This document contains a solicitation for tree clearing services at Naval Air Station Pensacola, Florida. The Navy is seeking quotes to remove trees and brush from four clear zones surrounding runways at Sherman Field, with work to include surveying, permitting, wetland delineation, erosion control planning, timber cutting, brush mulching, grading, and stabilization. The base period of performance is 365 days from award with optional 60-day periods for additional clear zones. Quotes are due by September 7th, 2022 with award anticipated on September 15th. The contract is set aside for small businesses only and has a total estimated value between $2-5 million, with fixed unit prices required for the base and option periods covering clear zones for runways 25, 1, 19, and 7. A mandatory site visit will be held between August 25-31st.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT COST PROPOSAL BREAKDOWN
CONTRACT COST PROPOSAL BREAKDOWN
BREAKDOWN OF DIRECT COSTSDATE:
FEAD PENSACOLASOLICITATION #:N6945022R0146
ITEMS OF WORK FORQTYUNITMATERIALLABOROEQUIPMENT
TITLE/DESCRIPTION:Sherman Airfield Clear Zone Tree ClearancePrime ContractorUnit CostTotal CostUnit CostTotal CostRQtyRateTotal
DATE:1.00.0000.00000.000
2.000
PRIME CONTRACTOR:3.000
CONTRACTOR'S WORKRevisions/Comments4.0000.000
1.Direct Materials|05.000
2.Sales Tax on Materials0.00%of line 10.00%0|6.000
3.Direct Labor|0|7.000
4.Insurance, Taxes, & Fringe Benefits0.00%of line 30.00%0|8.000
5.Rental Equipment|0|9.000
6.Sales Tax on Rental Equipment0.00%of line 50.00%0|10.000
7.Equipment Ownership & Operating Expenses|0|11.000
8.Subtotal||||||||||||||||||||||||||||||||||||||||||||||||||||||012.000
9.Prime's Field Office Overhead0.00%of line 80.0%0|||||||||||||||||||||||||||||||||15.000
10.SUBTOTAL (add lines 8 and 9)||016.000
Prime's Remarks:17.000
18.000
25.000
DIRECT Prime Contractor's TOTALS00RTotal (Rental)0
OTotal (Owned)0
SUBCONTRACTOR'S NAME:ITEMS OF WORK FORQTYUNITMATERIALLABOROEQUIPMENT
11.Direct Materials|0|SubcontractorUnit CostTotal CostUnit CostTotal CostRQtyRateTotal
12.Sales Tax on Materialsof line 110|1.00.0000
13.Direct Labor|0|2.000
14.Insurance, Taxes, and Fringe Benefits0.00%of line 130.00%0|3.000
15.Rental Equipment|0|4.000
16.Sales Tax on Rental Equipment0.00%of line 150.00%0|5.000
17.Equip. Ownership and Operating Expns|0|6.000
18.SUBTOTAL (add lines 11-17)||07.000
19.Field Overhead0.00%of line 180.00%0|8.000
20.SUBTOTAL (add lines 18&19)||09.000
21.Home Office Overhead0.00%of line200.00%0|10.000
22.Profit0.00%of line 200.00%0|11.000
23.SUBTOTAL (Add Lines 20-22)||012.000
Sub's Remarks:13.000
14.000
23.000
000
DIRECT Subcontractor's TOTALS00RTotal (Rental)0
OTotal (Owned)0
SUBCONTRACTOR'S NAME:
24.Direct Materials|0|ITEMS OF WORK FORQTYUNITMATERIALLABOROEQUIPMENT
25.Sales Tax on Materials0.00%of line 240|1.SubcontractorUnit CostTotal CostUnit CostTotal CostRQtyRateTotal
26.Direct Labor|0|2.00.0000.0000
27.Insurance, Taxes, and Fringe Benefits0.00%of line 260|3.000
28.Rental Equipment|0|4.000
29.Sales Tax on Rental Equipment0.00%of line 280.00%0|5.000
30.Equip. Ownership and Operating Expns|0|6.000
31.SUBTOTAL (add lines 24-30)||07.000
32.Field Overhead0.00%of line 310|8.000
33.SUBTOTAL (add lines 31&32)||09.000
34.Home Office Overhead0.00%of line0|10.0.00000
35.Profit0.00%of line 330|11.000
36.SUBTOTAL (Add Lines 33-35)||012.000
Sub's Remarks:13.000
14.000
23.000
000
DIRECT Subcontractor's TOTALS00RTotal (Rental)0
OTotal (Owned)0
SUMMARY
37.Prime Contractor's Work (from line 10)|0|
38.Sub-contractor's Work (from line 23&36)|0|
39.SUBTOTAL (add lines 37 and 38)||0
40.Prime's Field Office Overhead on sub.0.00%of line 380.00%0|
41.Prime's Home Office Overhead0.00%of line 370.00%0|Prime Contractor Name:_____________________________________
42.SUBTOTAL (add lines 39-41)||0
43.Prime's Profit0.00%of line 390.00%0|
44.SUBTOTAL (add lines 42 - 43)||0
45.Prime Contractor's Bond Premium0.00%of line 440.00%0|___________________________________________________________________________________
46.TOTAL COST (Add Lines 44 and 45)||0Signature & Title of preparerDate