This is a Design-Build Lump Sum Contract document for the Heintzelman Boulevard Pavement Rehabilitation & Related Improvements project (BP-00510) at Orlando International Airport, issued by the Greater Orlando Aviation Authority (GOAA). The project encompasses approximately 3.9 miles of roadway rehabilitation, including asphalt milling, resurfacing, drainage and lighting improvements, erosion control, roadway markings, and maintenance of traffic. The contract is structured as a two-step design-build solicitation process, with shortlisted firms required to submit detailed technical and price proposals following initial qualifications evaluation. A pre-submittal conference was scheduled for December 15, 2025, with questions due by December 22, 2025, initial qualifications responses due January 12, 2026, and tentative shortlisting on March 3, 2026. The contract requires substantial completion within 640 calendar days from the Notice to Proceed, with final completion required within 60 additional calendar days. The document establishes comprehensive general conditions covering contractor responsibilities, including architectural and engineering design services, construction supervision, permitting, safety, insurance, bonding, quality control, and payment procedures, along with special conditions specific to airport operations including security protocols, air operations area restrictions, and FAA compliance requirements.
The total estimated project cost is approximately $9,013,719.40, funded through Greater Orlando Aviation Authority Bond Series (GARBS) at $17,400,000. Shortlisted firms must provide a proposal guaranty equal to 10 percent of their total price proposal, and the successful contractor must furnish performance and payment bonds equal to the total contract price. Liquidated damages are assessed at $6,600 per calendar day for delays beyond substantial completion and $3,300 per calendar day for delays beyond final completion. The contractor must maintain comprehensive insurance coverage including $3,000,000 commercial general liability, $1,000,000 automobile liability, $5,000,000 professional errors and omissions coverage, and $1,000,000 pollution/environmental liability. The contract specifies retainage at up to 5 percent of certified payment amounts during construction, with provisions for early reduction upon milestone completion. Contractor mark-up on change orders is limited to tiered percentages ranging from 6 to 15 percent depending on work value and performance tier. The contract includes provisions addressing Florida statutory requirements, non-discrimination compliance, public records access, E-Verify employment verification, and whistleblower reporting protocols.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN BUILD CONTRACT
for
BP-00510, Heintzelman Blvd. Pavement Rehabilitation & Related Improvements
ORLANDO INTERNATIONAL AIRPORT
One Jeff Fuqua Boulevard Orlando, Florida 32827
GREATER ORLANDO AVIATION AUTHORITY
BP-00510, Heintzelman Blvd. Pavement Rehabilitation & Related Improvements i July 2025 Design-Build Lump Sum Version
DESIGN/BUILD LUMP SUM VERSION
DIVISION 0 – TABLE OF CONTENTS
DIV 0 PROCUREMENT AND CONTRACTING REQUIREMENTS
00 31 11 Project Directory 00 52 53 Contract Agreement Form 00 61 13 Performance/Payment Bond Cover Sheet 00 61 13.13 Performance Bond Form 00 61 13.16 Payment Bond Form 00 61 13.19 Performance and Payment Bond Certification Form 00 62 16 Certificate of Insurance Form
ATTACHMENT A Contractor’s Statement of Qualifications (Solicitation Response Step 1) ATTACHMENT B Contractor’s Proposal, including schedule and price proposal
(Solicitation Response Step 2) ATTACHMENT C Owner’s Authorization Documents
(Advertisement, Solicitation including all Addenda (export from OpenGov, Committee and Board Memoranda)
00 62 93 Construction Administration Forms 00 62 76.19 Partial Release and Waiver of Claims (including for Reduction of Retainage) 00 65 19.29 Final Release Form 00 65 19.33 Subcontractor Final, Conditional Release Form 00 72 53 General Conditions of the Design/Build Contract 00 73 19.13 Hazardous Materials 00 73 93 Special Conditions Regarding Construction at Airport Facilities 00 73 93.01 Security and Badging at Airports
DIVISION 01 GENERAL REQUIREMENTS
provided electronically and the most current version is incorporated herein by reference
01 11 00 Summary of Work 01 21 00 Allowances 01 23 00 Alternates 01 25 00 Substitution Procedures 01 29 73 Schedule of Values 01 31 00 Project Management and Coordination 01 31 14.13 System Interruptions/Utility Outage Notification Procedures 01 31 19 Project Meetings 01 32 13 Scheduling of Work 01 32 14 Project Acceleration and Inefficiency Claims 01 32 33 Photographic Documentation 01 33 23 Shop Drawings, Product Data and Samples 01 33 29 Sustainable Material Content Forms 01 35 46 Indoor Air Quality 01 42 00 References 01 43 39 Visual Mock-Up Requirements 01 45 00 Quality Control 01 50 00 Temporary Facilities and Controls 01 55 30 Requirements for use of Canal Road ii July 2025 Design-Build Lump Sum Version
01 60 00 Product Requirements 01 71 23 Field Engineering 01 73 29 Cutting and Patching 01 74 19 LEED V4 Construction Waste Management and Disposal 01 74 23 Final Cleaning 01 78 00 Closeout Submittals 01 81 13.14 Sustainable Design Requirements - LEED v4 BD+C 01 91 13 General Commissioning Requirements 01 91 15 Facility Exterior Enclosure Commissioning
Other Divisions provided electronically and the most current version incorporated herein by reference
Div 2 Existing Conditions Div. 3 Concrete Div. 4 Masonry Div. 5 Metals Div. 6 Wood, Plastics and Composites Div. 7 Thermal & Moisture Protection: Green and Sustainable Initiatives Div. 8 Openings Div. 9 Finishes Div. 10 Specialties Div. 11 Equipment Div. 14 Conveying Systems Div. 21 Fire Suppression Div. 22 Plumbing Div. 23 Heating, Ventilating and Air Conditioning (HVAC) Div. 26 Electrical Div. 27 Communications Div. 28 Electronic Safety and Security Div. 32 Exterior Improvements Div. 33 Utilities Div 34 Transportation
EDC Number Document Title
Documents have been provided electronically and the most current version is incorporated herein by reference, as applicable
Revision Date
EDC - 02 Coversheet April 2025 EDC-02a CAD Standards April 2025 EDC-02b BIM Standards April 2025 EDC-02c BIM Execution Plan April 2025 EDC-02d GIS Standards April 2025 EDC - 06 Project Deliverables June 2025 EDC - 08 Design Services Checklist Instructions Feb 2025 EDC-08a Design Services Checklist Feb 2025 EDC - 09 Designer’s General Scope of Services April 2025 EDC – 11 Technical Review Instructions April 2025 EDC-11a Technical Review Form April 2025
EDC-22 Permit Matrix Instructions TBD iii July 2025 Design-Build Lump Sum Version
EDC-22a Permit Matrix February 2010
EDC-29 Design Kick-Off Meeting Instructions August 2009
EDC-29a Design Kick-Off Meeting (Agenda) August 2009
EDC-39 Sensitive Security Information Instructions June 2015
EDC-40 Construction Safety & Phasing Plan (CSPP) Instructions June 2015
EDC-40a Form - Construction Safety & Phasing Plan (CSPP) June 2015
EDC-43 Horizontal Permitting Rules and Regulations August 2016
EDC-43a GOAA Signage Guidelines TBD
EDC-43b GOAA Parking Guidelines TBD
EDC-43c Horizontal Permitting Checklist December 2024
EDC-43d Horizontal Permit Review Form December 2024
EDC-45 Environmental Permitting November 2018
EDC-45 Environmental Permitting Process Diagram November 2018
EDC-46a GOAA Fence & Gate Details February 2019
ORLANDO INTERNATIONAL AIRPORT PROJECT DIRECTORY
BP-00510, Heintzelman Blvd. Pavement Rehabilitation & Related Improvements SECTION 00 31 11
00 31 11 - 1 September 2024 Design-Build Lump Sum Version
SECTION 00 31 11 - PROJECT DIRECTORY
OWNER
Greater Orlando Aviation Authority Mr. Scott Shedek, P.E.
Vice President of Construction Orlando International Airport 11314 Terminal C Service Road Orlando, Florida 32824 Phone: 407-825-2465
CONTRACTOR
DESIGN CRITERIA CONSULTANT
Kimley-Horn & Associates, Inc.
Project Manager Robert Harris 200 South Orange Ave. Suite 600, Orlando, FL 32801 Phone: 407.898.1511 Email: brian.ashby@kimley-horn.com
END OF SECTION 00 31 11
ORLANDO INTERNATIONAL AIRPORT CONTRACT AGREEMENT FORM
00 65 19.33 - 1 September 2024 Design-Build Lump Sum Version
SECTION 00 52 53 - CONTRACT AGREEMENT FORM
THIS CONTRACT made and entered into this_______ day of ___________, in the year _________, by and between the GREATER ORLANDO AVIATION AUTHORITY, hereinafter called the Owner, and ____________________, hereinafter called the Contractor.
The Contractor, for and in consideration of the Total Contract Price specified herein, agrees to furnish all labor, equipment, materials , supplies and services, to develop the design and construct the scope of work, all in conformity with the Contract Documents for BP-00510, Heintzelman Blvd. Pavement Rehabilitation & Related Improvements. The Contractor shall be responsible for paying to the appropriate governmental entity all applicable taxes enacted as of the effective date of the contract, whether or not yet effective or merely scheduled to go into effect, and whether or not included in its price proposal.
The Contractor agrees to make payment of all proper charges for labor, equipment, materials, supplies and services, and to indemnify, and hold harmless the Owner in accordance with the Contract Documents. If the Contractor fails to comply with any of the terms of the Contract Documents, the Owner may avail itself of any or all remedies provided in the Contract Documents or in law or equity. The acceptance of final payment by the Contractor shall be considered as a release in full of all claims against the Owner or any of its members, officers, agents, employees or servants, directly or indirectly relating to, arising out of, or by reason of, this Contract, except for those Claims that have been properly raised in accordance with the Contract Documents and specifically identified by the Contractor as unsettled in the final Application for Payment.
The Owner will pay the Contractor for satisfactory performance of the Work, according to the terms set forth in the Contract Documents, the Total Contract Price of _____________________________________ Dollars ($_____________.00) subject to approved Contract Modifications, if any.
The Contractor hereby certifies it will utilize the U.S. Department of Homeland Security's Employment Eligibility Verification System, in accordance with the terms governing the use of the system, to confirm the employment eligibility of persons employed by the Contractor, during the term of the Contract, to perform employment duties within Florida. The Contractor specifically represents that it will not discontinue use of the System until every Contract with the Owner has reached Final Completion. The Contractor further certifies that it will include this provision in each Subcontract that involves work for the Owner.
IN WITNESS WHEREOF, the said GREATER ORLANDO AVIATION AUTHORITY has caused this Contract to be executed in its name by its Chief Executive Officer or designee, and the Contractor has caused this Contract to be executed in its name by __________________________, its President or other authorized signatory, all on the day and year first above written.
SIGNATURES ON NEXT PAGE
ORLANDO INTERNATIONAL AIRPORT CONTRACT AGREEMENT FORM
00 65 19.33 - 2
Design-Build Lump Sum Version
By:___________________________________________ Lance Lyttle, Chief Executive Officer Approved as to Form and Legality (for the benefit of GOAA only) this _______ day of ________________, 20______
By:_______________________________________
NELSON MULLINS BROAD AND CASSEL
Legal Counsel for Greater Orlando Aviation Authority
CONTRACTOR:
By:
Title: ____________________________
Printed Name: ___________________
ORLANDO INTERNATIONAL AIRPORT PERFORMANCE/PAYMENT BOND
COVER SHEET
SECTION 00 61 13
00 61 13-1 GOAA March 2022 Design-Build Version
SECTION 00 61 13 - PERFORMANCE/PAYMENT BOND COVER SHEET
This cover sheet is an integral part of the attached bonds and must not be separated from them.
ORLANDO, FLORIDA
(Public Work)
In Compliance with Florida Statutes, Section 255.05(1)(a)
PERFORMANCE BOND NO.:
PAYMENT BOND NO.:
CONTRACTOR INFORMATION: Name:
Address:
Phone:
SURETY PRINCIPAL: Name:
BUSINESS INFORMATION Address:
OWNER INFORMATION: Name:
Greater Orlando Aviation Authority One Airport Boulevard Orlando, FL 32827
(407) 825-2001
BOND AMOUNT: $
CONTRACT NO. (if applicable):
DESCRIPTION OF WORK:
PROJECT LOCATION: Orlando International Airport, Orlando, FL
AGENT INFORMATION: Name:
PERFORMANCE BOND FORM
SECTION 00 61 13.13
00 61 13.13 - 1
Design-Build Version
SECTION 00 61 13.13 - PERFORMANCE BOND BOND NO.:____________________
The cover page that lists the contact information for the entities involved in this bond is considered the front page of this bond and is an integral part of this bond and, therefore, must not be separated from this bond.
KNOW ALL PERSONS BY THESE PRESENTS that ____________________, hereinafter called Principal, and ________________________________________________, a corporation organized under the laws of the State of __________________ and licensed to do business in the State of Florida, hereinafter called Surety, are held and firmly bound unto the Greater Orlando Aviation Authority, hereinafter called Owner, in the Penal Sum of __________________________________________ ____________________________________________ Dollars ($________________________), for the payment of which sum well and truly made, Principal and Surety bind ourselves, our heirs, personal representatives, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, Principal has by written agreement dated _______________________________, entered into a Contract with Owner for BP-0010, Heintzelman Blvd. Pavement Rehabilitation & Related Improvements, in accordance with the Contract Documents which are incorporated herein by reference and made a part hereof, and are herein referred to as the Contract.
WHEREAS, Surety is authorized to do business in the State of Florida.
NOW, THEREFORE, the condition of this obligation is such that if Principal:
1. Promptly and faithfully performs the Contract including, but not limited to, its construction and warranty provisions in the time and manner prescribed in the Contract, and correction of defective work, and
2. Pays Owner all losses, damages, expenses, costs, attorneys' fees and other legal costs (including, but not limited to, those for investigative and legal support services and appellate proceedings), that Owner sustains resulting directly or indirectly from the conduct of the Principal including, but not limited to, breach or default under the Contract, want of care or skill, negligence, patent infringement, or intentionally wrongful conduct on the part of the Principal, its officers, agents, employees or any other person or entity for whom the Principal is responsible, then this bond is void; otherwise it shall remain in full force and effect.
3. In the event that the Principal shall fail to perform any of the terms, covenants and conditions of the Contract during the period in which this Performance Bond is in effect, the Surety shall remain liable to the Owner for all such loss or damage (including reasonable attorneys' fees and other legal costs) resulting from any failure to perform up to the amount of the Penal Sum.
4. In the event that the Surety fails to fulfill its obligations under this Performance Bond, then the Surety shall also indemnify and save the Owner harmless from any and all loss, damage, cost and expense, including reasonable attorneys' fees and other legal costs for all trial and appellate proceedings resulting directly or indirectly from the Surety's failure to fulfill its obligations hereunder. This paragraph shall survive the termination or cancellation of this Performance Bond. The obligations set forth in this paragraph shall not be limited by the Penal Sum of this Bond.
5. The Surety's obligations hereunder shall be direct and immediate and not conditional or contingent upon Owner's pursuit of its remedies against Principal, and shall remain in full force and effect notwithstanding (i) amendments or modifications to the Contract entered into by Owner and Principal without the Surety's knowledge or consent, (ii) waivers of any default under the Agreement or the Contract granted by Owner to Principal without the Surety's consent, (iii) the discharge of Principal from its obligations under the Contract as a result of any proceeding initiated under The Bankruptcy Code of 1978, as the same may be amended, or any similar state or federal law, or any limitation of the liability of Principal or its estate as a result of any such proceeding, or (iv) any other action taken by Owner or Principal that
PERFORMANCE BOND FORM
SECTION 00 61 13.13
00 61 13.13 - 2
Design-Build Version would, in the absence of this clause, result in the release or discharge by operation of law of the Surety from its obligations hereunder.
6. The institution of suit upon this Bond shall be in accordance with Section 95.11(2)(b), Florida Statutes.
7. Any changes in or under the Contract Documents (which include the Plans, Drawings and Specifications) and compliance or noncompliance with any formalities connected with the Contract or the changes therein shall not affect Surety's obligations under this Bond and Surety hereby waives notice of any such changes. Further, Principal and Surety acknowledge that the Penal Sum of this bond shall increase or decrease in accordance with approved changes or other modifications to the Contract Documents.
IN WITNESS WHEREOF, the Principal and Surety have executed this instrument under their several seals on this ________ day of _________________________, _______, to be effective as of the date of the Contract, the name and corporate seal of each corporate party being hereto affixed and these presents fully signed by its undersigned representative, pursuant to authority of its governing body.
Signed, sealed and delivered in the presence of: Principal
Name and Title
(SEAL)
Surety
(SEAL) Agency
Address
(Countersignature by a Florida Licensed Agent)
Name and Title
Agency
Address
NOTE: If Principal or Surety are corporations, the respective corporate seals should be affixed.
Additionally, a certified copy of a Power-of-Attorney appointing the individual Attorney-in-Fact for the Surety, as well as the Power-of-Attorney appointing the Florida licensed agent, should be attached.
PAYMENT BOND FORM
SECTION 00 61 13.16
00 61 13.16 - 1
SECTION 00 61 13.16 - PAYMENT BOND FORM BOND NO.:______________________
The cover page that lists the contact information for the entities involved in this bond is considered the front page of this bond and is an integral part of this bond and, therefore, must not be separated from this bond.
KNOW ALL PERSONS BY THESE PRESENTS that _____________________________, hereinafter called Principal, and ______________________________________________________________, a corporation organized under the laws of the State of ____________________, having its home office in the City of ____________________ and licensed to do business in the State of Florida, hereinafter called Surety, are held and firmly bound unto the Greater Orlando Aviation Authority, hereinafter called Owner, for the use and benefit of claimants as herein below defined, in the Penal Sum of Dollars ($_________________________) for the payment of which sum well and truly to be made, Principal and Surety bind ourselves, our heirs, personal representatives, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, Principal has by written agreement dated _________________________________, entered into a contract with Owner for BP-0010, Heintzelman Blvd. Pavement Rehabilitation & Related Improvements, in accordance with the Contract Documents which are incorporated herein by reference and made a part hereof, and are herein referred to as the Contract.
WHEREAS, Surety is authorized to do business in the State of Florida.
NOW, THEREFORE, the condition of this obligation is such that if Principal shall promptly make payments to all claimants as defined in Section 255.05(1), Florida Statutes, supplying Principal with labor, materials, or supplies, used directly or indirectly by Principal in the prosecution of the work provided for in the Contract, then this obligation shall be void; otherwise, it shall remain in full force and effect subject, however, to the following conditions: requirement
1. This bond is given to comply with Section 255.05, Florida Statutes, and any action instituted by a claimant under this bond for payment must be in accordance with Sections 255.05(2) and 255.05(10), Florida Statutes, as amended, including, but not limited to, the notice and time limitation provisions therein.
2. Therefore, a claimant, except a laborer, who is not in privity with the Contractor shall, before commencing or not later than 45 days after commencing to furnish labor, services or materials for the prosecution of the work, serve the Contractor with a written notice that he or she intends to look to the bond for protection. A claimant who is not in privity with the Contractor and who has not received payment for furnishing his or her labor, services, or materials shall, serve a written notice of nonpayment on the Contractor and on the Surety. Notices must be served in accordance with Section 255.05(2), as amended. The notice of non-payment shall be under oath and served during the progress of the work or thereafter, but may not be served earlier than forty-five (45) days after the first furnishing of the labor, services or materials by the claimant or later than ninety (90) days after the final furnishing of the labor, services or materials by the claimant, or, with respect to rental equipment, later than 90 days after the date that the rental equipment was last on the job site available for use. Any notice of nonpayment served by a claimant who is not in privity with the contractor which includes sums for retainage must specify the portion of the amount claimed for retainage. No action for the labor, services, or materials may be instituted against the Contractor or the Surety unless both notices have been served. No action shall be instituted against the Contractor or the Surety on the bond after one (1) year from the performance of the labor or completion of the delivery of the materials or supplies.
PAYMENT BOND FORM
SECTION 00 61 13.16
00 61 13.16 - 2
Design-Build Version
3. The Surety's obligations hereunder shall remain in full force and effect notwithstanding (i) amendments or modifications to the Contract entered into by Owner and Principal without the Surety's knowledge or consent, (ii) waivers of compliance with or any default under the Contract granted by Owner to Principal without the Surety's knowledge or consent, (iii) the discharge of Principal from its obligations under the Contract as a result of any proceeding initiated under The Bankruptcy Code of 1978, as the same may be amended, or any similar state or federal law, or any limitation of the liability of Principal or its estate as a result of any such proceeding, or (iv) any other action taken by Owner or Principal that would, in the absence of this clause, result in the release or discharge by operation of law of the Surety from its obligations hereunder.
4. Any changes in or under the Contract Documents (which include the, Drawings and Specifications) and compliance or noncompliance with any formalities connected with the Contract or the changes therein shall not affect Surety's obligations under this Bond and Surety hereby waives notice of any such changes.
Further, Principal and Surety acknowledge that the Penal Sum of this Bond shall increase or decrease in accordance with the approved changes or other modifications to the Contract Documents.
IN WITNESS WHEREOF, the Principal and Surety have executed this instrument under their several seals on this ____ day of _________________________, ____, to be effective as of the date of the Contract, the name and corporate seal of each corporate party being hereto affixed and these presents fully signed by its undersigned representative, pursuant to authority of its governing body.
Signed, sealed and delivered in the presence of: Principal ________________________________________ By:
Surety
Agency
Address
(Countersignature by a Florida Licensed Agent)
Name and Title
Agency
Address
NOTE: If Principal or Surety are corporations, the respective corporate seals should be affixed.
Additionally, a certified copy of a Power-of-Attorney appointing the individual Attorney-in-Fact for the Surety, as well as the Power-of-Attorney appointing the Florida licensed agent, should be attached.
PERFORMANCE/PAYMENT BOND
CERTIFICATION FORM
SECTION 00 61 13.19
00 61 13.19 - 1
SECTION 00 61 13.19 – PERFORMANCE/PAYMENT BOND CERTIFICATION FORM
I, _____________________________________________, certify that I am the Secretary of the corporation, the General Partner of the Partnership or Manager or the Managing Member of the LLC, named as Principal in the foregoing Performance and Payment Bonds; that _____________________________________________ who signed the said Bonds on behalf of the Principal was then President or Vice-President of said corporation, the General Partner of the Partnership or the Manager or Managing Member of the LLC; that I know [his, her] signature, and [his, her] signature thereto is genuine, and that said Bonds were duly signed, sealed and attested for and in behalf of said Principal by authority of its governing body or is otherwise authorized by the Principal to enter into this Contract and the Performance and Payment Bonds.
Secretary Signature
Secretary Printed Name
(Corporate Seal)
00 65 19.33 - i
Design-Build Lump Sum Version
SECTION 00 62 16 – CERTIFICATE OF INSURANCE FORM
The Contractor shall provide evidence of insurance reflecting compliance with the insurance requirements as listed in Section 00 21 13 of the Contract Documents and Article 11 of the General Conditions.
Certificate(s) of Insurance shall be remitted using an ACORD form, or in a form acceptable to the Owner and submitted to the Owner's Procurement Services prior to contract execution and each policy renewal for the duration of the contract term and statute of repose. Any deductible or self-insurance retention ($0.00 and higher) for each coverage line must be indicated on the Certificate of Insurance.
The Certificate of Insurance shall state the following as certificate holder:
The Greater Orlando Aviation Authority
Engineering and Construction
One Jeff Fuqua Blvd.
Orlando, FL 32827
The Certificate of Insurance shall reflect the Greater Orlando Aviation Authority and the City of Orlando and their members (including without limitation, members of the Owner’s board and the City Council and members of the citizens’ advisory committees of each), and the OAR, as additional insured as outlined in Article 11.2 of the General Conditions. Owner may elect to utilize a third party for the collection and monitoring of Contractor’s insurance. Contractor will promptly respond to all requests for information, including, without limitation, requests for copies of insurance policies and Certificate(s) of Insurance evidencing renewal policy periods.
END OF SECTION 00 62 16
ORLANDO INTERNATIONAL AIRPORT CONSTRUCTION ADMINISTRATION FORMS
SECTION 00 62 93
00 62 93 - 1 GOAA March 2022 Design-Build Version
SECTION 00 62 93 - CONSTRUCTION ADMINISTRATION FORMS
PART 1 - GENERAL
The following forms are available electronically upon request and are hereby incorporated into the Construction Documents.
PART 2 - PRODUCT
Index of Construction Administration Forms for Contractor Form # Description
001 Parking Permit Office - Release Form 002 Badge & ID Office (Access Control Office) – Release Form 003 Key Shop - Release Form 005 Bulletin Proposal 007 Certificate of Substantial Completion (CoSC) 008 Substantial Completion List and Final Completion Form 009 Partial Occupancy/Use Agreement (POUA) 010 Application for Payment Forms:
010-Cover Cover Sheet 010-Bkdwn Breakdown 010-SM Stored Materials 010-DISB Contractor Disbursements to Subcontractors/Suppliers
010A Contractor Payment Application Checklist 013A Owner’s Close-Out Documentation Checklist 015 Request for Information 016 Request for Clarification 018 Electrical System Interruption/Utility Outage Notification
018A UON Procedures for Contractors and UON Checklist 018B Roofing Impact Notification (RIN) 018C Security System Interruption/Utility Outage Notification 018D TBD Blank Interruption/Utility Outage Notification 018E Energized Electrical Work Permit 018F Maintenance of Traffic (MOT) Notification 018G Smoke Detector Notification 020 Utility Service Request (to OUC by Owner) 021 Request for Use of Lot(s) on Canal Road 023 Subcontractor’s Sworn Statement of Account 024 Powder Actuated Tools Permit A5 City of Orlando Wastewater Division Construction Closeout Checklist A1 Construction Coordination Phone List A2 Airport Layout Plan (ALP) Change Request A3 Owner’s Hot Work Policy A4 Key Plans and Instructions
PART 3 - EXECUTION
3.1. During the administration of the Contract, the Contractor will be required to complete various construction administration forms as a part of the Greater Orlando Aviation Authority’s Management System. These forms are identified in the “Index of Construction Forms” and will be issued at the Pre-Construction Conference. These forms may be revised during the construction period and the Contractor will be required to comply with these revisions.
END OF SECTION 00 62 93
ORLANDO INTERNATIONAL AIRPORT PARTIAL RELEASE FORM
SECTION 00 62 76.19
00 62 76.19 - 1
Continuing Contractor Design-Build Version
SECTION 00 62 76.19 - PARTIAL RELEASE (INCLUDING FOR REDUCTION OF RETAINAGE)
GREATER ORLANDO AVIATION AUTHORITY
KNOW ALL PERSONS BY THESE PRESENTS, that the undersigned, conditioned upon payment of the sum of ____________________________________________________________________________ DOLLARS ($____________________________) (payment amount), paid by the Greater Orlando Aviation Authority (hereinafter referred to as "Owner"), does hereby fully and completely discharge and release the Owner from and waives any and all debts, accounts, promises, damages, liens, encumbrances, causes of action, suits, bonds, judgments, claims, and demands whatsoever, in law or in equity, which the undersigned ever had, now has, or might hereafter have on account of labor performed, material furnished, or services rendered, directly or indirectly, for the Contract between the parties, dated _____________________, known as BP-00510, Heintzelman Blvd. Pavement Rehabilitation & Related Improvementsexcept for the following Claims, if any, which have been properly raised by written demand and in accordance with the Contract Documents: _____________________________(list brief description of Claim or list None).
All Claims not specifically listed are hereby waived.
The undersigned further covenants that any payment of retainage which is attributable to the labor, services, supplies, or material supplied by one or more subcontractors; suppliers; materialmen; or any or all other persons supplying labor, services, supplies, or material used directly or indirectly in the prosecution of the Work, the undersigned shall timely remit payment of such retainage to those subcontractors, suppliers, materialmen, or persons.
The undersigned shall maintain in full force and effect the provisions of the Contract Documents respecting the guaranty against defective work, and any other special guaranties required by the Contract Documents, for the terms provided in the Contract Documents, which terms shall begin to run from the date specified in the Contract Documents.
The undersigned represents and warrants that the statements contained in the foregoing Release are true and correct and that the person signing this Release has full authority to bind the Contractor.
IN WITNESS WHEREOF, I hereunto set my hand and seal this ________ day of
WITNESSES:
CONTRACTOR
______________________________ By:
______________________________ Title: President
(CORPORATE SEAL)
(If Applicable)
FINAL RELEASE FORM
SECTION 00 62 76.29
00 62 76.29 - 1 July 2025 Design-Build Version
SECTION 00 62 76.29 - FINAL RELEASE FORM
GREATER ORLANDO AVIATION AUTHORITY
KNOW ALL PERSONS BY THESE PRESENTS, that the undersigned, conditioned upon payment of the sum of __________________________________________________________________ DOLLARS ($__________________________) (final total Contract amount), paid by the Greater Orlando Aviation Authority (hereinafter referred to as "Owner"), does hereby fully and completely discharge and release the Owner from and waives any and all debts, accounts, promises, damages, liens, encumbrances, causes of action, suits, bonds, judgments, claims, and demands whatsoever, in law or in equity, which the undersigned ever had, now has, or might hereafter have on account of labor performed, material furnished, or services rendered, directly or indirectly, for the Contract between the parties, dated _____________________, known as “BP-00510, Heintzelman Blvd. Pavement Rehabilitation & Related Improvements" except for those claims, disputes, and other matters arising out of or relating to said Contract which have been properly raised by written demand and in accordance with the Contract Documents prior to this date and identified by the Contractor as unsettled in the final Application for Payment.
The undersigned further covenants that all subcontractors, suppliers, materialmen, and any or all other persons supplying material, supplies, services, or labor used directly or indirectly in or for the Work will be paid in full upon receipt of final payment from Owner.
The undersigned shall maintain in full force and effect the provisions of the Contract Documents respecting the guaranty against defective work, and any other special guaranties required by the Contract Documents, for the terms provided in the Contract Documents, which terms shall begin to run from the date specified in the Contract Documents.
The undersigned represents and warrants that the statements contained in the foregoing Release are true and correct.
IN WITNESS WHEREOF, I hereunto set my hand and seal this ________ day of
WITNESSES:
CONTRACTOR
______________________________ By:
______________________________ Title:
(CORPORATE SEAL)
Final Release Form must be signed by a corporate officer or such other representative of the Contractor with authority to bind the Contractor to this Release.
SUBCONTRACTOR FINAL RELEASE FORM
00 62 76.29 - i July 2025 Design-Build Version
SECTION 00 62 76.33 - SUBCONTRACTOR FINAL, CONDITIONAL RELEASE FORM
GREATER ORLANDO AVIATION AUTHORITY
KNOW ALL PERSONS BY THESE PRESENTS, that the undersigned, conditioned upon payment of the sum of __________________________________________________________ _______________________________ DOLLARS ($____________________________) (final total Contract amount), paid by the Contractor does hereby fully and completely discharge and release the Greater Orlando Aviation Authority from and waives any and all debts, accounts, promises, damages, liens, encumbrances, causes of action, suits, bonds, judgments, claims, and demands whatsoever, in law or in equity, which the undersigned ever had, now has, or might hereafter have on account of labor performed, material furnished, or services rendered, directly or indirectly, for the Project known as BP-00510, Heintzelman Blvd. Pavement Rehabilitation & Related Improvements, except for those Claims, if any, which have been properly raised by written demand and in accordance with the Contract Documents prior to this date and identified by the Contractor as unsettled in the Contractor’s final Application for Payment.
This Final Release and Waiver is conditioned upon receipt of the final payment from the Contractor in the amount of ___________ Dollars ($_______) and is not effective until that payment is received.
The undersigned further covenants that all sub-subcontractors, suppliers, materialmen, and any or all other persons supplying material, supplies, services, or labor used, directly or indirectly, on or for the Project have been paid in full.
The undersigned shall maintain in full force and effect all guaranties against defective work, and any other special guaranties required by the Contract and Subcontract.
The undersigned represents and warrants that the statements contained in the foregoing Release are true and correct.
IN WITNESS WHEREOF, I hereunto set my hand and seal this ________ day of
WITNESSES:
SUBCONTRACTOR
______________________________ By:
______________________________ Title:
(CORPORATE SEAL)
BP-00510, Heintzelman Blvd. Pavement Rehabilitation & Related Improvements GENERAL CONDITIONS OF THE
DESIGN/BUILD CONTRACT
SECTION 00 72 53
00 62 76.29 - i
Design-Build Version
Table of Contents
ARTICLE 1 GENERAL PROVISIONS
1.1 BASIC DEFINITIONS
1.2 EXECUTION AND INTENT
1.3 OWNERSHIP AND USE OF DRAWINGS, SPECIFICATIONS AND OTHER DOCUMENTS AND DATA
1.4 CAPITALIZATION
1.5 INTERPRETATION
1.6 ORDER OF PRECEDENCE
1.7 STANDARD FORMS
1.8 OWNER FURNISHED ELECTRONIC DOCUMENTS:
ARTICLE 2 OWNER’S RESPONSIBILITIES
2.1 INFORMATION AND SERVICES REQUIRED OF THE OWNER
2.2 OWNER'S RIGHT TO STOP OR SUSPEND THE WORK
2.3 OWNER'S RIGHT TO CARRY OUT THE WORK
ARTICLE 3 CONTRACTOR’S RESPONSIBILITIES
3.1 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR
3.2 ARCHITECTURAL AND ENGINEERING DESIGN SERVICES, GENERALLY
3.3 PRE-CONSTRUCTION AND DESIGN SERVICES
3.5 CONSTRUCTION SUPERVISION AND OBLIGATIONS
3.6 LABOR, SERVICES AND MATERIALS
3.7 WARRANTY
3.8 TAXES
3.9 PERMITS, FEES, INSPECTIONS, AND NOTICES
3.10 ALLOWANCES
3.11 CONTRACTOR'S KEY PERSONNEL
3.12 CONTRACTOR'S DESIGN AND CONSTRUCTION SCHEDULES
3.13 DOCUMENTS AND SAMPLES AT THE PROJECT SITE; AS-BUILT AND RECORD DOCUMENTS .. 19
3.14 SUBMITTALS: DESIGN DOCUMENTS, DRAWINGS, AND SPECIFICATIONS; SHOP DRAWINGS,
PRODUCT DATA, AND SAMPLES
3.15 USE OF SITE AND COORDINATION
3.16 CUTTING AND PATCHING
3.17 CLEANING UP
3.18 ACCESS TO WORK
3.19 ROYALTIES AND PATENTS
ARTICLE 4 ADMINISTRATION OF THE CONTRACT
4.1 ROLE OF THE DESIGN CRITERIA CONSULTANT (DCC)
4.2 ROLE OF THE OWNER'S AUTHORIZED REPRESENTATIVE (OAR)
ARTICLE 5 SUBCONTRACTORS AND SUBCONSULTANTS
5.1 AWARD OF SUBCONTRACTS AND OTHER CONTRACTS FOR PORTIONS OF THE WORK
5.2 SUBCONTRACTUAL RELATIONS
ARTICLE 6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
00 62 76.29 - ii
Design-Build Version
6.1 OWNER'S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACTS ... 27
6.2 MUTUAL RESPONSIBILITY
6.3 OWNER'S RIGHT TO CLEAN UP
6.4 MULTIPLE CONTRACTS WITH CONTRACTOR SETOFF
ARTICLE 7 CHANGES IN THE WORK
7.1 CONTRACT MODIFICATIONS ............................................. ERROR! BOOKMARK NOT DEFINED.
7.2 CHANGE ORDERS (CO)
7.3 CONSTRUCTION CHANGE DIRECTIVES (CCD)
7.4 FIELD CHANGE ORDERS (FCO)
7.5 FORCE ACCOUNT WORK
7.6 MINOR CHANGES IN THE WORK
ARTICLE 8 TIME
8.1 PROGRESS AND COMPLETION
8.2 TIME OF COMPLETION, DELAYS AND EXTENSIONS OF TIME
8.3 LIQUIDATED DAMAGES
8.4 COMPUTATION OF TIME
ARTICLE 9 PAYMENTS AND COMPLETION
9.1.1 TOTAL CONTRACT PRICE
9.2 SCHEDULE OF VALUES
9.3 APPLICATION AND CERTIFICATE FOR PAYMENT
9.4 STORED MATERIALS
9.5 PROGRESS PAYMENTS AND RETAINAGE
9.6 CONTINUED PERFORMANCE PENDING PAYMENT
9.7 SUBSTANTIAL COMPLETION
9.8 PARTIAL OCCUPANCY OR USE
9.9 FINAL COMPLETION AND FINAL PAYMENT
9.10 PAYMENT OF LIQUIDATED DAMAGES AND BACKCHARGES
9.11 OWNER'S RECORDS REVIEW AND AUDIT RIGHTS
ARTICLE 10 PROTECTION OF PERSONS AND PROPERTY
10.1 SAFETY PRECAUTIONS AND PROGRAMS
10.2 SAFETY OF PERSONS AND PROPERTY
10.3 HAZARDOUS MATERIALS
10.4 EMERGENCIES
ARTICLE 11 INSURANCE AND BONDS
ARTICLE 12 UNCOVERING AND CORRECTION OF WORK
12.1 UNCOVERING WORK
12.2 CORRECTION OF WORK
12.3 ACCEPTANCE OF NONCONFORMING WORK
ARTICLE 13 MISCELLANEOUS PROVISIONS
13.1 GOVERNING LAW
13.2 SUCCESSORS AND ASSIGNS
13.3 WRITTEN NOTICE
00 62 76.29 - iii
Design-Build Version
13.4 RIGHTS AND REMEDIES
13.5 TESTS, EXAMINATIONS, AND INSPECTIONS
13.6 INTEREST
13.7 REPRESENTATIONS AND WARRANTIES
13.8 COMPLIANCE WITH NON-DISCRIMINATION REQUIREMENTS
13.9 PUBLIC RECORDS
13.10 NO WAIVER
13.11 SURVIVAL OF PROVISIONS
13.12 CONSULTATION WITH COUNSEL
ARTICLE 14 TERMINATION OR SUSPENSION OF THE CONTRACT
14.1 TERMINATION BY THE CONTRACTOR
14.2 TERMINATION BY THE OWNER FOR CAUSE
14.3 SUSPENSION OR TERMINATION BY THE OWNER FOR CONVENIENCE
ARTICLE 15 CLAIMS AND DISPUTES
ARTICLE 16 WHISTLEBLOWER REPORTING LINE
ARTICLE 17 E-VERIFY
GENERAL CONDITIONS OF THE DESIGN/BUILD CONTRACT
00 72 53 - 1 July 2025
Design Build Lump Sum Version
SECTION 00 72 53 - GENERAL CONDITIONS OF THE DESIGN/BUILD CONTRACT
ARTICLE 1 GENERAL PROVISIONS
1.1 BASIC DEFINITIONS
1.1.1 CLAIM
A Claim is a demand or assertion, made by written notice and quantified pursuant to Article 15, by the Owner or Contractor seeking, as a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract Documents.
1.1.2 CONTRACT
The phrase “Contract” or “Agreement” may be used as an abbreviation for Contract Documents, which together form the Design Build Contract.
1.1.3 CONTRACT DOCUMENTS
The Contract Documents consist of the executed Contract Agreement between the Owner and Contractor, the Design Criteria Package, the Owner’s Design Guidelines, the Request for Statements of Qualifications, Contractor’s Statement of Qualifications, Contractor’s Proposal, General Conditions of the Design Build Contract, all contract administration forms, and Contract Modifications.
1.1.4 CONTRACT MODIFICATIONS
A Contract Modification is issued after execution of the Agreement in the form of: (1) a Change Order,
(2) a Construction Change Directive, or (3) a Field Change Order.
1.1.5 CONTRACT TIME
Unless otherwise provided, Contract Time is the period of time, including adjustments authorized by a Contract Modification, to achieve Substantial Completion and Final Completion of the Work and is measured by actual calendar days.
1.1.6 CONTRACTOR
The term “Contractor” as used throughout the Contract Documents shall mean “Contactor”. Contactor means a partnership, corporation, or other legal entity that: is certified under Fla. Stat. s. 489.119 to engage in contracting through a certified or registered general contractor or a certified or registered building contractor as the qualifying agent; or is certified under Fla. Stat. s. 471.023 to practice or to offer to practice engineering; certified under s. 481.219 to practice or to offer to practice architecture;
or certified under s. 481.319 to practice or to offer to practice landscape architecture.
1.1.7 CONTRACTOR’S DRAWINGS
The Contractor’s Drawings are the graphic and pictorial portions of the Contract Documents prepared by the Contractor to depict the Contractor’s design, location and dimensions of the Work, 00 72 53 - 2 July 2025
Design Build Lump Sum Version generally including, plans, elevations, sections, details, schedules and diagrams, prepared in accordance with the Owner’s minimum CAD, BIM and Drawing Standards. The content of the Contractor’s Drawings shall not supersede the requirements of the Owner’s Design Guidelines unless establishing a higher level of standard.
1.1.8 CONTRACTOR’S PROJECT MANUAL
The Contractor’s Project Manual consists of one or more volumes of bound documents assembled for the Work by the Contractor which may include the specifications and other requirements prepared and issued for construction by the Contractor during the design phase of the Work for construction of the Work. The content of the Contractor’s Project Manual shall not supersede the requirements of the Owner’s Design Guidelines unless establishing a higher level of standard.
1.1.9 CONTRACTOR’S SPECIFICATIONS
The Contractor’s Specifications are those portions of the Contract Documents prepared by the Contractor in compliance with the Owner’s Design Guidelines, consisting of the written requirements for materials, equipment, construction systems, standards and workmanship for the Work, and performance of related services. The content of the Contractor’s Specifications shall not supersede the requirements of the Owner’s Design Guidelines unless establishing a higher level of standard. The Owner’s Design Guidelines and Division 01 specifications have been provided to the Contractor electronically and are incorporated into the Contractor’s Specifications by reference.
1.1.10 DAY
The term “day” as used in the Contract Documents shall mean calendar day unless otherwise specified. When any contractual obligation is measured by the number of days and the deadline date falls on a legal holiday or weekend when the Owner’s office is closed, the obligation will be allowed to be completed on the next business day without penalty.
1.1.11 DESIGN CRITERIA PACKAGE
The Design Criteria Package (DCP) describes the Work to be performed under this Contract and includes the performance and scope drawings, the Owner Design Guidelines, the quantity and quality requirements of the Work, the sample forms, the Conditions of the Contract, the location of the Work, and the time in which the Work must be completed. The purpose of the DCP is to furnish sufficient information to permit the Contractor to prepare the Proposal.
1.1.12 DESIGN CRITERIA CONSULTANT (DCC)
The Design Criteria Consultant is the entity, lawfully licensed in Florida to practice architectural or engineering services, that was retained by the Owner to prepare the DCP.
1.1.13 DESIGNER
The Designer is the Contractor’s person or entity lawfully licensed in Florida to provide architectural or engineering services in connection with the Project and is referred to throughout the Contract Documents as if singular in number. The term "Designer" means the Designer or the Designer's authorized representative and is the entity responsible for signing and sealing the Plans and Specifications prepared by Contractor for construction of the Work. The Designer is part of Contractor’s design-build team and includes subconsultants if applicable.
00 72 53 - 3 July 2025
Design Build Lump Sum Version
1.1.14 FINAL COMPLETION
Final Completion is the date when final acceptance of the Work in accordance with the Contract Documents is achieved and all other Contract requirements have been fully performed, including the delivery of all required close-out documentation.
1.1.15 LIQUIDATED DAMAGES
Liquidated Damages are those damages, identified in the Solicitation, which the Owner may assess against the Contractor or its Surety for the Contractor’s tardy Substantial or Final Completion of the Work.
1.1.16 PROJECT
The Project is the totality of the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner or by separate contractors.
1.1.17 PROPOSAL
The Proposal consists of the Contractor’s Statement of Qualifications, technical proposal, and price proposal, including any Proposal Forms, documents, reports and information referenced in the Request for Statements of Qualifications, Addenda, and the Contractor’s technical proposal and price proposal. The Proposal shall not lessen the minimum quality standards of the Owner’s Design Guidelines by omission, modification or revision. The quantity requirements, unless specifically listed as a minimum, are provided for guidance to the Proposer for development of its own approach, concept and final design. Written and verbal statements made by the Contractor during the solicitation process are deemed to be part of and included in the Proposal.
1.1.18 OWNER
The Owner is the Greater Orlando Aviation Authority.
1.1.19 OWNER’S AUTHORIZED REPRESENTATIVE (OAR)
The OAR is the person or entity that is selected by the Owner to perform the OAR's responsibilities of the Contract Documents.
1.1.20 RECORD DOCUMENTS
The Record Documents consist of those documents assembled by the Contractor at the conclusion of the Contractor’s performance of construction or service. Record Documents are developed from as-built drawings, as-built specifications and any other documents required to be submitted by the Contractor for closing out the Project. The Record Documents shall accurately document the Work as constructed, including all Contract Modifications and Changes.
1.1.21 SUBCONTRACTOR OR SUBCONSULTANT
A Subcontractor or Subconsultant is a person or entity who has a direct contract with the Contractor to furnish labor, material, equipment or services for the Work. The term "Subcontractor" or “Subconsultant” is referred to throughout the Contract Documents as if singular in number and means a Subcontractor or Subconsultant or an authorized representative of the Subcontractor.
00 72 53 - 4 July 2025
Design Build Lump Sum Version
1.1.22 SUB-SUBCONTRACTOR OR SUB-SUBCONSULTANT
A Sub-subcontractor or Sub-subconsultant is a person or entity who has a direct or indirect contract with a Subcontractor or Subconsultant to furnish labor, material, equipment or services for the Work. The term "Sub-subcontractor" or “Sub-subconsultant” is referred to throughout the Contract Documents as if singular in number and means a Sub-subcontractor or Sub-subconsultant or an authorized representative of the Sub-subcontractor or Sub-subconsultant.
1.1.23 SUBSTANTIAL COMPLETION
Substantial Completion is the date when the Work is deemed by the OAR and Design Criteria Consultant to be sufficiently complete in accordance with the requirements of the Contract Documents, agreed to by the Owner, and includes, but is not limited to, the requirements of Article 9 and Section 01 78 00, being fulfilled.
1.1.24 WORK
The "Work" means the labor, materials, equipment, and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor's obligations. The Work may constitute the whole or a part of the Project.
1.2 EXECUTION AND INTENT
1.2.1 The applicable Contract Documents shall be signed by the Owner and Contractor.
1.2.2 The intent of the Contract Documents is to include all information necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by one portion shall be as binding as if required by all.
Performance by the Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable as being necessary to produce the intended results. The Drawings indicate arrangements and results to be accomplished and the Contractor shall provide such necessary fastenings and accessories. If a conflict exists between the Contract Documents, the Order of Preference provision contained in Articles1.6.1 and 1.6.2 shall apply.
1.3 OWNERSHIP AND USE OF DRAWINGS, SPECIFICATIONS AND OTHER DOCUMENTS AND
DATA
1.3.1 All Drawings, Specifications and other documents and electronic data prepared by the DCC and the Contractor are and shall remain the property of the Owner, and the Owner shall retain all common law, statutory and other reserved rights with respect thereto. The Contractor, Subcontractors, Subconsultants, and material and equipment Suppliers are granted a limited license to use and reproduce applicable portions of the Drawings, Specifications and other documents appropriate to and for use in the execution of their Work under the Contract Documents.
Submittals or distributions necessary to meet official regulatory requirements or for other purposes relating to completion of the Project are not to be construed as a publication in derogation of the Owner's copyright or other reserved rights.
1.3.2 The Contractor acknowledges and agrees that all records, documents, drawings, notes, tracings, plans, specifications, maps, evaluations, reports and other technical data and electronic data, instruments of service (other than working papers), including but not limited to, all Architectural
00 72 53 - 5 July 2025
Design Build Lump Sum Version
Works as defined by the federal Architectural Works Copyright Protection Act (whether hard copy or electronically stored), prepared, developed or furnished by Contactor or the design professional(s) employed or retained by the Contactor under this Contract (Project Documents) will be and remain the property of the Owner. Project Documents will be deemed to be works made for hire, and all right, title and interest in and to the Project Documents will be vested in Owner.
Contactor will take all actions necessary to secure for Owner all such right, title and interest.
Contactor warrants that all materials comprising the Project Documents are original with the Contactor and have not been copied or derived from any…