Effective Date: <Date>
Expiration Date: <Date> [as required]
CHECK https://ipdtdms.gsfc.nasa.gov
TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE.
National Aeronautics and Space Administration
Goddard Space Flight Center Greenbelt, Maryland
WFIRST-IC-SOW-0001, Revision [-, A]
Wide Field Infrared Survey Telescope (WFIRST), Code 448
Instrument Carrier (IC)
Flight Structure Fabrication
Statement of Work (SOW)
DRAFT
https://ipdtdms.gsfc.nasa.gov/
Instrument Carrier (IC) Flight Structure Fabrication WFIRST-IC-SOW-0001, Revision [-, A] Draft iii
Instrument Carrier (IC)
Flight Structure Fabrication
Statement of Work (SOW)
Review/Signature/Approval Page
Prepared by:
Approved by:
Electronic Approval available on-line at: https://ipdtdms.gsfc.nasa.gov iv
Preface
This document is a Wide Field Infrared Survey Telescope (WFIRST)
Configuration Management (CM)-controlled document. Changes to this document require prior approval of the applicable Configuration Control Board (CCB) Chairperson or designee.
Proposed changes shall be submitted to the WFIRST CM Office (CMO), along with supportive material justifying the proposed change.
In this document, a requirement is identified by “shall,” a good practice by “should,” permission by “may” or “can,” expectation by “will,” and descriptive material by “is.”
Questions or comments concerning this document should be addressed to:
WFIRST Configuration Management Office
Mail Stop 448
Goddard Space Flight Center
Greenbelt, Maryland 20771 v
Change History Log
Revision Effective Date Description of Changes
(Reference the CCR & CCB/ERB Approval Date) vi
Table of 17050s/TBRs/TBSs [optional]
Item No. Location Summary Individual/
Organization
Actionee
Due Date
0001 Table 1 All dates for reviews vii
Table of Contents
1 INTRODUCTION
1.1 Purpose
1.2 Scope
1.3 Background
1.4 Related Documentation
1.4.1 Applicable Documents and Drawings
1.4.2 Reference Documents
1.4.3 Document Requirements Flow Down for reference
2 PROGRAM MANAGMENT
2.1 Project Management
2.1.1 Project Manager
2.1.2 Resource Management
2.1.3 Schedule
2.1.4 Subcontract Management
2.1.5 Configuration Management
2.1.6 Information, Data, Records, and Storage
2.1.7 Export Control and Technology Transfer
2.1.8 Government Insight
2.1.9 Internal proprietary Documents
2.2 Communications
2.2.1 Weekly Meetings
2.2.2 Kick-off Meeting
2.2.3 Technical Interchange Meetings
2.2.4 Reviews
2.2.5 Site Access
2.2.6 Reports
2.3 Risk Management
3 ENGINEERING
3.1 System Design and Support Activities
3.1.1 Systems Engineering
3.1.2 Systems Management and Engineering
3.1.3 System Analysis and Allocations
3.1.4 Contamination Control and Analysis
3.2 Design and Development Engineering and Analysis
3.2.1 Design and Process Development
3.2.2 Design and Analysis of GSE and Subscale Test Articles
3.2.3 Spares, Redundancy, and Long Lead Procurement
3.3 Ground Support Equipment
3.4 Mechanical Ground Support Equipment
4 SAFETY AND MISSION ASSURANCE
5 ASSEMBLY, INTEGRATION AND TEST
5.1 Tube Fabrication Process Development
5.2 IC Development Test Assemblies
viii
5.3 IC Flight Assembly and Integration
5.4 Performance Verification and Design Qualification
5.5 Logistics
5.6 Post Delivery Support
5.7 Mechanical Ground Support Equipment
6 DELIVERY INSTRUCTIONS
6.1 GSFC Responsibilities
6.2 Hardware Deliverables
APPENDIX A ABBREVIATIONS AND ACRONYMS
List of Figures
No table of figures entries found.
List of Tables
Table 1 WFIRST Instrument Carrier Flight Fabrication Review Summary
1 INTRODUCTION
1.1 Purpose
This Statement of Work (SOW) defines those tasks necessary to fabricate, process development, and integrate the flight structure. This SOW also defines the test articles to verify the processes and analysis as defined in the Instrument Carrier Development Test Assemblies and Flight
Structure Specification WFIRST-IC-SPEC-0057.
This SOW also defines the tasks necessary to support the subsequent integration, development article fabrication and testing, evaluation, and validation of the IC flight structure at NASA
GSFC, including post-delivery support to payload and observatory integration and test.
In this document, a requirement is identified by “shall,” a good practice by “should,” permission by “may” or “can,” expectation by “will” and descriptive material by “is”.
[Text]
1.2 Scope
This Statement of Work (SOW) defines
a. Requirements that govern the development and delivery of the WFIRST Instrument
Carrier, associated test hardware, and associated ground support equipment to NASA’s
Goddard Space Flight Center.
b. Tasks necessary to develop test articles and test them in support of the WFIRST engineering design effort at NASA’s GSFC.
c. Tasks necessary to support the testing, evaluation, validation, and qualification of the IC flight structure at NASA’s GSFC
d. Tasks necessary to support the WFIRST Payload and Observatory integration and test.
1.3 Background
The IC structure design concept consists of a bonded frame assembly, incorporating square
Graphite Fiber Reinforced Plastic (GFRP) tubes, fingerplate gussets, very large highly loaded titanium forged and machined plug joints, and titanium clips. The material baseline is Hexcel’s
M55J/954-6 and T300/954-6 pre-preg. The IC structure requires predictable and repeatable thermal distortion from room temperature to 140 Kelvin.
1.4 Related Documentation
The latest versions of all documents below should be used. WFIRST documents can be obtained from URL: https://ipdtdms.gsfc.nasa.gov.
1.4.1 Applicable Documents and Drawings
The documents listed below are applicable to this SOW to the extent specified herein, and apply directly to the performance of the IC Flight Structure contract. These documents establish detailed specifications, requirements, and interface information necessary for the performance of the contract.
In the event of conflicting requirements between this SOW and the Applicable Documents, the
Contractor shall follow the following precedence:
GSFC drawings
This Specification
Statement of Work
Other WFIRST documentation
GSFC approved contractor documents
Other Government approved documents
Industry standard documents
Document Number Title
NASA-STD-5005 Standard for the Design and Fabrication of Ground Support
Equipment
NASA NPR 6000.1 Requirements for Packaging, Handling and Transportation for
Aeronautical and Space Systems, Equipment and Associated
Components
540-PG-8700.2.1 Design and Certification of Dollies, Stands, and Shipping Containers
WFIRST-IC-LIST-
IC FLIGHT STRUCTURE Deliverable Items List and Schedule
(DILS)
WFIRST-SYS-PLAN-
WFIRST Contamination Control Plan
WFIRST-SMA-REQ-
0032A
WFIRST Mission Assurance Requirements Document (MAR)
WFIRST-IC-SPEC-
Instrument Carrier, Flight Structure Specification
WFIRST-IC-SPEC-
Material Specification, 954-6 pre-impregnated tape
WFIRST-IC-SPEC-
Process requirement for adhesive bonding
WFIRST-IC-SPEC-
Process requirements specification for composite laminate fabrication
WFIRST-IC-SPEC-
Requirements for machining, drilling and trimming of composite structures
WFIRST-IC-SPEC-
Non Destructive examination requirement and defect acceptance criteria for non- metallics
WFIRST-IC-SPEC-
Surface Process Requirements for bond preparation and Re-cast
2242498 Raw Diamond Tube Stock
2242499 Raw square Tube Stock
2250600 Raw Gusset panel Stock
2250602 Plug Joint assembly
2250603 T joint assembly
2250604 Diagonal Assembly
TBD Flight structure assembly
1.4.2 Reference Documents
The following documents shall be considered supplemental information to this specification in so far as they are applicable to this type of engineering effort
Document Number Title
NPR 7123.1B NASA Systems Engineering Processes and Requirements
GPR 8700.6C Engineering Peer Reviews
1.4.3 Document Requirements Flow Down for reference
Document Flow down of Requirements
2 PROGRAM MANAGMENT
2.1 Project Management
A. The Contractor shall establish, implement and maintain a management system that effectively and efficiently plans, organizes, controls, and reports on the contract objectives, as well as provide the necessary leadership and technical coordination of the activities to ensure schedules and technical progress are consistent with the contract objectives.
B. As part of this effort, the Contractor shall provide traceability of cost, schedule and technical progress data for work being performed by the Contractor and all of its suppliers and subcontractors in support of this contract.
C. The Contractor shall provide a verification matrix for the Specification WFIRST-IC-
SPEC-0057 (CDRL-PM1)
D. The Contractor shall provide a verification matrix for this SOW (CDRL-PM2)
E. The Contractor shall provide a verification matrix for the DILS WFIRST-IC-LIST-0023
(CDRL-PM3)
2.1.1 Project Manager
A. The Contractor shall designate, by name, an IC Flight Structure Project Manager (PM).
B. The PM shall be responsible for leading the IC flight structure team per the requirements and tasks laid out in this document.
C. The PM is the primary point of contact and shall provide full visibility to NASA/GSFC on all aspects of performance covered by this SOW
D. The PM shall provide full visibility including the immediate disclosure of existing or potential problems along with their planned resolutions.
E. The PM will utilize the COR as the primary point of contact with the GSFC team.
F. The PM shall coordinate the Contractor efforts with that of its subcontractors, the
Government Furnished Property (GFP) providers if outside of NASA/GSFC, and
NASA/GSFC.
2.1.2 Resource Management
A. Contractor shall provide the necessary resources for monitoring, controlling, executing, and administering the IC flight structure development test assembly’s contract and subcontracts to ensure compliance with all contractual requirements.
The contractor shall provide a detailed Work Breakdown Structure (WBS) Diagram and dictionary plus all updates and revisions in accordance with the IC flight Structure development test assemblies Work Breakdown structure Diagram and Dictionary (CDRL
PM-4)
B. The Contractor shall provide visibility into cost and schedule performance at a frequency identified in the DILs WFIRST-IC-LIST-0023
C. The Contractor shall provide monthly financial management reports in the form of 533’s
(CDRL PM-5)
D. The Contractor shall provide all necessary facilities, tools, test equipment, materials, and processes required for the execution of this statement of work. That list would include, but is not limited to: clean rooms, thermal vacuum chambers, thermal cycle chambers, vibration facilities, and inspection facilities.
2.1.3 Schedule
A. The Contractor shall establish, implement, and maintain an integrated scheduling system consistent with their corporate procedures and approved by GSFC.
B. This Integrated Master Schedule (IMS) shall be provided for planning, controlling, modeling and specifying work activities throughout the project life cycle in accordance with the IMS (CDRL PM-6).
C. The Contractor shall use Microsoft Project to maintain compatibility with the WFIRST project team.
2.1.4 Subcontract Management
A. The Contractor shall provide quality, technical and programmatic oversight over all subcontracts
B. The contractor shall report their progress and performance to GSFC
C. The Contractor shall conduct surveillance of all subcontracts to ensure satisfactory performance
D. The contractor shall report the results of this surveillance to GSFC
E. The Contractor shall deliver component and subassembly inspection reports for all subcontracted items, in accordance with (CDRL PM-7).
F. The Contractor shall provide a description of the methods used to flow down requirements and manage sub-tier suppliers. Sub-tier supplier management shall use established processes, practices and procedures to reduce risk to the program and increase sub-tier performance. Sub-tier supplier performance measures shall be used to provide the Contractor and WFIRST with visibility to sub-tier supplier performance and overall program status
2.1.5 Configuration Management
A. The Contractor shall use a configuration management (CM) system to configuration control all documentation and hardware related to this SOW at all times
B. The Contractor shall deliver a Configuration Management Plan in accordance with
(CDRL PM-8).
C. The Contractor shall maintain configuration of all documents and drawings verifying the correct version is used throughout all phases of the contract.
D. Configuration verification shall be performed and documented as assemblies are incorporated into higher-level assemblies and at major project milestones (i.e. pre-environmental cycling and testing, pre-ship, etc.).
E. The contractor shall provide a list once every 2 weeks and at each review with all revision level documents and drawings that are being used for fabrication. (CDRL PM 9)
F. The Contractor shall have in place a Configuration Control Board (CCB) to review and approve changes to the configuration of deliverable items.
G. The CM system shall have a change classification and impact assessment process that results in all changes being forwarded to the GSFC COR. These changes are defined as any change that affects requirements, levied on the contractor by GSFC
H. The Contractor shall provide photo documentation of all tasks associated with the fabrication, assembly, integration, and test of all hardware governed by this SOW.
I. Photo documentation shall be in accordance with the Digital Image and Video Records
Document (CDRL PM-10).
2.1.6 Information, Data, Records, and Storage
A. Contractor shall establish a method to provide access by Internet to authorized WFIRST
Project personnel for working data products. A GSFC or Contractor electronic database system or combination of both can be used.
B. If a Contractor database is used, the Contractor shall maintain access protection for the system, including an access control list for all authorized WFIRST Project personnel.
C. The Contractor shall store all data relating to testing governed by this SOW in a database that is accessible to WFIRST personnel through the life of the contract
D. The Contractor shall ensure accessibility of Electronic and Information Technology (EIT) in compliance with the Workforce Investment Act of 1998 amended section 508 of the
Rehabilitation Act of 1973. This accessibility shall be in developing, procuring, maintaining or using EIT as required by this Statement of Work.
2.1.7 Export Control and Technology Transfer
A. Contractor and all subcontractors shall work with GSFC to determine and identify whether information, data and records that it produces is designated International Traffic in Arms Regulations (ITAR), Export Administration Regulation (EAR), proprietary, before releasing in the public domain.
B. The Contractor and all subcontractors shall prepare, submit, and update as necessary any
ITAR and Export Control licensing documentation required.
C. The Contractor and all subcontractors shall prepare, submit, and update as necessary any
EAR licensing documentation required.
2.1.8 Government Insight
A. Contractor shall be open to Government attendance, all Contractor and subcontractor internal data, reviews, audits, meetings and other activities within the scope of the contract. For access and insight activity, “Government” includes Government personnel and Government Contractor personnel.
B. The Contractor shall allow and enable the use of Non-Disclosure Agreements (NDA) with Government Contractors where appropriate.
C. For meetings not called out in the DILS document, the Contractor shall notify the
Contracting Officer and the COR of meetings, reviews or tests in sufficient time
(nominally five working days) to permit meaningful Government participation. All major meetings shall follow the DILs document WFIRST-IC-LIST-0023
2.1.9 Internal proprietary Documents
A. The Contractor shall inform the government of such documents if they need to be used in the execution of this statement of work.
a. The Contractor and the Government shall, on a case by case basis, determine if and how the proprietary documents can be applied to the execution of the work governed by this SOW.
b. The Contractor cannot withhold information related to the output or result of a methodology or procedure.
c. The Contractor cannot withhold methodology or procedural information from a failure review board.
2.2 Communications
A. Contractor shall provide regular communications and meetings with WFIRST project to discuss programmatic, financial, contracts, technical, and mission assurance status and issues.
2.2.1 Weekly Meetings
A. Contractor shall report technical and programmatic progress in weekly telecom meetings with the COR. In-person attendance is encouraged if Contractor personnel are on site at
Goddard.
B. The Contractor shall generate a brief email status to the COR to be used in reporting IC flight structure weekly status to the WFIRST Project.
2.2.2 Kick-off Meeting
A. The Contractor shall organize and hold a Kick-off Meeting at the Contractor’s facility prior to any activity identified in this SOW. Kick off meeting shall be held no later than
15 calendar days after contract award. The Contractor shall provide to the NASA/GSFC
COR a Kick-off Presentation Package and all other required deliverables. (CDRL PM -
11) The Kick-off Meeting shall address program management and quality assurance activities outlined in this SOW, as well as the performance and environmental requirements outlined in the WFIRST-IC-SPEC-0057 specification in sufficient detail to demonstrate understanding of contract requirements. At a minimum, the presentation package should cover the following areas:
Program Management organization Chart
Review of flow-down documentation (SOW, MAR, Spec, DILS, applicable documents
Review of key baseline assumptions
Quality Assurance including non- conformance processing
Design Description review of technical approach
Flight Heritage including review of applicable Lessons Learned
Review of Critical Processes
Facilities
Review of Potential Risks and risk mitigation plan
Review of key technical areas, confirmation of plans for TIMs
Schedule Review including critical path and margin
Review of Deliverable Items
2.2.3 Technical Interchange Meetings
A. Contractor shall provide a minimum of two Technical interchange meetings (TIM) one before the fabrication of the development tubes and lamina/laminate material testing. The second coming before the flight Structure MRR but after the Flight tubes and gussets are produced. TIM’s will come up as needed to resolve and work out detailed technical issues (e.g. interfaces). As much as possible, these TIMs will be held remotely, but in some cases, there will be technical matters where it will be more effective to conduct the
TIM via face-to-face meetings. Whenever possible, the location of these TIMs will alternate between GSFC and the Contractor location. As a planning guide, the number of
TIMs to be held at GSFC per year will be one, and the number to be held at the
Contractor facility would be one, each for duration of 2 days. Attendance to these TIMs will depend on the topic to be discussed and should be limited to the appropriate personnel. Some examples of specific TIMs include, but are not limited to:
Review of the mandrels and material before manufacturing
Table Top reviews
IC Working Groups
2.2.4 Reviews
A. Contractor and the Government shall coordinate to finalize the review dates during regular weekly meetings, as outlined in above weekly meeting Section.
B. The Contractor shall organize and hold two Manufacturing Readiness Reviews (MRR’s)) at the Contractor’s facility prior to Fabrication of flight articles.
a) The First (CDRL PM-12) shall be before fabrication of flight tubes and gussets requirement as a minimum the following:
Fabrication and inspection flow
Key individuals working on the fabrication
Facilities
Quality/Verification plan
Contamination control plan
Material certifications and test reports
Mandrel evaluation or overall GSE
Thermal cycle details
Schedule
b) The third (CDRL PM-13) would be before flight assembly begins and after all tubes, gussets, titanium nodes and clips are completed
Fabrication and inspection flow
Assembly flow
Key individuals working on the fabrication
Facilities
Quality/Verification plan
Contamination control plan
Piece part inspection and test reports
Mandrel evaluation or overall GSE
Schedule
C. The Contractor shall conduct Test Readiness Reviews (TRRs) prior to the start of each sub-scale test as described in the specification WFIRST-IC-SPEC-0057. A TRR for each planned test or series of tests ensures that the test article (hardware/software), test facility, support personnel, and test procedures are ready for testing and data acquisition, data reduction, and procedure and data control including configuration management and data storing and archiving. There shall be a minimum of 2 TRR’s (CDRL PM-14) one before any joint testing article such as double lap shear and one at the start of the joint development test articles. This could be one TRR that covers the three or more development test articles such as the plug joint. If only one TRR is performed for the joint development test articles then all the documentation required shall be presented for all test configurations.
D. The Contractor shall hold a Pre-Ship/ acceptance review at the Contractor's facility at the completion of verification tests and prior to the shipment of the flight instrument carrier to NASA/GSFC. This presentation shall demonstrate completion of all activities required for delivery of any hardware deliverable item to NASA/GSFC, and note any activities that are incomplete. In particular, the Contractor shall present the completed verification matrix that shows verification of all requirements and presents actual data (results of tests or analyses from subscale test articles and complete materials testing package) where applicable (CDRL PM-15). Any requirements that are not met shall be identified in the
Deviations/Waivers etc. list and discussed with NASA/GSFC during the review.
E. An End Item Data Package (EIDP) shall be made available for review during pre-ship reviews for each of the different hardware deliverables (CDRL PM-16). This package shall also be delivered with each end item with the level of detail required of that item.
F. The Contractor shall implement a system for tracking the status and resolution of Action
Items initiated during peer and formal reviews whose status shall be reported at the formal reviews.
The following table summarizes the current reviews. Please note that the dates shown here are to be used as a guide for planning and cost estimating. These dates are subject to change during the course of the development effort.
Table 1 WFIRST Instrument Carrier Flight Fabrication Review Summary
Reviews Tentative Date Days Location/Comments
Kickoff Meeting 15 days ACA 2 Contractors
IC CDR 4/20 2 GSFC
MRR Tube Fabrication TBS 1 Contractor
MRR Test articles fabrication
TBS
2 Contractor
MRR Flight
Fabrication
TBS
TRR for Double lap shears
TBS
2 Contractor
TRR for development test assemblies
TBS
1 Contractor
PSR/acceptance for
Flight units and spares
TBS
1 Contractor
2.2.5 Site Access
A. NASA shall be granted access to the Contractor’s and subcontractor facilities. Procedures for visit requests; contacts and authorizations will be coordinated with the IC flight structure PM.
2.2.6 Reports
A. Contractor shall provide programmatic reports as outlined in the Instrument Carrier Flight structure development test assemblies DILS (WFIRST-IC-SPEC-0057).
B. The Contractor shall provide a Monthly Status Report identifying the technical and schedule progress made by the Contractor compared to the goals established for the
Program (CDRL-PM-17). This report shall include but is not limited to:
a. Description of work performed, including updated milestone plan
b. Cumulative action item list showing open and closed action items with
ECD and assigned responsibility, as well as status of any open action items.
c. Description of significant problems and proposed solutions.
d. Risk and Opportunity management listing and status.
e. Status of all changes.
f. Material Review Board status.
g. Part and material status including sub tier supplier status.
h. SDRL delivery status.
i. Other items as defined in applicable sections of the MAR.
C. The Contractor shall provide electronically to the WFIRST project, when requested, within five business days, any IC flight structure and development test assemblies related plans, reports, technical memoranda, procedures, and analyses that are Contractor or subcontractor generated under this contract for the WFIRST mission, but not listed in the DILS.
2.3 Risk Management
A. Contractor shall present for approval a risk management plan in support of the IC flight structure.
3 ENGINEERING
3.1 System Design and Support Activities
3.1.1 Systems Engineering
A. Contractor shall establish and maintain a Systems Engineering Program for directing, specifying and overseeing the technical process development of the IC flight structure and IC flight structure GSE.
B. The Contractor shall conduct systems engineering and systems management efforts to manage and verify requirements, perform risk assessment, conduct systems analyses and trade studies, sponsor peer reviews, manage interface control documentation, manage systems budgets, and guide an integrated design and test process.
C. The Contractor shall develop and maintain a requirements traceability tool or utilize an existing tool and use that tool to demonstrate that the IC flight structures design meets all requirements.
D. For all IC flight structure activities, the Contractor shall use the International System of
Units (SI) with the following exceptions:
a) SI units with parenthetical English units are permitted for engineering and manufacturing drawings.
b) Angular measurement may be expressed in degree of arc or in an appropriate subdivision of degree of arc such as minute or second of arc
(arc-min or arc-sec).
c) Hardware that has been previously built, or of similar design heritage, may be specified in English units where use of metric equivalents would lead to additional risk and cost to the program.
3.1.2 Systems Management and Engineering
A. Contractor shall document the plan, method, and artifacts of verifying all controlled technical requirements including inspection, analysis, demonstration, and test.
B. The Contractor shall provide or maintain, if supplied by GSFC, a Drawing Tree that includes all IC flight structure and IC flight structure GSE drawings, plus updates and revisions, in accordance with (CDRL SE-1).
C. The Contractor shall provide and maintain, if supplied by GSFC, a Document Tree that includes all IC flight structure and IC flight structure GSE documents, plus updates and revisions, in accordance with (CDRL SE-2).
3.1.3 System Analysis and Allocations
A. Contractor shall provide the following Computer Aided Design (CAD), models, and other supporting analyses to the WFIRST Project. These models would include but not limited to models and analysis of the test article GSE, and the transport carrier.
3.1.4 Contamination Control and Analysis
A. During all phases of the project the Contractor shall comply with the contamination requirements documented in the WFIRST Contamination Control Plan (CCP) (WFIRST-
SYS-PLAN-0051).
B. The Contractor shall document compliance with the CCP (WFIRST-SYS-PLAN-0051) in accordance with the IC flight structure Contamination Control Implementation Plan
(CDRL SE-3).
C. The Contractor shall provide suitable access-limited, clean room facilities as specified by the WFIRST CCP (WFIRST-SYS-PLAN-0051), including high-speed Internet connections, for post-delivery processing of GFP hardware, data, and GSE by instrument provider personnel.
D. The Contractor shall provide “contingency” capability of a temporary clean bench/tent if required for offline GFP processing/testing.
3.2 Design and Development Engineering and Analysis
3.2.1 Design and Process Development
A. The contractor shall provide support for all process development including
Square/diamond tube fabrication, circular and damming of bond areas, repair and assembly procedures
B. The contractor shall provide documented procedures for the following:
a. Tube fabrication meeting the dimensional tolerances required on drawings. This could be in the form of a traveler with inspection documentation to support(CDRL SE-4)
b. Development report on circular bonding and damming processes which includes taper bonds, any testing performed to identify process and inspection reports.
(CDRL SE-5)
c. NDE procedures and any standards that were produced for inspection process.
(CDRL SE-6)
d. Inspection reports both dimensional and NDE documentation process that has been approved by WFIRST (CDRL SE-7)
3.2.2 Design and Analysis of GSE and Subscale Test Articles
A. The Contractor shall provide all personnel, facilities, and support necessary to design and analyze a transportation unit and testing GSE that will maintain all thermal, mechanical, and structural requirements from the IC flight structure Specification (WFIRST- IC-
SPEC-0057.
B. The Contractor shall provide design and analysis documentation showing the
GSE/transportation/handling equipment will not harm the flight structure or effect the testing of the development joints in an adverse way
3.2.3 Spares, Redundancy, and Long Lead Procurement
The following requirements apply to the IC flight structure.
A. Contractor shall qualify, test, and calibrate the spare parts to the same standards as the flight articles consistent with their spared level of assembly.
B. The Contractor shall provide a Spare Parts Plan and List plus all updates and revisions, in accordance with (CDRL SE-8).
C. The Contractor shall identify critical procurements of long lead materials and items that must be procured in order to support the IC flight structure master schedule.
3.3 Ground Support Equipment
This section applies to Contractor-supplied GSE.
A. The Contractor shall design and certify Dollies, Stands, and shipping containers per 540-
PG-8700.2.1C, Design and Certification of Dollies, Stands, and Shipping Containers.
B. GSE shall include deliverable items listed in the contract as well as equipment required for the Contractor’s own use.
C. The contractor shall provide any certifications required such as proof tests and analysis performed on the GSE
D. The Contractor shall provide the GSE for use by the Government as requested during IC flight structure integration and testing.
E. The Contractor shall design, test and certify GSE that interfaces directly to the flight hardware per the requirements in the IC flight structure (WFIRST- SPEC-17050) and the
MAR.
3.4 Mechanical Ground Support Equipment
A. The IC flight structure Contractor shall be responsible for Mechanical GSE (MGSE) required to integrate and move the IC flight structure. The functions include: assembly integration and test work-stands, lifting, transporting, and storing, as well as environmental fixtures for post curing.
4 SAFETY AND MISSION ASSURANCE
A. The Contractor shall comply with the applicable safety and mission assurance requirements and the corresponding Data Item Descriptions (DIDs) documented in subsections 3.1 through 3.6, 4.1, 4.2.1, 4.2.2, 6.5, 6.7, 6.8, 6.9, 6.11, 6.12 and sections 9 through 11, subsection 12.3, and sections 13 through 14 of the WFIRST Mission
Assurance Requirements (MAR) (WFIRST-SMA-REQ-0032).
a. Note* Section 9 identifies electrical requirements and this can be negotiated depending on design
B. All Close Calls and Mishaps per NPR 8621.1, major non-conformances, and test failures shall be reported to the COR and WFIRST Chief Safety and Mission Assurance Officer
(CSO) immediately and followed up with a written report within 24 hours of the occurrence.
C. The Contractor shall prepare and provide inputs to the WFIRST Project Safety Manager for the System Safety requirements defined in section 5 of the MAR, to identify, evaluate, and eliminate or control hazards in support of MAR DIDs 5-1 through 5-6
D. The Contractor shall plan for Government Mandatory Inspection Points (GMIPS). The
Contractor shall provide work instructions, procedures, drawings, etc. that are appropriate for the activities. The following are examples of activities that may be subject to GMIPs.
- Unit and component level assembly – witness final assembly;
- Mechanical – final assembly and acceptance test;
- Rework and repairs to flight hardware;
- Pre-Ship Inspection/Data Review, etc.
5 ASSEMBLY, INTEGRATION AND TEST
The contractor shall perform all requirements listed in Specification document WFIRST-IC-
SPEC-0057 and this SOW. The contractor shall deliver the completed Flight structure to GSFC where the structural qualifications tests will be performed. The IC flight structure Assembly, and
Integration, applies to one flight unit only. The assembly and testing applies to development tests assemblies.
5.1 Tube Fabrication Process Development
The contractor shall provide process development for the Tube fabrications. The contractor shall work with the WFIRST project to develop the tube fabrication process that will be used on the flight tube fabrication: Once the process is established the same GSE, personnel, and process shall be used to produce the following: Flight tubes will not be fabricated until the WFIRST project has received both diamond and square tubes
A. The contractor shall fabricate three square tubes meeting all the requirements on drawing
2242499.
B. The contractor shall fabricate three diagonal tubes that meet all the requirements of drawing 2242498
5.2 IC Development Test Assemblies
A. Contractor shall develop and provide a component assembly and test plan for the joint development test assemblies (CDRL IT-1).
B. The Contractor shall generate work instructions for hardware assembly as part of the end item data package. These work instructions shall be available for review by GSFC at any time.
C. The Contractor shall assemble the development test assemblies’ hardware per the approved work instructions.
5.3 IC Flight Assembly and Integration
A. Contractor shall develop and provide an assembly plan for the flight structure. This will be broken down into manageable timeframes taking into consideration pot life and out times of the materials being used. (CDRL IT-2).
B. Contractor shall accommodate the IC delivery schedule or identify any issues.
C. The Contractor shall provide appropriate space for hardware and associated GSE.
D. The Contractor shall integrate all flight hardware using approved procedures, tools and
GSE.
5.4 Performance Verification and Design Qualification
A. A Verification Plan shall be generated by the Contractor to describe the details of how the analyses, inspections, and verification tests identified in the WFIRST-IC-SPEC-0057
Specification will be performed (CDRL IT-3). Verification tests shall demonstrate the item meets all of the specified performance requirements over the specified range of environments, measure performance parameters and reveal inadequacies in manufacturing and assembly such as workmanship or material problems. Any requirement that exceeds previous qualification test data shall be presented to the
NASA/GSFC COR as part of the planning process for evaluation and a possible delta qualification test.
a. The plan shall state the purpose of each test, state acceptance criteria, describe in detail the test method, set up, instrumentation, data analysis methods (if applicable), and give the test sequence. The plan shall include a verification matrix summarizing how all requirements are verified (analysis, inspection, test, per the definitions in the Spec.), and listing all tests that will be performed on the
IC flight Structure.
b. This plan shall be a Contractor controlled document and shall indicate all changes made after the initial approval by the NASA/GSFC COR. After Verification Plan approval, no changes shall be made without written NASA/GSFC COR approval.
B. The Contractor shall generate individual test plans plus updates and revisions for each verification test performed on the development test assemblies, in accordance with the
Individual Test Plans (CDRL IT-4).
C. The Contractor shall provide a method whereby GSFC can review and comment on the test plans.
D. The Contractor shall generate individual test procedures plus updates and revisions, in order to implement the test plans and to provide input to WFIRST payload and observatory level test procedures, in accordance with the Test Procedures (CDRL IT-5).
E. The Contractor shall provide a method whereby GSFC can review and comment on the test procedures.
F. The Contractor shall perform tests per the approved test procedures. These tests include but are not limited to:
a. Functional and Performance
b. Structural and Mechanical
c. Alignment and Calibration
G. The Contractor shall hold a post-test review with GSFC prior to test disassembly. The criteria for test disassembly should be clearly defined in the test plan.
H. The Contractor shall generate Test Reports per (CDRL IT-6).
5.5 Logistics
A. The Contractor shall comply with NASA NPG 6000.1H, Requirements for Packaging, Handling and Transportation for Aeronautical and Space Systems, Equipment and
Associated Components when handling and transporting hardware, documentation, software and Ground Support Equipment among test facilities, Goddard Space Flight
Center (GSFC), and the launch site.
B. The Contractor shall provide an IC flight structure, and GSE Transportation Plan in accordance with the Transportation Handling Plan and Procedures (CDRL IT-7).
C. The Contractor shall provide the shipping container and environmental monitoring equipment to demonstrate that no transportation design loads are exceeded.
D. The Contractor shall ensure that environmental requirements (per the IC flight structure
WFIRST- SPEC-17050) and the Contamination Control (WFIRST-SYS-PLAN-0051)) are met while shipping.
5.6 Post Delivery Support
A. Contractor shall support receiving of the structure with post-delivery NDE of all joints.
This will be verification from pre and post shipment on all bonded joints. Activities include, but are not limited to set up and instruct technicians at GSFC for use of the
Contractor’s devices. Specifically any reset and refurbishment that will need to be performed at GSFC For the purpose of this SOW the Contractor shall assume 160 hours of work.
5.7 Mechanical Ground Support Equipment
B. The IC flight structure Contractor shall be responsible for Mechanical GSE (MGSE) required to integrate and move the IC flight structure. The functions include: assembly integration and test work-stands, lifting, transporting, and storing, as well as environmental fixtures for post curing.
6 DELIVERY INSTRUCTIONS
A. Except as otherwise provided in this Contract, the point of inspection, acceptance and delivery of all DILS items deliverable under this Contract shall be the NASA Goddard
Space Flight Center, Greenbelt, Maryland 20771.
B. All such deliverables shall be packaged, packed, boxed or crated in such a manner to ensure safe delivery and shall be shipped prepaid and at the Contractor’s expense to the point of delivery.
C. The IC flight structure shall be shipped from the Contractor in a shipping container designed and tested by the contractor. The point of delivery for the IC flight structure shall be at GSFC, Maryland.
D. Residual flight and non-flight hardware shall be identified and GSFC will recommend disposition
6.1 GSFC Responsibilities
A. GSFC is responsible for the final designs of the items listed in section 6.2.
B. GSFC shall provide technical direction and shall be fully responsible for the final design of the Instrument Carrier Flight Structure.
C. GSFC shall provide all required documentation to the Contractor.
D. GSFC shall be responsible for documenting all changes
E. GSFC provided documentation as needed and providing said changes to the Contractor.
6.2 Hardware Deliverables
The deliverables outlined in the Statement of Work are described in the Instrument Carrier
Development Test Assemblies and Flight Structure Deliverable Items List and Schedule (DILS) document (WFIRST-IC-LIST-0023).
A. 2242499 Three square development tubes (HW-1)
B. 2242498 Three diamond development tubes(HW-2)
C. Instrument Carrier Flight Structure (HW-3)
D. Shipping container (HW-4)
E. Spare tubes (HW-5)
F. Spare Gussets (HW-6)
G. Repair panels (HW-7)
H. Completed Test Articles (HW-8)
I. Trials for adhesive processing (HW-9)
a. These would include but not limited to Plexiglas trials, repair procedures and articles, all broken test articles, NDE Standards, and any other testing items
Appendix A Abbreviations and Acronyms
Abbreviation/
Acronym
DEFINITION
ACA After Contract Award
AI&T Assembly, Integration, and Test
CAD Computer Aided Design
CCB Configuration Control Board
CCP Contamination Control Plan
CCR Configuration Change Request
CDR Critical Design Review
CDRL Contract Deliverables Requirement List
Abbreviation/
Acronym
DEFINITION
CM Configuration Management
CMO Configuration Management Office
COR Contracting Officer’s Representative
DILS Deliverable Items List and Schedule
EAR Export Administration Regulation
EGSE Electrical Ground Support Equipment
EIT Electronic and Information Technology
EMC Electromagnetic Compatibility
EMI Electromagnetic Interference
ESD Electro-Static Discharge
FEM Finite Element Model
GFP Government Furnished Property
GSE Ground Support Equipment
GSFC Goddard Space Flight Center
I&T Integration and Test
IBR Integrated Baseline Review
IC Instrument Carrier
ICD Interface Control Document
IM Integrated Modeling
IMS Integrated Master Schedule
ITAR International Traffic in Arms Regulations
MAIP Mission Assurance Implementation Plan
MAR Mission Assurance Requirements
MGSE Mechanical Ground Support Equipment
MRB Material Review Board
PDR Preliminary Design Review
PM Project Manager
PSR Pre-Ship Review
SI International System of Units
SMA Safety and Mission Assurance
SOW Statement of Work
STOP Structural-Thermal-Optical
TGSE Thermal Ground Support Equipment
TIM Technical Interchange Meeting
TRR Test Readiness Review
WBS Work Breakdown Structure
WFIRST Wide Field Infrared Survey Telescope