N6945018R1305_0002.pdf

PDF 35 KB Posted

Attached to
P-473 and P-474 TOWNSEND BOMBING RANGE
Solicitation number
N6945018R1305
Issued by

About this file

N6945018R1305_0002.pdf

View the file

Other files

File Type Posted
N6945018R1305_0005.pdf PDF
N6945018R1305_0004.pdf PDF
N6945018R1305-0003.pdf PDF
N6945018R1305_0001.pdf PDF
N69450-18-R-1305.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SOLICITATION FOR P-473/P-474, TOWNSEND BOMBING RANGE, MARINE CORPS AIR STATION (MCAS), BEAUFORT (TOWNSEND TARGET), GEORGIA.

The purpose of this amendment is to extend submittal of PPIs due date, revise Instructions to Offerors, revise draw ing sheet A101, and provide Tow nsend KMZ (w etlands map).

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 13-Mar-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6945018R1305

X 9B. DATED (SEE ITEM 11)

20-Feb-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-Mar-2018

CODE

NAVFAC SOUTHEAST

IPT SOUTH CENTRAL

BLDG 135, PO BOX 30

NAS JACKSONVILLE

JACKSONVILLE FL 32212-0030

N69450 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6945018R1305

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0002

The purpose of this amendment is to:

1. Extend submittal of PPIs due date to March 29, 2018.

2. Revise Instructions to Offerors, Section 00202, B, 4. Completion Date as follows (changes bolded):

4. The completion dates are as follows:

CLIN 0001 - P473, North of State Road 57 - Traditional Clearing Method, 270 days from date of contract award.

CLIN 0002 - P474, North of State Road 57 - Traditional Clearing Method, 270 days from date of contract award.

CLIN 0003 - P474, South of State Road 57 - Traditional Clearing Method, 365 days from date of contract award.

CLIN 0004 – P474, Target 6 - Traditional Clearing Method, 30 days from receive of notice to proceed (currently on or around 30Sep 2019)

CLIN 0005 – OPTION ITEM 1 - P473, North of State Road 57- Alternative Clearing Method, Forestry Mulching, 270 days from date of contract award.

CLIN 0006 -OPTION ITEM 2 - P474, North of State Road 57- Alternative Clearing Method, Forestry Mulching, 270 days from date of contract award.

CLIN 0007 – OPTION ITEM 3 - P474, South of State Road 57- Alternative Clearing Method, Forestry Mulching, 365 days from date of contract award.

CLIN 0008 – OPTION ITEM 4 - P474, Target 6 - Alterative Clearing Method, Forestry Mulching, 30 days from receive of notice to proceed (currently on or around 30 Sep 2019).

CLIN 0009 – P-473, Communication Tower, 180 days from date of contract award.

CLIN 0010 – P-474, Administration Building, 335 days from date of contract award.

CLIN 0011 - PLANNED MODIFICATION – Furniture, Fixtures, and Equipment (FF&E).

3. Revise Instructions to Offerors, Section 00202, III, D. Evaluation Factors for Award, 2. (b) Non-cost/Price (Technical Factors), (1) Factor 1, Experience, (i) Solicitation Submittal Requirements, and (ii) Basis of Evaluation to read as follows (changes bolded):

(1) Factor 1, Experience:

(i) Solicitation Submittal Requirements:

The Offeror shall submit the following information:

(a) Construction Experience: Submit a minimum of two (2) and a maximum of five (5) relevant construction projects of which your firm was the prime contractor. These projects shall be similar in scope, complexity, and of a size of approximately $8,000,000 or of similar square footage or acreage to the proposed Townsend Bombing Range project. A relevant project is further defined as a single project containing both horizontal and vertical elements. Projects shall have been completed within the last five years.

A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project;

rather Offerors should submit the work performed under a single task order as a project.

The attached Construction & Design Experience Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page or two (2) single-sided pages.

For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e.: unique features, area, construction methods).

If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity or the Joint Venture partners. Offerors are still limited a total of five (5) projects combined.

If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), The Offer must provide a letter of commitment and shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.

The Offeror may utilize experience of a subcontractor that will perform major or critical aspects of the requirement to demonstrate construction experience under this evaluation factor. The Offeror must provide a letter of commitment and an explanation of the meaningful involvement that the subcontractor will have in performance of this contract.

(b) Key Personnel: Submit resumes for key personnel identified below. Resumes shall include the following: (i) professional licenses and certifications, if any; (ii) number of years of experience; (iii) firms they have worked for in chronological order with dates; and (iv) description of projects that they have worked on including their role on these projects. Resumes for each individual shall be limited to two pages in length.

• Construction Project Manager – responsible for all construction project management. Must meet the following minimum requirements; (i) ten years of construction management experience; (ii) five years of experience serving as Construction Project Manager; (iii) resume must include documentation to demonstrate construction experience on projects that were similar in size, scope and complexity to the proposed Townsend Bombing Range project; and completed in the last five years.

• Project Superintendent – responsible for all on-site construction operations. Must meet the following minimum requirements; (i) seven years of experience as Superintendent on construction projects;

(ii) resume must include documentation to demonstrate construction experience on projects that were similar in size, scope and complexity to the proposed Townsend Bombing Range project; and completed in the last five years.

(c) Construction Narrative: Submit a narrative describing the proposed primary construction firm and the primary subcontractors, for this contract and the rationale of proposing this arrangement. Provide the role, responsibilities, and contractual relationships between the various firms. The narrative shall also include a simple organizational chart that clearly identifies the lines of authority between the entities. The technical narrative shall not exceed one (1) double-sided page or two (2) single-sided pages. Chart is not in this page count.

(ii) Basis of Evaluation:

The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the Offeror’s relevant experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. The Government will only review five (5) projects. Any projects submitted in excess of the five (5) for Construction Experience will not be considered.

These projects shall be similar in scope, complexity, and of a size of approximately $8,000,000 or of similar square footage to the proposed Townsend Bombing Range project. A relevant project is further defined as a single project containing both horizontal and vertical elements. Projects shall have been completed within the last five years.

4. Revise Drawing Sheet A101. Column Line “B” has been moved South 2” (changes are bubbled on the sheet)

The following documents have been incorporated and added to the RFP/Posted to NECO under Additional Documents section:

1) Sheet A101-ADD_01

2) Townsend_KMZ (wetlands map)

All other terms and conditions remain unchanged.

SECTION 00010 - SOLICITATION CONTRACT FORM

The contractor period of performance end date has increased by 5 days from 390 days to 395 days.

DELIVERIES AND PERFORMANCE

The following Delivery Schedule item for CLIN 0007 has been changed from:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

270 dys. ADC 1 N/A

FOB: Destination

To:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

365 dys. ADC 1 N/A

FOB: Destination

SECTION 00700 - CONTRACT CLAUSES

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 395 calendar days from the date of the contract award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than .

The time stated for completion shall include final cleanup of the premises.

(End of clause)