responses from IDS/Rockford.
a. Bid RFI 1 – Scope Clarification
b. Bid RFI 2 – Scope Clarifications – Sidewalks
c. Bid RFI 3 – Bleacher Aluminum Façade Clarification
d. Bid RFI 4 – Auxiliary Angle Frame Bleacher Clarification
e. Bid RFI 5 – Tread Plank Finish – Mill Finish Clarification
2. Contact Information for local excavation and concrete contractors that have expressed interest in the project. The Bidders may contract them for local pricing is they choose.
a. Excavation Contractors
i. John W. Potter – Cameron Potter, (616) 291-5717, cameron@JWPotter.com
ii. Dykema Excavators – Eric Olson, (616) 893-6936, eric@dykemaexcavators.com
b. Concrete Contractors
i. Choice Concrete Construction – Dendel Craven, (616) 723-5012, dcraven@choiceconcretecorp.com
ii. Schepers Concrete Construction – Zakery MacDonald, (616) 552-2844, estimator@schepersconcrete.com
iii. Prime Construction Co. – Ryan Pearson, (248) 387-9144, admin@primeconstructionco.net
End of Clarification http://www.rockford.com/
ROCKFORD CONSTRUCTION CO.
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger Grand Rapids, Michigan 49525
P: 616-327-9354
RFI #1: BID RFI 01 - Scope Clarification
Revision 0 Status Closed on 09/02/26
To Morgan Gross (Rockford Construction) (Response Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Sep 2, 2026 Due Date Sep 7, 2026
Location Project Stage Bidding
Cost Impact Schedule Impact
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Copies To Dan Korcek (Rockford Construction)
Activity
Question Question from Morgan Gross Rockford Construction on Wednesday, Sep 2, 2026 at 09:10 AM EDT Provide Lighting fixtures beneath the bleachers as walkways and other locations where required by code. See attached for further clarification requirement. Typically on previous projects, this would fall under the electrical Scope to furnish and install.
Attachments Bleacher BID RFI 01 REDACTED.pdf
Official Response Response from Morgan Gross Rockford Construction on Wednesday, Sep 2, 2026 at 09:13 AM EDT Remove Scope item 3 under PRESSBOX / BLEACHER ELECTRICAL / LIGHTING from Bid Category 13 Scope of Work. This will be designed into the overall electrical scope provided by others.
Bleacher BID RFI 01 REDACTED.pdf
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Sep 9, 2026 09:38 AM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M1H3SQK7D6VKRWHZ55BG16MV?companyId=562949953513905&projectId=562949955315041&sig=713392df65b2728e575c38e17af115d08bce93894ba3921c18d19e67d58a2507 https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M1H41CNBJMZ0BMB32Y0MWTDV?companyId=562949953513905&projectId=562949955315041&sig=28302aa07b83be82d9fa18c6d625ba92de883ae77ad574566d1ef1d8355aa438
DKorcek Text Box Remove Scope item 3 under PRESSBOX / BLEACHER ELECTRICAL / LIGHTING from Bid Category 13 scope of work. This will be designed into the overall electrical scope provided by others.
mgross Polygon mgross Polygon
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #2: BID RFI 02 - Scope Clarifications - Sidewalks
Revision 0 Status Closed on 09/02/26
To Morgan Gross (Rockford Construction) (Response Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Sep 2, 2026 Due Date Sep 7, 2026
Location Project Stage Bidding
Cost Impact Schedule Impact
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Question Question from Morgan Gross Rockford Construction on Wednesday, Sep 2, 2026 at 09:23 AM EDT There are numerous varied descriptions for the required foundations/concrete required to be furnished under this scope, as in exterior slabs, sidewalks, curbs, ramps, stairs, pads and other concrete flatwork, except as specifically excluded in this scope of work. The only exclusions listed are the AV rack and associated rack equipment.
Details 2 & 4/LD5.01 indicate specifically spread footings, ramp pads and stair pads for the Home Side and details 2 & 12/LD5.05 indicate specifically slab under the bleachers which includes ramp and stair pads for auxiliary bleachers. Please confirm these are the only foundations/concrete required under this scope of work. This would also include the required 21AA aggregate or stone base under this concrete flatwork as indicated by these details.
Bleacher BID RFI 02 REDACTED.pdf
Official Response Response from Morgan Gross Rockford Construction on Wednesday, Sep 2, 2026 at 09:24 AM EDT The intent of the scope is that Bid Category 13 is to include all concrete that is required for foundations for the bleachers, Grandstand, and press box. It is also the intent to include the slabs and flatwork shown on the bid documents under bleachers, Grandstand, and press box as well as any additional concrete required for the bleachers, Grandstand, and press box that may vary from the design provided by IDS. concrete work not shown on the plans is intended to be provided by others unless it is required for the bleacher install.
Per the scope, Bid Category 13 is to include all 21AA aggregate or other sand base under concrete as per the bid documents is by this bid category.
Bleacher BID RFI 02 REDACTED.pdf
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Sep 9, 2026 10:05 AM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M1H4KKYJY5S6NFSF58T94N6H?companyId=562949953513905&projectId=562949955315041&sig=f0ff48c2197b74901fa058d5c8019bcc361d995e5a19fc8de887e959883e5fcb https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M1H4MWEHBEWB60PD2RTPT6H5?companyId=562949953513905&projectId=562949955315041&sig=0f1edf700836f8077700f089982a9ad74ef813a78b0670815b86d32b12849fc8
The intent of the scope is that Bid Category 13 is to include all concrete that is required for foundations for the bleachers, Grandstand, and press box. It is also the intent to include the slabs and flatwork shown on the bid documents under bleachers, Grandstand, and press box as well as any additional concrete required for the bleachers, Grandstand, and press box that may vary from the design provided by IDS. concrete work not shown on the plans is intended to be provided by others unless it is required for the bleacher install.
Per the scope, Bid Category 13 is to include all 21AA aggregate or other sand base under concrete as per the bid documents is by this bid category.
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #3: Bid RFI 03 - Bleacher Aluminum Facade Clarification
Revision 0 Status Closed on 09/09/26
To Bill Zaske (Integrated Design Solutions) (Response Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Sep 2, 2026 Due Date Sep 7, 2026
Location Project Stage Bidding
Cost Impact Schedule Impact
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Question Question from Morgan Gross Rockford Construction on Wednesday, Sep 2, 2026 at 09:34 AM EDT Specification indicates lower front colored aluminum facade enclosing the lower full length of grandstand and stairs. Detail 7 &
8/LD5.02 indicates field installed black vinyl chain link fence for these areas. Which Applies?
Bleacher BID RFI 03 REDACTED.pdf
Official Response Response from Bill Zaske Integrated Design Solutions on Wednesday, Sep 9, 2026 at 09:22 AM EDT The intent for the area from the elevated walkway and stairs is black vinyl chainlink per details on sheet LD5.02.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Sep 9, 2026 10:12 AM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M1H549TZTPGXR2B9KV0HNX4X?companyId=562949953513905&projectId=562949955315041&sig=0febcab0681b49ac4eece2068cbb872c78795e74a745725c3e0d0180e1945b38
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #4: BID RFI 04 - Auxiliary Angle Frame Bleacher Clarifications
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Sep 2, 2026 Due Date Sep 7, 2026
Location Project Stage Bidding
Cost Impact Schedule Impact
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Question Question from Morgan Gross Rockford Construction on Wednesday, Sep 2, 2026 at 09:42 AM EDT For Auxiliary Angle Frame Bleachers, color coated risers are specified. Detail 7/LD5.05 indicates anodized risers which would be clear. Which Applies?
Bleacher BID RFI 04 REDACTED.pdf
Official Response Response from Bill Zaske Integrated Design Solutions on Wednesday, Sep 9, 2026 at 09:23 AM EDT The riser finish intent for the Auxiliary Angle Frame
Bleacher is clear anodized aluminum.
All Replies Response from Bill Zaske Integrated Design Solutions on Wednesday, Sep 9, 2026 at 09:23 AM EDT The riser finish intent for the Auxiliary Angle Frame
Bleacher is clear anodized aluminum.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Sep 9, 2026 10:48 AM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M1H5PX97RV7MVDGWTS41N3EC?companyId=562949953513905&projectId=562949955315041&sig=a07e397acf92dd8abc544beab455bdf66bf5f1fe9e05398f7201af187f28e766
Grand Rapids, Michigan 49504 P: (616) 285-6933
Project: NVPS - Northview Athletics Stadium Addition & Renovation
4451 Hunsberger
RFI #5: Bid RFI 05 - Tread Plank Finish - Mill Finish Clarification
Required)
From Morgan Gross (Rockford Construction) 601 First Street NW Grand Rapids, Michigan 49504
Date Initiated Sep 2, 2026 Due Date Sep 7, 2026
Location Project Stage Bidding
Cost Impact Schedule Impact
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Question Question from Morgan Gross Rockford Construction on Wednesday, Sep 2, 2026 at 09:48 AM EDT Tread Planks are called out as Mill Finish. The inherent trait of mill finish aluminum is oxidation and staining. Mill finish indicates uncoated. Section 133510.3.1.C & 133525.3.3.B states that Bleacher Contractor shall be responsible to clean or replace foot planks that become stained or oxidized beyond an acceptable level based on industry standards. Industry standards state that is mill finish aluminum is provided, expect staining and oxidation, because the metal is uncoated. The specification for any mill finish material is recommended to be changed to a minimum clear anodized finish. Coating the mill finish aluminum is the only assurance for acceptable staining and oxidation.
Bleacher BID RFI 05 REDACTED.pdf
Official Response Response from Bill Zaske Integrated Design Solutions on Wednesday, Sep 9, 2026 at 09:23 AM EDT The tread plank finish intent is mill finish.
All Replies Response from Bill Zaske Integrated Design Solutions on Wednesday, Sep 9, 2026 at 09:23 AM EDT The tread plank finish intent is mill finish.
ROCKFORD CONSTRUCTION CO. Page 1 of 1 Printed On: Sep 9, 2026 10:57 AM EDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/509315359949265-c/140513559949265-p/01M1H615QGDXTNZWQNC362FQRE?companyId=562949953513905&projectId=562949955315041&sig=b681d8ca09acca1ebdf0b10aa38c2e6f747fc30bf1545785509afa6a462b95bf