Attachment_J_-_Financial_Reporting.pdf

PDF 16 KB Posted

Attached to
Restore-L Rendezvous Proximity Operations Subsystem Visible Wavelength Spaceflight Cameras Federal contract opportunity
Solicitation number
NNG16598572R
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

Attachment J

View the file

Other files for this federal contract opportunity

Other files attached to Restore-L Rendezvous Proximity Operations Subsystem Visible Wavelength Spaceflight Cameras, newest first.
File Type Posted
RPO_Vis_Cam_Signed_Source_Selection_Statement.pdf PDF
sf30.pdf PDF
NNG16598572R_Amended_RFP_Sections_B-M.pdf PDF
Cover_Letter_Final_RFP_-_Amended_RFP.pdf PDF
Attachment_A_-_Revised_SOW.pdf PDF
Attachment_L-2_Cost_Exhibits.pdf PDF
Amendment_2.pdf PDF
Amendment_1.pdf PDF
NNG16598572R_RPO_VisCameras_RFP.pdf PDF
Cover_Letter_Final_RFP-signed.pdf PDF
Attachment_A_-_Restore-L-SOW-001978_released.pdf PDF
Attachment_L-3_RestoreL_RPO_VisCam_-_Value_Characteristics.pdf PDF
NNG16598572R_SF33.pdf PDF
Attachment_D_-_Restore-L_Mission_Assurance_Requirements_-_Sanitized.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT J

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

RFP NN16598572R

CONTRACT TBD

NNG16582857R

Attachment J

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial Management Reporting,” dated May 27, 2011, and additional instructions issued by the Contracting Officer.

a. Level of Detail

The Contractor’s 533 Reports shall contain a summary of total contract costs, as well as a separate 533 Report for each Work Breakdown Structure (WBS) Level element of the Statement of Work. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 5 percent (+/- 5%) between the Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total Cost amount shown in the current month at the total contract level. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the Core baseline and/or each individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the tenth (10th) working day following the close of the contractors' monthly accounting period.

The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

(06/2014) 2

NNG16582857R

Attachment J

1. Prime Direct Labor Hours:

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours

Subcontractor B Direct Labor Hours

Subcontractor C Direct Labor Hours

Total Subcontractors Direct Labor Hours

3. Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Total Prime Direct Labor Costs

5. Prime Overhead Expense

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

b. Material

c. Travel

d. Other (specify)

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost

10. Fixed Fee

11. Total Cost-Plus-Fixed-Fee (CPFF)