STATEMENT OF WORK (SOW)
Underwater Training Range (UTR) Underwater Communications Subsystem (UCS) Hardware Design, Procurement, Production PR No. 1301041505
1.0 BACKGROUND
The Naval Undersea Warfare Center Division, Newport (NUWDIVNPT) Code 70 will deliver an Underwater Communications System (UCS) for the Undersea Warfare Training Range (USWTR) and AUTEC Sensor Replacement Program (ASRP) recapitalization programs. An Underwater Training Range (UTR) is comprised of an In-Water Subsystem (IWS) and a Display, Processing, and Control Subsystem (DPCS), each with multiple subsystems. The IWS consists of the Ocean Sensor Subsystem (OSS), the Sea-Shore Interface (SSI), and the Shore Electronics Subsystem (SES). The SES contains electronics for transmission, reception, and monitoring of acoustic signals from the OSS and sends raw acoustic data to the DPCS. The DPCS provides the infrastructure to enable operators to process the acoustic sensor output, control and debrief training exercises, and to communicate via submarine acoustic transmission. The subsystems implementing these functions include the Underwater Communications Subsystem (UCS).
The purpose of the UCS is to communicate with subsurface vehicles using acoustic signals. The UCS is comprised of various electronic and computer components that fit in a standard electronic equipment rack. The rack includes a Primary and Secondary UCS, with some components shared between the two systems. The UCS can operate in both analog and digital mode, although the default usage mode is digital.
1.1 Places of Performance
Contractor’s Facilities
Atlantic Undersea Test and Evaluation Center (AUTEC)
Pacific Missile Range Facility (PMRF)
Southern California Tactical Training Range (SCTTR)
Jacksonville Tactical Training Range (JTTR)
1.2 Authorized Users
Naval Undersea Warfare Center Division Newport, Code 70
1.3 Sponsors
Office of the Chief of Naval Operations (OPNAV), Technology Requirements and Test and Evaluation (N94)
Program Executive Office Aviation Common Systems and Commercial Services PEO(CS)
NAVAIR Engineering, Navy MRTFB Program Management Division V542
1.4 Types of Funding
Operation and Maintenance (OMN)
Other Procurement, Navy (OPN)
Research, Development, Test and Evaluation (RDTE)
2.0 SCOPE
The contractor shall provide the material and services to design, document, manufacture, test, package, and deliver a Technical Data Package and Underwater Communication System hardware assemblies in accordance with (IAW) the requirements in the UCS performance specification provided as Government Furnished Information (GFI). The Government will provide a compact flash (CF) memory device that includes computer operating system and the government’s UCS application software as Government Furnished Equipment (GFE) that will integrate with and run on the contract hardware. The Government will operate this software during integration and factory acceptance testing. Services include corrective maintenance at each UCS installation site listed in Section 1.1.
3.0 APPLICABLE DOCUMENTS
The contractor shall perform the tasking required in Section 4.0 in accordance with the following Applicable Documents (AD) shown in
Table 1.
Table 1 Applicable Documents
Number Title
SOW
Reference
3.1 DoD Issuances
3.1.1 MIL-HDBK-217F Reliability Prediction of Electronic Equipment 4.1.6
3.1.2 DODI 5000.02; Operation of the Defense Acquisition System - December 2008 4.1.7
3.1.3 DoD 8570.01M; Information Assurance Workforce Improvement Program 4.1.7
3.1.4 Department of the Navy (DoN) Application and Database Management System (DADMS), http://www.esd.whs.mil/DD/
4.1.7
3.1.5 DOD Cyber Exchange, https://public.cyber.mil 4.1.7
3.1.6 DOD Patch Repository, https://patches.csd.disa.mil 4.1.7
3.1.7 SECNAV M-5510.30C 4.1.7
3.2 Navy Issuances
3.2.1 Department of the Navy (DoN) Application and Database Management System (DADMS). http://www.esd.whs.mil/DD/)
4.1.7
3.3 Industry Standards
3.3.1 ISO 9001:2015 Quality Management Systems 4.1.4
3.3.2 AS9100D Quality Management Systems 4.1.4
3.3.3 SAE STD-0016 Standard for Preparing a DMSMS Management Plan 4.1.8
3.3.4 SAE AS6500 Manufacturing Management Program Plan 4.1.11
4.0 TECHNICAL REQUIREMENTS
The Contractor shall perform the following tasks and subtasks in accordance with (IAW) ADs in Section 3.0 and using GFI in Section 6.0. Upon receipt of a Government issued task or delivery order, the contractor shall provide the tasking as specified in individual orders.
4.1 Task A (CLIN 0001) Technical Data Package
4.1.1 Program Management Planning
The contractor shall develop and maintain an Integrated Master Schedule (IMS) that covers all of the SOW tasks and subtasks. The contractor shall include the following items to the IMS:
a) Manufacturing Time-Phase Schedule that logically represent events in the manufacturing process to ensure contract requirements are met including:
a. Development, design, redesign, and test efforts for system elements
b. Implementation schedules of major elements of the manufacturing process
c. Development and testing of software necessary to support manufacturing or testing
d. Subcontractor deliveries including Critical/Strategic Material deliveries
e. Government property need dates
f. End item delivery schedules
Deliverables:
The contractor shall deliver the following:
Integrated Master Schedule IAW CDRL A001
4.1.2 Technical Interchange Meetings
The contractor shall conduct, and attend semi-annual Technical Interchange Meetings (TIM) at the contractor’s facility. The contractor shall present, at a minimum, the following topics at each TIM:
o Schedule status, variance, and schedule risk assessment o Risk assessment and its mitigation o Review of action items o Summary of non-conformance items and request for variance o Technical discussion of CDRL delivered and in-process, CDRL look ahead and address delinquent CDRL deliveries o Test and Evaluation Program Plan status o Diminishing Manufacturing Sources and Material Shortages (DMSMS)/Obsolescence o Product Drawings/Models & Associated List new or revised from the previous meeting o Assessment of manufacturing readiness o Review of test planning and results o Status of procurements, time phased production status
A meeting duration shall be a maximum of 3 days with anticipated average of 2 days. The contractor shall accommodate five Government or Government contractor employees at each meeting. The contractor shall record and complete action items. The contractor shall create meeting minutes and presentation materials for each TIM.
In addition to the semi-annual TIMs, the contractor shall conduct, the TIMs captured in Table 2 in support of the development, test and acceptance of the systems. A semi-annual TIM can be met by a TIM captured in Table 2 if the Table 2 TIM is conducted within 30 calendar days of a scheduled semi-annual TIM.
Table 2 TIM List
Review Name Purpose Performed During CLIN
Anticipated Schedule1
Kickoff TIM #1 Define contract expectations including a review of the SOW and Government Furnished Information.
10 DACA
TIM #2
Review and discuss preliminary design details, including reliability estimates, in relation to the specifications.
90 DACA
TIM #3
Review and discuss final design details in relation to the specifications. Review and discuss system manufacturing and production plans.
180 DACA
TIM #4, #5, #6, and #7 [one per SOW tasks C, D, E, F, G]
Review of test results compared against requirements.
270 DACA
1 DACA in Table 2 refers to calendar days after CLIN/task order award.
Deliverables:
The contractor shall deliver the following:
Report, Record of Meeting Minutes IAW CDRL A002
Presentation Materials IAW A003
4.1.3 Integrated Product Team Teleconferences
The contractor shall lead bi-weekly Integrated Product Team (IPT) teleconferences. The contractor shall discuss the following:
Schedule status, variance, and schedule risk assessment, discussion of progress made towards completing planned work (including work conduction by subcontractors), Technical progress and performance
Risk assessment and its mitigation
Test and Evaluation Program Plan status
Status of procurements, time phased production status
Non-conformances, deficiencies, failure reports and corrective actions
Updates to contractor action items
CDRL look ahead and address delinquent CDRL deliveries
The expected duration for each teleconference is one hour. The contractor shall perform the teleconference within 30 calendar days after contract award.
4.1.4 Engineering Management Program
The contractor shall provide ISO 9001:2015 Quality Management Systems or AS9100D Quality Management Systems certifications on an annual basis via email to the TPOC. The contractor shall provide Government personnel access to their facilities on an annual basis for verification of the contractor quality systems. The contractor shall provide a quality assessment reports.
Deliverables:
The contractor shall deliver the following:
Quality Assessment Report (QAR) IAW CDRL A004
4.1.5 Physical Component Design and Interface Control
The contractor shall deliver a System/Subsystem Design Description (SSDD). The SSDD shall include design details such as proposed hardware and software components and quantities as well as the interfaces / interconnections between the documented design components. The SSDD shall show linkages between the contractor design components and GFI #6.1.
Deliverables:
The contractor shall deliver the following:
System/Subsystem Design Description IAW CDRL A005
4.1.6 Reliability
The contractor shall create a Reliability and Maintainability Predictions Report. The report shall detail the functional block diagrams, hardware components and mathematical models to determine the UCS reliability and maintainability compared to the reliability requirements captured in GFI #6.1. The contractor report shall include a Failure Modes and Effects Criticality Analysis (FMECA) on the UCS hardware components. The contractor shall provide a Proposed Spares List and shall identify spares on a 7-year lifecycle for Commercial off the Shelf (COTS) items and 10-year lifecycle for any custom components.
Deliverables:
The contractor shall deliver the following:
Reliability and Maintainability Predictions Report IAW CDRL A006
Proposed Spares List IAW CDRL A007
4.1.7 Cybersecurity Workforce Qualifications (CSWF)
Per “DFARS 252.239-7001, Information Assurance Contracting Training and Certification” all personnel performing cyber functions must be trained and qualified. Note: DFARS uses the term Information Assurance (IA), which is the old title and acronym; Cybersecurity Workforce (CSWF) has replaced it. Using AD #3.1.3, the contractor is required to earn and maintain appropriate baseline certification for the position and tasking being performed. All identified CSWF personnel identified by the contractor and level approved by the government are required to be certified with criteria IAW AD #3.1.3 within six months of contract award. The contractor shall provide a copy of CWSF certifications and a screenshot of their CompTIA dashboard to the Government. The contractor shall not be required to enter the CSWF certifications in the personnel system referenced in AD #3.1.3.
Using AD #3.1.4, the contractor shall only acquire Commercial off The Shelf (COTS) software application that are listed and approved in the Department of the Navy (DoN) Application and Database Management System (DADMS). If the contractor’s solution contains software, the contractor shall ensure that the UCS incorporates Cybersecurity-Enabled Operating Systems that have been validated or are under evaluation by National Information Assurance Partnership (NIAP) or Common Criteria (CC) scheme and are as follows:
1. Using AD #3.1.5: Configurable IAW applicable DoD Security Technical Implementation Guides (STIG) or System and Network Attack Center (SNAC) guides, and Security Requirements Guides (SRG).
2. Using AD #3.1.5: Able to incorporate the DoD Information Assurance Vulnerability Management Program
(IAVMP)
3. Using AD #3.1.6: Supportable for the expected lifecycle of the system. The contractor shall ensure that the system shall incorporate the DOD licensed virus protection software available at the following DOD website: https://patches.csd.disa.mil upon delivery.
4.1.8 Diminishing Manufacturing Sources and Material Shortages
The contractor shall perform DMSMS reporting and deliver a report. The report shall include identification of DMSMS / Obsolescence issues, cost and readiness impacts, and strategies for issue resolution. The contractor shall modify CDRLs A006 and A007 coincident with the DMSMS report. The contractor shall notify (via email) the Government of forecasted and identified DMSMS issues within five business days of discovering the issue or receiving alert notifications from a vendor.
Deliverables:
Diminishing Manufacturing Sources and Material Shortages Report IAW CDRL A008
4.1.9 Test and Evaluation Program
The contractor shall implement a test program and document it in a Test and Evaluation Program Plan (TEPP). The TEPP shall contain design verification, component integration tests and factory acceptance tests. The TEPP shall contain a matrix that shows the proposed verification methods for compliance with GFI #6.1. The TEPP shall include methods for the Government to test Government off the Shelf (GOTS) software in accordance with GFI #6.2.
The TEPP shall identify the following:
Identify contractor testing prior to factory acceptance tests, Identify the process to record and report all failures, deficiencies, global trend analysis, and anomalies that may occur during production or factory acceptance testing, Identify how the contractor shall implement corrective actions as a result of deficiencies, Test plans and procedures shall be executed IAW Government approved plans and procedures, The contractor shall use GFI #6.2 (Production Representative Display Processing and Control System Test Plan) for integration tests.
Identify integrated tests that will use Government Property. The Government will operate GFE during integration tests.
Deliverables:
Test and Evaluation Program Plan IAW CDRL A009
4.1.10 Product Drawings
The contractor shall perform production engineering using the GFI #6.1 and create product drawings. The contractor prepared product drawings shall include the location of IUID ident-a-plates.
Deliverables:
The contractor shall deliver the following:
Product Drawings/Models & Associated List IAW CDRL A00A
Commercial Off-The-Shelf (COTS) Manuals and Associated Supplemental Data IAW CDRL A00B
4.1.11 Manufacturing Management
The contractor shall develop and maintain a Manufacturing Management Plan. The contractor shall include in the manufacturing plan a list of contractor, subcontractor, and supplier production facilities. The contractor shall identify the products manufactured at each of these facilities.
Manufacturing Plan IAW CDRL A00C
4.2 Task C (CLIN 0002) NUWC System Procurement, Production, and Test
The contractor shall provide material and services to manufacture, assemble and test UCS(s). The contractor shall perform design verification, qualification, and integration testing. The contractor shall conduct a FAT at the contractor’s facility utilizing contractor-provided test equipment and Government operated GFE with observations by Government personnel. The contractor shall deliver a Factory Acceptance Test (FAT) Procedure. The procedure shall include all steps necessary for full verification of the specifications IAW GFI 6.1. The FAT shall include integration testing using GFI #6.2, and the GFE. The contractor shall conduct the FAT and create a FAT Report that captures the results of the test procedures. Any test procedure failures observed during the Government tests will not automatically mean a failure of the contractor system. The contractor shall perform a Physical Configuration Audit at the contractor’s facility, witnessed by the Government, and immediately following the FAT. The contractor shall create a Physical Configuration Audit Plan and Report.
Test Procedures IAW CDRL A00D
Test Report IAW CDRL A00E
Configuration Audit Plan IAW A00F
Configuration Audit Summary Report IAW CDRL A00G
Commercial Off-The-Shelf (COTS) Manuals and Associated Supplemental Data IAW CDRL A00B
4.3 Task D (CLIN 0002) PMRF System Procurement, Production, and Test
The contractor shall provide material and services to procure, manufacture, assemble and test a quantity of one (1) UCS. The contractor shall perform design verification, qualification, and integration testing. The contractor shall conduct a FAT at the contractor’s facility utilizing contractor-provided test equipment and Government operated GFE with observations by Government personnel. The contractor shall deliver a Factory Acceptance Test (FAT) Procedure. The procedure shall include all steps necessary for full verification of the specifications IAW GFI 6.1.
The FAT shall include integration testing using GFI #6.2, and the GFE. The contractor shall conduct the FAT and create a FAT Report that captures the results of the test procedures. Any test procedure failures observed during the Government tests will not automatically mean a failure of the contractor system. The contractor shall perform a Physical Configuration Audit at the contractor’s facility, witnessed by the Government, and immediately following the FAT. The contractor shall create a Physical Configuration Audit Plan and Report.
Test Procedures IAW CDRL A00D
Test Report IAW CDRL A00E
Configuration Audit Plan IAW A00F
4.4 Task E (CLIN 0002) AUTEC System Procurement, Production, and Test
The contractor shall provide material and services to procure, manufacture, assemble and test a quantity of one (1) UCS. The contractor shall perform design verification, qualification, and integration testing. The contractor shall conduct a FAT at the contractor’s facility utilizing contractor-provided test equipment and Government operated GFE with observations by Government personnel. The contractor shall deliver a Factory Acceptance Test (FAT) Procedure. The procedure shall include all steps necessary for full verification of the specifications IAW GFI 6.1.
The FAT shall include integration testing using GFI #6.2, and the GFE. The contractor shall conduct the FAT and create a FAT Report that captures the results of the test procedures. Any test procedure failures observed during the Government tests will not automatically mean a failure of the contractor system. The contractor shall perform a Physical Configuration Audit at the contractor’s facility, witnessed by the Government, and immediately following
Test Procedures IAW CDRL A00D
4.5 Task F (CLIN 0002) SCTTR System Procurement, Production, and Test
The contractor shall provide material and services to procure, manufacture, assemble and test a quantity of one (1) UCS. The contractor shall perform design verification, qualification, and integration testing. The contractor shall conduct a FAT at the contractor’s facility utilizing contractor-provided test equipment and Government operated GFE with observations by Government personnel. The contractor shall deliver a Factory Acceptance Test (FAT) Procedure. The procedure shall include all steps necessary for full verification of the specifications IAW GFI 6.1.
The FAT shall include integration testing using GFI #6.2, and the GFE. The contractor shall conduct the FAT and create a FAT Report that captures the results of the test procedures. Any test procedure failures observed during the Government tests will not automatically mean a failure of the contractor system. The contractor shall perform a Physical Configuration Audit at the contractor’s facility, witnessed by the Government, and immediately following
Test Procedures IAW CDRL A00D
Test Report IAW CDRL A00E
Configuration Audit Plan IAW A00F
4.6 Task G (CLIN 0002) JTTR System Procurement, Production, and Test
The contractor shall provide material and services to procure, manufacture, assemble and test a quantity of one (1) UCS. The contractor shall perform design verification, qualification, and integration testing. The contractor shall conduct a FAT at the contractor’s facility utilizing contractor-provided test equipment and Government operated GFE with observations by Government personnel. The contractor shall deliver a Factory Acceptance Test (FAT) Procedure. The procedure shall include all steps necessary for full verification of the specifications IAW GFI 6.1.
The FAT shall include integration testing using GFI #6.2, and the GFE. The contractor shall conduct the FAT and create a FAT Report that captures the results of the test procedures. Any test procedure failures observed during the Government tests will not automatically mean a failure of the contractor system. The contractor shall perform a Physical Configuration Audit at the contractor’s facility, witnessed by the Government, and immediately following
Test Procedures IAW CDRL A00D
4.7 Task H (CLIN 0003) NUWC Corrective Maintenance (1-year technical support)
The contractor shall provide telephone and email assistance to resolve any integration and associated problems upon completion of Task C. The Government anticipates up to 96 hours will be required for telephone and email assistance services. The contractor shall provide on-site support services if problems cannot be resolved via telephone or email. The Government estimates two trips, 5 days each trip, will be required to provide on-site support services. The contractor shall prepare Meeting Minutes in performance of this support.
Deliverables:
4.8 Task I (CLIN 0003) PMRF Corrective Maintenance (1-year technical support)
The contractor shall provide telephone and email assistance to resolve any integration and associated problems upon completion of Task D. The Government anticipates up to 96 hours will be required for telephone and email assistance services. The contractor shall provide on-site support services if problems cannot be resolved via telephone or email. The Government estimates two trips, 5 days each trip, will be required to provide on-site support services. The contractor shall prepare Meeting Minutes in performance of this support.
Deliverables:
4.9 Task J (CLIN 0003) AUTEC Corrective Maintenance (1-year technical support)
The contractor shall provide telephone and email assistance to resolve any integration and associated problems upon completion of Task E. The Government anticipates up to 96 hours will be required for telephone and email assistance services. The contractor shall provide on-site support services if problems cannot be resolved via telephone or email. The Government estimates two trips, 5 days each trip, will be required to provide on-site support services. The contractor shall prepare Meeting Minutes in performance of this support.
Deliverables:
4.10 Task K (CLIN 0003) SCTTR Corrective Maintenance (1-year technical support)
The contractor shall provide telephone and email assistance to resolve any integration and associated problems upon completion of Task F. The Government anticipates up to 96 hours will be required for telephone and email assistance services. The contractor shall provide on-site support services if problems cannot be resolved via telephone or email. The Government estimates two trips, 5 days each trip, will be required to provide on-site support services. The contractor shall prepare Meeting Minutes in performance of this support.
Deliverables:
The contractor shall deliver the following:
Report, Record of Meeting Minutes IAW CDRL A002
4.11 Task L (CLIN 0003) JTTR Corrective Maintenance (1-year technical support)
The contractor shall provide telephone and email assistance to resolve any integration and associated problems upon completion of Task G. The Government anticipates up to 96 hours will be required for telephone and email assistance services. The contractor shall provide on-site support services if problems cannot be resolved via telephone or email. The Government estimates two trips, 5 days each trip, will be required to provide on-site support services. The contractor shall prepare Meeting Minutes in performance of this support.
4.12 Task M (CLIN 0004) Technical Data Package Revisions
The contractor shall provide updates and revisions to the technical data package delivered by the contractor and accepted by the Government as part of Task A (CLIN 0001). The TDP delivered as part of Task A is the baseline for making updates. Tasking will be specified in individual task orders and includes updates for parts obsolescence, Diminishing Manufacturing Sources and Material Shortages, manufacturing lessons learned / efficiencies / rework, and rework due to testing. The contractor shall also make updates for changes to the form, fit, function, interface, reliability, supportability, or safety to the baseline.
Deliverables will be specified in individual task orders.
5.0 PROGRESS REPORTS
For all assigned tasks, the contractor shall prepare a Contract Status Report (in accordance with CDRL A00H) that indicates the progress of work, status of the program(s), and existing or potential problem areas. The contractor shall submit the Contract Status Report for the same timeframe as each invoice submitted in the Invoicing, Receipt, Acceptance, and Property Transfer (iRAPT) module of Wide Area Work Flow (WAWF).
Contract Performance Reports IAW CDRL A00H
6.0 GOVERNMENT FURNISHED INFORMATION & EQUIPMENT
The following Government Furnished Information (GFI) will be made available under this contract.
Number Title SOW section
6.1. 20220905 PR 1301041505 MMTS 101408 Encl (4) UCS Hardware PS
20220815_RR_WES
4.1.5, 4.1.6, 4.1.9, 4.1.10, 4.2, 4.3, 4.4, 4.5, and 4.6
6.2. USWTR_ASRP UCS Hardware Integration Test Plan
4.1.9, 4.2, 4.3, 4.4, 4.5, and 4.6
7.0 EXCEPTION FROM INFORMATION AND COMMUNICATION TECHNOLOGY
ACCESSIBILITY REQUIREMENTS
The Government has determined that this procurement is an exception to the Information and Communication Technology (ICT) Accessibility Standards (36 C.F.R. Part 1194, Appendix A). Notwithstanding that an exception exists, the Contractor may furnish items or services provided under this contract that comply with the ICT Accessibility Standards (36 C.F.R. Part 1194, Appendix A).
Exception #2 located in space frequented by service personnel at the following:
Atlantic Undersea Test and Evaluation Center (AUTEC), Command and Control Building
Pacific Missile Range Facility (PMRF), Range Operations Center
Southern California Tactical Training Range (SCTTR), Cable Termination Shelter
Jacksonville Tactical Training Range (JTTR), Cable Termination Facility