This document contains an industry day announcement and solicitation for the Norfolk Harbor and Channels Navigation Improvements project. The U.S. Army Corps of Engineers Norfolk District is seeking qualified firms to perform maintenance and new work dredging of the Channel to Newport News and Norfolk Harbor Inner Channels. Dredging is estimated to generate approximately 2.7 million cubic yards of material for the Channel to Newport News and 7.3 million cubic yards for the Inner Channels, to be placed at the Craney Island Dredged Material Management Area. The period of performance for the Channel to Newport News work will be approximately 270 days, while performance for the Inner Channels work is estimated at 540 days. Firms must register by November 9, 2021 to attend the virtual industry day on November 10, 2021, where the Corps will provide project details and address questions. The estimated value of the contract is between $25-100 million. The solicitation will be issued on SAM.gov and utilize definitive responsibility criteria regarding experience.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NORFOLK HARBOR
DEEPENING:
CHANNEL TO NEWPORT NEWS
AND INNER HARBOR
INDUSTRY DAY
Norfolk District 17 November 2021
AGENDA
• Project Overview
• Norfolk Harbor Channel to Newport News Deepening Scope, Dredged Material Characteristics
• Norfolk Harbor Inner Harbor Deepening Scope, Dredged Material Characteristics
• Craney Island Dredged Material Management Area – use and constraints
• City of Norfolk water main
• Requirement for Subcontracting Plan
• Environmental Considerations
• Period of Performance
• Proposed bid schedule and optional items
• Contracting method - Invitation for Bids with Definitive Responsibility Criteria
PROJECT HISTORY
• The cost sharing non-Federal sponsor is the Virginia
Port Authority (VPA)
• Project was authorized in 1986 to a depth of -55 ft
• Maintained to a controlling depth of -50 ft since 2007
• A General Reevaluation Report (GRR) re-validated project economics in June 2018 and allowed project to move into design for the nominal 55 ft channel
• Notable Milestones
• Chief’s Report Signed (June 2018)
• TSC-W Designs Complete in June 2019
• Award TSC-W October 2019
• Dredging Commenced December 2019
PROJECT OVERVIEW
Task Target Date Status Award Sediment Sampling Task Order 9/15/21 Completed 95% Draft Plans and Specifications (P&S) 10/25/21 Completed District Quality Review Complete 11/12/22 Completed
Agency Technical Review Complete 1/7/22
Industry Coordination Day 11/17/22 Sources Sought 10/04/22 Completed Sediment Sampling Data Interim Deliverable, District 404(b)1 CWA Determination for CIDMMA Placement Complete
1/12/22 Required before advertisement
RTA (BCOES Complete and AQ Plan Approved)* 2/11/22 Advertisement* 3/01/22 30 day advertisement Bid Opening* 3/31/22
Award* 5/3/22 Congressional Notification required prior to award
Notice to Proceed* 5/13/22 Construction Physical Completion on Channel to NN* 9 months Anticipated completion by Jan/Feb 2023
CRITICAL TASKS TO NEWPORT NEWS & INNER
HARBOR DREDGING
*Requires a New Start Decision, Executed PPA and sufficient Federal funding for the estimated Federal share of the contract.
CHANNEL TO NEWPORT NEWS/CIDMMA
• Channel to Newport News deepening being moved ahead of Inner Harbor work to provide needed material to raise CIDMMA dikes.
• Target project award date: May 2022
CHANNEL TO NEWPORT NEWS & NORFOLK HARBOR
INNER CHANNELS DEEPENING
SCOPE OF WORK
• May include full scope of deepening from a nominal depth of 50-feet MLLW to 55-feet MLLW for the two Norfolk Harbor channel elements:
• Channel to Newport News/ Preparation of the Upland Site
• Inner Harbor
• Pay depth includes 1-foot of advanced maintenance and 1-foot of allowable overdepth. A not-to-exceed depth is established allowing for an additional 1-foot of non-payable over-depth.
• Approximately 2.4 MCY of payable material is expected from the Channel to Newport News to be dredged over 270-day period of performance.
• Approximately 6.8 MCY of payable material is expected from the Inner Harbor to be dredged over a 540-day period of performance.
CHANNEL TO NEWPORT NEWS AND NORFOLK
HARBOR INNER CHANNEL DEEPENING
Schedule 1 Contract Work (Channel to Newport News Dredging)
• CLIN 1001 Mobilization/Demobilization
• CLIN 1002 Dredging to -55 feet MLLW - 1,645,600 CY
• CLIN 1003 Prepare Containment Area*
• CLIN 1004 Optional Dredging to -56 feet MLLW – 751,300 CY
Schedule 2 Contract Work (Norfolk Harbor Inner Channels)
• CLIN 2001 Mobilization/Demobilization
• CLIN 2002 Dredging to -54 feet MLLW – 3,747,700 CY
• CLIN 2003 Optional Dredging to -55 feet MLLW – 1,427,800 CY
• CLIN 2004 Optional Dredging to -56 feet MLLW – 1,633,100 CY
* may be completed through separate contract.
CHANNEL TO NEWPORT NEWS AND NORFOLK
HARBOR INNER CHANNEL DEEPENING
GEOTECHNICAL CONSIDERATIONS
SUMMARY OF AVAILABLE SUBSURFACE DATA
CHANNEL TO NEWPORT NEWS
In general, sandy material is between stations 86+00 and 324+00. Higher sand concentrations are located between stations 150+00 and 250+00.
SUMMARY OF AVAILABLE SUBSURFACE DATA
NORFOLK HARBOR INNER CHANNELS
Norfolk Harbor and Channels Navigation Improvement Project General Reevaluation Report (2018)
• Summarized and evaluated geotechnical information for the entire Norfolk Harbor Improvements project.
• Subsurface data obtained between 1981 and 2009
• Exploration methods: Vibracores, Gravity cores, Grab samples, Boreholes, and
Cone Penetration Test (CPT) probes.
• Material encountered in Norfolk Harbor Inner Channels: fat clays (CH) and elastic silts (MH) with isolated pockets of sands and silty sands.
PROJECT CONSTRAINTS
UTILITIES
36-inch Water Main Mitigation Measures
• A technical report titled “Norfolk Harbor and
Channels Deepening PED City of Norfolk Water Line Verification” by Moffat & Nichol
• No spud, No anchor zone
• Max allowable dredging depth is -57 feet
MLLW
• Communication and monitoring plan for dredging over the designated “No spud, No anchor” area. This plan shall be developed in close coordination with USACE, VPA and the City of Norfolk.
• Emergency Response Plan Submittal
36-inch Water Main (continued)
Virginia Natural Gas Pipeline Crossing
• Within the vicinity of Channel to Newport
News, top of pipeline elevation for the 24-inch pipeline is a minimum -83 feet MLLW.
• Several stitch points exist throughout the pipeline with a minimum of 10 feet of cover.
• Contractor to verify with Virginia Natural Gas exact locations.
Craney Island
• Intent is to capture sandy material in a confined location for immediate use through separate earthwork contract.
• General location for placement of dredged material from CNN.
• Fine grain material may be directed for placement outside of this confined area (likely North cell).
• Maximum daily production rate in a 24-hour period per cell is 22,500 cubic yards.
Craney Island
• Confined placement cell shall be constructed prior to CNN dredging operations commencing.
• Confined placement cell may be constructed by Dredging Contractor or through separate contract (TBD).
• Earthwork Contractor will be working in previously filled sub-cells concurrent with ongoing dredging operations.
• For CNN, dredged material placement will occur from east to west. Once a sub-cell is filled, a training dike will be created to prevent backwash of outfall pipe dredged material slurry.
Miscellaneous Constraints
• Mechanical Dredging
• Only allowed for CLEAN UP activities
• Material Placement in Craney Island Rehandling Basin (CIRB)
• Input limited to 150,000 CY for entire project
• Contractor is responsible for tolls at $5.43 per CY
• Cell Rotation Requirements at CIDMMA
• Not to exceed 22,500 CY of placed material in a 24-hour period per cell
• Government’s intent to limit the use of facility to one cell at a time
• NAVY Silencing Range (Norfolk Harbor Entrance Reach)
• Sta. 419+00 to 423+00
• Not included in the contract, no dredging
ENVIRONMENTAL CONSIDERATIONS
WATER QUALITY MONITORING
• Comply with requirements for Section 404 of the
Clean Water Act for discharges associated with confined disposal facilities.
• Manage spillboxes to ensure adequate ponding depth for effective sedimentation & to maximize use of the available effective weir length ensuring that only the clarified supernatant flows over the weir crest.
• The Contractor must maintain a daily average TSS concentration of less than 500 mg/l. The "less than" 500 mg/l TSS concentration is a threshold limit and is not a TSS target or goal.
WATER QUALITY MONITORING
• Environmental Testing and Upland Effluent
• TSS samples
• collected every 12 hours at the weird crest of each operating spillbox
• Hach 850/DR Colorimeter model #48450-00, program 94
"Suspended Solids", or approved equal
• 1000 ml wide mouth polyethylene bottle (Nalgene 2104-
0032 or equal)
• Logged digitally in Water Quality Database
• Visual inspection for clarified water required every 4 hours at each operating spillbox
• Spillboxes shall be maintained and weir boards adjusted so that only clarified water is released
PROTECTED SPECIES
• Native habitat for eagles, hawks, egrets, herons, pelicans, terns, plovers, dolphins, manatees, whales, sturgeon, & other wildlife protected by federal law or species of special concern for Virginia agencies
• Nesting birds may cause delays if found in placement/work area
• May 15 – August 30: Least Tern and Black Necked Stilt nesting season
• January – May: 1st Bald Eagle Nest in 2020
• The Contractor shall monitor the pond area in the active containment cell to ensure pond backwaters do not flood nesting areas
ENDANGERED SPECIES MONITORING
• Endangered Species Training provided by USACE
• Designate a look out to monitor visible action area from dredge plant:
• Look for parts/pieces of Atlantic sturgeon entrained in the cutterhead, floating around the dredge or collected in the inflow inside the upland placement area
• Document observations & notify COR ASAP
• Follow “Sturgeon Incidental Take Procedures”
• Fin clips
• Measurements, photos, specimen preservation
ENVIRONMENTAL PROTECTION PLAN (E.P.P.)
• Contractor must submit E.P.P. that includes:
• Spill Control Plan
• Hazardous Waste Controls
• Non-Hazardous Solid Waste
Disposal Plan
• Recycling & Solid Waste Disposal
Plan
• Contaminant Prevention Plan
• Historical, Archaeological, Cultural, Biological, & Wetland Resources Plan
CONTRACTING REQUIREMENTS
ACQUISITION STRATEGY
• Dredging contract will most likely be full and open Sealed Bid.
• Sources Sought issued in October 2021.
• Magnitude $25 - $100 M anticipated.
• C type contract will be awarded.
• Contract will be advertised as early as Spring 2021 following:
• Federal funding decision
• Execution of a Project Partnership Agreement between the
Department of the Army and Virginia Port Authority to start the Federal Construction Phase of the Project.
• Web-page: Beta System for Award Management (SAM) www.beta.sam.gov
NORFOLK DISTRICT SMALL BUSINESS
Mrs. Cherie Kunze Deputy for Small Business Programs Norfolk District, U.S. Army Corps of Engineers 803 Front Street Norfolk, VA 23510-1096
Phone: (757) 675-4428 cherie.a.kunze@usace.army.mil
OPEN DISCUSSION
OTHER SLIDES
PROJECT ELEMENTS
| Norfolk HARBOR deepening:��Channel to Newport News and Inner Harbor��industry day |
| agenda |
| Project History |
| Project Overview |
| Critical Tasks to Newport News & Inner Harbor Dredging |
| Channel to Newport News/CIDMMA |
| Channel TO NEWPORT NEWS & Norfolk Harbor inner channels deepening ��scope of WORK |
| Channel to Newport News and Norfolk Harbor Inner Channel Deepening |
| Channel to Newport News and Norfolk Harbor Inner Channel Deepening |
| Geotechnical considerations |
| Summary of available subsurface data�CHANNEL TO NEWPORT NEWS |
| Summary of available subsurface data�Norfolk Harbor inner channels |
| Project constraints |
| Project constraints |
| Project constraints |
| Project constraints |
| Project constraints |
| Project constraints |
| Project constraints |
| Project constraints |
| Environmental considerations |
| water Quality Monitoring |
| water Quality Monitoring |
| Protected species |
| Endangered species Monitoring |
| Environmental protection plan (e.p.p.) |
| Contracting requirements |
| Acquisition strategy |
| Norfolk District SMALL BUSINESS |
| Open discussion |
| Other Slides |
| Project Elements |