SHIIVER_MLI_QA1.docx

DOCX document 20 KB Posted

Attached to
Large Scale Multi-Layer Insulation (MLI) Blankets for Exploration Missions Federal contract opportunity
Solicitation number
NNC16ZLT005R
Issued by
National Aeronautics and Space Administration Glenn Research Center

About this file

SHIIVER MLI Blanket Questions and Answers 1

View the file

Other files for this federal contract opportunity

Other files attached to Large Scale Multi-Layer Insulation (MLI) Blankets for Exploration Missions, newest first.
File Type Posted
SHIIVER_MLI_QA4.docx DOCX document
MLI_Amend_1_SF30.pdf PDF
MLI_RFP_Rev2.doc DOC document
SHIIVER_MLI_QA3.docx DOCX document
SHIIVER_MLI_QA2.docx DOCX document
MLI_RFP_Rev1.doc DOC document
eCryo-SCM-0086_-_SHIIVER_Tank_Dimensions.pdf PDF
eCryo-DOC-0103_-_SHIIVER_Acoustical_Test_Profile.docx DOCX document
MLI_RFP.doc DOC document
eCryo-DOC-0102_-_SHIIVER_MLI_Materials_Specification.docx DOCX document
eCryo-DOC-0105_-_GRC_Calorimeter_Dimensions.docx DOCX document
eCryo-DOC-0104_-_SHIIVER_Venting_Profile_Compete.docx DOCX document
SHIIVER_MLI_vendor_SOW.docx DOCX document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NNC16ZLT005R Multi-Layer Insulation (MLI) Blanket Questions and Answers #1

1. Could you please provide a clarification between the following two statements in the RFP as to which one takes precedent?

· Section 1: “The MLI insulation system design will include development of an attachment scheme for the MLI such that: MLI is not in physical contact with the SOFI”

· Section 3.2.3.2 “The MLI system shall not be attached to the spray on foam insulation (SOFI).”

One could conceive of a concept that allows the MLI to lay on the SOFI yet not be attached to the SOFI. Would this be allowed?

Section 3.2.3.2 takes precedent. A more clear expression of our intent in saying that the MLI should not be in physical contact with the SOFI is: the MLI must remain in its intended configuration under static or dynamic (launch environment) conditions, while not exerting tensile or shear forces on the SOFI.

2. What are represented by the dots on the tank drawing (eCryo-SCM-0086)? Assuming these are some sort of structural mounts that protrude through the MLI, are they available for attaching the MLI?

These are structural mounts for potentially attaching active thermal control piping at a future date. These will be buried beneath the SOFI, and will not be available for attaching MLI.

3. Is there a targeted mass for the “MLI System”?

There is no targeted mass. Lower mass at a given performance level is always preferable.