This document is an announcement for an industry day webinar regarding a dredging project. The U.S. Army Corps of Engineers Norfolk District is seeking firms to dredge the Norfolk Harbor channels including Channel to Newport News and the inner channels of Norfolk Harbor. The work includes maintenance and new work dredging by hydraulic cutterhead dredge and potential clean-up by mechanical dredge. Dredged material will be placed at the Craney Island Dredged Material Management Area. The total estimated dredging quantities are approximately 2.7 million cubic yards for Channel to Newport News and 7.3 million cubic yards for the inner channels. Firms must pre-register by November 9th for the webinar on November 10th which will provide an overview of the project scope as well as restrictions and environmental considerations. Definitive responsibility criteria will be used to evaluate experience with hydraulic pipeline dredging, performing similar large and complex jobs, and managing disposal facilities. The estimated price range for the project is $25-100 million.

View the file

Other files for this federal contract opportunity

Other files attached to Norfolk Harbor and Channels Navigation Improvements, Inner Channels Deepening, newest first.
File Type Posted
Industry Day KTR Inquiries_Govt Responses_20211202.pdf PDF
NH Deepening Project Slides Industry Day_17 November 2021.pdf PDF
DRAFT CNNPS2101C-HP2207.pdf PDF
Norfolk Harbor - Excel worksheet for pre-submitted questions.xlsx XLSX spreadsheet
DRAFT NHICPS 2021-06-08.pdf PDF
CNN Deepening Specs_95.pdf PDF
CNN and NHIC Deepening_DRAFT BID SCHEDULE.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Norfolk Harbor Inner Channel Deepening 2022NHCDEEPENING

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15 LIST OF DRAWINGS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 SPECIAL WORK CONDITIONS

01 22 00 MEASUREMENT AND PAYMENT

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 30 ENVIRONMENTAL PERMIT WORK REQUIREMENTS

01 57 50 ENDANGERED SPECIES EQUIPMENT AND PROCEDURES - PIPELINE

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

35 20 23.13 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM SCOW -

MONITORING PROFILE

35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM PIPELINE

HYDRAULIC DREDGE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

NOT FOR SOLICITATION

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 01 15

LIST OF DRAWINGS

01/07

PART 1 GENERAL

1.1 SUMMARY

1.2 CONTRACT DRAWINGS

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

DOCUMENT 00 01 15 Page 1

SECTION 00 01 15

LIST OF DRAWINGS

01/07

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

Title File Number

Norfolk Harbor Inner Channel

TITLE SHEET N50.2020-12-01.PS(1)

INDEX SHEET N50.2020-12-01.PS(2)

MAPPING SHEET N50.2020-12-01.PS(3)

MAPPING SHEET N50.2020-12-01.PS(4)

MAPPING SHEET N50.2020-12-01.PS(5)

MAPPING SHEET N50.2020-12-01.PS(6)

MAPPING SHEET N50.2020-12-01.PS(7)

MAPPING SHEET N50.2020-12-01.PS(8)

MAPPING SHEET N50.2020-12-01.PS(9)

MAPPING SHEET N50.2020-12-01.PS(10)

MAPPING SHEET N50.2020-12-01.PS(11)

MAPPING SHEET N50.2020-12-01.PS(12)

MAPPING SHEET N50.2020-12-01.PS(13)

MAPPING SHEET N50.2020-12-01.PS(14)

MAPPING SHEET N50.2020-12-01.PS(15)

MAPPING SHEET N50.2020-12-01.PS(16)

MAPPING SHEET N50.2020-12-01.PS(17)

MAPPING SHEET N50.2020-12-01.PS(18)

DOCUMENT 00 01 15 Page 2

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section --

DOCUMENT 00 01 15 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

1.1.2 Location

1.2 SEQUENCE OF WORK

1.3 Special Requirements for Craney Island Dredged Material Management

Area

1.4 COOPERATION WITH USING AGENCY AND OTHER CONTRACTORS

1.5 HISTORICAL AND ARCHAEOLOGICAL FINDS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The work at Norfolk Harbor consists of deepening dredging of the following inner channels: Norfolk Harbor Entrance Reach, Norfolk Harbor Reach, and Craney Island Reach, which terminates at Lambert Bend. These segments are being deepened to a required depth of -54 feet MLLW. Up to one (1) foot of allowable overdepth dredging will be allowed as part of the contract dredging pay prism. Dredged material generated by the project to be placed at Craney Island Dredged Material Management Area (CIDMMA).

1.1.2 Location

The work will be done in the Norfolk Harbor inner channels: Norfolk Harbor Entrance Reach, Norfolk Harbor Channel, and Craney Island Reach with dredged material placed at CIDMMA.

1.2 SEQUENCE OF WORK

Work under this contract includes deepening dredging Channel to Newport News and Norfolk Harbor Inner Channels. Two separate Notices to Proceed (NTP) will be issued. The first NTP will direct the Contractor to proceed with all work associated with Bid Schedule I, limited to bid items 1001 through 1004. The second NTP will be issued after dredging of Channel to Newport News is complete and earthwork improvements at the CIDMMA, under separate contracts, is completed. The second NTP will direct the Contractor to proceed with all work associated with deepening Norfolk Harbor Inner Channels under Bid Schedule II, limited to bid items 2001 to 2004.

1.3 Special Requirements for Craney Island Dredged Material Management Area

All activities at Craney Island Dredged Material Management Area shall be conducted in accordance with "COMMANDER'S POLICY MEMORANDUM NUMBER WRD-01" which is available for review at the Craney Island Reservation Office.

Point of contact for review of the Regulation or to visit the site is Carlos Quinones, telephone (757) 484-1021. It is also included in Appendix A of these specifications. The government retains ownership of all materials deposited within the disposal area. The removal of existing scrap iron, steel, or any other material located in CIDMMA for personal use is prohibited.

1.4 COOPERATION WITH USING AGENCY AND OTHER CONTRACTORS

During the period of this contract, other contracts may be in force for the construction of other features of work on or adjacent to the site of work being accomplished under this contract. It shall be the responsibility of the Contractor on this contract to be fully informed of the extent of the limits of work to be performed by other Contractors. Should there be any conflict between these limits, it shall be brought to the attention of

SECTION 01 11 00 Page 2 the Contracting Officer(CO)and the CO's decision shall be final. Also, prior to completion of work under this contract, members of the Using Agency may be performing work or occupying facilities on or adjacent to the area. The Contractor shall arrange his plant and shall schedule and perform this work so as to effectively cooperate with all other Contractors and Government agencies. Adjacent contracts anticipated at this time include, but are not limited to:

Various dredging contracts requiring use of the Rehandling Basin.

The Contractor shall anticipate barges and scows putting dredged material in the Rehandling Basin during this contract

Various dredging contracts hydraulically placing dredged material into the existing CIDMMA placement cells. The Contractor shall anticipate pipelines and support barges operating along the eastern CIDMMA perimeter and associated landbased support equipment during this contract.

1.5 HISTORICAL AND ARCHAEOLOGICAL FINDS

Federal legislation provides for the protection, preservation, and collection of scientific, prehistoric, historical, and archaeological data, including relics and specimens which might otherwise be lost due to alteration of the terrain or building features as a result of any Federal construction project. Should the Contractor, or any of the Contractor's employees, or parties operating or associated with the Contractor, in the performance of this contract discover evidence of possible scientific, prehistoric, historical, or archaeological data, the Contractor shall immediately cease work at that location, avoid further disturbance, and notify the Contracting Officer, giving the location and nature of the findings. The Contractor shall forward written confirmation to the Contracting Officer as directed. The Contractor shall exercise care so as not to disturb or damage artifacts or fossils uncovered during excavation operations, and shall provide such cooperation and assistance as may be necessary to preserve the findings for removal or other disposition. Any person who, without permission, injures, destroys, excavates, appropriates, or removes any historical or prehistoric artifact, object of antiquity, or archaeological resource on the public lands of the United States is subject to arrest and penalty of law. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance or changes in the work, or both. If such delays or changes are ordered, an equitable adjustment will be made in the contract in accordance with the applicable clauses of the contract.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00

SPECIAL WORK CONDITIONS

04/15

PART 1 GENERAL

1.1 SUBMITTALS

1.2 CONTRACTOR NOTIFICATIONS

1.3 CONTRACTOR WORK REQUIREMENTS

1.3.1 Special Work Requirements and Conditions

PART 2 PRODUCTS (THIS PART NOT USED)

PART 3 EXECUTION (THIS PART NOT USED)

-- End of Section Table of Contents --

SECTION 01 14 00 Page 1

SECTION 01 14 00

SPECIAL WORK CONDITIONS

04/15

PART 1 GENERAL

1.1 SUBMITTALS

The Contractor shall make submittals for the following listed reports and certificates as required by the specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the Contractor's Quality Control (CQC) representative and each item shall be stamped, signed, and dated by the CQC representative indicating action taken in accordance with SECTION 01 45 00. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction and Postconstruction Submittals

Dredging Notification to the U.S. Coast Guard

Prior to commencement of dredging, submit a copy of Dredging Notification to the U.S. Coast Guard and the Contracting Officer.

The Dredging Intent Notification to U.S. Coast Guard must be given in sufficient time so that it appears in the Notice to Mariners at least 5 workdays prior to the commencement of this contract.

Advance Notice for Dredging

The Contractor shall advise the Government in writing of the date that he will commence dredging. This Contractor advance notice for dredging will constitute his request for Before Dredging Surveys.

After Dredging Survey Request

The Contractor shall advise the Government in writing of the date that he will complete dredging. This is defined to be the Contractor After Dredging Survey Request.

1.2 CONTRACTOR NOTIFICATIONS

A Dredging Intent Notification shall be prepared and sent to the agencies identified below identifying the dredging locations, placement areas, and dates the Contractor intends to start and complete dredging. A copy of all Notifications furnished shall at the same time be provided to the Contracting Officer.

a. Dredging Intent Notification to the U.S. Coast Guard

The Contractor shall notify the Commander, Fifth Coast Guard

SECTION 01 14 00 Page 2

District of his intended operations to dredge and request that it be published in the Local Notice to Mariners. This Dredging Intent Notification to U.S. Coast Guard must be given in sufficient time so that it appears in the Notice to Mariners at least 5 workdays prior to the commencement of this contract.

b. Dredging Intent Notification to the U.S. Army Corps of Engineers

Notify the Contracting Officer's Representative at least 7 days in advance of both mobilization, and the start of dredging.

c. Dredging Intent Notification to the U.S. Navy

The Contractor shall notify the U.S. Navy at least 14 days prior to commencement of dredging near the Fairway area as shown in the drawings.

1.3 CONTRACTOR WORK REQUIREMENTS

The work shall be performed by hydraulic dredge with all dredged material hydraulically placed into Craney Island Dredged Material Management Area (CIDMMA) in accordance with the latest edition of COMMANDER’S POLICY MEMORANDUM NUMBER WRD-01 (see Appendix A). The Contractor shall perform the scheduled dredging work in accordance with all requirements as specified herein and as identified in the contract drawings.

1.3.1 Special Work Requirements and Conditions

a. Mechanical Dredging

Should any shoals, lumps, or other lack of contract depth be disclosed by the After Dredging Survey results, the Contractor will be required to remove same by dredging at the contract rate for dredging. At the contractor's option, it will be allowed to perform mechanical dredging for clean up of shoals and lumps to meet the contract's depth requirements. All mechanically dredged material shall be transported by scows and bottom-placed into the Craney Island Rehandling Basin (CIRB). However, if mechanical dredging is utilized for clean up, the contractor shall be responsible for paying tolls associated with placement of dredged material into the CIRB in the amount of $5.43 per cubic yard.

Furthermore, the amount of dredged material to be allowed for placement into the CIRB will be limited to 150,000 cubic yards for the entire project.

b. NAVY Silencing Range

The Contractor shall be aware of existing NAVY Silencing Range located between stations 419+00 and 423+00 of the Norfolk Harbor Channel as shown on the contract drawings. This area is not included in this contract and shall not be dredged under any circumstances.

c. City of Norfolk 36-inch Water Line

A 36-inch water main has been identified within the footprint of the Norfolk Harbor Channel prism. It crosses the Elizabeth River, from Craney Island Fuel Depot to Lamberts Point. Water main's approximate horizontal alignment is shown on the drawings. Based

SECTION 01 14 00 Page 3 on the recently completed bathymetric and geophysical surveys, the top of the pipe should be at or just below elevation -60.0 MLLW;

its exact vertical alignment is unknown.

A "No spud, No anchor" buffer zone is designated from shoreline to shoreline along the identified alignment of the waterline with a minimum 30-foot offset on each side of the waterline. See contract drawings for "NO SPUD ZONE" location.

The maximum allowable dredging depth within the designated "No spud, No anchor" zone will be reduced to -57 feet MLLW compared to -58 feet MLLW for the rest of the channel. The dredging prism within the designated vicinity of the waterline will consist of the required dredging depth of -55 feet MLLW; one (1) foot of overdepth pay will be allowed. One (1) foot of non-pay overdepth is being considered with a maximum not-to-exceed dredging depth of -57 feet MLLW established within the "No spud, No anchor" zone.

d. Placement at the Craney Island Dredge Material Management Area

Dredged material placed by hydraulic method may not exceed a rate of 22,500 cubic yards in a 24-hour period in accordance with

COMMANDER’S POLICY MEMORANDUM NUMBER WRD-01.

The facility manager has the discretion to direct users of CIDMMA in their placement of material based on cell capacity, or functionality of the appurtenances. At any time, the Contractor may be required to re-arrange the placement sequence and move the discharge point to a different containment cell as directed by the Contracting Officer. Daily placement rate may also be limited during periods of time.

e. Designated Acceptance Sections

The Government has specified Designated Acceptance Sections for completion of the scheduled work. The Contractor's Dredging and Dredged Material Placement Plan and Progress Schedule shall be coordinated with this requirement for completing the scheduled work in suitable sections for timely acceptance by the Government.

f. Dredging Buffer Areas

Two No Dredging buffer areas are identified on the plans for dredging.

No dredging shall occur within these areas.

PART 2 PRODUCTS (THIS PART NOT USED)

PART 3 EXECUTION (THIS PART NOT USED)

-- End of Section --

SECTION 01 14 00 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

05/08

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 SINGLE JOB PAYMENT ITEMS

1.3.1 Payment Item No. 2001 Mobilization and Demobilization for

Norfolk Harbor Inner Channels

1.3.1.1 Mobilization

1.3.1.2 Demobilization

1.4 UNIT PRICE PAYMENT ITEMS

1.4.1 Payment Item No. 2002 Dredging Norfolk Harbor Inner Channel to

-54 Feet MLLW

1.4.2 Payment Item No. 2003 Dredging Norfolk Harbor Inner Channel to

-55 Feet MLLW

1.4.3 Payment Item No. 2004 Dredging Norfolk Harbor Inner Channel to

-56 Feet MLLW

1.5 MISPLACED MATERIAL

1.6 EXCESSIVE DREDGING

1.7 MONTHLY PARTIAL PAYMENTS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

SECTION 01 22 00 Page 1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

05/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ENGINEERING MANUALS, U.S. ARMY

EM 1110-2-1003 (2013) Hydrographic Surveying Manual

1.2 SUBMITTALS

Not Used.

1.3 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.3.1 Payment Item No. 2001 Mobilization and Demobilization for Norfolk Harbor Inner Channels

All costs connected with the mobilization and demobilization of all of the Contractor's dredging plant and equipment as defined below will be paid for at the contract job price for this item. Sixty percent of the lump sum price will be paid to the Contractor upon completion of his mobilization at the work site. The remaining forty percent will be paid to the Contractor upon completion of demobilization. In the event the Contracting Officer considers that the amount in this item, sixty percent which represents mobilization and forty percent which represents demobilization, does not bear a reasonable relation to the cost of the work in this contract, the Contracting Officer may require the Contractor to produce cost data to justify this portion of the bid. Failure to justify such price to the satisfaction of the Contracting Officer will result in payment of actual mobilization costs, as determined by the Contracting Officer, at the completion of mobilization, and actual demobilization costs, as determined by the Contracting Officer, at the completion of demobilization. The determination of the Contracting Officer is not subject to appeal.

SECTION 01 22 00 Page 2

1.3.1.1 Mobilization

Mobilization shall include all costs for operations accomplished prior to commencement of actual dredging operations. This shall include as a minimum the following:

a. Transfer of dredge and attendant plant, booster pumps, and other like equipment and machinery.

b. All initial installation of pipe

c. All costs for any other associated work that is necessary in advance of the actual dredging operations.

1.3.1.2 Demobilization

Demobilization shall include general preparation for transfer of plant to its home base, removal of pipelines, cleanup of all work sites, and transfer of plant to its home base.

1.4 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.4.1 Payment Item No. 2002 Dredging Norfolk Harbor Inner Channel to -54 Feet MLLW

New Work dredging of Norfolk Harbor Inner Channel to a depth of -54 feet MLLW with one foot of allowable overdepth. Payment to be made for all costs associated with dredging shall include the cost of removal and placement of material as indicated and specified, exclusive of the mobilization and demobilization as defined above. The total amount of material removed and to be paid for under this payment item will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last surveys made before dredging, and the bottom surface shown by the soundings of surveys made as soon as practicable after the work has been completed. The volume for measurement and payment shall include the material within the limits of overdepth and side slopes described in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" of SECTION 35 20 23, less any deductions that may be required for misplaced material described in subparagraph "Misplaced Material", below.

The drawings are believed to accurately represent conditions at the time of the surveys indicated. New soundings will be taken before dredging as specified in paragraph "Before Dredging Surveys" of SECTION 35 20 23. The Contractor's unit price for dredging, based on the above method of computation of the quantity for payment, shall include his evaluation of shoaling, other natural changes in the waterway, or changes caused by the Contractor's operations that might occur during the period between the surveys before dredging and the surveys for acceptance of the work.

Computations for payment purposes will be made by the Government using, as defined in the USACE Hydrographic Survey Manual EM 1110-2-1003, the Average End Area (AEA) method, Triangulated Irregular Network (TIN) method, or a combination of these methods at the discretion of the Government, utilizing electronic data processing software and machines for the calculations.

SECTION 01 22 00 Page 3

Determination of quantities removed and the deductions made to determine quantities in place to be paid for in the areas specified, after having once been made, will not be reopened except on evidence of collusion, fraud, or obvious error.

Should any shoals, lumps, or other lack of contract depth be disclosed by the After Dredging Survey results, the Contractor will be required to remove same by dredging at the contract rate regardless of method(s) used for clean up. At the contractor's option, it will be allowed to perform mechanical dredging for clean up of shoals and lumps to meet the contract's depth requirements. See specifications Section 35 20 23

DREDGING.

1.4.2 Payment Item No. 2003 Dredging Norfolk Harbor Inner Channel to -55 Feet MLLW

New Work dredging of Norfolk Harbor Inner Channel to a depth of -55 feet MLLW with one foot of allowable overdepth. Payment to be made for all costs associated with dredging shall include the cost of removal and placement of material as indicated and specified, exclusive of the mobilization and demobilization as defined above. The total amount of material removed and to be paid for under this payment item will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last surveys made before dredging, and the bottom surface shown by the soundings of surveys made as soon as practicable after the work has been completed. The volume for measurement and payment shall include the material within the limits of overdepth and side slopes described in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" of SECTION 35 20 23, less any deductions that may be required for misplaced material described in subparagraph "Misplaced Material", below.

The drawings are believed to accurately represent conditions at the time of the surveys indicated. New soundings will be taken before dredging as specified in paragraph "Before Dredging Surveys" of SECTION 35 20 23. The Contractor's unit price for dredging, based on the above method of computation of the quantity for payment, shall include his evaluation of shoaling, other natural changes in the waterway, or changes caused by the Contractor's operations that might occur during the period between the surveys before dredging and the surveys for acceptance of the work.

Computations for payment purposes will be made by the Government using, as defined in the USACE Hydrographic Survey Manual EM 1110-2-1003, the Average End Area (AEA) method, Triangulated Irregular Network (TIN) method, or a combination of these methods at the discretion of the Government, utilizing electronic data processing software and machines for the calculations.

Determination of quantities removed and the deductions made to determine quantities in place to be paid for in the areas specified, after having once been made, will not be reopened except on evidence of collusion, fraud, or obvious error.

Should any shoals, lumps, or other lack of contract depth be disclosed by the After Dredging Survey results, the Contractor will be required to remove same by dredging at the contract rate regardless of method(s) used for clean up. At the contractor's option, it will be allowed to perform mechanical dredging for clean up of shoals and lumps to meet the contract's depth requirements. See specifications Section 35 20 23

DREDGING.

SECTION 01 22 00 Page 4

1.4.3 Payment Item No. 2004 Dredging Norfolk Harbor Inner Channel to -56 Feet MLLW

New Work dredging of Norfolk Harbor Inner Channel to a depth of -56 feet MLLW with one foot of allowable overdepth. Payment to be made for all costs associated with dredging shall include the cost of removal and placement of material as indicated and specified, exclusive of the mobilization and demobilization as defined above. The total amount of material removed and to be paid for under this payment item will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last surveys made before dredging, and the bottom surface shown by the soundings of surveys made as soon as practicable after the work has been completed. The volume for measurement and payment shall include the material within the limits of overdepth and side slopes described in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" of SECTION 35 20 23, less any deductions that may be required for misplaced material described in subparagraph "Misplaced Material", below.

The drawings are believed to accurately represent conditions at the time of the surveys indicated. New soundings will be taken before dredging as specified in paragraph "Before Dredging Surveys" of SECTION 35 20 23. The Contractor's unit price for dredging, based on the above method of computation of the quantity for payment, shall include his evaluation of shoaling, other natural changes in the waterway, or changes caused by the Contractor's operations that might occur during the period between the surveys before dredging and the surveys for acceptance of the work.

Computations for payment purposes will be made by the Government using, as defined in the USACE Hydrographic Survey Manual EM 1110-2-1003, the Average End Area (AEA) method, Triangulated Irregular Network (TIN) method, or a combination of these methods at the discretion of the Government, utilizing electronic data processing software and machines for the calculations.

Determination of quantities removed and the deductions made to determine quantities in place to be paid for in the areas specified, after having once been made, will not be reopened except on evidence of collusion, fraud, or obvious error.

Should any shoals, lumps, or other lack of contract depth be disclosed by the After Dredging Survey results, the Contractor will be required to remove same by dredging at the contract rate regardless of method(s) used for clean up. At the contractor's option, it will be allowed to perform mechanical dredging for clean up of shoals and lumps to meet the contract's depth requirements. See specifications Section 35 20 23

DREDGING.

1.5 MISPLACED MATERIAL

Any material that is deposited elsewhere than in places designated or approved by the Contracting Officer will not be paid for, and the Contractor may be required to remove such misplaced material and deposit it where directed by the Contracting Officer at the Contractor's expense.

1.6 EXCESSIVE DREDGING

Material taken from outside the specific areas to be dredged or beyond the limits as extended in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" will be considered as excessive overdepth dredging, or excessive side slope dredging, for which payment will not be made. Nothing in these specifications shall be construed to prevent payment for the

SECTION 01 22 00 Page 5 removal of shoals performed in accordance with the applicable provisions of Paragraphs SHOALING and FINAL EXAMINATION AND ACCEPTANCE of Section 35 20 23.

1.7 MONTHLY PARTIAL PAYMENTS

Monthly partial payments will be based on estimated quantities determined by the Contracting Officer.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

SECTION 01 22 00 Page 6

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

08/15

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROGRESS AND COMPLETION PICTURES

1.4 SUPERVISION

1.4.1 Minimum Communication Requirements

1.4.2 Superintendent Qualifications

1.4.2.1 Duties

1.4.3 Non-Compliance Actions

1.5 PRECONSTRUCTION CONFERENCE

1.5.1 Scheduling

1.5.2 Purpose

1.5.3 Discussion Items

1.6 OTHER MEETINGS DURING THE CONTRACT

1.7 MINUTES OF MEETINGS

1.8 NOTICE TO PROCEED (NTP)

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

08/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Progress and Completion Pictures

1.3 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions during dredging operations.

Provide during the first month and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color 1200 dpi minimum resolution in JPEG file format showing the work. Take a minimum of 20 digital photographs of the Dredge and on Craney Island, about 10-each .

Show clean water leaving Craney Island spillways and show the inflow at the outfall pipe and material building up at the outfall. Submit two sets of digital photographs each set on a separate CD-R, in the first and last month of the project. Include on the second CD all photos taken. Include photographs demonstrating environmental procedures. Photographs for the two months shall be in a separate monthly directory and each file shall be named to indicate its subject, location and direction in which the camera is looking. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.

1.4 SUPERVISION

1.4.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication

SECTION 01 30 00 Page 2 skills.

1.4.2 Superintendent Qualifications

The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.4.2.1 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.4.3 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.5 PRECONSTRUCTION CONFERENCE

1.5.1 Scheduling

After award of the construction contract and prior to the start of any construction work, the Contracting Officer's Representative (COR) will schedule and conduct a preconstruction conference. The Contractor's Project Manager, Superintendent and Quality Control System Manager shall attend these meetings. The Contractor is encouraged to have an officer of his company (Project Manager could be this person) and representation from each of his sub-contractors and major construction work divisions at the conferences.The conferences will be held at a location and time as specified by the COR.

1.5.2 Purpose

The purpose of this preconstruction conferences is to enable the COR to outline the procedures that will be followed by the Government in its administration of this construction contract and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's supervision and inspection of contract work, about security requirements, regulations, and other similar matters. The COR may invite other Government personnel involved in the work to attend this conference.

SECTION 01 30 00 Page 3

1.5.3 Discussion Items

The following is a sample list of items for discussion during the preconstruction conference; however, the Contracting Officer's Representative may modify this list or include additional items for discussion as conditions and the work require.

a. Authority of the Contracting Officer/Contracting Officer's Representative.

b. Contractor's Progress Schedule.

c. Correspondence Procedures.

d. Contractor Labor Standards Provisions.

e. Contract Modifications and Administrative Procedures.

f. Contractor's Administrative, Laydown and Storage Areas.

g. Procedures for Processing Submittals.

h. Payment Estimate Data and Procedures.

i. Contractor Utilities.

j. Security Requirements and Other Regulations, if applicable.

k. Government Furnished Equipment, if applicable.

l. Disposition of Salvage Property, if applicable.

m. Contractor Insurance Requirements.

n. Environmental Protection Plan.

o. Contractor Performance Evaluation.

p. Emergency and Safety Procedures.

q. Plant and Suitability to Perform the Work.

r. Contractor Required Notification Procedures.

s. Contractor's Submittal Register.

t. Contractor's Survey and Information Reporting Procedures.

u. Contractor's Quality Control Plan and Activity Hazard Analysis.

v. Turnover of Placement Areas After Dredging.

w. Tidal zoning values developed by NOS and, if necessary, bench mark descriptions for the project

1.6 OTHER MEETINGS DURING THE CONTRACT

Other meetings may be held after the Preconstruction Conference, for the

SECTION 01 30 00 Page 4 purpose to discuss concerns and deficiencies that may include the following:

a. Contractor's Site Safety and Health Plan.

b. Quality Control Plan.

c. Environmental Protection Plan.

d. Progress Schedule updates.

1.7 MINUTES OF MEETINGS

The Government will prepare minutes of all meetings and will provide the contractor with a signed original for review and concurrence. The minutes shall include all items discussed at the meeting and the Government will make all accepted corrections provided by the contractor and resubmit the corrected minutes to the contractor within seven days.

1.8 NOTICE TO PROCEED (NTP)

Notice to Proceed (NTP) will be issued shortly after completion of the preconstruction conference. If the Contractor has failed to submit required documentation, including but not limited to, the Accident Prevention Plan per Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS; the Quality Control Plan per Section 01 45 00.00 10 QUALITY CONTROL; and the Environmental Protection Plan per Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS; or has not yet received the Contracting Officer's conditional approval to work under an interim plan, the Contractor shall not proceed with the work and shall consider the work to be suspended in accordance with the Suspension of Work clause of the contract. While the Contractor is working under a conditionally accepted interim plan, funds may be retained from progress payments in accordance with the Payments Under Fixed Price Construction Contracts clause of this contract until such time as the Contractor submits an acceptable plan. If the Contractor does not submit an acceptable plan within a reasonable time, as determined by the Contracting Officer, the Officer may order the Contractor to suspend work. Any suspension order issued for the Contractor's failure to submit an acceptable plan(s) will not constitute unreasonable delay under the Suspension of Work clause and the Contractor will not be entitled to an equitable adjustment of either the performance period or contract price.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 30 00 Page 5

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 SUBMITTALS

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Approved Project Schedule

3.1.2 Schedule Status Reports

3.1.3 Default Terms

3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.2.1 PROGRESS SCHEDULE FORMAT

3.2.2 Level of Detail Required

3.2.2.1 Activity Durations

3.2.2.2 Critical Activities

3.2.2.3 Government Activities

3.2.2.4 Definable Features of Work Coding (FOW1, FOW2, FOW3)

3.2.3 Scheduled Project Completion and Activity Calendars

3.2.3.1 Project Start Date

3.2.3.2 Schedule Constraints and Open Ended Logic

3.2.3.3 Early Project Completion

3.2.4 Milestones

3.3 PROJECT SCHEDULE SUBMISSIONS

3.3.1 Preliminary Project Schedule Submission

3.3.2 Initial Project Schedule Submission

3.3.3 Periodic Schedule Updates

3.4 OWNERSHIP OF FLOAT

-- End of Section Table of Contents --

SECTION 01 32 01.00 10 Page 1

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Preliminary Project Schedule; G

Periodic Schedule Update; G

Initial Project Schedule; G

Submit a copy of the Initial Project Schedule at the Pre-Construction Conference indicating the measures and processes the Contractor will employ to produce an end product that complies with the contract requirements.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design (if any) and construction sequences, is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.1.1 Approved Project Schedule

Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress

SECTION 01 32 01.00 10 Page 2 payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

3.1.2 Schedule Status Reports

Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

3.1.3 Default Terms

Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.

3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS

The Contractor shall submit his Progress Schedule to the Contracting Officer for approval at the Pre-Construction Conference specified in SECTION ADMINISTRATIVE REQUIREMENTS. The Progress Schedule shall be submitted and certified as complete by the Contractor's Quality Control Representative in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed, arrival date of Contractor's plant to the job site, all activities scheduled prior to dredging, dredging start and completion dates, calendar days to completion of all work, and contract completion date.

The Contractor shall indicate on the chart the important work activities that are critical to the timely overall completion of the project. Key dates for important features or portions of work features are milestone dates and shall be so indicated on the chart.

3.2.1 PROGRESS SCHEDULE FORMAT

Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule and prepare the Project Schedule using the Precedence Diagram Method (PDM) OR prepare the Progress Schedule in the form of a Gantt Chart.

3.2.2 Level of Detail Required

Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

SECTION 01 32 01.00 10 Page 3

3.2.2.1 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

3.2.2.2 Critical Activities

The following activities shall be listed as separate line activities on the Contractor's Project Schedule and may be submitted on a separate sheet.

This list represents a partial lists and is not considered complete:

a. Submission and approval of Accident Prevention Plan.

b. Submission and approval of pipeline Routing.

c. Submission and approval of Quality Control Plan.

d. Coast Guard Notification and the U.S. Army Corps of Engineers notification.

e. Submittal of current marine plant certification and recent plant inspection.

f. Submission and approval of List of Floating Plant

3.2.2.3 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to:

a. Government surveys for payment

b. Required Contractor submittals for Government approval

c. Inspections required by the contract.

3.2.2.4 Definable Features of Work Coding (FOW1, FOW2, FOW3)

Assign a Definable Feature of Work Code to appropriate activities based on the definable feature of work to which the activity belongs. Definable Feature of Work is defined in Specification Section 01 45 00 QUALITY CONTROL. An activity shall not have more than one Definable Feature of Work Code. Not all activities are required to be Definable Feature of Work Coded.

3.2.3 Scheduled Project Completion and Activity Calendars

The schedule interval shall extend from NTP date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor.

3.2.3.1 Project Start Date

The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Project"( or NTP). The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was acknowledged, and a zero day duration.

3.2.3.2 Schedule Constraints and Open Ended Logic

Constrain completion of the last activity in the schedule by the contract

SECTION 01 32 01.00 10 Page 4 completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the contract completion date for the project, and with a zero day duration or by using the "project must finish by" date in the scheduling software. The schedule shall have no constrained dates other than those specified in the contract. The use of artificial float constraints such as "zero fee float" or "zero total float" are typically prohibited. There shall only be 2 open ended activities:

Start Project (or NTP) with no predecessor logic and End Project with no successor logic.

3.2.3.3 Early Project Completion

In the event the project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not approve an early completion schedule with zero float on the longest path. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.

3.2.4 Milestones

The schedule must include milestone activities for each significant project event including but not limited to: milestone activities for mobilization complete (including initial installation of pipeline); dredging complete.

3.3 PROJECT SCHEDULE SUBMISSIONS

Provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.

Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.

3.3.1 Preliminary Project Schedule Submission

Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP.