The document is a Statement of Work (SOW) for on-site equipment calibration services for the Materials Engineering Branch at Naval Air Warfare Center, Weapons Division in China Lake, CA. The calibration contract will be structured as a base year with two option years, with all calibration work to be performed in accordance with ISO-17025 standards. The supplier must be accredited to ISO-17025 and will calibrate laboratory equipment primarily on-site in Building 02466, Rooms 2000-2019 of the Michelson Laboratory complex, with some specific items (weights, gage blocks, hygrometers, ring gages) allowed for off-site calibration.
Key requirements include completing on-site calibration within 2 business days, providing personnel information for badge requests 30 days prior to the on-site date, and submitting comprehensive documentation. Documentation must include calibration stickers on equipment showing calibration date, expiration date, and vendor name, as well as Certificates of Calibration to be submitted electronically or in hard copy within 2 weeks of work completion. The solicitation (N6893626Q5007) is set for competitive procurement on a full and open basis, with the solicitation expected to be posted on Beta.SAM.gov on or about 10/7/2025, and all interested contractors must be registered in the System for Award Management (SAM).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment N6893626Q50070002.pdf | ||
| Questions and Answers.pdf | ||
| Amendment N6893626Q50070001.pdf | ||
| SF 1449 - N6893626Q5007.pdf | ||
| Equipment List 2025 - 2028.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work for PID ___________
05AUG2025
The supplier shall calibrate the laboratory equipment for the Materials Engineering Branch at Naval Air Warfare Center, Weapons Division at China Lake, CA. Specific instructions and requirements are listed below:
1. Calibrate various lab equipment (see separate calibration list)
2. Calibration contract shall be as a base year and 2 option years.
3. All calibration shall be in accordance with ISO-17025.
4. The supplier shall be accredited to ISO-17025 for all items listed.
5. All calibration shall be performed in place at the Materials Engineering Branch Laboratory in Building 02466, Rooms 2000 through 2019, of the Michelson Laboratory complex, Naval Air Warfare Center, China Lake, CA, 93555, except as noted in paragraph 5.
1. Expected on-site calibration time is not to exceed 2 business days, unless otherwise arranged with the Materials Engineering POC
2. Vendor shall provide personnel info for badge requests to Materials Engineering POC not less than 30 days prior to on-site date
3. Materials Engineering POC will provide badge request forms upon contract release
6. Supplier shall calibrate all items in the Materials Engineering Branch Laboratory with the exception of the following, which may be calibrated at the supplier’s facility:
1. Weights
2. Gage Blocks
3. Hygrometers
4. Ring Gages
7. Any other items that require off-site calibration shall have prior approval from the Materials Engineering POC.
8. All off-site items shall be returned to the Materials Engineering Branch within 1 week, unless otherwise arranged with the Materials Engineering POC.
9. Documentation. The following documentation shall be provided:
1. All calibrated equipment or the storage box shall be marked with a sticker giving the following:
i. Calibration date
ii. Calibration expiration date
iii. Vendor name
2. Certificate of Calibration for each of the items
i. Certificates may be provided as hard copies or electronically (PDF, Word, Excel, etc), to the Materials Engineering POC
ii. Certificates shall be provided no later than 2 weeks after completion of work