NKB A-wing Switchgear & D-wing PDU - Plans.pdf
PDF 4 MB Posted
- Solicitation number
- ITB-13835
- Issued by
- Leon County, Florida
About this file
The document is a 100% Construction Documents set for the Neil Kirkman Building A-Wing Switchgear Replacement & D-Wing PDU/UPS/Surge Protection Upgrades project, administered by the Florida Department of Management Services' Real Estate Development and Management division for the Department of Highway Safety and Motor Vehicles. The project, located in Tallahassee, Florida, involves comprehensive electrical infrastructure upgrades across multiple building wings, including replacing switchgear in the A-Wing, upgrading power distribution units (PDUs) in the D-Wing, replacing uninterruptible power supply (UPS) systems, and installing new surge protection devices. The project is scheduled for completion by September 5, 2025, and involves phased electrical system replacements and modifications across the building's basement and multiple floors.
The project's electrical scope includes installing a new 1600A, 480V, 3-phase switchgear with 100% rated main breaker, replacing pad-mount transformers, installing new power distribution units, upgrading UPS systems to full chassis rating, and implementing surge protection devices at various electrical equipment locations. The total estimated peak load is calculated at 1433A at 480V, with the new switchgear rated to handle 1600A. The project will require carefully coordinated power outages, primarily scheduled for weekends and non-business hours, with generators maintaining critical loads during transitions. An allowance of $4,500 for generator fuel has been included, with any unused funds to be credited back to the owner. The project also includes optional additive alternates for replacing primary electrical feeders and removing abandoned HVAC equipment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NKB A-Wing Switchgear Replacement &
4050 Esplanade Way Tallahassee, Florida 32399
State Project No. HSMV-02425040
100% Construction Documents
Real Estate Development and Management Department of Management Services administered by
2900 Apalachee Parkway Tallahassee, Florida 32399
Neil Kirkman Building Department of Highway Safety and Motor Vehicles to be constructed for:
September 5, 2025
Neil Kirkman Building, Tallahassee, FL
M
FE
P ro je ct
N
KB
A
-W in g Sw itc hg ea r R ep la ce m en t &
D -w in g
PD
U
/U
PS
/S ur ge P ro te ct io n U pg ra de s
- N ei l K irk m an
B ui ld in g
- H
SM
V-
0% C on st ru ct io n
D oc um en ts
Se pt em be r 5 , 2
JON BARBER, PE 55427 | BRIAN WALLACE, PE 75562
820 EAST PARK AVE, I-200, TALLAHASSEE, FL 32301
MFE-INC.COM | 850.681.6424
D-Wing PDU / UPS / Surge Protection Upgrades
COVER
E100 General Notes E101 Symbol Legend E102 Details E103 Details E104 Site Plan E105 Sequencing Notes E200 A-Wing Basement Demolition Plan E201 C-Wing Basement and First Floor Demolition Plans E202 D-Wing Basement Demolition Plan E300 A-Wing Basement New Work Plan E301 C-Wing Basement New Work Plan E302 C-Wing First Floor New Work Plan E303 D-Wing Basement New Work Plan E400 A-Wing Demolition One Line E401 C-Wing and D-Wing Demolition One Line E402 A-Wing Switchgear Conduit Plan and Elevation E403 A-Wing New Work One Line E404 C-Wing and D-Wing New Work One Line E500 Panel Schedules E501 Panel Schedules E502 Panel Schedules
THE INSTALLATION SHALL COMPLY WITH THE INDICATED EDITION OF THE FOLLOWING
CODES AND ORDINANCES. WHERE SPECIFIC EDITION IS NOT INDICATED, COMPLY WITH
THE LATEST PUBLISHED EDITION.
NATIONAL FIRE PROTECTION ASSOCIATION - NFPA
NFPA 70 - 2020; NATIONAL ELECTRICAL CODE
NFPA 72 - 2019; NATIONAL FIRE ALARM AND SIGNALING CODE
FLORIDA BUILDING CODE
FBC-B 2023; THE FLORIDA BUILDING CODE (8th EDITION) FPC 2023; THE FLORIDA FIRE PREVENTION CODE (8th EDITION)
INCLUDING NFPA 101 - 2021; THE LIFE SAFETY CODE
FBC-M 2023; THE FLORIDA MECHANICAL CODE (8th EDITION) FBC-A 2023; THE FLORIDA BUILDING CODE, ACCESSIBILITY (8th EDITION) FBC-EB 2023; THE FLORIDA BUILDING CODE, EXISTING BUILDING (8th EDITION)
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION
NATIONAL ELECTRICAL SAFETY CODE
SERVING UTILITY COMPANY POLICIES
STATE AND MUNICIPAL CODES AND REQUIREMENTS
AERIAL PHOTO NOT TO SCALE
VICINITY MAP NOT TO SCALE
N
N
SHEET INDEX
CODES AND REQUIREMENTS
1. FURNISH ALL LABOR, MATERIALS, EQUIPMENT AND INCIDENTALS REQUIRED TO COMPLETE ALL
ELECTRICAL WORK AS SHOWN ON THE CONTRACT DRAWINGS.
2. THIS SHALL INCLUDE THE INSTALLATION OF A COMPLETE AND PROPERLY OPERATING
ELECTRICAL SYSTEM. THIS SYSTEM REQUIRED CONSISTS BASICALLY OF, AND IS NOT LIMITED
TO, THE FOLLOWING:
· EXTEND THE DISTRIBUTION SYSTEM FOR POWER INCLUDING THE NECESSARY FEEDERS,
BRANCH CIRCUITS, INSTALLATION OF AND CONNECTION TO DEVICES, PANELBOARDS,
TRANSFORMERS, SWITCHES, AND ALL OTHER EQUIPMENT SHOWN.
· EXTEND THE BUILDING GROUND SYSTEM AND PROVIDE SPECIAL GROUNDS AS INDICATED.
· PERFORM REPLACEMENT OF A-WING SWITCHGEAR AND COMPONENTS.
· PERFORM REPLACEMENT OF A-WING PAD-MOUNT TRANSFORMER AND MAIN BUSDUCT
WITH NEW FEEDERS IN RACEWAY.
· PERFORM REPLACEMENT OF PDU's IN D-WING DATA CENTER, INCLUDING DISTRIBUTION
PANELS, FEEDERS, AND RACEWAY AS SHOWN.
· PROVIDE SURGE PROTECTION DEVICES AS SPECIFIED AND WHERE NOTED IN
CONSTRUCTION DOCUMENTS.
· PRINT AND APPLY ARC FLASH LABELS FOR EQUIPMENT NOTED. LABELS WILL BE PROVIDED
TO CONTRACTOR BY ENGINEER IN PDF FORMAT AND ARE INCLUDED IN THESE PLANS FOR
REFERENCE.
· SECURE THE SERVICES OF FLORIDA CRITICAL POWER TO COMPLETE UPGRADES TO
EXISTING UPS AS NOTED. ALL UPS WORK SHALL BE COMPLETED ON WEEKENDS TO ALLOW
SYSTEM TO BE DOWN DURING NON-OCCUPIED HOURS.
· SECURE THE SERVICES OF MECHANICAL CONTRACTOR AS PART OF ADDITIVE ALTERNATE
SCOPE TO REMOVE AND DISPOSE OF HVAC EQUIPMENT IN D-WING. REFER TO ADD
ALTERNATE NOTES.
· PROVIDE (18) 30A RATED, 208V, 3Ø VERTICAL RACK-MOUNT PDU POWER STRIPS FOR
OWNER INSTALL WITHIN EXISTING DATA RACKS. PDU's SHALL HAVE L21-30 PLUG. (GUIDE:
APC #AP8865)
· PERFORM TESTING REQUIRED ON NEW SWITCHGEAR MAIN BREAKER FOR ERMS AND GFCI
PER ONE LINE NOTES AND GENERAL NOTES. COMPLETE TESTING FORM AND SUBMIT TO
ENGINEER AT TIME OF COMPLETION.
· PERFORM THE DEMOLITION WORK INDICATED.
3. THE BIDDER SHALL INSPECT THE PRESENT JOBSITE CONDITIONS BEFORE PREPARING HIS BID.
THE SUBMISSION OF A BID WILL BE CONSIDERED EVIDENCE THAT SUCH A VISIT AND
INSPECTION WAS PERFORMED BY THE BIDDER AND THAT HE TAKES FULL RESPONSIBILITY FOR
ALL FACTORS GOVERNING HIS WORK.
4. THE ELECTRICAL WORK SHALL BE COMPLETE, FULLY OPERATIONAL, AND SUITABLE IN EVERY
WAY FOR THE SERVICE REQUIRED. DRAWINGS ARE GENERALLY DIAGRAMMATIC IN NATURE
AND DO NOT SHOW ALL DETAILS, DEVICES AND INCIDENTAL MATERIALS NECESSARY TO
ACCOMPLISH THEIR INTENT. THEREFORE, IT SHALL BE UNDERSTOOD THAT SUCH DEVICES
AND INCIDENTAL MATERIALS REQUIRED SHALL BE FURNISHED AT NO COST TO THE OWNER.
1. ALL CONDUCTORS SHALL BE INSTALLED IN METAL CONDUIT OR TUBING. CONDUIT FOR BURIAL IN SOIL OR UNDER CONCRETE SHALL BE PLASTIC. FLEXIBLE CONDUIT INSTALLED OUT-OF-DOORS, IN ANY MECHANICAL EQUIPMENT ROOM, OR IN NORMALLY WET AREAS, SHALL BE LIQUID TIGHT FLEX WITH SUITABLE FITTINGS.
2. CONDUIT SHALL BE INSTALLED TIGHT TO DECK WHERE INSTALLED ABOVE CEILING. CONDUIT SHALL BE INSTALLED TIGHT TO FLOOR WHERE INSTALLED BELOW RAISED COMPUTER ROOM FLOOR. RELOCATE
INCIDENTAL HANGERS, BRACKETS, ETC. WHERE IN CONFLICT. MAXIMIZE USE OF SPACE.
3. PROVIDE CONDUIT EXPANSION FITTINGS WITH BONDING JUMPERS FOR ALL CONDUITS PASSING THROUGH
EXPANSION JOINTS.
4. CONDUIT SHALL PASS THROUGH WALLS AT 90 DEGREES AND SHALL BE RUN PARALLEL AND PERPENDICULAR TO
WALLS.
5. BRANCH CIRCUITS AND HOMERUNS SHALL BE #12 WIRE AND 3/4" CONDUIT MINIMUM. EVERY CONDUIT SHALL
HAVE A GREEN GROUND WIRE (#12 MINIMUM).
6. ALL CONDUCTORS SHALL BE COPPER WITH THHN/THWN INSULATION. CONDUCTORS SIZE # 8 AWG AND LARGER
SHALL BE STRANDED.
7. NO MORE THAN 3 PHASE CONDUCTORS SHALL BE INSTALLED IN ONE CONDUIT UNLESS NOTED OTHERWISE.
SHARED NEUTRALS ARE NOT PERMITTED.
8. COLOR OF ALL NORMAL BRANCH RECEPTACLES, SWITCHES, ETC. TO BE WHITE. COVERPLATES SHALL BE STAINLESS STEEL, UNLESS NOTED OTHERWISE. CEILING MOUNTED RECEPTACLES SHALL BE WHITE WITH
MATCHING NYLON COVERPLATES.
9. MAINTAIN NEC MINIMUM CLEARANCE IN FRONT OF ALL SAFETY SWITCHES AND PANELBOARDS.
10. ALL ITEMS ON PLANS ARE NEW UNLESS NOTED OTHERWISE.
11. EXISTING PANELS TO REMAIN SHALL HAVE THEIR PANEL SCHEDULES UPDATED AND RETYPED AFTER
COMPLETION OF NEW WORK. NEW PANEL LOAD DESCRIPTIONS SHALL CLEARLY DEFINE LOAD TYPE AND LOCATION. PANEL SCHEDULES SHALL INCLUDE CONTRACTOR COMPANY NAME, PHONE NUMBER, AND DATE
SCHEDULE WAS MADE AND APPLIED.
12. ALL WALL PENETRATIONS SHALL BE SEALED USING AN APPROPRIATE UL ASSEMBLY TO MAINTAIN THE RATING OF
THE WALL.
13. WHERE RECEPTACLES ARE INDICATED TO BE EQUIPPED WITH GROUND FAULT INTERRUPTING CIRCUITRY, IT SHALL BE INTEGRAL TO THE DEVICE AND HAVE A TEST/RESET MECHANISM INTEGRAL WITH THE DEVICE. REMOTE TEST/RESET OR THE INTERWIRING OF ADDITIONAL RECEPTACLES UTILIZING GF SENSING OF A SINGLE
RECEPTACLE IS NOT ACCEPTABLE.
14. ALL WALL AND CEILING DEVICES SHOWN ON THE NEW WORK PLANS REQUIRE CONCEALED RACEWAYS AND RECESSED METAL BOXES UNLESS NOTED OTHERWISE. COORDINATE WITH DEMOLITION TO REUSE EXISTING BOXES IN CMU WALLS WHERE THE CONDUITS AND BOXES ARE ACCEPTABLE. WHERE NEW BOXES OR RACEWAYS ARE REQUIRED IN EXISTING HOLLOW CELL CMU WALLS, CUT-IN BOXES AND FISH APPROVED FLEXIBLE METAL CONDUIT WITHIN THE CELL TO THE FIRST JUNCTION ABOVE CEILING. CONSULT WITH ARCHITECT FOR ALL LOCATIONS WHERE SURFACE RACEWAYS AND BOXES ARE REQUIRED TO COMPLETE THE CIRCUIT AND DEVICE
ARRANGEMENTS SHOWN.
15. ALL SINGLE POLE CIRCUITS SHALL TERMINATE ON A SINGLE POLE CIRCUIT BREAKER ASSEMBLY. DO NOT USE MULTI-POLE CIRCUIT BREAKER OVERCURRENT PROVISIONS FOR 120 VOLT OR 277 VOLT CIRCUITS. PROVIDE
INDIVIDUAL GROUNDED CONDUCTORS FOR ALL SINGLE POLE CIRCUITS.
16. ALL GROUND FAULT PROTECTION DEVICES INSTALLED ON SERVICE DISCONNECTING MEANS, WHERE REQUIRED, SHALL BE PERFORMANCE TESTED WHEN FIRST INSTALLED ON SITE. TESTING SHALL BE CONDUCTED BY A QUALIFIED PERSON USING A TEST PROCESS OF PRIMARY CURRENT INJECTION AND IN ACCORDANCE WITH MANUFACTURE'S INSTRUCTIONS. TESTING REPORT SHALL BE MADE AVAILABLE TO THE AHJ AND THE OWNER.
17. ALL UNDERGROUND PVC CONDUIT RUNS SHALL HAVE RIGID STEEL ELBOWS AND RIGID STEEL SECTIONS AT GRADE PENETRATIONS WHERE SUBJECT TO POSSIBLE DAMAGE. WHERE RIGID STEEL IS USED AND IN CONTACT WITH EARTH OR CONCRETE, IT SHALL BE COMPLETELY COATED WITH AN ALKALI AND RUST-RESISTANT
BITUMASTIC PAINT, AND THREADS SHALL BE COATED WITH ZINC CHROMATE.
18. CALL SUNSHINE 811 OR GO ONLINE TO WWW.SUNSHINE811.COM, AT LEAST TWO FULL BUSINESS DAYS BEFORE
DIGGING TO HAVE UTILITIES LOCATED & MARKED.
19. WHERE CORE DRILLING OCCURS, CONTRACTOR SHALL USE CAUTION TO AVOID DAMAGING SURROUNDING SURFACES. CONTRACTOR RESPONSIBLE FOR CLEANING UP ALL SLURRY AND ENSURING A CLEAN AND PROFESSIONAL FINISH. CONTRACTOR SHALL REPLACE OR REPAIR BUILDING SURFACES OR EQUIPMENT
DAMAGED BY SLURRY OR CORE DRILLING MATERIALS.
20. WHERE INSTALLING ELECTRICAL CONDUIT, MAINTAIN CONDUIT STRAPPING AND FASTENING PER NEC.
21. WHERE INSTALLING ELECTRICAL CONDUIT, MAINTAIN PULL POINTS PER NEC AND DO NOT EXCEED 360 DEGREES
IN BENDS IN ANY CONDUIT RUN WITHOUT APPROPRIATE PULL POINTS.
22. ALL JUNCTION BOXES, PULLBOXES, AND DEVICES SHALL BE LABELED WITH CIRCUIT NUMBER AND CIRCUIT
VOLTAGE.
1. THE LOCATIONS OF ALL ELECTRICAL EQUIPMENT INDICATED (FIXTURES AND DEVICES) MAY VARY
FROM DRAWINGS. CONDITIONS AND DEMOLITION WORK WAS DETERMINED BY SITE OBSERVATION
AND REVIEW OF EXISTING DOCUMENTS WITHOUT THE BENEFIT OF DESTRUCTIVE INVESTIGATION.
VERIFY ACTUAL LOCATIONS, TYPES, CIRCUITING, AND QUANTITIES OF EQUIPMENT AND APPLY
DEMOLITION NOTES AS APPROPRIATE FOR THE EQUIPMENT AND ROOM OR AREA.
2. ALL ELECTRICAL ITEMS SHOWN ON DEMOLITION PLANS ARE TO BE REMOVED UNLESS NOTED
OTHERWISE. REMOVE ALL ELECTRICAL TRADE MATERIALS ASSOCIATED WITH ITEMS SHOWN TO BE REMOVED. THIS SHALL INCLUDE BUT NOT BE LIMITED TO CONDUIT AND RACEWAYS (BOTH SURFACE
MOUNTED AND CONCEALED ACCESSIBLE), WIRE, DEVICES AND CONDUIT SUPPORTS, BACK TO
SERVING PANEL.
3. REMOVE ALL CONDUIT STUB-UPS IN FLOOR. CUT OR GRIND CONDUITS BELOW FLOOR LEVEL AND
GROUT OPENING. GROUT FINISH SHALL BE ABSOLUTELY FLAT AND READY FOR FLOOR FINISH.
4. ALL REMOVED ELECTRICAL EQUIPMENT, INCLUDING FIXTURES, DISCONNECTS, SWITCHGEAR, TRANSFORMER, SPD's, CONDUIT, WIRE, DEVICES, AND ALL OTHER MATERIALS SHALL BE DISPOSED OF
OFFSITE BY THE CONTRACTOR AT NO ADDITIONAL COST.
5. BLANKING PLATES SHALL MATCH NEW PLATES INSTALLED.
6. WHERE EXISTING CIRCUITS ARE REWORKED BY THE ADDITION OR REMOVAL OF CONDUCTORS, THE
OLD WIRE SHALL BE REMOVED, THE CONDUIT SWABBED OUT, AND NEW THWN WIRES REPULLED
UNLESS INDICATED OTHERWISE.
7. IF ANY EXISTING ELECTRICAL EQUIPMENT THAT IS TO REMAIN BECOMES ISOLATED BY THE REMOVAL
OF WALLS, CEILINGS, ELECTRICAL EQUIPMENT, ETC., IT SHALL BE THE CONTRACTOR'S
RESPONSIBILITY TO REROUTE AND RECONNECT THE EQUIPMENT SO THAT THE SYSTEM REMAINS
OPERABLE. ANY REQUIRED WORK SHALL BE IN ACCORDANCE WITH SPECIFICATIONS.
8. MOTORS AND HVAC DEVICES SHALL BE REMOVED BY CRAFTSMEN SKILLED IN THE HVAC TRADE.
REMOVE ELECTRICAL CONNECTIONS TO SAME. COORDINATE REMOVAL OF CONTROL DEVICES AND
ASSOCIATED RACEWAY WITH MECHANICAL TRADE. ALL LINE VOLTAGE WIRING SHALL BE
DISCONNECTED AND REMOVED BY A QUALIFIED ELECTRICIAN.
9. RELOCATE EXISTING ELECTRICAL EQUIPMENT AS REQUIRED TO AVOID NEW CONSTRUCTION. ALL
WORK REQUIRED SHALL BE PERFORMED IN ACCORDANCE WITH THE SPECIFICATIONS.
10. WHILE REMOVING ALL ELECTRICAL ITEMS INSIDE THE INDICATED ALTERATION AREA, RECONNECT CIRCUITS TO MAINTAIN INTEGRITY OF EXISTING CIRCUITS AND CONTINUED OPERATION OF LIGHTING, EQUIPMENT AND DEVICES TO REMAIN.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY CUTTING OR PATCHING OF WALLS AND CEILINGS REQUIRED. CUTTING AND PATCHING WORK SHALL BE PERFORMED BY SKILLED CRAFTSMEN. RETURN
ALL WALLS AND THEIR FINISHES TO ORIGINAL CONDITION.
12. ANY ITEM ABOVE CEILINGS IN EXISTING CORRIDORS OR ROOMS WHICH NEED TO BE RELOCATED FOR
INSTALLATION OF NEW ELECTRICAL EQUIPMENT SHALL BE RELOCATED AND RECONNECTED AS
REQUIRED. THIS INCLUDES BUT IS NOT LIMITED TO CONDUIT, WIRE, PIPING, AND DUCTWORK.
RELOCATION SHALL BE MINIMUM DISTANCE POSSIBLE.
13. ABANDONED CONDUIT SHALL BE REMOVED WHERE POSSIBLE. ABANDONED CONDUIT IN SLAB OR CONCRETE WALLS WHICH CANNOT BE REMOVED SHALL HAVE WIRES PULLED FROM THEM. CUT OFF CONDUIT FLUSH WITH CONCRETE. PATCH OPENINGS AND PENETRATIONS WITH GROUT AND GRIND
OR TROWEL SMOOTH, READY FOR NEW FINISH.
14. EXISTING CONDUITS WHICH PENETRATE EXTERIOR WALLS SHALL BE REMOVED AND EXTERIOR WALL
PATCHED WITH LIKE MATERIALS.
15. ANY AND ALL HOLES OR DAMAGED SURFACES DUE TO DEMOLITION WORK SHALL BE PATCHED BY A
SKILLED CRAFTSMAN.
16. WHERE ITEMS ARE DESIGNATED EXISTING TO REMAIN, THEY SHALL BE PROTECTED DURING
DEMOLITION. RELOCATE AS REQUIRED WHERE ITEMS ARE INSTALLED IN CEILING.
17. ANY HAZARDOUS MATERIAL OR MATERIAL POSING A THREAT TO HEALTH OR THE ENVIRONMENT SHALL BE CAREFULLY DISPOSED OF IN AN APPROVED MANNER. THIS INCLUDES, BUT IS NOT LIMITED TO, FUEL OIL AND CONTAINERS, BATTERIES, BATTERY ACID, OILS, GREASE OR OTHER PETROLEUM
PRODUCTS, OR ANTIFREEZE COOLANT.
DEMOLITION NOTES - GENERAL GENERAL NOTES DESCRIPTION OF WORK
THE PEAK RECORDED METER DATA FOR THE PERIOD BETWEEN 12/10/24 AND 1/14/25 IS EQUAL TO THE
FOLLOWING:
AØ = 626A
BØ = 954A
CØ = 542A
USING THE HIGHEST RECORDED VALUE AND ADDING THE FOUR 25HP HYDRAULIC A-WING ELEVATORS (DUE TO THE ASSUMPTION THAT THE 15-MINUTE RECORDING INTERVAL DID NOT PICK-UP THE ELEVATORS
RUNNING), THE PEAK LOAD ON THE SWITCHGEAR IS AS FOLLOWS:
954A + (4 * 48A) = 1146A, 480V, 3Ø
APPLYING THE NEC 125% FACTOR, THE TOTAL LOAD TO BE USED FOR SIZING NEW SERVICE IS EQUAL TO 1433A, 480V, 3Ø.
THE SWITCHGEAR RATING SHALL BE 1600A, 480V, 3Ø WITH 100% RATED MAIN.
THE PAD-MOUNT TRANSFORMER RATING SHALL BE 1500KVA, 480V, 3Ø WITH FLA = 1807A.
THE SERVICE FEEDER SHALL BE RATED FOR 1600A AND CONSIST OF (5) RUNS OF 4#400KCMIL IN 4" CONDUIT.
1. THE CONTRACTOR IS EXPECTED TO PLAN OUT THE EXECUTION OF THE WORK SO AS TO
MINIMIZE INTERFERENCE TO THE OWNER'S OPERATIONS. PHASING AND PREPARATION FOR
THE WORK SHALL TAKE PLACE SO AS TO ACHIEVE THIS REQUIREMENT.
2. ELECTRICAL POWER OUTAGES ARE A REQUIREMENT OF THIS PROJECT AND SHALL BE
THOROUGHLY PLANNED AND COORDINATED WITH HSMV. THERE IS EXPECTED TO BE
OUTAGES TO A-WING, B-WING, C-WING, AND D-WING DURING THE PROJECT, BUT NOT ALL AT
ONCE. NOTE THAT IN ORDER TO REMOVE POWER TO A-WING, B-WING MUST ALSO BE
DE-ENERGIZED.
3. PROVIDE COMPLETE PROPOSED CONSTRUCTION SCHEDULE TO ENGINEER AND HSMV FOR
REVIEW AND APPROVAL PRIOR TO BEGINNING CONSTRUCTION.
4. ELECTRICAL OUTAGES WILL BE LIMITED TO AFTER HOURS ON WEEKENDS OR STATE
HOLIDAYS WHILE BUILDING IS CLOSED. OUTAGES DURING NORMAL BUSINESS HOURS WILL
NOT BE PERMITTED. ALL OUTAGES MAY BEGIN ON FRIDAY EVENINGS AT 6:00PM AND MUST
BE COMPLETED BY 6:00PM ON THE EVENING PRIOR TO BUILDING TENANTS RETURNING FOR
WORK TO ALLOW TIME FOR PROPER START-UP BY FACILITIES STAFF. THE CONTRACTOR
SHALL PLAN AND STAFF THE PROJECT ACCORDINGLY.
5. SCHEDULE A MEETING WITH THE ENGINEER AND THE OWNER'S PROJECT MANAGER WITHIN
TWO WEEKS AFTER ACTIVATION TO DISCUSS CONTRACTOR'S STRATEGY FOR OUTAGES AND
ACCOMPLISHING THE WORK.
6. COORDINATE ALL POWER OUTAGES WITH HSMV PRIOR TO OUTAGE. PROVIDE 14 DAY
MINIMUM NOTICE TO HSMV PROJECT MANAGER AS TO WHEN PROPOSED POWER OUTAGES
WILL OCCUR TO RECEIVE APPROVAL. ALL POWER OUTAGES AND CHANGEOVERS SHALL BE
SCHEDULED WITH THE HSMV PROJECT MANAGER AND SCHEDULES STRICTLY ADHERED TO.
OUTAGES THAT ARE NOT SCHEDULED WILL NOT BE ALLOWED.
7. CONTRACTOR SHALL BE RESPONSIBLE FOR TEMPORARY LOW VOLTAGE CONSTRUCTION
POWER AND LIGHTING DURING OUTAGES.
8. THE CONTRACTOR SHALL PROVIDE A TRAINED AND KNOWLEDGEABLE STAFF MEMBER
REPRESENTATIVE TO CONSULT WITH THE OWNER PRIOR TO ANY SWITCHING, AND TO
PERFORM SWITCHING, TEST CIRCUITS, AND DEEM GROUNDED AND SAFE PRIOR TO WORK.
NO HOT WORK WILL BE ALLOWED. ALL SWITCHING OF ELECTRICAL EQUIPMENT IS BY
CONTRACTOR.
9. COORDINATION WITH HSMV PROJECT MANAGER MUST OCCUR FOR ENERGIZING AND
DE-ENERGIZING FEEDERS. HSMV PROJECT MANAGER WILL LEAD COORDINATION EFFORTS
WITH ISA, IDEMEA, AND OTHER BUILDING TENANTS.
10. DURING NORMAL POWER OUTAGES, STAND-BY GENERATOR(S) WILL RUN TO MAINTAIN
STAND-BY POWER FOR THE OWNER'S CRITICAL LOADS.
11. CONTRACTOR SHALL MAINTAIN FUEL DURING ALL OUTAGES TO KEEP GENERATORS
RUNNING FOR DURATION OF OUTAGES.
12. CONTRACTOR SHALL PROVIDE GENERATOR FUEL FOLLOWING THE OUTAGE TO TOP OFF
THE FUEL TANK FOR THE BUILDING GENERATORS.
13. CONTRACTOR SHALL INCLUDE IN THE BID AN ALLOWANCE OF $4,500 FOR FUEL CHARGES
FOR THE GENERATORS AND SHALL COORDINATE TOP OFF OF FUEL STORAGE TANKS NOTED
ABOVE WITH #2 FUEL OIL AT COMPLETION OF EACH OUTAGE TO REPLENISH FUEL USED
DURING OUTAGE. THE ALLOWANCE AMOUNT REMAINING AT THE COMPLETION OF THE
CONTRACT SHALL BE CREDITED BACK TO THE OWNER.
SCHEDULED OUTAGE NOTES
ADDITIVE ALTERNATE NOTES
ADDITIVE ALTERNATE #1
ADDITIVE ALTERNATE #1 SHALL INCLUDE THE PROVISION AND INSTALLATION OF A NEW 15KV PRIMARY FEEDER FROM EXISTING SWITCH 'SW-1' TO NEW PAD-MOUNT TRANSFORMER 'T-A2'. NEW FEEDER SHALL BE INSTALLED IN EXISTING 3" SPARE CONDUIT. CONDUIT SHALL BE SWABBED AND CLEANED PRIOR TO PULLING IN NEW FEEDER. FEEDER SHALL BE 3-1/C #2 CU EPR (15KV) WITH 1-1/C #4 CU (600). PROVIDE GROUND BUSHING ON EXISTING SPARE CONDUIT EACH END AND BOND GROUND CONDUCTOR TO BOTH SWITCH AND TRANSFORMER. SCOPE SHALL ALSO INCLUDE ALL TERMINATIONS AT BOTH SWITCH AND TRANSFORMER, DISCONNECTING AND REMOVAL OF EXISTING FEEDER WITH CONDUIT REMAINING AS NEW 'SPARE', NEW CABLE TAGS PER DETAIL, AND TESTING OF NEW CABLE PRIOR TO ENERGIZING.
TERMINATIONS AT SWITCH SHALL BE 15KV COMPRESSION 2-HOLE LUGS. TERMINATIONS AT TRANSFORMER SHALL BE 15KV, 200A LOADBREAK ELBOWS. COMPLETE INITIAL TESTING OF NEW 15KV CABLE INSTALLED.
CABLE TESTING SHALL BE VERY LOW FREQUENCY (VLF) AND BE IN ACCORDANCE WITH NETA
MAINTENANCE TESTING STANDARDS AND CABLE MANUFACTURER RECOMMENDATIONS. UNLESS
MANUFACTURER DATA STATES OTHERWISE, VLF TESTING SHALL BE AT 16KV RMS, 0.1Hz, FOR 1 HOUR.
RECORD ALL TEST DATA AND SUBMIT TESTING REPORT TO OWNER.
BASE BID SCOPE IS TO REUSE EXISTING 15KV FEEDER CURRENTLY IN PLACE AND LAND EXISTING FEEDER 200A LOADBREAK ELBOWS TO NEW PAD-MOUNT TRANSFORMER PRIMARY BUSHINGS WHEN PAD-MOUNT IS REPLACED. NEW TRANSFORMER SHALL BE CAPABLE OF LANDING EXISTING CABLES ON NEW BUSHINGS, MATCHING BUSHING HEIGHT OF EXISTING TRANSFORMER. EXISTING BUSHING HEIGHT IS 26" ABOVE
CONCRETE PAD.
ADDITIVE ALTERNATE #2
ADDITIVE ALTERNATE #2 SHALL INCLUDE THE DEMOLITION SCOPE TO REMOVE THE ABANDONED DATA CENTER HVAC EQUIPMENT, INCLUDING BUT NOT LIMITED TO, AC INDOOR AND OUTDOOR EQUIPMENT, REFRIGERANT LINES, AND ALL SUPPORTS, MOUNTING HARDWARE, AND PIPE STRAPS. REFRIGERANT SHALL BE DISPOSED OF PROPERLY. ALTERNATE #2 ALSO INCLUDES STEEL PLATES TO COVER FLOOR OPENINGS AS NOTED ON NEW WORK PLAN, AND SEALING WALLS WHERE PIPING AND CONDUIT ARE
REMOVED.
BASE BID SCOPE SHALL INCLUDE REMOVING FEEDERS AND ACCESSIBLE RACEWAY SERVING DATA CENTER HVAC EQUIPMENT BACK TO SERVING PANELS. BREAKERS SPACES IN EXISTING PANELS ARE TO BE
USED FOR NEW AC LOADS. REFER TO PANEL SCHEDULES.
PROVIDE NEW SURGE PROTECTION DEVICES FOR THE EXISTING EQUIPMENT AT THE FOLLOWING
LOCATIONS WITHIN THE KIRKMAN BUILDING AS PART OF THIS PROJECT SCOPE.
SERVICE ENTRANCE EQUIPMENT LOCATIONS:
• A-WING CHILLER SWITCHBOARD - REPLACE EXISTING WITH NEW
• B-WING BASEMENT NORTH MAIN PANELBOARD 'MPB' - PROVIDE NEW
• C-WING MAIN SWITCHGEAR (A) - REPLACE EXISTING WITH NEW
• C-WING MAIN SWITCHGEAR (B) - REPLACE EXISTING WITH NEW
ELEVATOR LOCATIONS:
• ELEVATOR 6 (LOCATED IN C-WING) - PROVIDE SPD AT NEW ELEVATOR FUSED DISCONNECT SWITCH
• ELEVATORS 7, 8, 9, AND 10 (LOCATED IN A-WING) - PROVIDE SPD AT ELEVATOR ENCLOSED CIRCUIT
BREAKERS
NETWORK:
• TWO-WAY RADIO ANTENNA CABLE IN 4TH FLOOR B-CENTRAL STAIR LANDING
SPD SCOPE OF WORK NOTES
SWITCHGEAR / SERVICE SIZING DESIGN NOTES
SHEET:
September 5, 2025
REVISED:
DATE:
SHEET TITLE:
JOB NUMBER:
DRAWN BY:DESIGNED BY:
100% Construction Documents
SUBMITTAL:
JON BARBER, PE 55427 | BRIAN WALLACE, PE 75562
820 EAST PARK AVE, I-200, TALLAHASSEE, FL 32301
MFE-INC.COM | 850.681.6424
HSMV-02425040
NKB A-Wing Switchgear Replacement & D-Wing PDU / UPS / Surge Protection Upgrades
Neil Kirkman Building Tallahassee, Florida
BW AC
GENERAL NOTES
E100
CIRCUITING AND BRANCH CIRCUITS
ABBREVIATIONS
POWER, PANELS, SWGR, & EQUIPMENT
J
T
L2A-2,4,6
10's
L2A-2,4
LPA-2,4
WALL OUTLETS
JUNCTION BOXES AND OUTLETS
SPD
A AMPERE
AC ABOVE CEILING, ABOVE COUNTERTOP, ALTERNATING CURRENT
AIC EQUIPMENT AMPERE INTERRUPTING CAPACITY
AFC AVAILABLE FAULT CURRENT
AFF MOUNTING HEIGHT ABOVE FINISHED FLOOR OR GRADE TO CENTERLINE
ATS AUTOMATIC TRANSFER SWITCH
EM EMERGENCY
ER EXISTING DEVICE SHOWN IN RELOCATED POSITION
EX EXISTING - RECONNECT AS REQUIRED AT EXISTING LOCATION. REMOVE
AND REINSTALL IF REQUIRED
ETR EXISTING TO REMAIN
FA FIRE ALARM
GFCI GROUND FAULT CIRCUIT INTERRUPTER
HP HORSE POWER
J JUNCTION
MCC MOTOR CONTROL CENTER
RELO DEVICE TO BE RELOCATED
T TRANSFORMER, THERMOSTAT
V VOLT
VA VOLT-AMPS
W WATT
WP WEATHERPROOF (NEMA 3R)
PANELBOARD 208/240 VOLT - SURFACE MOUNTED - SEE PANELBOARD SCHEDULE
POWER DISTRIBUTION PANEL OR 480 VOLT - SEE PANELBOARD SCHEDULE
MOLDED CASE CIRCUIT BREAKER
STEP DOWN, DRY-TYPE TRANSFORMER
PANELBOARD OR ENCLOSED CIRCUIT BREAKER - RECESSED MOUNTED
ARROW INDICATES CIRCUIT HOMERUNS IN CONDUIT
INDICATES HOMERUN TO CIRCUIT NUMBERS 2 & 4 IN PANEL "LPA"
NOTE:
NUMBER OF HOMERUNS SHOWN ON THE PLANS ARE THE NUMBER OF
HOMERUNS REQUIRED. DO NOT RUN MORE THAN THREE HOMERUNS IN
ONE CONDUIT. DO NOT RUN 2 CIRCUITS ON THE SAME PHASE IN ONE
CONDUIT.
INDICATES CONTINUATION OF RUN SHOWN ON ANOTHER PLAN VIEW
INDICATES 1 #12 PHASE CONDUCTOR, 1 #12 NEUTRAL & 1 #12 GND - 3/4" C. TO 1-POLE
BREAKER, SIZED AS SHOWN IN PANEL SCHEDULES, ON CIRCUIT No. 3, IN PANEL 'L2A'.
INDICATES 2 #12 PHASE CONDUCTORS & 1 #12 GND - 3/4" C. TO 2-POLE
BREAKER, SIZED AS SHOWN IN PANEL SCHEDULES, ON CIRCUIT No.'s 2 & 4 IN
PANEL 'L2A'.
INDICATES ALL CONDUCTORS ARE TO BE MINIMUM #10 GAUGE, CONDUIT PER NEC
OR AS INDICATED.
INDICATES 3 #12 PHASE CONDUCTORS & 1 #12 GND - 3/4" C, TO 3-POLE
BREAKER, SIZED AS SHOWN IN PANEL SCHEDULES, ON CIRCUIT No.'S 2,4,6
IN PANEL 'L2A'.
NEUTRALS SHALL NOT BE SMALLER SIZE THAN PHASE CONDUCTORS UNLESS
SPECIFICALLY INDICATED OTHERWISE. PROVIDE THE APPROPRIATE NUMBER
OF NEUTRALS IN ACCORDANCE WITH NEC.
INSULATED GROUNDING CONDUCTORS SHALL BE USED IN ALL CIRCUITS, SIZED
IN ACCORDANCE WITH NEC ARTICLE 250.
2-#12, 1-#12 GROUND SHALL BE RUN IN 3/4" CONDUIT. 4 OR MORE #12
CONDUCTORS SHALL BE RUN IN 3/4" C. OR AS REQUIRED BY NEC. LARGER
THAN #12 CONDUCTORS SHALL BE RUN IN CONDUIT SIZED IN ACCORDANCE
WITH NEC.
CONCEALED OVERHEAD OR IN WALLS.
CONCEALED IN OR BELOW FLOORS OR GRADE.
FLEXIBLE CONDUIT TO EQUIPMENT
TRANSIENT VOLTAGE AND SURGE PROTECTION DEVICE
JUNCTION BOX IN OR ABOVE CEILING
JUNCTION BOX IN WALL - MOUNT 1'-6" UNLESS NOTED OTHERWISE.
L2A-3
PANELBOARD - EMERGENCY POWER SYSTEM - SEE PANELBOARD SCHEDULE
J
J
GROUNDING
3/4" X 10'-0" GROUND ROD.
SHORTER TICKMARKS INDICATE 2 OR MORE PHASE CONDUCTORS, OR SWITCH LEGS
LONGER TICKMARKS INDICATE GROUNDED CONDUCTOR(S), QUANTITY AS SHOWN.
SYMBOL LEGEND
CONTROLS & MECHANICAL EQUIPMENT
5-30
GFCI
WP
EX
NEW RECEPTACLE AND COVERPLATE TO REPLACE EXISTING DEVICE: REFEED IF
REQUIRED DUE TO DEMOLITION WORK
DISCONNECT SWITCH, FUSIBLE, SIZE AND NEMA TYPE AS NOTED, FUSE AS
NOTED OR PER MANUFACTURER'S RECOMMENDATION FOR EQUIPMENT
SERVED. NON-FUSED SWITCH MAY BE USED IF UNIT IS UL TESTED WITH
BREAKER PROTECTION
DISCONNECT SWITCH, NON-FUSIBLE, SIZE AND NEMA TYPE AS NOTED.
DUPLEX RECEPTACLE, 20A, 125V, 2 POLE, 3 WIRE, MOUNT 1'-6" AFF, NEMA 5-20R.
DOUBLE DUPLEX RECEPTACLE, 20A, 125V, 2 POLE, 3 WIRE,MOUNT 1'-6"AFF, NEMA 5-20R.
SINGLE RECEPTACLE, 20A, 125V, 2 POLE, 3 WIRE, MOUNT 1'-6" AFF, NEMA 5-20R.
DUPLEX RECEPTACLE, 20A, 125V, 2 POLE, 3 WIRE, MOUNT BOTTOM OF RECEPTACLE
ABOVE COUNTER 3'-8" AFF, NEMA 5-20R.
DUPLEX RECEPTACLE, 20A, 125V, 2 POLE, 3 WIRE, WITH WEATHERPROOF-IN-USE COVER
DUPLEX RECEPTACLE, 20A, 125V, 2 POLE, 3 WIRE, WITH GROUND FAULT INTERRUPTER.
MOUNT 1'-6" AFF
SPECIAL RECEPTACLE - NEMA CONFIGURATION AS SHOWN ON FLOOR
PLANS OR IN EQUIPMENT SCHEDULE - SHOWN NEMA 5-30R.
DUPLEX RECEPTACLE, 20A, 125V, 2 POLE, 3 WIRE MOUNTED BELOW RAISED
COMPUTER FLOOR
N3R 30A
N3R 30A
J
POWER SYSTEMS FURNITURE CONNECTION WITH WHIP
CIRCUIT BREAKER
FUSE
PM POWERLOGIC METER
ERMS ENERGY REDUCING MAINTENANCE SWITCH WITH LOCAL STATUS INDICATOR
CIRCUIT INTERRUPTING SWITCH
EMERGENCY POWER OFF (EPO)
SPECIAL RECEPTACLE - NEMA CONFIGURATION AS SHOWN ON FLOOR PLANS, MOUNTED
BELOW RAISED COMPUTER FLOOR
DOUBLE DUPLEX RECEPTACLE, 20A, 125V, 2 POLE, 3 WIRE, MOUNTED BELOW RAISED
COMPUTER FLOOR
SINGLE RECEPTACLE, 20A, 125V, 2 POLE, 3 WIRE, MOUNTED BELOW RAISED COMPUTER
FLOOR
SHEET:
September 5, 2025
REVISED:
DATE:
SHEET TITLE:
JOB NUMBER:
DRAWN BY:DESIGNED BY:
100% Construction Documents
SUBMITTAL:
JON BARBER, PE 55427 | BRIAN WALLACE, PE 75562
820 EAST PARK AVE, I-200, TALLAHASSEE, FL 32301
MFE-INC.COM | 850.681.6424
HSMV-02425040
NKB A-Wing Switchgear Replacement & D-Wing PDU / UPS / Surge Protection Upgrades
Neil Kirkman Building Tallahassee, Florida
BW AC
SYMBOL LEGEND
E101
RECEPTACLE WIRING DIAGRAM NOT TO SCALE
TERMINATE GROUND
GROUND SCREW
CONDUCTORS UNDER
GREEN
GROUND PIG TAIL
CONDUCTOR
EQUIPMENT GROUND
23,25HF-21
EACH JUNCTION BOX COVER SHALL BE LABELED WITH A
PERMANENT "MAGIC" MARKER OR OTHER PERMANENT MEANS TO
IDENTIFY THE CIRCUITS OR SYSTEMS CABLES WITHIN. INCLUDE
THE PANEL AND CIRCUIT BREAKER NUMBER FOR ALL POWER
CIRCUITS WITHIN. FOR EXAMPLE, A JUNCTION BOX CONTAINING
LIGHTING CIRCUITS 21, 23, 25 FROM PANEL "HF" WOULD BE
LABELED "HF-21,23,25" AS SHOWN.
JUNCTION BOX IDENTIFICATION NOT TO SCALE
SURGE
PROTECTION
DEVICE
GROUND BUS
NEUTRAL BUS
NOTES:
1. THE SPD SHALL BE LOCATED
IMMEDIATELY ADJACENT TO THE
SWITCHBOARD, PANELBOARD, OR
DISCONNECT SWITCH BEING PROTECTED
(CLOSE-NIPPLE TO PANELBOARDS).
2. CONDUCTORS SHALL NOT BE MORE THAN
12” IN LENGTH. ALL CONDUCTORS SHALL
BE CUT TO PRECISELY THE SAME LENGTH
BEFORE INSTALLATION. CONDUCTORS
SHALL AVOID UNNECESSARY BENDS.
3. THE INSTALLER MAY REARRANGE
BREAKER LOCATIONS TO ENSURE THE
SHORTEST AND STRAIGHTEST LEADS TO
THE SPD. BREAKER AND SPD SHALL BE
INSTALLED CLOSE TO NEUTRAL BUS.
4. THE LAYOUT IN THIS DETAIL WILL NOT
MATCH ALL INSTALLATIONS, BUT IS
INTENDED TO SHOW PROPER PLACEMENT
AND INSTALLATION OF SPD AND
CORRESPONDING BREAKER. COORDINATE
WITH EQUIPMENT PROVIDED.
SYSTEM NO. C-AJ-1014
(FORMERLY SYSTEM NO. 133)
F RATING - 2 HOUR
T RATING - 0 HOUR
L RATING AT AMBIENT - LESS THAN 1 CFM/SQ FT (SEE ITEM 4)
L RATING AT 400°F - LESS THAN 1 CFM/SQ FT (SEE ITEM 4)
1. FLOOR OR WALL ASSEMBLY - MIN 3-1/4" THICK REINFORCED
LIGHTWEIGHT OR NORMAL WEIGHT (100-150 PCF) CONCRETE. WALL
MAY ALSO BE CONSTRUCTED OF ANY UL CLASSIFIED CONCRETE
BLOCKS*. MAX DIAMETER OF CIRCULAR OPENING IS 6".
SEE CONCRETE BLOCK (CAZT) CATEGORY IN THE FIRE RESISTANCE
DIRECTORY FOR NAMES OF MANUFACTURERS.
2. THROUGH PENETRANTS - ONE METALLIC PIPE OR CONDUIT TO BE
CENTERED WITHIN THE FIRESTOP SYSTEM. A NOMINAL ANNULAR
SPACE OF 3/4" IS REQUIRED WITHIN THE FIRESTOP SYSTEM. PIPE OR
CONDUIT TO BE RIGIDLY SUPPORTED ON BOTH SIDES OF FLOOR OR
WALL ASSEMBLY. THE FOLLOWING TYPES AND SIZES OF METALLIC
PIPES OR CONDUITS MAY BE USED:
2.1. STEEL PIPE - NOMINAL 4" DIAMETER (OR SMALLER) SCHEDULE 10
(OR HEAVIER) STEEL PIPE.
2.2. CONDUIT - NOMINAL 4" DIAMETER (OR SMALLER) STEEL
ELECTRICAL METALLIC TUBING OR STEEL CONDUIT.
3. PACKING MATERIAL - MINIMUM 4 PCF MINERAL WOOL BATT
INSULATION FIRMLY PACKED INTO OPENING AS A PERMANENT FORM.
PACKING MATERIAL TO BE RECESSED FROM TOP SURFACE OF FLOOR
OR FROM BOTH SURFACES OF WALL AS REQUIRED TO ACCOMMODATE
THE REQUIRED THICKNESS OF FILL MATERIAL. MINIMUM THICKNESS
OF PACKING MATERIAL IN FLOORS AND WALLS TO BE 2-3/4" AND 2-1/4",
RESPECTIVELY.
4. FILL, VOID OR CAVITY MATERIAL* - SEALANT - MINIMUM 1/2" THICKNESS
OF FILL MATERIAL APPLIED WITHIN ANNULUS, FLUSH WITH TOP
SURFACE OF FLOOR OR WITH BOTH SURFACES OF WALL. AS AN
ALTERNATE, THE PERMANENT FORMING MATERIAL (ITEM 3) MAY BE
OMITTED IF THE FILL MATERIAL THICKNESS IS INCREASED TO A
MINIMUM OF 1-1/2".
MINNESOTA MINING AND MFG CO - (TYPES FB-2000 OR
FB-2000+). (NOTE: L RATINGS APPLY ONLY WHEN FB-2000+
IS USED.)
*BEARING THE UL CLASSIFICATION MARKING.
SECTION A - A
A
A
2 3
1 4 2
PENETRATION DETAIL - A
SYSTEM NO. W-L-1001
(FORMERLY SYSTEM NO. 147)
F RATINGS - 1, 2, 3 AND 4 HOUR (SEE ITEMS 2 & 3)
T RATING - 0, 1, 2, 3 AND 4 HOUR (SEE ITEM 3)
L RATING AT AMBIENT - LESS THAN 1 CFM/SQ FT
L RATING AT 400°F - LESS THAN 1 CFM/SQ FT
1. WALL ASSEMBLY - THE 1, 2, 3 OR 4 HOUR FIRE-RATED GYPSUM WALLBOARD /
STUD WALL ASSEMBLY SHALL BE CONSTRUCTED OF THE MATERIALS AND IN THE
MANNER DESCRIBED IN THE INDIVIDUAL U300 OR U400 SERIES WALL OR
PARTITION DESIGNS IN THE UL FIRE RESISTANCE DIRECTORY AND SHALL
INCLUDE THE FOLLOWING CONSTRUCTION FEATURES:
1.1. STUDS - WALL FRAMING MAY CONSIST OF EITHER WOOD STUDS (MAXIMUM 2
HOUR FIRE RATED ASSEMBLIES) OR STEEL CHANNEL STUDS. WOOD STUDS
TO CONSIST OF NOMINAL 2"x4" LUMBER SPACED 16" O.C. WITH NOMINAL 2"x4"
LUMBER END PLATES AND CROSS BRACES. STEEL STUDS TO BE MINIMUM
3-5/8" WIDE BY 1-3/8" DEEP CHANNELS SPACED MAXIMUM OF 24" O.C.
1.2. WALLBOARD, GYPSUM - NOMINAL 1/2" OR 5/8" THICK, 4' WIDE WITH SQUARE
OR TAPERED EDGES. THE GYPSUM WALLBOARD TYPE, THICKNESS, NUMBER
OF LAYERS, FASTENER TYPE AND SHEET ORIENTATION SHALL BE AS
SPECIFIED IN THE INDIVIDUAL U300 OR U400 SERIES DESIGN IN THE UL FIRE
RESISTANCE DIRECTORY. MAXIMUM DIAMETER OF OPENING IS 13-1/2".
2. PIPE OR CONDUIT - NOMINAL 12" DIAMETER (OR SMALLER) SCHEDULE 10 (OR
HEAVIER) STEEL PIPE, NOMINAL 12" DIAMETER (OR SMALLER) SERVICE WEIGHT
(OR HEAVIER) CAST IRON SOIL PIPE, NOMINAL 12" DIAMETER (OR SMALLER)
CLASS 50 (OR HEAVIER) DUCTILE IRON PRESSURE PIPE, NOMINAL 6" DIAMETER
(OR SMALLER) STEEL CONDUIT, NOMINAL 4" DIAMETER (OR SMALLER) STEEL
ELECTRICAL METALLIC TUBING, NOMINAL 6" DIAMETER (OR SMALLER) TYPE L (OR
HEAVIER) COPPER TUBING OR NOMINAL 1" DIAMETER (OR SMALLER) FLEXIBLE
STEEL CONDUIT. WHEN COPPER PIPE IS USED, MAXIMUM F RATING OF FIRESTOP
SYSTEM (ITEM 3) IS 2 HOUR. STEEL PIPES OR CONDUITS LARGER THAN NOMINAL
4" DIAMETER MAY ONLY BE USED IN WALLS CONSTRUCTED USING STEEL
CHANNEL STUDS. A MAXIMUM OF ONE PIPE OR CONDUIT IS PERMITTED IN THE
FIRESTOP SYSTEM. PIPE OR CONDUIT TO BE INSTALLED NEAR CENTER OF STUD
CAVITY WIDTH AND TO BE RIGIDLY SUPPORTED ON BOTH SIDES OF WALL
ASSEMBLY.
3. FILL, VOID OR CAVITY MATERIAL - CAULK - CAULK FILL MATERIAL INSTALLED TO
COMPLETELY FILL ANNULAR SPACE BETWEEN PIPE OR CONDUIT AND GYPSUM
WALLBOARD AND WITH A MINIMUM 1/4" DIAMETER BEAD OF CAULK APPLIED TO
PERIMETER OF PIPE OR CONDUIT AT ITS EGRESS FROM THE WALL. CAULK
INSTALLED SYMMETRICALLY ON BOTH SIDES OF WALL ASSEMBLY. THE HOURLY F
RATING OF THE FIRESTOP SYSTEM IS DEPENDENT UPON THE HOURLY FIRE
RATING OF THE WALL ASSEMBLY IN WHICH IT IS INSTALLED, AS SHOWN IN THE
FOLLOWING TABLE. THE HOURLY T RATING OF THE FIRESTOP SYSTEM IS
DEPENDENT UPON THE TYPE OR SIZE OF THE PIPE OR CONDUIT AND THE
HOURLY FIRE RATING OF THE WALL ASSEMBLY IN WHICH IT IS INSTALLED, AS
TABULATED BELOW:
MAXIMUM ANNULAR F RATING T RATING
PIPE DIAMETER SPACE (HOURS) (HOURS)
4 0 - 1-1/2 1 OR 2 0
A
A
SECTION A - A
3 3
1.1
1.2
NOT TO SCALE
(INCHES) (INCHES)
PENETRATION DETAIL - B NOT TO SCALE
SURGE PROTECTION DEVICE PANEL DETAIL NOT TO SCALE
TEST WELL GROUND ROD INSTALLATION NOT TO SCALE
GRADE
2" MIN.
EXOTHERMIC
WELDED/CONNECTION
6" COVER WASHED
ROCK
DRIVEN GROUND ROD
GROUND CONDUCTOR
GROUND ROD TEST WELL W/
LID LABELED AS "GROUND"
1'-0" 1'-6"
2'-0"
3'-0" 4'-0"
BUILDING SIDEWALK YARD DRIVEWAY AND PARKING LOT
1" MIN
DETECTABLE WARNING TAPE
AT LEAST 12" ABOVE CONDUIT
PER NEC 300.5
SECONDARY CONDUITS PER
UTILITY REQUIREMENTS
PRIMARY CONDUITS PER
UTILITY REQUIREMENTS
UNDERGROUND CONDUIT BURIAL DEPTHS NOT TO SCALE
WIRING SCHEDULE FOR
VOLTAGE DROP
NOTE: FOR CIRCUITS WITH #6
CONDUCTORS, REDUCE TO #8
CONDUCTORS AT PANEL FOR
FINAL CONNECTIONS TO CIRCUIT
BREAKER.
DISTANCE
120V - 20A BRANCH CIRCUIT
277V - 20A BRANCH CIRCUIT
CONDUCTOR SIZE
UP TO 100' #12
100' - 150'
150' - 250'
250' - OVER
UP TO 200'
200' - 375'
375' - OVER
#10
#8
#6
#12
#10
#8
NEW FEEDER CIRCUIT IN NEW PAD-MOUNT
TRANSFORMER AND IN SWITCH 'SW-1'
(IF FEEDER IS REPLACED AS PART OF ADD ALTERNATE #1)
KV #2AØ
MEDIUM VOLTAGE CABLE TAGS NOT TO SCALE
SHEET:
September 5, 2025
REVISED:
DATE:
SHEET TITLE:
JOB NUMBER:
DRAWN BY:DESIGNED BY:
100% Construction Documents
SUBMITTAL:
JON BARBER, PE 55427 | BRIAN WALLACE, PE 75562
820 EAST PARK AVE, I-200, TALLAHASSEE, FL 32301
MFE-INC.COM | 850.681.6424
HSMV-02425040
NKB A-Wing Switchgear Replacement & D-Wing PDU / UPS / Surge Protection Upgrades
Neil Kirkman Building Tallahassee, Florida
BW AC
DETAILS
E102
NFPA 70 ART. 210.5. WHERE THE PREMISES WIRING SYSTEM HAS
BRANCH CIRCUITS SUPPLIED FROM MORE THAN ONE NOMINAL
VOLTAGE SYSTEM, EACH UNGROUNDED CONDUCTOR OR
BRANCH CIRCUIT SHALL BE IDENTIFIED BY PHASE OR LINE AND
SYSTEM AT ALL TERMINATIONS, CONNECTIONS AND SPLICE
POINTS IN COMPLIANCE WITH 210.5(C)(1)(a) AND (b).
IDENTIFICATION SHALL BE PLACED AT EACH PANELBOARD OR
SWITCHBOARD AND SHALL BE PERMANENT AND CLEARLY
IDENTIFIABLE. IDENTIFY CONDUCTORS AS FOLLOWS.
208/120 VOLTS 480/277 VOLTS
PHASE A - BLACK PHASE A - BROWN
PHASE B - RED PHASE B - ORANGE
PHASE C - BLUE PHASE C - YELLOW
NEUTRAL - WHITE NEUTRAL - GRAY
WARNING
480 VOLTS
WARNING
XXXXX
XXXXXXXXXXXX
XXXXXXXXXX
1/4" HIGH ENGRAVED
LETTERING (MINIMUM)
STAINLESS STEEL MACHINE SCREW
WITH NUT AND STAR WASHER BEHIND
METAL PRESSURE PIN
(BLIND OR "POP" RIVET)
LAMINATED PLASTIC - BLACK ON
WHITE OR WHITE ON BLACK. USE RED
ON WHITE FOR EMERGENCY SYSTEMS.
-OR-
ALL ENCLOSURES CONTAINING ENERGIZED
COMPONENTS SHALL BE MARKED WITH
STANDARDIZED MYLAR LABELS IDENTIFYING
HAZARDS. SUCH WARNING MESSAGES AS
"WARNING-HAZARDOUS VOLTAGE", "480
VOLTS", "208 VOLTS", ETC. ARE
ACCEPTABLE. APPLY AS APPROPRIATE
EQUIPMENT IDENTIFICATION SHALL BE MADE USING
ENGRAVED LAMINATED PLASTIC PLATES (INDENTED
TAPE LABELS WILL NOT BE PERMITTED).
CHARACTERS SHALL BE WHITE ON A BLACK
BACKGROUND AND 1/4" HIGH MINIMUM. PLATES
SHALL BE SECURED TO THE PANELS BY MEANS OF
SCREWS OR METAL PRESSURE PINS. CEMENT, BY
ITSELF, WILL NOT BE ACCEPTABLE. ALL
NAMEPLATES SHALL BE MOUNTED ON THE OUTSIDE
SURFACE OF THE PIECE OF EQUIPMENT.
NAMEPLATE DETAILS NOT TO SCALE
~ 61'-2"~ 73'-5"
A-WING BUILDING ROOFTOPBUILDING ROOFTOP
DRIVEWAY FOR CRANE PARKING
COVERED LOADING DOCK 'A' (A-WING)
EXISTING
GENERATOR
AND FUEL TANK
TRANSF. 'T-A2'
NOTE: ALL DIMENSIONS SHOWN ARE APPROXIMATE AND SHOWN FOR
REFERENCE. CONTRACTOR IS RESPONSIBLE FOR COORDINATING ALL
CRANE REQUIREMENTS AND FINALIZING LOGISTICS FOR
TRANSFORMER REPLACEMENT.
~ 62'~ 62'
~ 54'
CRANE PLAN NOT TO SCALE
AS REQUIRED
PORTIONS OF THIS FACILITY ARE EQUIPPED WITH
MULTIPLE STANDBY POWER GENERATORS AND
ADDITIONAL SERVICES AS NOTED BELOW.
DISCONNECTING THIS UTILITY SERVICE WILL NOT
REMOVE POWER FROM FACILITY.
3/8" LETTERS - WHITE ON RED
BACKGROUND MOUNT TO
MAIN BREAKER SECTION
MAIN DISTRIBUTION SECTIONS SHALL HAVE EACH
CIRCUIT IDENTIFIED AS TO CIRCUIT NUMBER,
BREAKER SIZE, AND LOAD WITH ELECTRICAL
CHARACTERISTICS OF LOAD. FOR EXAMPLE, A 480
VOLT, 3 PHASE PANEL 'N4BB' FED FROM 150A
BREAKER IN SWITCHGEAR, CIRCUIT No. 4 WOULD
BE LABELED AS FOLLOWS WITH THE PLATE
ATTACHED ADJACENT TO THE CIRCUIT BREAKER:
SWGR - 4
150A
480V, 3Ø PANEL 'N4BB'
NOTE: ALL LOADS SHALL BE TESTED AND VERIFIED
BY CONTRACTOR PRIOR TO APPLYING LABELS.
SWBD 'SD-1' - 4
150A
480V, 3Ø PANEL 'N4BB'
A-WING
GENERATOR 1 OF 3: 'GEN-1' IS LOCATED AT A-WING NEAR LOADING DOCK. GENERATOR SERVES LIFE SAFETY LOADS FOR ENTIRE KIRKMAN BUILDING. GENERATOR EPO LOCATED ON EXTERIOR WALL ADJACENT TO
GENERATOR.
NORMAL SERVICE #1 ENTERING A-WING BASEMENT: DISCONNECT LOCATED IN MAIN SWITCHBOARD IN ELECTRICAL
ROOM A813A.
NORMAL SERVICE #2 ENTERING A-WING BASEMENT: DISCONNECT LOCATED IN CHILLER PLANT SWITCHBOARD IN
ELECTRICAL ROOM A813A.
B-WING
NORMAL SERVICE #3 ENTERING B-WING: DISCONNECT LOCATED IN SERVICE PANEL 'MPB' IN ELECTRICAL ROOM B802.
NORMAL SERVICE #4 ENTERING B-WING: DISCONNECT LOCATED IN SWITCHBOARD 'B2' IN OUTDOOR MECHANICAL
ROOM NEAR TRASH COMPACTOR.
NORMAL SERVICE #5 ENTERING B-WING: DISCONNECT LOCATED IN SWITCHBOARD 'B1' IN FIRST FLOOR ELECTRICAL
ROOM NEAR FRONT ENTRY OF BUILDING.
C-WING AND D-WING
GENERATOR 2 OF 3: 'GEN-2' IS LOCATED ON EAST SIDE OF C-WING. GENERATOR SERVES STAND-BY LOADS IN DATA
CENTER. GENERATOR EPO LOCATED ON GENERATOR.
GENERATOR 3 OF 3: 'GEN-3' IS LOCATED ON EAST SIDE OF C-WING. GENERATOR SERVES STAND-BY LOADS IN DATA
CENTER. GENERATOR EPO LOCATED ON GENERATOR.
NORMAL SERVICE #6 ENTERING C-WING: DISCONNECT LOCATED IN SWITCHBOARD 'C-1' IN MECHANICAL ROOM C802.
NORMAL SERVICE #7 ENTERING C-WING: DISCONNECT LOCATED IN SWITCHBOARD 'D-1' IN MECHANICAL ROOM C802.
UPS NORMAL SERVICE #8 ENTERING C-WING: DISCONNECT LOCATED IN SWITCHBOARD 'D-1' IN MECHANICAL ROOM C802.
WHITE LETTERS ON
RED BACKGROUND
PRIOR TO OPENING, SERVICING, OR INVESTIGATING
ANY SWITCHGEAR DISTRIBUTION SECTIONS,
ENGAGE ENERGY-REDUCING MAINTENANCE
SWITCH AT MAIN BREAKER SECTION.
NEW SWITCHGEAR - INSTALL ON EACH SECTION NEW SWITCHGEAR - INSTALL AT ALL FEEDER BREAKERS
AVAILABLE FAULT CURRENT
* A
CALCULATION COMPLETED: 07/2025
MAIN SERVICE DISCONNECT
A-WING
FED BY PAD-MOUNT
TRANSFORMER 'T-A2'
WHITE LETTERS ON
BLACK BACKGROUND
WHITE LETTERS ON
BLACK BACKGROUND
NEW SWITCHGEAR - INSTALL ON MAIN BREAKER SECTION
NEW SWITCHGEAR - INSTALL ON MAIN BREAKER SECTION
NEW SWITCHGEAR - INSTALL ON MAIN BREAKER SECTION
A S
R E Q U I R E D
* IN ADDITION TO NEW SWITCHGEAR, SIGNAGE SHALL BE PROVIDED AND INSTALLED ON ALL OTHER NORMAL POWER SERVICE LOCATIONS. NOTE A FEW OF THESE LOCATIONS ALREADY HAVE SIMILAR
SIGNAGE, WHICH ARE TO BE REMOVED AND REPLACED WITH NEW SIGNAGE.
* OBTAIN FINAL VALUE FROM
ENGINEER PRIOR TO MAKING SIGN
SHEET:
September 5, 2025
REVISED:
DATE:
SHEET TITLE:
JOB NUMBER:
DRAWN BY:DESIGNED BY:
100% Construction Documents
SUBMITTAL:
JON BARBER, PE 55427 | BRIAN WALLACE, PE 75562
820 EAST PARK AVE, I-200, TALLAHASSEE, FL 32301
MFE-INC.COM | 850.681.6424
HSMV-02425040
NKB A-Wing Switchgear Replacement & D-Wing PDU / UPS / Surge Protection Upgrades
Neil Kirkman Building Tallahassee, Florida
BW AC
DETAILS
E103
(NORTH)
N/C
SW - B
(SOUTH)
N/C
SW - A
M
FROM: BP9
CIRCUIT DF-924
UNDERGROUND
CITY OF
TALLAHASSEE
METERING UNITN
/C N /O
DF-925
OVERHEAD
#4/0 CU 15KV EPR 133%
TYPE MV90 IN 4" C.
SM4
100E(STD)
SM4
125E(STD)
SW-1 SW-2
S1B N/C
S1A N/C
S2A N/C
S2B N/O
80E 50E 200E 20E
B-Wing
500KVA
PadMounted Transformer
XFMR
T-B1
A-Wing
750KVA
PadMounted Transformer
XFMR
T-A1
A-Wing
1500KVA
PadMounted Transformer
NEW XFMR
T-A2
S&C Type PMH-5 Cat # 55312R1
S&C Type PMH-5 Cat # 55312R1
#4/0 CU 15KV EPR 133%
TYPE MV105
#4/0 CU 15KV EPR 133%
TYPE MV105
MH
PP
PP
N /C N
/C PP
208Y/120480Y/277 208Y/120
To Panel 'B2', 'MPB', &
'SD-1'
SW-3SW-4
S3B N/C
S3A N/C
S4B N/C
S4A N/C
UNK 50EUK
C-Wing North Gear Serving D-wing
C-Wing North
750KVA
PadMounted Transformer
500KVA
PadMounted Transformer
C-Wing Computer Room (UPS System)
750KVA
Dry-Type Transformer
XFMR
T-C4
XFMR
T-C2
XFMR
T-C1
208Y/120208Y/120208Y/120
To D-2To MDP
MAIN
M-2
To MDP
MAIN
M-1
To
A-WING
SWGR
To
CHILLER
PLANT
UNK
ABANDONED
750KVA
Pad-Mount Transformer
XFMR
T-C3
208Y/120
NEW FEEDER IN EXISTING SPARE 3" RACEWAY - 3-1/C #2 CU EPR (15KV)
W/ 1-1/C #4 CU (600V) (33% FILL, 3.06 LOW JAM PROBABILITY)
(ADD ALTERNATE #1)
12.47kV
NOTE 1 SW-A (EX)
SW-B (EX)
SW-2
(EX)
SW-1
(EX)
SW-3
(EX)
SW-4
(EX)
PRIMARY RISER POLE (EX)
COT PRIMARY OHE CIRCUIT DF-925
RISER POLE (EX)
COT UE MANHOLE (EX)
T-C1
750KVA
(EX)
T-C3
750KVA
(ABANDONED)
T-A1
750KVA
(EX)
1500KVA 'T-A2'
TO BE REPLACED
T-C2
500KVA
(EX)T-C4
750KVA (EX)
COT PRIMARY UE
CIRCUIT DF-924 (EX)
E
O
HE
TRANSFORMER REPLACEMENT MAY REQUIRE A
CRANE TO ACCESS COURTYARD OVER PORTION OF
KIRKMAN BUILDING A-WING - SEE CRANE DETAIL
SWBD 'C-1'
(EX)
SWBD 'D-1'
(EX)
SWBD 'B2'
(EX)
PANEL 'MPB'
(EX)
A-WING SWITCHGEAR IN
BASEMENT - TO BE REPLACED
REFER TO ENLARGED PLANS
CHILLER
SWITCHGEAR
(EX)
PARKING
COURTYARDCOURTYARD
A-WING
B-WING
C-WING D-WING
SWBD 'SD-1'
(EX)
T-B1
500KVA
(EX)
REPLACE PDU's IN D-WING DATA
CENTER - SEE ENLARGED PLANS
AND ONE LINES
UPGRADE EXISTING UPS IN C-WING FIRST FLOOR
AND COMPLETE BATTERY REPLACEMENT - REFER
TO ENLARGED PLANS
NEW FEEDER IN
EXISTING SPARE 3"
RACEWAY - SEE NOTE 2
(ADD ALTERNATE #1)
LOADING DOCK 'A'
PROVIDE NEW SPD AT EXISTING MAIN DISTRIBUTION PANEL
'MPB' LOCATED IN B-NORTH BASEMENT MECHANICAL ROOM
- RELOCATE "RECEPT ON ROOF" CIRCUIT TO SPARE
20A, 1P BREAKER IN ADJACENT PANEL 'N2BB' AND
REMOVE REMAINING 20A, 1P BREAKER FROM 'MPB'
- MOVE 3P BREAKERS FOR "TRASH COMPACTOR",
"N2B2", AND "N3B3" UP BY ONE BREAKER SPACE
- ADJUST CONDUCTORS FOR (3) BREAKERS MOVED UP
ONE SPACE TO MATCH EXISTING PHASING
- INSTALL NEW 30A, 3P BREAKER IN AVAILABLE SPACE
BELOW "N3B3" BREAKER TO SERVE NEW SPD
- INSTALL SPD ADJACENT TO PANEL 'MPB' BELOW
ENCLOSED CIRCUIT BREAKER
PANEL 'N2BB'
(EX)
PROVIDE NEW SPD FOR ELEVATOR 6 MAIN POWER IN C-WING ELEVATOR MACHINE ROOM
- REPLACE EXISTING ELEVATOR 6 MAIN POWER FUSED SWITCH WITH NEW 100A, 208V, 3Ø, NEMA 1
SWITCH, FUSED AT 100A
- SWITCH TO BE LOCKABLE IN THE OFF POSITION, HAVE EARLY BREAK CONTACTS FOR FUTURE USE, AND INCLUDE DOUBLE SECONDARY SIDE LUGS FOR CONNECTING OUTGOING FEEDER AND SPD
- RECONNECT EXISTING INCOMING/OUTGOING FEEDERS TO NEW SWITCH
- INSTALL SPD BELOW SWITCH AND CONNECT TO LOAD SIDE LUGS
- PROVIDE NAMEPLATES / SIGNAGE ON NEW SWITCH TO MATCH SIGNAGE OF EXISTING SWITCH
REPLACE EXISTING SPD FOR 2-WAY RADIO ANTENNA
COAXIAL CABLE THAT ENTERS BUILDING IN 4TH FLOOR
OF B-CENTRAL STAIR WITH NEW TYPE N F/F COAXIAL RF,
125MHz-1GHz, 50kA SPD (GUIDE: POLYPHASER IS-50NX-C2)
SHEET NOTES:
1. EXISTING MV LOOP SETUP HAS NORMALLY
OPEN SWITCH AT 'SW-2B'. SWITCH WAY 'SW-2B'
CANNOT BE CLOSED AND SHALL REMAIN AS
THE NORMALLY OPEN PORTION OF THE LOOP.
2. EXISTING FEEDER BETWEEN 15KV SWITCH
'SW-1' AND PAD-MOUNT TRANSFORMER
CONSISTS OF A SINGLE RUN OF 15KV, #2, WITH
GROUND IN 3" CONDUIT. THERE IS AN
ADDITIONAL SPARE 3" CONDUIT BETWEEN
SWITCH AND TRANSFORMER TO BE USED FOR
ADD ALTERNATE FEEDER. EXACT LENGTH IS
UNKNOWN. CONTRACTOR TO VERIFY LENGTH
PRIOR TO CUTTING FEEDER. SEE GENERAL
NOTES SHEET FOR ALTERNATE SCOPE AND
SEE ONE LINE FOR NEW FEEDER SIZING.
SHEET:
September 5, 2025
REVISED:
DATE:
SHEET TITLE:
JOB NUMBER:
DRAWN BY:DESIGNED BY:
100% Construction Documents
SUBMITTAL:
JON BARBER, PE 55427 | BRIAN WALLACE, PE 75562
820 EAST PARK AVE, I-200, TALLAHASSEE, FL 32301
MFE-INC.COM | 850.681.6424
HSMV-02425040
NKB A-Wing Switchgear Replacement & D-Wing PDU / UPS / Surge Protection Upgrades
Neil Kirkman Building Tallahassee, Florida
BW AC
SITE PLAN
E104
ELECTRICAL SITE PLAN
1" = 20'-0"1
N
15KV DISTRIBUTION ONE LINE
NOT TO SCALE2
GENERAL NOTES:
1. THE COMPLETE SCOPE OF WORK AS NOTED WITHIN THESE DOCUMENTS SHALL BE
COMPLETED IN PHASES. PHASING NOTES DO NOT INCLUDE ALL DETAILS OF CONSTRUCTION.
2. THE CONTRACTOR IS EXPECTED TO PLAN OUT THE EXECUTION OF THE WORK SO AS TO
MINIMIZE INTERFERENCE TO THE OWNER'S OPERATIONS.
3. ELECTRICAL POWER OUTAGES FOR THIS FACILITY IS A REQUIREMENT OF THIS PROJECT
AND SHALL BE THOROUGHLY PLANNED AND COORDINATED WITH HSMV.
4. ELECTRICAL OUTAGES WILL BE LIMITED TO SCHEDULED TIMES APPROVED BY HSMV. THE
CONTRACTOR SHALL PLAN AND STAFF THE PROJECT ACCORDINGLY.
5. COORDINATE ALL POWER OUTAGES WITH HSMV AND DMS PROJECT MANAGER PRIOR TO
OUTAGE. PROVIDE 21 DAY MINIMUM NOTICE TO HSMV AND DMS PROJECT MANAGER AS TO
WHEN PROPOSED POWER OUTAGES WILL OCCUR TO RECEIVE APPROVAL. ALL POWER
OUTAGES AND CHANGEOVERS SHALL BE SCHEDULED AND SCHEDULES STRICTLY ADHERED
TO. OUTAGES THAT ARE NOT SCHEDULED WILL NOT BE ALLOWED.
6. CONTRACTOR SHALL BE RESPONSIBLE FOR TEMPORARY LOW VOLTAGE CONSTRUCTION
POWER AND LIGHTING DURING OUTAGES.
7. THE CONTRACTOR SHALL PROVIDE A TRAINED AND KNOWLEDGEABLE STAFF MEMBER
REPRESENTATIVE TO CONSULT WITH THE OWNER PRIOR TO ANY SWITCHING, AND TO
PERFORM SWITCHING, TEST CIRCUITS, AND DEEM GROUNDED AND SAFE PRIOR TO WORK.
8. COORDINATION WITH HSMV MUST OCCUR FOR ENERGIZING AND DE-ENERGIZING FEEDERS
AND EQUIPMENT.
9. WORK DONE UNDER THIS SECTION SHALL BE IN ACCORDANCE WITH THE NATIONAL
ELECTRIC CODE (NFPA 70) AND THE NATIONAL ELECTRIC SAFETY CODE (ANSI C2).
10. CONTRACTOR SHALL BE RESPONSIBLE FOR PERFORMING ALL WORK IN A SAFE MANNER
AND COMPLETING ALL NECESSARY LOCK-OUT, TAG-OUT PROCEDURES. NO HOT WORK IS
PERMITTED. CONTRACTOR SHALL BE RESPONSIBLE FOR CONFIRMING ALL SEQUENCING,
SWITCHING, AND REQUIRED ACTIONS FOR SAFELY PERFORMING ALL WORK NOTED. SAFETY
ITEMS INCLUDING LOCK-OUT, TAG-OUT PROCEDURES ARE NOT SPECIFICALLY NOTED IN
PHASING NOTES BUT ARE EXPECTED.
11. SWITCHING OF BUILDING'S EQUIPMENT AS LISTED IN SEQUENCING NOTES SHALL BE
COMPLETED BY ELECTRICAL CONTRACTOR. CONTRACTOR SHALL COORDINATE SWITCHING
SCHEDULE WITH OWNER. CONTRACTOR SHALL VISIT SITE AND REVIEW EXISTING SWITCH
CONDITIONS PRIOR TO SCHEDULED OUTAGES TO FAMILIARIZE THEMSELVES WITH
SEQUENCE AND OPERATIONS.
12. SEQUENCING NOTES WERE DEVELOPED AT TIME OF DESIGN WITHOUT ANY COORDINATION
WITH CONTRACTOR. SHOULD CONTRACTOR HAVE IDEAS TO SIMPLIFY CONSTRUCTION,
PROVIDE SAFER WORK ENVIRONMENT, OR TO REDUCE OUTAGE QUANTITIES OR TIME
FRAMES, CONTRACTOR SHALL PRESENT PLANS TO OWNER AND ENGINEER FOR DISCUSSION
AND CONSIDERATION.
13. NOTES AT RIGHT MAY INCLUDE SCOPE IDENTIFIED AS ADDITIVE ALTERNATE AND / OR BASE
BID. CONTRACTOR SHALL MODIFY SEQUENCING ACCORDINGLY DEPENDING ON WHETHER
ADDITIVE ALTERNATE SCOPE IS INCLUDED BY OWNER OR NOT.
SEQUENCING NOTES
C-WING AND D-WING PHASE:
PRE-OUTAGE:
1. INSTALL PANEL 'UPSDP' IN C-WING FIRST FLOOR UPS ROOM. INSTALL CONDUIT FROM PANEL
TO UPS LOCATION. INSTALL CONDUIT FROM PANEL TO C-103 AND C-104 PANEL LOCATIONS.
INSTALL CONDUIT DOWN TO BASEMENT LEVEL ADJACENT TO EXISTING CONDUIT TIE-IN
LOCATIONS.
2. REMOVE EXISTING PDU-1 THAT IS CURRENTLY DOWN. REMOVE ALL ABANDONED
RECEPTACLES AND BRANCH CIRCUITS FED FROM PDU-1. REMOVE PDU-1 FEEDER BACK TO
SERVING PANEL 'MCDP'. REMOVE PORTION OF FLEXIBLE CONDUIT BELOW RAISED FLOOR
BETWEEN PDU-1 AND PULLBOX TO REMAIN. REMOVE PORTION OF CONDUIT IN C-WING.
3. USING A PHASED APPROACH SUCH THAT NOT ALL AC UNITS ARE DOWN AT SAME TIME,
DISCONNECT THE FOLLOWING AC UNITS FROM UPS FED PANELS OR PDU's AND RECIRCUIT
TO NEW BREAKERS IN EXISTING PANELS AS SHOWN ON NEW WORK POWER PLANS. ROUTE
NEW CIRCUITS FOR D-WING UNITS IN RACEWAY OVERHEAD ABOVE ACCESSIBLE CEILINGS
BACK TO C-WING. TYPICAL FOR AHU-1, AHU-2, AHU-3, CU-1, CU-2, CU-3, C-103 AC-1, C-103
AC-2, C-103 CU-1, AND C-103 CU-2.
UPS OUTAGE #1:
4. SHUTDOWN UPS FOR CONNECTING NEW FEEDER TO UPS OUTGOING LUGS AND FOR
UPGRADING UPS AND INSTALLING NEW BATTERIES.
[48 HOUR WEEKEND OUTAGE FOR ALL UPS LOADS ]
5. PERFORM UPS UPGRADES TO ADD NEW BATTERY CABINET AND EXPAND CAPACITY OF UPS
TO FULL CHASSIS RATING.
6. DISCONNECT EXISTING OUTGOING FEEDER FROM UPS OUTGOING LUGS.
7. PROVIDE POLARIS LUGS IN TOP OF UPS TO CONNECT BOTH EXISTING AND NEW FEEDERS TO
UPS OUTPUT LUGS.
8. INSTALL SHORT RUN OF FEEDER FROM UPS OUTGOING LUGS TO POLARIS LUGS. MATCH
EXISTING FEEDER SIZE.
9. INSTALL NEW FEEDER FROM POLARIS LUGS IN UPS TO PANEL 'UPSDP' AND MAKE
PROVISIONS TO ENERGIZE PANEL. NEW FEEDER SHALL BE OF SUFFICIENT LENGTH TO
ALLOW FOR TERMINATING TO UPS OUTGOING LUGS AT END OF PROJECT.
10. WHILE UPS LOADS ARE DOWN, INSTALL NEW FEEDER IN RACEWAY TO EXISTING PANELS
'C-103' AND 'C-104' AND CONNECT TO NEW PANEL 'UPSDP'. PREPARE TO ENERGIZE EXISTING
PANELS FROM NEW PANEL AT COMPLETION OF OUTAGE.
11. DISCONNECT AND REMOVE EXISTING FEEDERS AND RACEWAY TO PANELS 'C-103' AND
'C-104' BACK TO EXISTING SERVING PANEL IN C-WING BASEMENT.
12. TURN BACK ON UPS AND ENERGIZE ALL UPS LOADS, INCLUDING 'UPSDP', 'C-103', AND 'C-104'.
[UPS LOADS ARE BACK ONLINE]
BETWEEN OUTAGES:
13. INSTALL NEW PDU-1 IN DATA CENTER.
14. CONNECT NEW CONDUIT TO EXISTING IN C-WING BASEMENT AND INSTALL NEW FEEDER
FROM 'UPSDP' TO EXISTING PULLBOX BELOW RAISED FLOOR AND EXTEND IN RACEWAY
BELOW RAISED FLOOR TO NEW PDU-1.
15. REWORK ALL RECEPTACLES IN LARGE DATA CENTER AREA FROM EXISTING PDU-3 TO NEW
PDU-1. SOME WILL BE ONLY TEMPORARILY ON PDU-1 UNTIL NEW PDU-2 IS ONLINE.
[SCOPE REQUIRES EQUIPMENT DOWNTIME - COORDINATE OUTAGE TIME WITH OWNER]
16. INSTALL NEW 3Ø RECEPTACLES TO BE CONNECTED TO PDU-1.
17. REMOVE EXISTING PDU-3. REMOVE ALL ABANDONED RECEPTACLES AND BRANCH CIRCUITS
FED FROM PDU-3. REMOVE PDU-3 FEEDER BACK TO SERVING PANEL 'CD'. REMOVE PORTION
OF FLEXIBLE CONDUIT BELOW RAISED FLOOR BETWEEN PDU-3 AND PULLBOX TO REMAIN
BELOW FLOOR. REMOVE PORTION OF CONDUIT IN C-WING.
18. INSTALL NEW PDU-2 IN DATA CENTER.
19. CONNECT NEW CONDUIT TO EXISTING C-WING BASEMENT AND INSTALL NEW FEEDER FROM
'UPSDP' TO EXISTING PULLBOX BELOW RAISED FLOOR AND EXTEND IN RACEWAY BELOW
RAISED FLOOR TO NEW PDU-2. ENERGIZE NEW PDU-2.
20. REWORK ALL RECEPTACLES IN LARGE DATA CENTER AREA FROM EXISTING PDU-2 TO NEW
PDU-2. REMOVE ALL ABANDONED RECEPTACLES AND BRANCH CIRCUITS FED FROM
EXISTING PDU-2. EXISTING PDU-2 SHOULD NOW BE EMPTY OF ALL LOADS.
[SCOPE REQUIRES EQUIPMENT DOWNTIME - COORDINATE OUTAGE TIME WITH OWNER.]
21. REWORK RECEPTACLES THAT WERE TEMPORARILY ON NEW PDU-1 TO FINAL LOCATION ON
NEW PDU-2.
[ SCOPE REQUIRES EQUIPMENT DOWNTIME - COORDINATE OUTAGE TIME WITH OWNER.]
22. INSTALL NEW 3Ø RECEPTACLES TO BE CONNECTED TO NEW PDU-2.
23. REMOVE EXISTING PDU-2. REMOVE PDU-2 FEEDER BACK TO SERVING PANEL 'CD'. REMOVE
PORTION OF FLEXIBLE CONDUIT BELOW RAISED FLOOR BETWEEN PDU-2 AND PULLBOX TO
REMAIN BELOW FLOOR. REMOVE PORTION OF CONDUIT IN C-WING.
24. INSTALL NEW PDU-3 IN DATA CENTER.
25. CONNECT NEW CONDUIT TO EXISTING C-WING BASEMENT AND INSTALL NEW FEEDER FROM
'UPSDP' TO EXISTING PULLBOX BELOW RAISED FLOOR AND EXTEND IN RACEWAY BELOW
RAISED FLOOR TO NEW PDU-3.
26. REWORK ALL RECEPTACLES IN SMALLER DATA CENTER AREA FROM EXISTING PDU-4 TO
NEW PDU-3. REMOVE ALL ABANDONED RECEPTACLES AND BRANCH CIRCUITS FED FROM
EXISTING PDU-4. EXISTING PDU-4 SHOULD NOW BE EMPTY OF ALL LOADS.
[SCOPE REQUIRES EQUIPMENT DOWNTIME - COORDINATE OUTAGE TIME WITH OWNER.]
27. REMOVE EXISTING PDU-4. REMOVE PDU-4 FEEDER AND RACEWAY IN THEIR ENTIRETY BACK
TO SERVING PANEL 'MCDP'.
28. PANELS 'MCDP' AND 'CD' SHOULD HAVE ALL LOADS REMOVED AT THIS POINT.
UPS OUTAGE #2:
29. SHUTDOWN UPS FOR MAKING FINAL CONNECTION OF NEW FEEDER TO UPS OUTGOING
LUGS.
[2 HOUR WEEKEND OUTAGE FOR ALL UPS LOADS]
30. DISCONNECT EXISTING FEEDER SERVING PANEL 'MCDP' FROM POLARIS LUGS AND PULL
FEEDER BACK TO PULLBOX WITHIN UPS ROOM.
31. REMOVE POLARIS LUGS AND CONNECT PANEL 'UPSDP' FEEDER TO OUTGOING LUGS.
32. REMOVE EXISTING CONDUIT BETWEEN UPS AND PULLBOX AND PROVIDE KNOCK-OUT CAPS
IN TOP OF UPS.
33. TURN BACK ON UPS AND ENERGIZE ALL UPS LOADS.
[UPS LOADS ARE BACK ONLINE]
34. COMPLETE DEMOLITION OF FEEDER AND RACEWAY, INCLUDING PULLBOXES, BETWEEN UPS
ROOM AND PANELS 'MCDP' AND 'CD'. REMOVE ALL CONDUIT SUPPORTS, WIREWAY, AND
PANELS IN THEIR ENTIRETY.
C-WING AND D-WING OUTAGE:
35. MAKE PREPARATIONS FOR A FULL C-WING AND D-WING OUTAGE TO REPLACE SPD's.
36…