Building_4802_Ramp_Briefing_for_Contractors.pptx
PPTX presentation 14 MB Posted
- Solicitation number
- NND16575398Q
About this file
Presentation Slides
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B4802_North_Ramp_Scaled_Drawing.pdf | ||
| Questions_and_Answers.pdf | ||
| Sign-In_Sheet.pdf | ||
| Soil_Boring_Location_Map.pdf | ||
| Past_Performance_Questionnaire_Rating_Guidelines.pdf | ||
| Soil_Boring_Logs.pdf | ||
| SOW_Rev._1.pdf | ||
| NND16575398Q_-_Combined.pdf | ||
| Past_Performance_Questionnaire.pdf | ||
| Visit_Request.pdf | ||
| SOW.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Structural Integrity Study of the Aircraft Parking Ramp at Hangar 4802 Site Visit
February 18, 2016
NASA Armstrong Flight Research Center
Presentation Outline Introduction Instructions for Site Visit Acquisition Information Request for Quote (RFQ) Due Date
Introduction
Structural Integrity Study of the Aircraft Parking Ramp at Hangar 4802 Solicitation # NND16575398Q
Contracting Officer’s Representative (COR): Robert Callahan Contract Specialist (CS): Jenny Staggs Contracting Officer (CO): Brian Bowman
Instructions of Site Visit
Remain with group This presentation, including the sign-in sheets, will be posted as part of an amendment to the solicitation (everyone must sign in) Procedures for asking and presenting questions All questions shall be submitted in writing Due date for all questions is February 24, 2016 Q&As will be posted as an amendment to the solicitation
Instructions of Site Visit Photography- no pictures can be taken during towards the flight line Safety No Personal Protective Equipment (PPE) required No smoking, except in designated smoking areas
Acquisition Information This acquisition is a Total Small Business set-aside.
Period of Performance- a total of 80 days from the date of award
RFQ Due Date
RFQ Due Date March 2, 4:00 p.m. PDT Everything said at this site visit is not binding. All official changes to the RFQ will be issued via a written amendment.
Thank You for Coming
Building 4802 Repair Ramp Timeline of Friday, Dec 4, 2015 8:58:37-8:59:08 am - fire pumps 1, 3 , and 4 turn on
| 8:59:02 am - first leak appears at hangar 4802 door |
| 9:00:15 am - 8” concrete begins to lift |
| 9:00:37 am - water begins to flow from around fire hydrant |
9:05:30 am - water begins to flow from east edge of ramp near oleanders
| 9:12:15 am - first eyes on leak !! |
| 9:13:00 am - first responders approach |
| 9:14:20 am - service truck enters the flooded area |
9:38:20 am - flow stopped
1B
1A Next Slide
Armstrong Flight Research Center 12/15/2015
First Water Video
Back to Events
First Water Video (in hangar)
Water From Oleanders Video
First Response Video
End of Upwelling Video
Next Slide
Building 4802 Repair Ramp Explanation of What Happened
Code F working theory:
Pipe failed under north side ramp at hangar 4802 Water began to saturate surrounding subgrade searching for relief point Due to pressure drop, fire pumps kicked in increasing flow Path of least resistance was to joint at hangar door/ramp Additional paths to 8” slab, asphalt under storage sheds, and east edge of ramp Several 16” slabs uplifted and cracked Large quantity of soil material washed up at various relief points at least 15-20 cu.yd.