This is a QA Solicitation Checklist for Navy Standard Items (NSI) applicable to the USS Oscar Austin (NAPL-007-27) with a period of performance from 10/22/2026 to 11/6/2026.

The checklist outlines mandatory quality management system documentation and certifications required by FDRMC Code 130 QA to verify contractor compliance with work package specifications. For Quality Management System supporting documents, contractors must submit a Quality Manual describing their QMS per NSI 009-04, with ISO 9001 certification copies required if applicable. Quality Assurance/Control Procedures must be submitted, including Process Control Procedures (NSI 009-09) for annotated work items. Calibration and inspection documentation requirements include calibration records for all measuring and test equipment (NSI 009-04), a qualified inspector list identifying inspection and test qualifications for each inspector including subcontractors (NSI 009-04), Marine Chemist/Gas Free Engineer certifications (NSI 009-07), and coatings inspector certifications per NAVSEA Basic Paint Inspector, NACE International CIP Level 1 or higher, or SSPC PCI Level 2 with minimum two years marine coatings experience (NSI 009-32). QP-1 certification is required for organizations performing blasting or coating application operations. Welding and brazing documentation must include procedure qualifications per S9074-AQ-GIB-010/248 Sections 4 and 5, and brazing qualifications per NAVSEA 0900-LP-001-7000 Section 4. NDT/NDI certifications and procedures must comply with T9074-GIB-010/271 Sections 1.6 and 1.7, with written practice available upon government inspector request. A draft Test and Inspection Plan (TIP) must be submitted with the proposal indicating understanding of solicited work items, with the final version required post-award including all required inspections and government notification symbols (I), (V), (Q), and (G).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FDRMCSOP-130-111

QA Solicitation Checklist Navy Standard Items (NSI)

Ship Name: SSP#: POP: To

Enclosure 1

Quality Management System (QMS) Supporting Documents

Checked block indicates documentation submission is required

Documents requested for review are required by FDRMC Code 130 QA to determine contractor’s ability to comply with Work Package specification requirements

Quality Manual

NSI 009-04

Para 3.1 & Para 3.2: Submit for review, a copy of the Quality Manual that describes your Quality Management System.

**If ISO 9001 certified please also attach a copy of your certificate**

Quality

Assurance / Control

Procedures

Submit for review copies of processes and/or procedures anticipated for use during performance of this contract as annotated below:

Process Control Procedures (PCP) NSI

009-09

The Work Item(s) annotated below may require a PCP

Calibration / Inspectors / Confined Space / Coatings

Checked block indicates documentation submission is required

Documents requested for review are required by FDRMC Code 130 QA to determine contractor’s ability to comply with Work Package specification requirements

Measuring and Test Equipment Calibration NSI

009-04

Para 3.2.1.1: Submit records of calibration for all measuring and test equipment anticipated for use during execution of the contract

Qualified Inspector List NSI 009-04

Para 3.15: Submit a list of qualified inspectors who witness and sign inspections and tests indicated by Work Item(s) symbol (I). The list shall indicate the type(s) of inspections and tests for which each inspector is qualified. Include sub-contracted inspectors if applicable.

Marine Chemist Gas Free engineer

Certifications NSI 009-07

Para 3.1.2 & Para 3.1.2.1: Provide copies of Marine Chemist / Gas Free Engineer (Competent Person) certification.

Coatings Inspector(s) Certification

NSI 009-32

Para 3.9

When accomplishing preservation operations to areas as listed in paragraph 3.7

[critical coated areas]

Para 3.9.1 Submit copies of Coatings Inspectors Certifications.

NAVSEA

Basic Paint Inspector (NBPI) course, NACE International Coating Inspector Program (CIP) Level 1 or higher, or SSPC Protective Coating Inspector Program (PCI) Level 2. Coating inspectors shall also have a minimum of 2 years of marine coatings related work experience.”

Para 3.9.2: QP-1 CERTIFICATION Organizations performing blasting operations (abrasive and water-jetting) or coating application shall be certified in accordance with QP 1 of [Systems and Specifications, SSPC Painting manual, Volume 2] (with the exception of the Coating Application Specialist (CAS) requirement) or NAVSEA-approved equivalent.

Welding / Non Destructive Testing / Inspection Documentation

Checked block indicates Documents requested for review are required by documentation submission is FDRMC Code 130 QA to determine contractor’s ability to comply with required Work Package specification requirements

Welding / Brazing Certifications, Qualifications and Procedures

S9074-AQ-GIB-010/248

Section 4, WELDING PROCEDURE QUALIFICATION, in its entirety.

S S9074-AQ-GIB-010/248

Section 5, WELDING PERFORMANCE QUALIFICATION, in its entirety.

Brazing Certifications, Qualifications and Procedures

NAVSEA 0900-LP-001-7000 Section 4, QUALIFICATION REQUIREMENTS, in its entirety.

NDT/NDI Test Personnel Certifications and NDT

Procedures

T9074-GIB-010/271 Para 1.6, NONDESTRUCTIVE TEST PERSONNEL CERTIFICATION, in its entirety.

T9074-GIB-010/271 REV 1 Para 1.7, PROCEDURE QUALIFICATION AND APPROVAL, in its entirety.

NDT Written Practice

T9074-GIB-010/271

Para 1.6: “A copy of the activity’s written practice shall be provided to the Government inspector upon request.”

Test and Inspection Plan

Test and Inspection Plan/Schedule (TIP)

Submit draft of Test and Inspection Plan (TIP) of scheduled work items in the solicitation to indicate understanding of the solicited work items.

After contract award, the TIP must include all inspections required by references as well as the symbols (I), (V), (Q) at test/inspections points and (G) when government notification identified in each Work Item.

Please see example Test & Inspection