N6945021Q00070002.pdf
PDF 113 KB Posted
- Attached to
- KV OG ATCT Roof & Paint
- Solicitation number
- N6945021Q0007
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6945021Q00070004.pdf | ||
| Second Site Visit Announcement.pdf | ||
| N6945021Q00070003.pdf | ||
| NALF ATCT Photos rev 20210128.pdf | ||
| N6945021Q00070001.pdf | ||
| CLIN 0002 OG ATCT Paint.pdf | ||
| KV NEW PASS APPLICATION FORM.pdf | ||
| CLIN 0001 OG ATCT Roof.pdf | ||
| N6945021Q0007.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Pre-Proposal Inquiries
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-Feb-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6945021Q0007
X 9B. DATED (SEE ITEM 11)
20-Jan-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
05-Feb-2021
CODE
NAVFAC ENGINEERING SYSTEMS COMMAND SE
PWD CORPUS CHRISTI
8851 OCEAN DRIVE, BLDG 19
CORPUS CHRISTI TX 78419-5021
N69450 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
joel.overson@navy.milEMAIL:361-961-3397TEL:
JOEL OVERSON / CONTRACTING OFFICER
N6945021Q0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
PRE-PROPOSAL INQUIRIES
PRE-PROPOSAL INQUIRY
Solicitation Number: N6945021Q0007, NAS Kingsville, TX
Contractor Name: N/A
Contractor POC (Name and email): N/A
Contracto r PPI#
Section of RFP Question Answer
Scope of Work
CLIN 0001
Do you have a specific coating you would like to see installed? Mesh can be incorporated into most coating systems.
The SOW states “The contractor shall prepare existing roof surface and apply a Mesh
Reinforced Elastomeric Roof Coating (MERC) to the roof”. We are not specifying any particular name-brand product.
CLIN 0001
What is the substrate this is going to? The tower is a concrete roof with a bituminous roof system installed.
CLIN 0001
Is there a warranty you are looking for? We require a 2yr labor warranty for roofs. The manufacturer warranties that come with the roof system must be provided as a part of closeout.
CLIN 0002
The specs mention that interior painting may only be done on the weekend, due to the tower remaining in use during the week.
a. What is the earliest day and time that work may start on the weekend, and
b. what is the latest day and time that work may continue during the weekend?
c. What hours are allowed during the weekend? Is working nights acceptable?
a. Airfield is closed Saturday and Sunday so it will be up to the NAVFAC
Engineering Technician however long he will be escorting, assume Sat & Sun, 0800-1630.
b. Airfield is closed Saturday and Sunday so it will be up to the NAVFAC
Engineering Technician however long he will be escorting, assume Sat & Sun, 0800-1630.
c. All hours are available, working nights would only be reasonable if it were due to environmental concerns
CLIN 0001
Does the roofing work have to take place during the weekend? Can roofing work take place while the facility is in use?
Yes the Tower roof can be worked on during weekdays while occupied. However coordination with Ground Electronics will be the deciding factor due to multiple RF antennas concerning proximity and hazards.
CLIN 0001
If roofing work can take place while the facility is in use, is access available to the roof via the inside of the tower, that can be used while the facility is in use?
Tower roof is accessible from the tower cab only. Yes the tower roof is accessible while in use but space is limited due to the angle of the stair case.
CLIN 0002
What kind of paint is currently on the walls? Unknown. It might be latex, but we do not know for sure.
CLIN 0002
What is the thickness of the current coating system?
Currently a thin white layer is cracking and flaking/peeling away from the walls and the primer underneath as well
CLIN 0002
What condition is the current coating system in?
dry cracking flacking and peeling away on its own from the wall surface the entire stairwell height.
10 Scope of Work Are there any pictures available of the job site? And more specifically, of
A typical segment of wall
A particularly damaged segment of wall
A typical segment of roof
A particularly damaged segment of roof
Exterior shot of the site
Additional pictures provided via separate attachment.
11 Scope of Work
CLIN 0001
CLIN #1 reference's design under 2. Scope of Work. This is the only reference to design in the RFP. Can the Gov. clarify if design is required and what the requirements are for a design.
There is no design requirement.
12 Scope of Work
CLIN 0001 &
CLIN 0002
There is no mention of weekend work in
SOW
however it was mentioned in walk thru that would more likely be case due to the view not being disturbed. Please verify working days and the time that the work can be done on the Towers Roofing.
CLIN 0001-The roof coating can happen during flight operations as long as there is limited disturbance to the Air Traffic Controllers.
OG- CLIN 0002-Painting weekend work is mentioned in SOW. Contractor will have to accomplish all work on the weekends due to day/night flight operations during the work-week.
The painting of the OG ATCT stairwell must be on the weekend but flight operations typically end at 1700 on Friday and do not begin until
0800 on Monday morning.
13 Scope of Work
CLIN 0002
SOW does not mention painting the ceiling or the blue borders on the base of steps of stairwell. Will the blue border be removed and replaced?
Where is the cutoff for painting the stairwells? If not CMU walls... are other walls painted also?
SOW does not mention of sheet rock only
CMU. Will the CMU only be encapsulated and painted?
The blue border on the base of the steps will be abated and encapsulated with the eggshell color, the same as the rest of the walls. All walls in the stairwell will be painted.
The walls are not CMU, they are sheet rock and plaster.
14 Scope of Work
CLIN 0002
SOW states to apply 2 coats of primer and 1 topcoat. That seems to be backwards but maybe they have a purpose. Normally you apply one coat of primer and 2 topcoats.
Yes, two coats primer one coat paint. The primer must be suitable for encapsulating lead based paint.
15 Scope of Work
The color requested is egg-shell white in color, but no sheen was requested.
Was “Egg-shell” the sheen or the color? If it is the color, what sheen is to be painted?
Match Existing
16 Scope of Work
The contractor shall paint 4,800 SF of walls.
So, we are to assume that we are not painting the ceilings?
The Ceiling Should be painted
17 Scope of Work
Handrails and stairs need to be protected from overspray. When the abatement is performed, it is going to affect the blue runner up the side of the stairs, are we to touch this up, or is the runner getting painted
The blue runner should be painted over with the
Eggshell color.
“Egg-shell” as well?
18 Scope of Work
CLIN 0002
Will the stairs get painted? The underside of the stairs will be painted, but the stair tread, riser and handrail will NOT be painted.
19 Scope of Work
CLIN 0002
Will the Handrail get painted? The stair tread, riser and handrail will NOT be painted.
20 Scope of Work
Also, it says to prep the walls with water blast, CMU should be fine but not the drywall once wet.
The walls are not CMU, they are sheet rock and plaster.
The contractor shall prep all surfaces via low volume high pressure water blasting, scraping, or power/hand tool cleaning per (NFGS-13283) with appropriate environmental and worker safety controls prior to painting.
21 Scope of Work
CLIN 0002
After all the abatement is performed, are we to float and texture walls to match existing or do we need to float and texture the drywall completely to make look smooth and uniform?
The walls should have a smooth finish.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .