NOAA Standard Specification 8634.0.docx.pdf
PDF 218 KB Posted
- Attached to
- FY27 NOAA Ship Gordon Gunter Drydock REFERENCES Federal contract opportunity
- Solicitation number
- 1305M226Q0144REF
About this file
NOAA STDSPEC-8634.0: Drydocking and Routine Drydock Work on NOAA Vessels
This is a standard specification document that establishes requirements for drydocking and routine drydock work performed on National Oceanic and Atmospheric Administration (NOAA) vessels. The specification applies to contractors performing drydocking services at certified facilities and encompasses all phases from preparation through undocking. Key certifications required include validation from Naval Sea Systems Command (NAVSEA) per MIL-STD-1625D, membership in the International Association of Classification Societies (ICAS), or certification by a qualified independent engineering firm based on safety and condition inspections conducted within the preceding 24 months. Contractors must submit multiple pre-docking documents to the Contracting Officer's Representative (COR) at least 72 hours prior to docking, including facility certifications, completed NOAA Pre-Drydocking Worksheets, dock master qualifications with resume, and detailed drydocking and undocking procedures accounting for vessel characteristics, water depth, and tide/current conditions.
The specification mandates hauling the ship within the first 25 percent of the contract performance period and maintaining the vessel in drydock until all required work is completed. Critical requirements include block arrangement per the ship's docking plan with minimum 2-inch soft wood caps, installation of grounding cables before keel clears water (minimum 500,000 circular mils), and immediate dock basin washdown. Protection measures include temporary hull closures during non-work hours, discharge fittings and spigots for all hull openings, and comprehensive protection of transducers with plywood covers throughout cleaning and painting operations. Cleaning must occur within 12 hours of drydocking using stiff bristle brushes and high-pressure fresh water, with specific protocols for rubber-faced transducers (mineral spirits degreasing and MIL-P-22298/MIL-P-22299 paint coats) and metallic-faced transducers (nitric acid solution and crocus cloth polish). The specification requires joint damage inspections immediately after drydocking and underwater hull inspections within 48 hours, with condition reports submitted to the COR including NOAA Drydocking Reports (Form 2410). A final quality assurance requirement mandates a joint pre-docking inspection of block placement with the COR, Project Manager, and dock master, with the contractor providing a 300-foot tape measure and blocking diagram. Part 6 provides a comprehensive drydocking checklist for contractor guidance throughout all phases of the operation.
View the file
Other files for this federal contract opportunity
Show all 50
FY27 NOAA Ship Gordon Gunter Drydock REFERENCES has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA STDSPEC-8634.0
NOAA Standard Specification
8634.0 DRYDOCKING and ROUTINE DRYDOCK WORK ON NOAA VESSELS
PART 1 GENERAL
SCOPE: This specification contains the requirements for drydocking and routine drydock work for NOAA Vessels.
1.1 References
National Oceanic and Atmospheric Administration (NOAA)
NOAA DD Report NOAA Drydocking Report, Form 2410
NOAA Pre-DD Worksheet NOAA Pre-Drydocking Worksheet
1.2 Government-Furnished
1. None.
PART 2 DEFINITIONS
2.1 None.
PART 3 REQUIREMENTS
3.1 Submittals
1. Prior to drydocking the ship, prepare and submit to the Contracting Officer's Representative (COR) a minimum of 72 hours prior to docking procedure:
a. A current certification issued by Naval Sea Systems Command (NAVSEA) in accordance with MIL-STD-1625D or member of the International Association of Classification Societies (ICAS) validating that the drydock or railway facility is in good operating condition.
1. If the facility does not have NAVSEA certification or classification by an ICAS member, then a certification prepared and signed by a qualified independent engineering firm, may be substituted. This certification must be based on a safety and condition inspection of the facility within the preceding 24 months, and must attest that the facility:
a.Is safe and in acceptable material condition.
b. Is capable of hauling the intended ship and that the ship does not exceed the drydock's dimension rating, maximum entry draft, maximum lift capacity, and maximum linear load rating.
c. Has provided an incident history and claim information covering the last five years from the insurer of the drydock facility including all incident dates, description, and final disposition.
d.Has a detailed procedure for hauling and floating.
e.Has effective emergency response systems and plans.
2. A completed copy of NOAA Pre-DD Worksheet; Part B, Part D, and if applicable, Part C; or contractor equivalent. A copy of NOAA Pre-DD Worksheet will be provided by the COR.
3. A letter certifying that the dock master in charge of the hauling and floating evolutions is professionally qualified, through training and experience, to conduct the evolutions in a safe and reliable manner. Attach a copy of the dock master's resume to the letter.
4. A drydocking and undocking procedure which includes operating practices, and special precautions that are required due to the characteristics of the dock or ship, depth of water, and tide and current conditions which will exist.
3.2 General Requirements
1. Drydocking shall be in a facility that is certified by NAVSEA, an ICAS member, or a qualified independent engineering firm.
2.Haul the ship within the first 25% of the time allowed for the contract performance period.
3. Protect the ship against damage and fire during the entire hauling and floating procedure, and while the ship is out of the water.
4. Keep the ship in drydock until all work which requires drydocking has been completed, including all work included in the initial contract award and all additional work authorized or being negotiated.
a. If the Contractor desires to float the ship and subsequently re-haul the ship for completion of work, submit to the Contracting Officer a letter which clearly outlines the reasons for the request. If the Contracting Officer decides to grant the request, the extent of the Government's liability for costs related to the floating and re-hauling shall be limited to the additional lay day costs for which the Government would be liable if the ship were not floated and re-hauled.
5. Provide adequate staging, or other safe means in accordance with applicable federal a, state and local regulations/laws, to accomplish all contract work and to permit a thorough inspection of the underwater body.
6. While the ship is in drydock, install temporary closures over all hull openings during hours outside the normal work shifts. Blank flanges and closure plates shall have sufficient strength and tightness to prevent water entry into the hull in the event of drydock failure or flooding.
7. Fit all hull discharge openings and scupper drains with discharge fittings, spigots and hoses to direct liquids away from the hull. Hull discharge openings which will not be in service while the ship is in drydock may be plugged in lieu of being fitted with the fittings, spigots and hoses. If the ship is docked in cold or freezing weather, drain all sea valves, pipes or similar fittings attached to the hull to prevent freezing and possible damage.
3.3 Preparations for Drydocking
1.Arrange the blocks in the drydock or railway according to the ship's docking plan.
2. Position the blocks to haul the ship in the position specified in the detail specification item. If the detail specification item does not specify a docking position, the COR shall specify the docking position.
3. The minimum height of the keel blocks shall be in accordance to the ship's docking plan or dictated by the COR. In some cases a minimum height will be dictated to accomplish work outside of the contractors scope by ships force or other entity.
4.All keel blocks must have 2 inches minimum soft wood caps.
5.Ensure that all transducers, domes, and other protuberances are clear of all blocks.
6. Ensure there are no obstructions between the floor surface of the drydock and the hull, hull openings, appendages, and fittings.
7. Provide ample horizontal and vertical clearance for removal and replacement of rudders, bow thrusters, fathometers, sea scanners, and sonar gear on the ship, whether or not such removals or replacement are known to be required.
3.4 Drydocking
1.Record the fore and aft draft mark readings port and starboard of the ship prior to drydocking.
2. After obtaining the consent of the COR, haul the ship without strain or injury in a drydock or marine railway. If any tendency to strain or injure the ship is observed, immediately refloat the ship and rearrange the blocks or make other corrections required to relieve the condition.
3. Prior to the keel clearing the water, attach two grounding cables from the ship's hull to ground to protect against lightning or other static discharges. Connect one of the cables near the bow and the other cable near the stern. Each cable shall be a minimum size of 500,000 circular mils.
4. Immediately after the ship is in drydock, wash the dock basin down to remove silt, mud, and debris.
3.5 Drydocking Damage Inspection
1. Immediately after completing the drydock operations, conduct a joint inspection by the Contractor, the COR and the Commanding Officer/Master's representative to ensure no damage occurred to the hull or appendages during the drydocking.
3.6 Cleaning
1. Transducer faces are extremely fragile membranes. Use extreme caution when washing, cleaning, prepping, and painting to prevent damage. When growth and grime are present, it can appear that the transducer faces are extremely durable, however they are easily damaged by pressure or hard scraping. Carefully follow all instructions provided in this specification.
2. As soon as practical, but in all cases within 12 hours after drydocking the ship, clean the entire underwater hull and boot-topping of all marine growth, dirt and loose paint using stiff bristle brushes, scrapers, and high pressure fresh water.
a. Prior to high pressure wash, cover all transducer faces with a plywood cover to protect the transducers from damage.
b. Exercise extreme care to avoid scratching, gouging or otherwise damaging transducers, dome windows, shaft coverings, or other appendages.
c. Exercise care not to remove anti-fouling paint, especially during high pressure wash, unless detail specifications include work items that require repainting the underwater hull.
3. Clean sea strainer plates, sea chests, bow thrusters, rudders, anodes, propellers, shafts, struts, and other underwater hull appendages, as follows:
a.Fiberglass surfaces - clean with non-metallic scrapers and bristle brushes.
b.Anodes - clean with a wire brush to remove all corrosion products.
c.Propellers and bow thrusters - polish to bright metal.
4.Clean transducers as specified in paragraph 4.8 below.
3.7 Underwater Hull Inspection
1. Within 24 hours after drydocking the ship, remove all sea chest covers, strainer plates, rope guards, and fairwaters.
2. Within 48 hours after drydocking the ship, or as specified by the COR, conduct a joint inspection of the ship's underwater hull by the Contractor, the COR, and the Commanding Officer/Master's representative. The inspection shall include the following:
a. Condition of the hull, particularly inspecting for evidence of structural damage and deterioration of plating, welds, and fasteners.
b.Condition of anodes and paint system.
c. Condition of propellers, rudders, sea chests, shafts, overboard discharge piping, bilge keels, transducers, and all other underwater hull appendages.
1.To enable inspection of the transducers, temporarily remove the protective plywood covers.
d.Inspect for evidence of leaks, damage, and deterioration.
3. A Condition Report of the inspection findings shall be submitted to the COR, including a completed preliminary copy of NOAA DD Report; or contractor equivalent. A blank copy of NOAA DD Report will be provided by the COR.
4. Reinstall the removed items after the inspection and acceptance of the Condition Report by the COR.
3.8 Transducers
1. Keep the transducer faces covered with a plywood protective cover except when work is being performed on the transducer.
2.Do not apply props or forced pressure on the face of the transducers.
3. Clean the exposed surfaces of each transducer while the surfaces are damp. Use non-metallic, non-abrasive brushes. DO NOT use scrapers.
3.8.1 Rubber-Faced
1. Degrease the faces of rubber-faced transducers with mineral spirits and rinse with fresh water. Do not use detergents on the rubber faces.
2. Coat all rubber-faced transducers with two coats, 2.0 dry mils each, of MIL-P-22298 Formula 133 and two coats, 2.0 dry mils each, of MIL-P-22299 Formula 134 in accordance with the paint manufacturer's printed recommendations and instructions.
3.8.2 Metallic-Faced
1. Swab metallic-faced transducers with a solution of one part nitric acid to five parts fresh water, and follow with rich soapy water wash and fresh water rinse. Polish with crocus cloth.
2. Coat all metallic-faced transducers with one coat of anti-foulant same as prescribed for the underwater hull. This is to be accomplished by removing the plywood protective covers immediately prior to applying the last coat of paint to the underwater hull. If the underwater hull is not being painted, apply one coat of anti-foulant same as exists on the underwater hull. All painting shall be in accordance with the paint manufacturer's printed recommendations and instructions.
4.NOAA reserves the right to inspect and adjust transducers.
3.9 In-Accessible Void Inspections
1. Remove the void plugs in underwater appendages as identified in the vessel specific specification. As the plugs are removed, inspect for drainage of water from the voids.
a.If water is present, advise the COR before proceeding.
2. After the source of water in the voids has been determined and all additional work authorized by the Contracting Officer has been completed, fill the voids with a rust preventive compound complying with MIL-C-16173, Grade 5. Drain the rust preventive compound and reinstall the plugs using an anti-seize compound on the threads.
3.10 Undocking
1. Float the ship after all work requiring drydocking has been completed, and after obtaining consent of the COR.
a. Flood the drydock or lower the railway until as many underwater openings as possible are covered with water, but without floating the ship off the blocks.
b. Provide adequate personnel and check for leaks. If leaks are found, re-dock the ship and repair the leaks. If no leaks are found or after repair of all leaks, continue undocking the ship.
2.After undocking, record the fore and aft draft mark readings port and starboard of the ship.
Compare docking drafts to undocking drafts, submit a CFR to the COR.
3. Submit to the COR a "marked-up" copy of the docking plan to show all alterations and modifications made to the underwater hull.
PART 4 QUALITY ASSURANCE
1. After the blocks have been set and before lowering the dock for hauling the ship, conduct a final inspection of the blocking with the COR, Project Manager and the dockmaster. This requirement is not a delegable responsibility and the ship shall not be dry-docked until this joint inspection has occurred and a contractor furnished inspection document has been signed by the COR, Project Manager and Dockmaster. COR to be given 24-hour notice of when the dock will be ready for final inspection. Recheck measurements as necessary to satisfy the COR that the block locations are in accordance with the contract requirements. Acceptance of the blocking arrangement by the COR in no way relieves the Contractor of the responsibility for safely dry-docking the ship without strain or damage.
2. The contractor shall provide a 300 ft tape measure and copy of the blocking diagram used for positioning the blocks to the COR for use during the block inspection.
3. Recheck measurements as necessary to satisfy the COR that the block locations are in accordance with the docking plan and other contract requirements have been met.
4. Acceptance of the blocking arrangement by the COR in no way relieves the Contractor of the responsibility for safely drydocking the ship without strain or damage.
PART 5 NOTES
1. None.
PART 6 APPENDIX A
6.1 This Checklist is for guidance only. The Contractor is required to meet all requirements in the specification, whether or not they are captured accurately or fully in this checklist.
Drydocking Checklist
Numb Paragraph Delivery Period Action Service
1 3.1.1 Prior to Drydockin g
Submit Submit to COR, certification that drydocking facility is in good operating condition and can safely drydock the ship.
2 3.1.2 Prior to Drydocking
Submit Submit to COR, a completed copy of Reference 2.2, NOAA Drydocking Worksheet.
3 3.1.3 Prior to Drydockin g
Submit Submit to COR, a letter certifying qualifications of dock master, including a copy
4 3.1.4 Prior to Drydockin g
Submit Submit to COR, drydocking and undocking procedure, including operating practices, and
5 3.2.2 Within first Perform After getting consent from COR, haul the ship.
6 3.2.3 During haul, Perform Protect ship against damage and fire.
7 3.3.5, 3.3.6, 3.3.7
Prior to haul, after blocks have been set
Inspect Ensure all protuberances are clear of blocks.
Ensure there are no obstructions between floor surface of drydock and the hull, hull openings, appendages, and fittings. Ensure there is ample horizontal and vertical clearance for removal and replacement of
8 4.1, 4.2 Prior to haul, after blocks have been set
Inspect Conduct a joint Pre-Docking Inspection with COR to ensure block locations are in accordance to docking plan and other
9 3.4.1 Immediately prior to haul
Perform Record fore and aft draft mark readings, port and starboard of the ship.
10 3.4.3 During haul, prior to keel clearing the
Install Attach two grounding cables, bow and stern.
11 3.4.4 Immediately Perform Wash down the dock basin.
12 3.5 Immediately after
Inspect Conduct joint Drydocking Damage inspection with COR and Commanding Officer.
13 3.6.2.a Before fresh water wash of
Install Install protective plywood coverings over all transducers.
Drydocking Checklist
14 3.6.2 Within 12 hours after drydocking
Perform Clean underwater hull, boot-topping, sea strainers, sea chests, bow thrusters, rudders, anodes, propellers, shafts, struts, transducers, and other underwater hull appendages.
15 3.7.1 Within 24 Perform Remove all sea chests, strainer plates, rope
16 3.7.2 Within 48 hours after
Inspect Conduct joint Underwater Hull Inspection with COR and Commanding Officer.
17 3.7.4 After Underwater Hull Inspection
Install Reinstall all removed sea chests, strainer plates, rope guards, fairwaters, and transducer coverings.
18 3.7.3 Within 24 hours after Underwater
Submit Submit to COR, a Condition Report, including a completed preliminary copy of reference 2.1, NOAA Docking Report, Form 2410.
19 3.2.5 During drydock Provide Provide staging to enable underwater body inspection and repairs.
20 3.2.7 During drydock Install Install fittings, spigots and hoses to all hull discharge openings and scupper drains. If docked in cold or freezing weather, drain all sea valves, pipes, or similar fittings to prevent
21 3.8 During drydock Perform Protect and paint transducers.
22 3.2.6 During drydock, outside normal
Install Install temporary closures over all hull openings to prevent water entry in the event of drydock failure.
23 3.9 During drydock Perform, if Inspect voids and treat with rust preventative
24 3.10 During drydock Perform, if required
Packing Renewals and Clearance Readings and submit Condition Report to COR.
25 3.11 During drydock Perform, if Take Run-out Readings and submit Condition
26 3.12 After all work requiring drydock has
Perform After approval of COR, float the ship.
27 3.12.1.b During Float Operations, after underwater openings are covered with
Perform Check for leaks. If leaks are found, re-dock the ship and fix the leaks. If no leaks are found, then proceed with undocking the ship.
28 3.12.2 Immediately after undocking
Perform Record fore and aft draft mark readings, port and starboard of the ship.
29 3.12.3 After undocking
Submit Submit to the COR a "marked-up" copy of the docking plan that shows all alterations and modifications made to the underwater hull.
-- End of Section --
| PART 1 GENERAL |
| PART 2 DEFINITIONS |
| PART 3 REQUIREMENTS |
| PART 4 QUALITY ASSURANCE |
| PART 5 NOTES |
| PART 6 APPENDIX A |