N6945021Q0019.pdf
PDF 680 KB Posted
- Attached to
- B-4792 Sewer Line at NAS Kingsville, TX
- Solicitation number
- N6945021Q0019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6945021Q0019-0003.pdf | ||
| N6945021Q0019-0002.pdf | ||
| N6945021Q0019-0001.pdf | ||
| NASK Map Location of Soil Stockpile.pdf | ||
| NASK B4792 Sewer Line Area Utilities.pdf | ||
| Enclosures.pdf | ||
| KV Pass Application SECNAV 5512-1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PWD KINGSVILLE
INSPECTOR OF RECORD
201 NIMITZ AVE, BLDG 4711
KINGSVILLE TX 78363-5103
TEL: 361-516-6044 FAX:
REQUEST FOR QUOTATIONS
(THIS IS NOT AN ORDER) 1
PAGE OF PAGES
1. REQUEST NO. 2. DATE ISSUED RATING
DO-C2N6945021Q0019 29-Jun-2021
5a. ISSUED BY
8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE
IMPO RTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State, and local taxes)
ITEM NO.
(a)
SUPPLIES/ SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e) (f)
SEE SCHEDULE
AMOUNT
% No. %
NO TE: Additional provisions and representations [ ] are [ ] are not attached.
13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION
16. NAME AND TITLE OF SIGNER (Type or print) ( Include area code)
TELEPHONE NO.
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)
PREVIOUS EDITION NOT USABLE Prescribed by GSA
FAR (48 CFR) 53.215-1(a)
THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE
6. DELIVER BY (Date)
SEE SCHEDULE
AND/OR DMS REG. 1
UNDER BDSA REG. 2
4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE
REQUEST NO.
NAVFAC ENGINEERING SYSTEMS COMMAND SE
PWD CORPUS CHRISTI
8851 OCEAN DRIVE, BLDG 19
CORPUS CHRISTI TX 78419-5021
9. DESTINATION (Consignee and address, including ZIP Code)
7. DELIVERY
[ ]X FOB
DESTINATION
[ ] OTHER
(See Schedule)
05-Aug-2021(Date)
PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.
361-961-3397JOEL OVERSON
(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:
d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS
N6945021Q0019
Section SF 30 - BLOCK 14 CONTINUATION PAGE
STATEMENT OF WORK
GENERAL INFORMATION:
Solicitation Number: N6945021Q0019 Set Aside: 100% Total Small Business NAICS Code: 237110, Size standard in Millions: $39.5M
This announcement constitutes the only solicitation; no separate written solicitation will be issued.
BASIS FOR AWARD:
The Government will award a contract using the simplified acquisition procedures of FAR Subpart 13.1 to the offeror whose quotation, conforming to the solicitation, offers the lowest price and is determined responsible under FAR Subpart 9.1. The Government reserves the right to not award if a contract award is not in the best interest of the Government.
Target Price Range is less than $250K
The SF18 should be received no later than 1:00 p.m. local time on 05 August 2021. The completed SF18 should be emailed to joel.overson@navy.mil as well as any requests for clarifications or information concerning the solicitation. Requests for clarification and information concerning the solicitation must be provided in writing.
Any amendments to the solicitation will be posted in the Contract Opportunities module of beta.sam.gov website for the mutual benefit of all interested parties.
Acknowledgement of all amendments is mandatory by returning the SF30 appropriately filled out for each amendment issued, if applicable.
PERIOD OF ACCEPTANCE
The offeror agrees to hold its offer firm for 90 calendar days from the date specified for receipt of offers. The anticipated award date is contingent upon receipt of necessary funding.
INCURRED EXPENSES
The Government is not responsible for any costs incurred or associated with preparation and submission of a quote in response to this solicitation.
ADDITIONAL INFORMATION:
Bidders shall sign solicitation documents and all applicable Representations and Certifications shall be completed. FAR provision 52.222-22 Previous Contracts and Compliance Reports contained in this solicitation shall be filled out and returned unless already filled out in their Reps & Certs section of their profile in the System of Award Management (SAM) website. Be advised that mailto:joel.overson@navy.mil all interested parties must be registered in the SAM Database in order to receive payment for work/services rendered to the Government as the result of an award.
SITE VISIT INFORMATION:
One site visit will be held to ensure all potential offerors have uniform information in order to make an accurate proposal. Site visit will be conducted on Thursday, 8 July 2021 at 9:00 a.m. local time at NAS Kingsville. Meet at McCoy’s at the intersection of Carlos Truan Blvd. and US 77. Site visit POC is below. All potential offerors are encouraged to attend the site visit to perform an inspection of the size and current layout.
Offerors are expected to satisfy themselves as to the general and local conditions that may affect the cost of the performance of the work to the extent that such information is reasonably obtainable. It is considered impractical to determine, without inspection, the exact nature of the work and site conditions under which the work is to be performed.
To attend please contact the Site Visit POC:
Mr. Hector Gomez hector.a.gomez@navy.mil 361-516-6370
The contractor may require, and should have, their own ear plugs, safety glasses and safety shoes to have access to the work site.
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND SOUTHEAST
PUBLIC WORKS DEPARTMENT
NAVAL AIR STATION, BLDG. 4711
201 NIMITZ AVE., SUITE 103
KINGSVILLE, TEXAS 78363-5119
B4792 INSTALL NEW SANITARY SEWER LINE AND 2-
WAY DOUBLE BARREL CLEANOUTS
1. GENERAL REQUIREMENTS
1.1. The contractor shall provide all labor, materials, equipment, tools, transportation and management necessary to accomplish the project. Report any unforeseen findings to the attention of the Contracting Officer’s Representative (COR) assigned to the project. COR is the individual designated by as the authorized representative of the
Contracting Officer. The COR is responsible for monitoring performance and technical management of the effort required and should be contacted regarding mailto:hector.a.gomez@navy.mil questions or problems of a technical nature. The COR will be the CM, ET, and/or
PAR assigned to the project. Materials mentioned herein shall be the same or equal to specified manufacturer and or in quality. Contractor shall verify provide design, procurement, demolition, construction, and installation services.
2. SCOPE OF WORK:
2.1.1. The contractor shall refer to Enclosure (1) for the existing location of BLDG 4792’s holding tank, sewer lines, and existing cleanouts on NAS Kingsville, TX.
2.1.2. The contractor shall provide and install new sanitary sewer line for B4792. The contractor shall install approximately 710 LF of 8” diameter Sch 80 PVC and tie in to existing lift station. The contactor shall refer to enclosure (2) for approximate location of the new 8 in sewer line.
2.1.3. The contractor shall provide and install (6) - 8 in. Hub x SDR PVC 2-Way Double
Barrel Cleanouts, approximately 100ft apart. The contactor shall refer to enclosure (2) for approximate locations of the 8 in. Hub x SDR PVC 2-Way Double Barrel
Cleanouts.
2.1.4. The contractor shall install first, new 4” to 8” PVC Adapter then (2) 8” SC 80 45
Degree Elbow(s) separated by 3ft of 8” Sch 80 pipe. All work can consist of hydro excavation, normal excavation or a combination of.
2.1.5. Testing the sewer lines: The contractor shall test the sewer lines. The contractor shall air test at 4 PSI, or water exfiltration tests are required on building sewer lines including dry lines.
2.1.6. Backfill and fill Material: ASTM D2487, classification GW, GP, GM, SW, SP, SM, with a maximum ASTM D4318 liquid limit of 35, maximum ASTM D4318 plasticity index of 12, and a maximum of 25 percent by weight passing ASTM D1140, 75 micrometers No. 200 sieve. Bedding Material Use coarse sands and gravels with maximum particle size of 1.5 inches, including various graded sands and gravels containing small percentages of fines, generally granular and non-cohesive, either wet or dry. Soil Types GW, GP, SW, and SP are included as specified in ASTM D2487.Use coarse sands and gravels with maximum particle size of 1.5 inches, including various graded sands and gravels containing small percentages of fines, generally granular and non-cohesive, either wet or dry. Soil Types GW, GP, SW, and SP are included as specified in ASTM D2487.
2.1.7. The contractor shall grade the finished surface to provide positive drainage while maintaining current drainage patterns. Grading shall be performed in accordance with
UFC 3-201-01 Civil Engineering.
2.1.8. Contractor shall provide erosion and sediment control features in order to protect the storm system and adjacent areas from sedimentation.
2.1.9. The existing right of way shall be used to not interfere with other utilities. GPRS required.
2.1.10. All 8” sewers shall be installed on a 0.5% slope or greater.
2.1.11. The contractor shall remove the existing holding tank and residual 4” PVC sewer line and backfill according to Sections 2.1.6-2.1.8 above.
2.1.12. Enclosure (3) is a reference of the current lift station elevation.
1. Material/Equipment Specification
1.1.1. The pipe material shall be PVC. Any other material proposed must be approved by Table I of the UFGS. 3-240-01,3-240-03,3-240-07
1.1.2. Mohole’s UFC 4-150-02\
1.1.3. PVC ATM D3034, ASTM F679.
2. APPLICABLE REFERENCE DOCUMENT
2.1. Federal Unified Facilities Criteria (UFC), State and/or Local regulations: the most stringent standard shall prevail.
2.2. Closeout Submittals UFGS-01 78 00
2.3. American National Standards Institute (ANSI) National Fire Protection Association
2.4. American Society of Testing and Materials
2.5. EM 385-1-1 dated November 2014 “Safety and Health Requirements Manual”
2.6. 29 CFR 1910 (OSHA) “2015 General Industry Regulations”
2.7. UFC 3-240-01 WASTEWATER COLLECTION, WITH CHANGE 2
2.8. UFGS 22 00 00 PLUMBING, GENERAL PURPOSE
2.9. UFGS 33 30 00 SANITARY SEWERS
3. PRE-AWARD SITE VISIT
3.1. Prior to submitting proposals, prospective bidders can and will be expected to visit the job site, inspect the work in place and satisfy themselves as to the character and amount of work to be accomplished. Bidders will refer to Federal Biz Ops advertisement for the scheduled site visit time and date. Failure by the Contractor to familiarize oneself with available information regarding site conditions prior to bid shall not relieve the Contractor from the responsibility of successfully completing the work. It is very important bidders contact the COR for a day pass application
(SECNAV 5512/1) enclosed in the solicitation to fill in within 10 days of the scheduled site visit. Failure to comply may mean denial to attend the site visit scheduled.
4. CONTRACTOR PERSONNEL BASE ACCESS REQUIREMENTS
4.1. The base access protocol implemented is the DBIDS system. The system provides background checks of contractor personnel. A personnel badge that affords base access for one year shall be issued to each Contractor employee that meets background check criteria. There is no cost for contractors to sign up and participate in the DBIDS system except for the time it takes to sign up. Costs to participants are recaptured through increased productivity of their employees due to the reduction in waiting times at the Pass and Identification Office and Entry Control
Points (ECP). Contractors are required to participate in the DBIDS Program.
5. PERFORMANCE PERIOD
5.1. Background checks and requests for daily passes must be filled in (SECNAV 5512/1) and submitted to the assigned COR a minimum 10 days prior to any new work.
5.2. Performance Period: Performance period shall be 90 calendar days. The performance period begins upon the date of award of the contract and ends on the contract completion date (CCD). The performance period shall include pre-construction submittals, material procurement, pre-construction meetings, construction, commissioning, punch-list completion, and acceptance of closeout documentation.
6. PROJECT SCHEDULE
6.1. The Project Schedule shall show submittals, government review periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. The Bar Chart shall be time scaled and generated using an electronic spreadsheet program.
6.2. The contractor shall use the critical path method (CPM) to schedule and control project activities. Project schedules shall be prepared and maintained electronically. Save files in applicable format to be importable. Schedule shall be updated at least monthly for any project exceeding 60 calendar days. The schedule shall be built as follows.
6.3. The project schedule shall show design periods, submittals, government review periods, material/equipment delivery, utility outages, all on-site construction, inspection, testing, and closeout activities. Government and Contractor on-site work activities shall be driven by work schedules that reflect Saturdays, Sundays and all Federal
Holidays as non-work days unless notified.
6.4. The schedule; shall display Start Contract and End Contract milestone activities. No activities shall be open-ended; each activity shall have predecessor and successor ties. Schedule shall be cost-loaded to aid in the submission of invoices.
6.5. Date/time constraint(s) and/or lags, other than those required by the contract, shall not be, allowed unless accepted by the QA. The Contractor shall include as the last activity in the contract schedule, a milestone activity named "Contract Completion
Date." The CCD milestone shall have a "Mandatory Finish" constraint equal to the
CCD.
7. PRE-CONSTRUCTION MEETING FOR PROJECTS
7.1. The Contractor shall participate in the pre-construction meeting to discuss administrative and contract requirements. The contractor will work with the COR to set up.
During the meeting, the Contractor shall discuss the conceptual process of the project with drawings, specifications, catalog cuts, job plans, and all required documents as available at the time of the meeting.
8. PRE-CONSTRUCTION SUBMITTAL REQUIRMENTS
8.1. The Contractor shall have the following submitted within 14 calendar days of award and prior to the Pre-Construction Meeting:
8.1.1. Approved Site Safety and Health Officer (SSHO) employee (must work for the prime contractor)
8.1.2. Approved Quality Control employee (must work for the prime contractor)
8.1.3. Approved Site Superintendent employee (must work for the prime contractor)
8.1.4. Approved Project Schedule
8.1.5. Accident Prevention Plan (APP): (must be site specific) with Activity Hazard
Analysis (AHA) for each Definable Feature of Work.
8.1.6. Emergency Action Plan: can be separate or an attachment to Accident
Prevention Plan.
8.1.7. Quality Control Plan: will identify the Contractor’s Organizational Chart and provide associated documentation, methods, and testing to ensure quality.
8.1.8. Material/Equipment Submittal Plan will identify projected dates that material submittals shall be forwarded to the government. Manufacturing lead-time shall be afforded for manufacturing of equipment. Contractor must provide proof of manufacturing. Purchase from vendor to the KO and request a no cost time extension via the Request for Information (RFI) process.
8.1.9. Material/Equipment Laydown Area Plan shall identify areas where
Contractor plans to store equipment and materials during construction and is subject to approval by COR and PW Environmental Division.
8.1.10. Schedule of Prices: Submit on forms furnished by the Government. The initial schedule of prices may be preliminary for construction activities until the design is developed. Include a detailed breakdown of the contract price, with quantities for each kind of work. Include General Conditions, profit, and overhead in the unit prices. Break down into design and each construction category if stated in Attachment A. The Contractor may invoice for bonds once the Government has approved the bonds, however, no other requests for payment will be processed without an approved Schedule of
Prices.
9. SUBMITTAL REGISTER:
9.1. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
9.2. Contractor shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements shall be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; Operations and Maintenance (O&M) Manuals (including parts list); certifications; warranties; and other such required submittals.
9.3. Project Schedule
9.4. Accident Prevention Plan (must be site specific)
9.5. Activity Hazard Analysis
9.6. Emergency Action Plan
9.7. Quality Control Plan
9.8. Material/Equipment Submittals, (use NASK PWD transmittal form)
9.9. Environmental Plan
9.10. Proof of manufacturing purchase from vendor, as requested.
9.11. Material Safety Data Sheets (MSDS) as applicable.
9.12. Licenses and Permits
9.13. Digging Permit (14 days prior to excavation)
9.14. NAVFAC Red-Zone (NRZ) Checklist/POA&M
9.14.1. Closeout Submittals UFGS-01 78 00
9.14.1.1. Government Furnished Materials
9.14.1.2. As-Built Signed and Stamped Drawings in CADD and PDF format
9.14.1.3. As-Built Record of Equipment and Materials in CADD and PDF format
9.14.1.4. Construction Contract and Project Specifications
9.14.1.5. eOMSI Facility Data Workbook (FDW – Excel Spreadsheet data filled in by KTR; KTR shall not modify fields)
9.14.1.6. Spare Parts Data
9.14.1.7. Preventative Maintenance Plan
9.14.1.8. Warranty Management Plan (incl Warranty Letters and POC information)
9.14.1.9. Warranty Tags (provide on all equipment with digital back-up copy)
9.14.1.10. Operation and Maintenance Manuals
9.14.1.10.1. The Contractor shall provide one complete set of (O&M
Manuals for the system or systems and CD of information.
O&M Manual sections shall include, at a minimum, the following sections: General Description, Detailed
Description, Systems Description, Operation (all modes), Maintenance, Troubleshooting, Manufacturers Literature
(catalog cuts), and Bill of Material.
9.14.1.11. Building Commissioning
9.14.1.12. Training and Instruction (signed), Videos
9.14.1.12.1. The contractor shall coordinate with the CM/ET to provide training on new systems provided for PWD Productions
Division
9.14.1.13. NAVFAC sustainable & energy data record card
9.14.1.14. Properly completed DD Form 1354 with associated costs
10. POST- CONSTRUCTION SUBMITTALS
10.1. Prior to the CCD, the contractor shall provide one hardcopy and two electronic copies on CD+R of all required closeout submittals.
10.2. Reference section 12.13.2 of this document to see required closeout submittals
10.2.1. Acceptable format shall be compatible with NASK PW latest software versions in AUTODESK- (AUTOCAD) DWG format, Adobe Acrobat and
Microsoft Office format. Data shall be provided during acceptance period in a digital optical disc storage format (DVD+R).
11. SUBMITTALS AND PROCEDURES
11.1. Updated Project Schedule: Update the Project schedule at monthly intervals, if applicable or, as revisions occur. The updated schedule shall be kept current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the assigned COR.
11.2. Three week look ahead and schedule: At the start of construction, the Contractor shall prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Project Schedule. The work plans shall be keyed to activity numbers when a Network Analysis type schedule is required and updated each week to show the planned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead
Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Project Schedule on an electronic spreadsheet program and printed on 8-½ by 11 sheets as directed by the Contracting Officer. Activities shall not exceed
5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work. Provide an electronic file of the 3-
Week Look Ahead Schedule to the assigned COR no later than 1000 each Monday for review during the weekly Coordination Meeting.
11.3. Correspondence and acceptance test reports: All correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and Daily
Reports, material delivery tickets, photographs, etc.) shall reference the Design and
Construction Schedule activities that are being addressed. All test reports (e.g., equipment, concrete, soil compaction, weld, pressure, etc.) shall reference schedule activities that are being addressed.
12. FIRE, SAFETY AND CONFINED SPACE REQUIREMENTS
12.1. The Contractor is required to comply with all Station Safety Regulations. The
Contractor shall observe all requirements for handling and storage of combustible materials, waste and trash. Open flames aboard the station/hot work (i.e. welding) require a permit from the fire department, phone number 361-516-6135.
13. SAFETY REQUIREMENTS
13.1. Contractor shall perform Operational Risk Management (ORM) and Activity Hazard
Analysis (AHA) as required by USACE EM 385-1-1. Contractor shall submit the required AHA form to the COR at least one week prior to each new work phase in the project schedule, when new hazards are identified, or when a new work crew is brought on site.
14. OCCUPATIONAL HEALTH REQUIREMENTS
14.1. The contractor shall be responsible for maintaining a safe work environment for assigned personnel for the duration of the tasks. Personnel injuries, regardless of severity shall be reported immediately to the assigned COR.
15. EMERGENCY ACTION PLAN (OSHA 29 CFR 1910.38)
15.1. The contractor shall develop an emergency action plan in accordance with applicable rules and regulations and it shall be adhered to in the event of an emergency and shall address the following sections. It is the responsibility of the project supervisor, and shift supervisor to educate and brief all personnel on this emergency plan.
16. CONTRACTORS SAFETY RESOURCES WEB SITE (APP and AHA information)
16.1. http://www.navfac.navy.mil/products_and_services/sf/products_and_services/construction/s afety_shack/contr_safety_resources.html
17. CONTRACTOR WEIGHT HANDLING EQUIPMENT (WHE) REQUIRMENTS
17.1. The Contractor shall comply with specific activity regulations pertaining to crane safety and operation, notify the Contracting Officer, in advance, of any cranes entering the http://www.navfac.navy.mil/products_and_services/sf/products_and_services/construction/safety_shack/contr_safety_resources.html http://www.navfac.navy.mil/products_and_services/sf/products_and_services/construction/safety_shack/contr_safety_resources.html activity and comply with ASME B30.5 for mobile cranes and ASME B30.22 for articulating boom cranes. Cranes used in construction, demolition, or maintenance shall comply with 29 CFR 1926 and the Corps of Engineers Manual EM 385-1-1.
Further requirements shall be provided at the Pre-Con, if required.
18. WORK IN CONFINED SPACES
18.1. In addition to the requirements of Section 06.I of USACE EM 385-1-1, OSHA 29 CFR
1910.146 and OSHA 29 CFR 1926.21(b) (6), comply with the following paragraphs.
Any potential for a hazard in the confined space requires a permit system and shall be used.
18.2. Confined Space Signage: Provide permanent signs integral to or securely attached to access covers for permit-required confined spaces provided by this contract. Signs wording: "DANGER-PERMIT-REQUIRED CONFINED SPACE - DO NOT
ENTER -" in bold letters a minimum of 25 mm (one inch) in height and constructed to be clearly legible with all paint removed. The signal word "DANGER" shall be red and readable from 1.52 m (5 feet).
18.3. Entry Procedures: Prohibit entry into a confined space by personnel for any purpose, including hot work, until the qualified person has conducted appropriate tests to ensure the confined or enclosed space is safe for the work intended and all potential hazards are controlled or eliminated and documented. (See Section 06.I.06 of
USACE EM 385-1-1 for entry procedures.) Review all hazards pertaining to the space with each employee during AHA process.
18.4. Forced air ventilation is required for all confined space entry operations. Maintain minimum air exchange requirements to ensure exposure to any hazardous atmosphere is kept below its' action level.
18.5. Sewer wet wells require continuous atmosphere monitoring with audible alarm for toxic gas detection.
19. ENVIRONMENTAL PROTECTION REQUIREMENTS
19.1. The Contractor shall comply with all applicable environmental protection requirements as well as Federal, State and Local Laws. The Contractor shall comply with the
Executive Order 12856, EMERGENCY PLANNING AND COMMUNITY RIGHT-
TO-KNOW ACT (EPCRA); Section 313 requires that all releases of the chemicals in the section 40 of the Code of Federal Regulation (CFR) 372 report to the State
Emergency Response Commission and EPA. The Contractor is required to provide the amount in pounds of listed chemicals released in the environment to the
Contracting Officer.
20. CONTRACT ADMINISTRATIVE REQUIREMENTS
20.1. Required Insurance: The Contractor shall procure and maintain during the entire period of performance under this contract insurance at a level that satisfies all State minimum requirements for General Liability, Automobile Liability, and Worker’s
Compensation.
20.2. Licenses/Permits: Obtain all appointments, licenses, and permits required to perform work under this contract at no additional expense to the Government. Comply with all applicable federal, state, and local laws, and base regulations and procedures.
Provide evidence of such permits and licenses to the Contracting Officer before work commences and at other times as requested by the Contracting Officer (see
FAR 52.236-7, Permits and Responsibilities). The Contractor will coordinate permit applications with the Navy.
21. ACTIVITY REGULATIONS
21.1. The Contractor and their employees shall become acquainted with and obey Activity regulations as posted or as requested by the Contracting Officer. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter restricted areas unless required to do so and until cleared for such entry. The Contractor’s equipment shall be conspicuously marked for identification.
22. PROPRIETARY RIGHTS
22.1. All field notes, design drawings, specifications, and other documents collected and produced as part of this contract shall be considered property of the Government.
Data shall not be, used in whole or parts published or unpublished, as a part of any technical or non-technical presentation without written pre-approval of the
23. PROTECTION OF GOVERNMENT PROPERTY
23.1. Take special care to protect Government property. Return areas damaged as a result of construction under this contract to their original condition. In addition to FAR
52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements, perform the following:
23.2. Remove or alter existing work or facilities in such a manner as to prevent injury or damage to any portion of the existing work or facilities that remain.
23.3. Repair or replace portions of existing work altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
23.4. Preserve the natural resources in accordance with the approved environmental protection plan.
24. ORAL MODIFICATION
24.1. No oral statement by any person other than the Contracting Officer, as provided in the contract clause entitled, “CHANGES AND CHANGED CONDITIONS,” will in any manner or degree modify or otherwise affect the terms of this contract.
25. NO WAIVER BY THE GOVERNMENT
25.1. The failure of the Government in any one or more instances to insist upon strict performance to any of the terms of this contract or to exercise any option herein conferred shall not be construed as a wavier or relinquishment to any extent of the right to assert or rely upon such terms or options on any future occasion.
26. CONTRACTOR INVOICES
26.1. See contract clause 252.232-7006 Wide Area Workflow Payment Instructions
26.2. Payment shall be made on Contractor's submission of itemized requests and will be subject to reduction for overpayments or increased for underpayments from previous payments. Progress payments will be based on the percent of work complete in accordance with the schedule of values. The Government may withhold payment or reduce payments for the following:
26.2.1. Defects in material or workmanship.
26.2.2. Claims the Government may have against the Contractor under or in connection with this contract.
26.2.3. Contractor's failure to submit an updated schedule.
26.2.4. Payroll violations.
26.2.5. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor.
26.2.6. Payments may be made for materials, stored off construction sites, under the following conditions specified in FAR 52.232-5(b) Payments Under Fixed
Price Construction Contracts:
26.2.7. Materials adequately insured and protected from theft and exposure.
26.2.8. Materials not susceptible to deterioration or physical damage in storage or in transit to the job site are acceptable for progress payments. Items such as steel, machinery, pipe and fittings and electrical cable are acceptable, but items such as gypsum board; glass, insulation and wall covering are not.
26.2.9. Materials in transit to the job or storage site are not acceptable for payment.
27. AUTHORITY TO MAKE MODIFICATIONS
27.1. No person other than the Contracting Officer has the authority to bind the Government with respect to this contract.
27.2. No action or omission of any government employee or representative other than the
Contracting Officer shall increase or decrease the scope of this contract or shall otherwise modify the terms and conditions of this contract.
27.3. In no event shall any of the following be effective or binding on the Government or imputed to the Contracting Officer with respect to this contract:
27.3.1. An understanding, or agreement between the Contractor and anyone other than the Contracting Officer;
27.3.2. A purported modification or change order issued by anyone other than the
Contracting Officer;
27.3.3. A promise by anyone other than the Contracting Officer to provide additional funding or make payments; or
27.3.4. An order, direction, consent, or permission from anyone other than the
Contracting Officer to;
27.3.4.1. Incur costs in excess of a specified estimated cost, allotment of funds, or other ceiling; or
27.3.4.2. Expend hours in excess of a specified level of effort
28. COMMUNICATION PLAN
28.1. Provide a plan for key decisions and possible problems the Contractor and Government may encounter during the project. At a minimum, the Communication Plan shall indicate the frequency of QC meetings and what information is covered in those meetings, key decision points tied to the schedule, and required coordination efforts.
29. QUALITY CONTROL PHASES.
29.1. Preparatory Phase: Review all applicable documents for compliance with all applicable laws, codes, regulations, and the requirements of the contract, including contract drawings and specifications. Determine requirements for testing and certification.
Review submittal approvals for materials, equipment, shop drawings, and applicable methods of construction and installation. Include all Preparatory Phase items in the
QC Report.
29.1.1. Initial Phase: Observe and inspect the initial portion of the work performed under a DFOW to establish the quality of the workmanship, resolve conflicts in construction, ensure that testing is done and certified as required, and to check all work procedures to ascertain the work is in conformance with required safety requirements. Record and report nonconforming work and work not of acceptable quality and requiring correction or rework. Include all
Initial Phase items, along with initial phase checklist and, in the QC Report.
29.1.2. Follow-Up Phase: Occurs at the completion of each DFOW. Ensure the work is in compliance with contract requirements, quality of workmanship for all work is maintained, and all work performed meets safety requirements. Include all Follow-Up Phase items, including date, in the QC
Report.
29.1.3. Contractor must possess a current certificate of completion: of the Army
Corps of Engineers NAVFAC Contractor Quality Management (CQM)
Training. The Contracting Officer may have the option of waiving the requirement only once, if the Contractor is new to NAVFAC contracts.
29.1.4. Supervision Requirements: In accordance with FAR Clause 52.236-6, Superintendence by the Contractor, at all times during performance of this contract and until the work is completed and accepted, the prime contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the contractor. The superintendent shall be fluent in
English.
30. SCHEDULING WORK PROCEDURES AND OUTAGES
30.1. Schedule work construction for minimal impact on normal Government operation that involve designated area.
30.2. Prior to construction work, the contractor shall meet with the assigned COR for construction approval of scheduling and sequence of construction/ or outages.
30.3. The Government's normal hours of operation are 0700 to 1630 Monday through Friday, excluding Government holidays.
30.4. If the contractor decides to work other than normal hours/working days, they shall submit a request to the QA for approval three work days prior to the work.
31. UTILITY LOCATIONS AND VERIFICATION PRIOR TO EXCAVATION
31.1. If applicable, obtain appropriate digging permit from Base personnel through the FEAD office prior to digging. Maintain all markings during utility investigation throughout the contract. “At the contractor’s expense, all underground utilities in the work area must be positively identified by a private utility locating service in addition to any station locating service and coordinated with the station utility department.”
31.2. Physically verify underground utility: Locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. Use hand digging within three feet of a known utility. If construction is parallel to an existing utility, expose the utility by hand digging every 100 feet if parallel within five feet of the excavation.
31.3. Utilities within Concrete Slabs: Utilities located within concrete slabs are extremely difficult to identify due to the reinforcing steel used in the construction of these structures. Whenever work involves concrete chipping, saw cutting, or core drilling, the existing utility location must be coordinated with station utility departments in addition to a private locating service. Outages to isolate utility systems shall be executed in circumstances where utilities are not positively identifiable. Use of historical drawings and data shall not alleviate the contractor from meeting this requirement.
32. CONDUCT OF ELECTRICAL WORK
32.1. Follow electrical safety criteria specified in UFC 3-560-01, USACE EM 385-1-1, and
NFPA 70E during the conduct of all work. As delineated in USACE EM 385-1-1 electrical work shall be conducted in a de-energized state unless there is no alternative method for accomplishing the work.
32.1.1. Energized Work: energized work requires a permit and shall be obtained from the Commanding Officer.
33. CONTRACTOR WORK SITE
33.1. The contractor shall limit use of the premises for work and for storage of material and equipment associated with the contract. Unless otherwise specified or separately agreed to, Government owned material handling equipment, transportation equipment or general tools will not be available for contractor’s use.
33.2. Clean work area daily and after completion of the work, removing all loose debris and disposing of all non-permanent materials IAW the contractor’s Waste Management
Plan. Submit a monthly summary of removed solid waste in weight to assigned
COR.
33.3. Temporary Facilities (if applicable): The contractor may provide his own office facilities/fencing; coordinate and obtain advance approval from the COR. Submit a location plan of temporary facilities indicating requested utility connections.
Provide and maintain suitable sanitary facilities within the construction limits of the contract. Dispose of sanitary waste in accordance with the applicable laws, and local regulation at no cost to the Government. If temporary facilities are installed or constructed, the contractor will request a meter to
33.4. Contractor Furnished Equipment: Equipment is subject to the inspection and approval of the COR, prior to and during the life of the contract.
34. CONTRACTOR’S PRODUCTION REPORT
34.1. Complete the reports weekly unless otherwise requested by the Contracting Officer.
Reports at a minimum shall include:
34.2. Worker hours by classification, move-on and move-off of construction equipment furnished by the prime, subcontractor or the Government, and materials and equipment delivered to the site.
34.3. Safety meetings checks and inspections.
34.4. Disposition of Construction Waste Material (See Section 17)
34.5. Design and Construction Issues: Including, but not necessarily limited to:
34.5.1. Check all Contract Documents for correctness and correlation. If the
Contractor notes any discrepancy or ambiguity; immediately notify the assigned COR.
34.5.2. Examine the work site as to conditions affecting the work. Field verify the site and scope of work, including but not limited to the measurement and location of all significant items required to perform the work.
35. CLEANING / REMOVAL/ SALVAGE AND DISPOSAL OF WASTE
35.1. Cleaning project area of materials and rubbish, resulting from the contractors work is the property and responsibility of the contractor. Keep the premises free of debris, accumulation of waste materials, rubbish, tools and all surplus materials at all times.
35.2. Generated Waste shall be removed from Government property, during and before the completion of the project by the contractor or contractors.
35.3. Salvage, report and submit with each invoice the amount (by weight) and type of materials salvaged for sale, reused and or recycled. Provide destination, means of transportation, cost of transportation and handling, tipping fee saving and revenue generated for each material.
35.4. Disposal of generated waste from project should occur during and before the completion of the project, with all generated debris removed from Government
Property upon completion of project. The Contractor shall report/submit with each invoice the amount of waste (by weight) and type of waste materials disposed of in a landfill or incinerator, the tip fee per ton, and the total cost of disposal including transportation costs, container rental costs, etc.
35.5. Waste Management: Contractor shall reduce, recycle or salvage as much waste material as possible with a goal of diverting at least 50% of construction waste from landfill. Address waste reduction, recycling and salvage.
36. INSPECTION AND ACCEPTANCE REQUIREMENTS
36.1. All work is subject to inspection during the work and upon completion of the work.
Any corrective discrepancies need to meet the satisfaction of the Government prior to presenting an invoice for payment. At the 75% completion point, the assigned
COR will conduct a Red-Zone checklist review with the Contractor.
37. WARRANTY
37.1. Warrant all materials and work for not less than one year after final acceptance of the work, except as otherwise indicated in this RFP. If required to provide remedial repair of previously installed work due to latent defect or unacceptable work performance, warrant the repaired work for one year after the completion and acceptance of the repair.
37.2. Warranted items: furnish the manufacturers’ original written warranty accompanied by a copy of the supplier’s receipt showing place of purchase, telephone number of supplier, address, delivery order number and or a ticket number.
38. TRANSMITTER REQUIREMENTS
38.1. The base policy concerning the use of transmitters such as radios, cell phones, etc., shall be adhered to by all Contractor personnel. They must also obey Emissions control (EMCON) restrictions.
39. HAZARDOUS MATERIAL EXCLUSIONS
39.1. N/A
*********************END SCOPE OF WORK********************************
Section 00010 - Solicitation Contract Form
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job B-4792 Sewer Line
FFP
Install sewer line at Bldg 4792 at NAS Kingsville, TX, in accrdance with statement of work. Period of performance is 90 days after contract award.
FOB: Destination
PSC CD: Z2QA
NET AMT
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 90 dys. ADC 1 PWD KINGSVILLE
INSPECTOR OF RECORD
201 NIMITZ AVE, BLDG 4711
KINGSVILLE TX 78363-5103
361-516-6044
FOB: Destination
N45974
CLAUSES INCORPORATED BY FULL TEXT
52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2004)
(a) Definitions. As used in this provision--
“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting
Officer's discretion, result in the offeror being allowed to revise its proposal.
“In writing or written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
“Proposal modification” is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
“Time”, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include
Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror.
Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show--
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, or revision, of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications, or revisions, so as to reach the
Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and--
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the
Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent
Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal
Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at
52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall--
(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the
Government and shall not be duplicated, used, or disclosed--in whole or in part--for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of--or in connection with-- the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title…