NACRC_RFI_Clarifications_2016_1_13.docx

DOCX document 20 KB Posted

Attached to
NIMITZ-class Aircraft Carrier Recovery Capability
Solicitation number
N68335-16-RFI-0084
Issued by

About this file

Questions Response

View the file

Other files

File Type Posted
NACRC_RFI_2016_1_13_1.docx DOCX document
NACRC_System_Metrics_template_2016_1_5.xlsx XLSX spreadsheet
NACRC_TMSA_Template_2015_11_30.docx DOCX document
NACRC_RFI_2015_12_1.docx DOCX document
NACRC_System_Metrics_template_2015_11_10.xlsx XLSX spreadsheet
NCRC_MIL-STD-881C-based_Electronic_Systems_WBS_Template_2015_10_1.docx DOCX document
NACRC_RFI_NDA_2015_11_24.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NIMITZ-Class Aircraft Carrier Recovery Capability Request for Information (RFI) Questions and Answers 13 January, 2016

1. Is there a target carrier / timeframe for the prototype shipset?

Government Response: The initial shipset will be installed on the NIMITZ-Class carrier whose availability best aligns with the delivery of the initial shipset.

2. For Top Level Schedule, does "production, installation, test events.” refer to the outfitting of one of the 4 land-based systems identified in the cost section?

Government Response: The top level schedule should include development, production, installation and test events for two systems dedicated to land-based testing for developmental test, one each at Jet Car Track Site (JCTS) and Runway Arrested Landing Site (RALS), NAWCAD Lakehurst. The top level schedule should reflect production and installation of one land-based system at the Mk-7 Arresting Gear site, NAWCAD Patuxent River after completion of Milestone C. The RFI has been revised to three land- based systems from four land-based systems.

a. If so, is it a JCTS or RALS type installation?

Government Response: RFI responses should assume a JCTS type installation and a RALS type installation at NAWCAD Lakehurst and a RALS type installation at NAWCAD Patuxent River.

3. Should our top level schedule assume that the proposed system will be built and tested at one of the land-based units prior to install / test of the prototype shipset, which would precede any of the other shipset deliveries?

Government Response: The top level schedule should assume that completion of the land-based testing will precede the decision to produce the initial shipset which will precede installation and operational test of the initial shipset on a NIMITZ-Class carrier.

a. If so, we need to understand the stand-off times expected by the Government between land-based, ship prototype, and ship delivery requirements.

Government Response: RFI responses should assume the time required to complete the acquisition process as described in SECNAV 5000.2E, 1 September 2011. It is the intent of the Government to procure and install shipsets in the manner that optimizes the cost and time required to increase the recovery capability of the NIMITZ-Class carriers. The stand-off time will be determined by the time required to complete Milestone C, the time required to manufacture the shipset, the time required to install and test the shipset on a NIMITZ-Class carrier, and the availability periods of the NIMITZ-class carriers.

4. Are the 4 total land-based systems JCTS or RALS type installations? Should we assume that the requisite facilities / infrastructure (like a track with buildings at JCTS, or a pit like RALS) are provided by the Government?

Government Response: The RFI will be updated to revise the number of land-based units as follows: two systems dedicated to land based testing for developmental test, one each at JCTS and RALS sites, NAWCAD Lakehurst; and one land-based system at NAWCAD Patuxent River. RFI responses should assume a JCTS type installation and a RALS type installation at NAWCAD Lakehurst and a RALS type installation at NAWCAD Patuxent River. The RFI responses should assume the requisite facilities / infrastructure are provided by the Government. The arresting gear test hardware and software are the responsibility of the contractor.

a. If so we will assume from a schedule standpoint that these facilities / infrastructure will be available to coincide with our planned hardware deliveries.

Government Response: RFI responses should assume the test facilities and test infrastructure will be in place to support the planned test unit hardware deliveries. The RFI response should identify any known additional requirements over and above existing Government facilities at the JCTS and RALS sites.

5. For delivery of the 9 additional shipsets, are you looking just for our normal projected throughput, or do you want us to try to match deliveries with first opportunity for each carrier availability (RCOH or extended DPIA) per the carrier availability schedule?

Government Response: It is the intent of the Government to procure and install shipsets in the manner that optimizes the cost and time required to increase the recovery capability of the NIMITZ-Class carriers. Therefore carrier availability should be taken into consideration.

File details come from the government source that posted it. Updated .