Node 49 Underground Repairs - Brentwood Dr.pdf
PDF 88 KB Posted
- Solicitation number
- BD-22-1324-SELCO-SELCO-67208
- Issued by
- Worcester County, Massachusetts
About this file
This document is a scope of work for underground repairs and conduit work to be performed by a contractor for SELCO - Shrewsbury Electric and Cable Operations in Brentwood Dr., Shrewsbury, MA. The contractor will be responsible for excavating, repairing, and restoring damaged or broken conduit that houses active coax cable lines. The contractor must adhere to all safety requirements and OSHA regulations, and work to minimize disturbances to the property. SELCO will provide the necessary conduit materials, while the contractor is responsible for supplying the labor, tools, equipment, and consumables required to complete the repairs. Upon completion, the contractor must certify that the work has been performed in accordance with the contract documents and that all equipment and systems are operational.
The related state and local contract opportunity is for conduit repairs across multiple nodes (22, 23, 24, 29, 49, and 51) in October 2021, located in the state of Massachusetts. No additional details about the pricing terms, set asides, incumbents, funding, or contract duration are provided in the given document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SELCO- Shrewsbury Electric and Cable Operations Node 49 “Underground Repairs” Brentwood Dr.
Underground/ Digging Construction: Conduit repair around multiple locations in Brentwood Dr. Shrewsbury MA.
CONTRACTOR REQUIREMENTS:
Contractor to Adhere to all safety requirements and OSHA Regulations, The Contractor shall be responsible for developing, implementing, and managing all safety protections, work flow, precautions and programs to prevent damage, injury, or loss to all employees on the work site and other persons that may be affected thereby; and all work, materials, and equipment to be incorporated therein, whether in storage on or off site.
*Dig-safe pre-marked areas of possible damaged or broken schedule 40 conduit areas before any work is performed.
WORK SCOPE:
• Contractor will dig and or excavate to repair existing- damaged or broken conduit which houses active Coax Hardline to make conduit passable.
• Contractor needs to be aware of the existing Coax and not remove or cut existing cable which will affect customer services. In the case the Contractor needs to remove coax they must contact SELCO representatives before doing so.
• Contractor will supply all the Labor, tools and equipment needed to repair the conduit. SELCO will supply scheduled 40 conduit solid or split duct. Consumables such as glue and or miscellaneous items are Contractors responsibilities.
• When Contractor has finished repairing conduit they need to rod and rope the repaired duct with mule-tape provided by SELCO in the span of conduit ensuring a reliable pull rope for later cable installation.
Contractor will keep all disturbances of property to a minimum and will return all excavated areas to "pre-excavation" condition after the conduit is in place. This may require sod to be laid and concrete and asphalt to be repaired. Work areas to be cleaned of debris daily by the Contractor. Contractor shall be responsible for protection of landscape and plants and surrounding structures.
FINAL INSPECTION: When the Contractor considers the work complete, the Contractor shall submit written certification that:
1. Contract Documents have been reviewed.
2. Work has been inspected for compliance with Contract Documents.
3. Work has been completed in accordance with Contract Documents.
4. Equipment and systems have been tested in the presence of the SELCO representative and are operational.