Node 22 Underground Repairs - Kenda Rd and Doranna Ave.pdf

PDF 155 KB Posted

Attached to
Conduit Repairs, Node 22, 23, 24, 29, 49, 51 - October 2021
Solicitation number
BD-22-1324-SELCO-SELCO-67208
Issued by
Worcester County, Massachusetts

About this file

This document is a Scope of Work for underground repairs and conduit restoration for SELCO - Shrewsbury Electric and Cable Operations in Massachusetts. The work involves excavation and repair of damaged or broken schedule 40 conduit in multiple locations on Kenda Rd. and Doranna Ave. in Shrewsbury, MA. The contractor will be responsible for all labor, tools, and equipment needed to complete the conduit repairs, while SELCO will supply the conduit materials. The contractor must adhere to all safety requirements, OSHA regulations, and restoration of the excavated areas. A final inspection and written certification of the completed work is required.

The related state and local contract opportunity is for conduit repairs on Nodes 22, 23, 24, 29, 49, and 51 in the state of Massachusetts, to be completed in October 2021. Pricing terms, set asides, funding details, and other contract specifics are not provided in the scope of work document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SELCO- Shrewsbury Electric and Cable Operations Node 22 “Underground Repairs” Kenda Rd and Doranna Ave.

Underground/ Digging Construction: Conduit repair around multiple locations in Kenda Rd. and Doranna Ave. Shrewsbury MA.

CONTRACTOR REQUIREMENTS:

Contractor to Adhere to all safety requirements and OSHA Regulations, The Contractor shall be responsible for developing, implementing, and managing all safety protections, work flow, precautions and programs to prevent damage, injury, or loss to all employees on the work site and other persons that may be affected thereby; and all work, materials, and equipment to be incorporated therein, whether in storage on or off site.

*Dig-safe pre-marked areas of possible damaged or broken schedule 40 conduit areas before any work is performed.

WORK SCOPE:

• Contractor will dig and or excavate to repair existing- damaged or broken conduit which houses active Coax Hardline to make conduit passable.

• Contractor needs to be aware of the existing Coax and not remove or cut existing cable which will affect customer services. In the case the Contractor needs to remove coax they must contact SELCO representatives before doing so.

• Contractor will supply all the Labor, tools and equipment needed to repair the conduit. SELCO will supply scheduled 40 conduit solid or split duct. Consumables such as glue and or miscellaneous items are Contractors responsibilities.

• When Contractor has finished repairing conduit they need to rod and rope the repaired duct with mule-tape provided by SELCO in the span of conduit ensuring a reliable pull rope for later cable installation.

Contractor will keep all disturbances of property to a minimum and will return all excavated areas to "pre-excavation" condition after the conduit is in place. This may require sod to be laid and concrete and asphalt to be repaired. Work areas to be cleaned of debris daily by the Contractor. Contractor shall be responsible for protection of landscape and plants and surrounding structures.

FINAL INSPECTION: When the Contractor considers the work complete, the Contractor shall submit written certification that:

1. Contract Documents have been reviewed.

2. Work has been inspected for compliance with Contract Documents.

3. Work has been completed in accordance with Contract Documents.

4. Equipment and systems have been tested in the presence of the SELCO representative and are operational.