N64498-21-Q-0195 Amendment 0001.pdf
PDF 623 KB Posted
- Attached to
- Bldg 77H Split System HP-3 Replacement, NSWCPD Federal contract opportunity
- Solicitation number
- N6449821Q0195
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SOW Attach 1_SiteMap PNBC.pdf | ||
| SOW Attach 2_Contractor Production Report Form.doc | DOC document | |
| SOW Attach 3_Contractor Lift Plan Form.pdf | ||
| SOW Attach 8_Instrumentation Drawings - Split HP-3 DDC Schematic.pdf | ||
| SOW Attach 4_Mobile Equipment Check List.pdf | ||
| SOW Attach 6_NSWCPD ENTRY SCREENING ASSESSMENT 26 APR 2021 Rev 10.pdf | ||
| SOW Attach 9_Sketch 1 -- Bldg 77H Split System HP-3.pdf | ||
| Attach 10_ Construction Cost Breakdown.xlsx | XLSX spreadsheet | |
| N64498-21-Q-0195.pdf | ||
| SOW Attach 5_AHA Form.docx | DOCX document | |
| SOW Attach 7_Photographs - B-77H Split System HP-3 Replacement.docx | DOCX document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
1) The purpose of this amendment is to make a change to the Statement of Work (SOW) as follow s:
Change Section 2.5.1.4 from:
Section 2.5.1.4 - The contractor shall move the inlet to the condensate drain north along the side of the control house building such that a person does not have to traverse over or under the new AHU HP- 3 Ductw ork to access the drain location. The contractor shall relocate all lines that go to this drain to the new locations w ith like materials. See Attachment 9 for schematic of new location of drain.
Change Section 2.5.1.4 to:
Section 2.5.1.4 - The contractor shall reconnect the new AHU HP-3 drains to the existing drain location using like materials.
2) The closing date and time for reciept of quotes remains unchanged.
3) All other terms and conditions remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 21
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Aug-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6449821Q0195
X 9B. DATED (SEE ITEM 11)
12-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Aug-2021
CODE
NAVAL SURFACE WARFARE CENTER PHILA
CODE 0222, LINDA M. DOBBS
267-990-6017, LINDA.M.DOBBS@NAVY.MIL
5001 SOUTH BROAD STREET
PHILADELPHIA PA 19112
N64498 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6449821Q0195
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The Issued By organization has changed from
NAVAL SURFACE WARFARE CENTER PHILA
CODE 0222, LINDA M. DOBBS
267-990-6017, LINDA.M.DOBBS@NAVY.MIL
5001 SOUTH BROAD STREET
PHILADELPHIA PA 19112
to
NAVAL SURFACE WARFARE CENTER PHILA
5001 SOUTH BROAD STREET
PHILADELPHIA PA 19112
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
SOW
BLDG 77H SPLIT SYSTEM HP-3 REPLACEMENT
STATEMENT OF WORK
1.0 SECTION 1: GENERAL
1.1 SYNOPSIS: This Statement of Work (SOW) defines the requirement to remove and replace the existing
Bldg 77H Split System HP-3, also referred to as Split System #3. The new air-handling unit shall consist of installing a 10-ton split system rated for no less than 4,000 cubic feet per minute (CFM) with a minimum of 5-kilowatts (-KW) of electric heat. The new condenser unit shall consist of a multi-stage condenser containing a minimum of two (2) separate independent refrigeration units. Additionally, the contractor shall install new outside-air ductwork capable of supplying 100 percent outside air for economizing with associated mixing box and actuated return and outside-air dampers. The contractor shall provide a new controller, run conduit and wire, as required. The contractor shall also supply a new handrail for the new AHU unit. Upon completion of the work, the contractor shall deliver a full and complete operating cooling system that is to be fully controlled by the existing Automated Logic Direct Digital Control (DDC) System. The Contractor shall furnish all labor, material, tools, equipment, supplies, testing and supervision to perform this work as described in Section 2.
1.2 SITE LOCATION: The work is located on Government-owned property at the Philadelphia Naval Business
Center (PNBC), also referred to as the Philadelphia Navy Yard Annex (PNYA). The work is located in the southwestern side of Naval Surface Warfare Center Philadelphia Division (NSWCPD), Building 77H, having street address of 901 Admiral Peary Way, Philadelphia, PA, 19112. Bldg 77H is predominantly an industrial, high-bay type of building occupied with working equipment, machinery, and laboratory space. The existing air handling unit (Model # TWE120A300EL) for Split System HP-3 is located on top of the Control House within Building 77H, with the condenser (Model #TTA120) being located on the roof of Bldg 756. See SOW Attachment 1 for overall site location within PNBC.
1.3 TIME OF COMPLETION: Work shall be prosecuted diligently and completed for use within 90 calendar days after award. The time stated for completion shall include final clean-up of the premises, acceptance of the work by the Government, and submittal of any contract required documentation or reports. Contractor is required to furnish proof of any cause for delay and shall request an extension of the completion date in writing through the NSWCPD Contracting Officer.
1.4 GOVERNMENT TECHNICAL POINT OF CONTACT (TPOC): The TPOC is a representative of the
NSWCPD Contracting Officer and provides technical and administrative assistance related to the subject contract and work. All scheduling and coordination shall be through the NSWCPD TPOC.
1.5 SITE VISIT: Contractor shall verify all conditions, dimensions and methods at the site prior to start of work.
The contractor shall notify the TPOC in writing of differences in site conditions described in this SOW versus the contractor’s field verifications within five days of the contactor’s site visit.
1.6 PAYMENT: Shall be made in one lump sum after completion and acceptance of the work by the Government Quality Assurance Representative.
1.7 WORK MATERIALS: Unless otherwise noted, the Contractor shall furnish all materials to complete the Statement of Work. The Contractor is responsible for procurement, shipping and storage of all material.
1.8 GOVERNMENT FURNISHED UTILITIES: The Government shall furnish the following utility services for use as may be required for the work to be performed under the contract: electricity and potable water.
Government-furnished electricity may be used by the contractor unless contractor’s use adversely impacts a building’s electrical distribution system and equipment. Information concerning the location of existing outlets may be obtained from the NSWCPD TPOC. The Contractor shall provide and maintain the necessary service lines from existing Government outlets to the site of the work. For the utilities specified above, they shall be furnished at no cost to the Contractor. In the event that the Government is unable to provide the required types of utilities, the Contractor shall, at its expense, arrange for the required utilities.
1.9 EXECUTION OF WORK: The Contractor’s and subcontractor(’s) work shall be performed during normal duty hours from 0700 to 1700, Monday through Friday (excluding Federal Holidays). Any work requiring shutdown or temporary disruption of electrical, mechanical, security and fire-protection systems may be performed off normal duty hours subject to approval from the NSWCPD TPOC. Off-hour work shall be coordinated with the NSWCPD TPOC.
1.10 QUALITY CONTROL (QC) AND DAILY PRODUCTION REPORTS: The Contractor shall submit a “Contractor Production Report” (SOW Attachment 2) for each day work is performed for review and approval by the NSWCPD TPOC. This is required to account for each calendar day throughout the life of the Contract. The reporting of work shall be identified by terminology consistent with the work schedule. Enter pertinent information including directions received, problems encountered during work, work progress and delays, conflicts or errors in the drawings or specifications, field changes, safety hazards encountered, instructions given and corrective actions taken, a record of visitors to the work site, quality control problem areas, deviations from the QC Plan, work deficiencies encountered, and meetings held. The completed reports shall be submitted to the NSWCPD TPOC by 1000 the following day.
1.11 CLEAN-UP OF SITE: The contractor shall maintain a clean and safe worksite. All scrap materials, waste, and debris shall be removed from work site on a daily basis. Contractors are not permitted to use Government dumpsters or other Contractor dumpsters for disposal of debris. Do not use building restrooms occupied by NSWCPD personnel for cleaning of equipment.
1.12 HOT WORK: For all hot work, a hot-work permit is required and a permit shall be obtained through the
Government Fire Inspector. Requests for hot work permits shall be submitted to the NSWCPD TPOC with a 48-hour notice for review. Hot work in electrical- or mechanical-room space shall require a gas-free test prior to the Government fire inspector granting approval. In accordance with the Government fire inspector’s requirements, the Contractor shall perform this test daily. The Government fire inspector shall approve the instrument used. Fire extinguishers shall be provided by the Contractor at ALL locations where cutting is performed.
1.13 CONTRACTOR REQUIREMENTS FOR LIFT OPERATIONS: Contractor shall comply with the requirements of Naval Facilities Command (NAVFAC) P-307, Weight Handling Program Management, and SOW Attachment 3, “Requirements for Contractor Lift Operations” for all work performed with cranes or other machines used to lift equipment or materials. Related to lift and weight-handling operations, contractor shall submit Machinery and Mobile Equipment Check List (SOW Attachment 4) if required.
1.14 DUST CONTROL: All dust resulting from the performance of this work shall be controlled to prevent the spread of dust to occupied portions of the site and to avoid the creation of a nuisance in the surrounding areas.
Use of water shall not be permitted when it shall result, or create, hazardous or objectionable conditions such as ice, flooding and pollution. Note: The prevention and control of dust is especially important when repair work is performed adjacent to building HVAC-outside-air intakes, return ductwork, or vents.
1.15 SUPERVISION AND CONTRACTOR PERSONNEL: The Contractor shall have at least one qualified supervisor, i.e., Project Superintendent, capable of reading, writing, and conversing fluently in the English language on the work site full-time during all working hours. The Contractor shall provide personnel and subcontractors meeting the minimum requirements or qualifications stated in Section 2, Detailed Description of Work, below. A minimum of two Contractor personnel are required to perform the functions of Project Superintendent, Site Safety and Health Officer (SSHO), and Contractor Quality Control System Manager (CQCSM); the latter two personnel responsibilities are described in Subsections 1.15.1 and 1.15.2 below:
1.15.1 Site Safety and Health Officer (SSHO): The contractor shall provide a Safety oversight team that includes a minimum of one (1) Competent Person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO shall visit the work site daily, unless specified differently in the contract, to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The SSHO’s training, experience, and qualifications shall meet EM 385-1-1 paragraph 01.A.17 and all associated sub-paragraphs. The SSHO may serve as the Superintendent on this project.
1.15.2 Contractor Quality Control System Manager (CQCSM): Provide a CQCSM for the work site to manage and implement the Contractor Quality Control (CQC) program. The CQCSM shall be responsible for overall management of the Contractor Quality Control program and has the authority to act and give direction in all CQC matters for the Contractor. The CQCSM shall have been regularly engaged in work and repair projects of similar type, size, and complexity that has included the major trades executing the work of this contract. The CQCSM shall be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification, safety compliance, and sustainability. The CQCSM may serve as the SSHO; however, the CQCSM cannot perform the duties of Project Superintendent.
1.16 SUBMITTALS: The Contractor shall submit the pre-work submittals of SOW Section 1.17 below within fourteen (14) calendar days after award. The Contracting Officer or NSWCPD TPOC may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal shall be legible, well-organized, complete, and in sufficient detail to allow ready determination of compliance with contract requirements. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only “FIO.”
1.16.1 Submittal Procedures: Both “G” and “FIO” submittals shall be transmitted to NSWCPD using a
Transmittal format. Provide submittals in electronic format, with the exception of material samples.
Compile the submittal file as a single, complete document, to include the Transmittal Form (ENG Form 4025-R) as the first page. Form available for download at:
https://www.publications.usace.army.mil/USACE-Publications/Engineer-Forms/. Note that all instances of the “US Army Corp of Engineers” on the transmittal form shall be interpreted as “Naval Surface Warfare Center Philadelphia Division.” Name the electronic submittal file according to its contents. Name the electronic submittal file according to its contents. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Provide hard copies of submittals when requested by the Contracting Officer or NSWCPD TPOC. Submittals requiring
Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby.
1.17 PRE-WORK SUBMITTALS:
1.17.1 Pre-work submittals marked with a “G” require Government approval prior to the Contractor's mobilization to the work-site location.
1.17.2 Project Schedule - G: Prior to the start of work, the Contractor shall prepare and submit, a work schedule to the NSWCPD TPOC. The schedule shall, as a minimum, show work activities, submittals, material/equipment delivery, utility outages, on-site work, testing, and closeout activities.
The schedule shall be time scaled and generated using scheduling software. The schedule shall be kept current during this contract, reflecting actual activity progress and plan for completing the remaining work.
1.17.3 Activity Hazard Analysis - G: in accordance with EM 385-1-1. See SOW Attachment 5 for blank form and sample. See SOW paragraph 3.6.2 for additional information. The AHA shall cover all aspects of the work, including fall protection.
1.17.4 NSWCPD Entry Screening Assessment: See SOW Attachment 6. See Section 3.6.2 for Daily review requirements.
1.17.5 Accident Prevention Plan (APP) - G: The Contractor shall submit a site-specific APP to the NSWCPD TPOC. The site-specific APP shall outline the job-specific hazards associated with the project scope and reflect the Contractor’s overall safety and health program. As a minimum, the plan shall meet the requirements of the abbreviated Accident Prevention Plan identified in the U. S. Army Corps of Engineers Safety and Health Requirements Manual, EM-385-1-1, Appendix A. The plan shall also address all items listed in SOW Section 3.5.
1.17.6 Certified Technicians. The contractor shall submit documentation that their workers are certified to dispose of equipment and recycle refrigerants that could release refrigerants to the atmosphere per Section 608 of the Clean Air Act. All technicians working on equipment that contain ozone depleting refrigerants must be certified as a Section 608 Technician to meet requirements in 40 CFR 82, Subpart F.
1.17.7 Contractor’s Daily Production Report: See SOW Attachment 2. The Requirements are listed in SOW Section 1.10 above
1.17.8 Requirements for Contractor Lift Operations: See SOW Attachment 3. This shall be completed as required per SOW Section 1.13.
1.17.9 Machinery and Mobile Equipment Checklist: See SOW Attachment 4. This shall be completed as required per SOW Section 1.13 and SOW Section 3.5.2.14.
1.17.10 Forms Required For Security Vetting and Badging – See SOW Section 3.6.
1.17.11 Ductwork Layout – See SOW Section 2.5.3.
1.17.12 List of proposed Subcontractors – FIO: Provide the NSWCPD TPOC a list of all proposed subcontractors including address, telephone number, point of personal contact, qualifications, and certifications for the completion of project tasks stated in Section 2, Detailed Description of Work, below.
1.17.13 List of proposed Products - G: Provide the NSWCPD TPOC a list of proposed products, cut sheets, lead times, and applicable Safety Data Sheets (SDS) for all Contractor furnished materials to be used in the performance of this work. Note that this overall, comprehensive list of proposed products is G;
however, some individual items on this list of proposed products may be considered FIO by the NSWCPD TPOC. Contractor shall submit submittals on AHU, Condenser, outside air intake/grille, ductwork, and mixing box prior to ordering and installing any equipment.
1.18 ADDITIONAL SUBMITTALS: Contractor shall make other submittals as required in Sections 2 and 3 of this Statement of Work, in addition to the pre-work submittals of Section 1.17 above. In general, the additional submittals of Section 2 are material samples, material information or cuts sheets, Safety Data Sheets (SDS), contractor qualifications, technical manuals, test plans, etc. All submittals other than pre-work submittals shall be submitted by the Contractor a minimum of fourteen (14) calendar days before the start of the particular task or definable feature of work (DFOW) to which the submittal is associated to provide sufficient Government review-and-approval time. One additional submittal is listed below:
1.18.1 Warranty Information – G: Contractor shall submit warranty information guaranteeing all products and workmanship used in this work shall be free of defects for a minimum of one year.
1.19 CONFINED SPACE: The Contractor shall comply with 29 CFR 1910.146 regarding permit-required confined space entry. The contractor shall provide a competent person to write all confined space permits.
1.20 HAZARDOUS MATERIAL: The Contractor is responsible for the handling, storage, removal, and disposal of hazardous material. Hazardous material waste shall be collected, stored, and disposed of in accordance with Navy, Federal, State, and Local requirements. Contractor shall remove and recycle refrigerant according to local and federal laws.
1.21 ELECTRICAL SAFETY: Comply with Electrical Safety procedures in accordance with 29 CFR 1926. For additional information, refer to Chapter 12, of NAVSSESINST 5100.14G.
1.22 LOCK-OUT, TAG-OUT: Comply with NSWCPD Lock-out/Tag-out procedures in accordance with
Chapter 11 of NAVSSESINST 5100.14G and 29 CFR 1926. Only authorized NSWCPD personnel shall perform the Lock-Out and Tag-Out of Electrical, Mechanical, Piping, Machinery, or Equipment.
1.23 OPERATION SECURITY (OPSEC): The Contractor shall protect critical information associated with this contract to prevent unauthorized disclosure. The NSWC Philadelphia Division's (NSWCPD) Critical Information List, (CIL) will be provided on site, if warranted. Performance under this contract requires the contractor to adhere to OPSEC requirements. The Contractor may not impose OPSEC requirements on its subcontractors unless NSWCPD approves the OPSEC requirements. During the period of this contract, the Contractor may be exposed to, use, or produce, NSWCPD Critical Information (CI) and/or observables and indicators which may lead to discovery of CI. NSWC PD’s CI will not be distributed to unauthorized third parties, including foreign governments, or companies under Foreign Ownership, Control, or Influence (FOCI). CUI correspondence transmitted internally on the contractor's unclassified networks or information systems, and externally, shall be protected per NIST SP-800-171, Protecting Controlled Unclassified Information (CUI) in Non-federal Systems and Organizations. Assembled large components/systems being transported to and from testing areas, other production or government facilities (whether or not on public roadways) shall be in an enclosed van trailer or covered flatbed trailer. Component/System outside storage, staging, and test areas shall be shielded/obscured from public view wherever physically possible.
NSWCPD’s CI shall not be publicized in corporate wide newsletters, trade magazines, displays, intranet pages or public facing websites. Media requests related to this project shall be directed to the PCO, and the COR who will forward the required to the NSWCPD Public Release Authority for review. Any attempt by unauthorized third parties to solicit, obtain, photograph, or record, or; incidents of loss/compromise of government Classified or CI, Business Sensitive, Company Proprietary information related to this or other program must be immediately reported to the contractor's Facility Security Officer and Cognizant Security Office and/or the Naval Criminal Investigative Service, and the NSWC PD Security Division (Code 105.1).
Questions concerning these requirements shall be directed to the PCO, and the COR who will forward the request to the NSWCPD Security Division (Code 105.1).
1.24 REFERENCES: The publications listed below form a part of this Statement of Work and are incorporated by reference. Provision and installation of the materials and components comprising this Statement of Work shall be in compliance with applicable or relevant and appropriate requirements, including the following industry standards and regulations:
Air-Conditioning, Heating and Refrigeration Institute (AHRI) AHRI 260 I-P(2012) Sound Rating of Ducted Air Moving and Conditioning Equipment AHRI 410(2011) Forced-Circulation Air-Cooling and Air-Heating Coils AHRI 430(2009) Central-Station Air-Handling Units AHRI Guideline D(1996) Application and Installation of Central Station Air-Handling Units
American Bearing Manufacturers Association (ABMA) ABMA 9 (2015) Load Ratings and Fatigue Life for Ball Bearings
ABMA 11 (2014) Load Ratings and Fatigue Life for Roller Bearings
American National Standards Institute (ANSI) ANSI C80.3 (2015) Electrical Metallic Tubing – Steel (EMT-S) ANSI/ASME Y14.1 (2012) Decimal Inch Drawing Sheet Size and Format ANSI Z87.1 (2020) International Standard for Occupational and Educational Personal Eye and Face
Protection Devices ANSI Z89.1 (2014) Industrial Head Protection ANSI Z535.1 (2017) American National Standard for Safety Colors
American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE) ASHRAE 15 (2019) Safety Standard for Refrigeration Systems ASHRAE 34 (2019) Designation and Safety Classification of Refrigerants ASHRAE 52.2(2012) Method of Testing General Ventilation Air-Cleaning Devices for Removal
Efficiency by Particle Size ASHRAE 62.1(2010) Ventilation for Acceptable Indoor Air Quality ASHRAE 70(2006; R 2011) Method of Testing for Rating the Performance of Air Outlets and Inlets ASHRAE 90.1 (2019) Energy Standard for Buildings Except Low-Rise Residential Buildings ASHRAE 135 (2020) BACnet, A Data Comunicatino Protocol for Building Automation and Control
Networks
Associated Air Balance Council (AABC) AABC MN-1(2002; 6th ed) National Standards for Total System Balance AABC MN-4(1996) Test and Balance Procedures
American Society of Mechanical Engineers (ASME) ASME B16.1 (2015) Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125, and 250 ASME B16.5 (2017) Pipe Flanges and Flanged Fittings NPS 1/2 Through NPS 24 Metric/Inch Standard ASME Section IX Welding and Brazing
American Welding Society (AWS) AWS Z49.1 (2012) Safety in Welding and Cutting and Allied Processes
ASTM International (ASTM) ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless ASTM A123/A123M(2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and
Steel Products ASTM A126 (2019) Standard Specification for Gray Iron Castings for Valves, Flanges, and Pipe Fittings ASTM A167(2011) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel
Plate, Sheet, and Strip ASTM A276/A276M (2017) Standard Specification for Stainless Steel Bars and Shapes ASTM A307 (2017) Standard Specification for Carbon Steel Bolts, Studs, and Threaded Rod 60
000 PSI Tensile Strength ASTM A924/A924M(2018) Standard Specification for General Requirements for Steel Sheet, Metallic-
Coated by the Hot-Dip Process ASTM B75/B75M(2011) Standard Specification for Seamless Copper Tube ASTM B117(2016) Standard Practice for Operating Salt Spray (Fog) Apparatus ASTM B152/B152M(2013) Standard Specification for Copper Sheet, Strip, Plate, and Rolled Bar ASTM B209(2014) Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate ASTM B280(2018) Standard Specification for Seamless Copper Tube for Air Conditioning and
Refrigeration Field Service
ASTM B766(1986; R 2015) Standard Specification for Electrodeposited Coatings of Cadmium ASTM C553(2013) Standard Specification for Mineral Fiber Blanket Thermal Insulation for
Commercial and Industrial Applications ASTM C916(2014) Standard Specification for Adhesives for Duct Thermal Insulation ASTM C1071(20162019) Standard Specification for Fibrous Glass Duct Lining Insulation (Thermal and
Sound Absorbing Material) ASTM D520(2000; R 2011) Zinc Dust Pigment ASTM D1654(2008; R 2016; E 2017) Standard Test Method for Evaluation of Painted or Coated Specimens
Subjected to Corrosive Environments ASTM D1785(2015; E 2018) Standard Specification for Poly(Vinyl Chloride) (PVC), Plastic Pipe, Schedules 40, 80, and 120 ASTM D2466(2017) Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 40 ASTM D2564(2012) Standard Specification for Solvent Cements for Poly(Vinyl Chloride) (PVC)
Plastic Piping Systems ASTM D2855(2015) Standard Practice for Making Solvent-Cemented Joints with Poly(Vinyl Chloride)
(PVC) Pipe and Fittings ASTM D3359(2017) Standard Test Methods for Rating Adhesion by Tape Test ASTM E84(2018a) Standard Test Method for Surface Burning Characteristics of Building Material ASTM E2016(2015) Standard Specification for Industrial Woven Wire Cloth ASTM F104 (2020) Standard Classification System for Nonmetallic Gasket Materials ASTM F2412 (2018) Standard Test Methods for Foot Protection
Institute of Electrical and Electronics Engineers (IEEE) IEEE 112(2017) Standard Test Procedure for Polyphase Induction Motors and Generators IEEE C2(2017;) National Electrical Safety Code
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) MSS SP-67 (2017) Butterfly Valves MSS SP-72 (2010) Ball Valves with Flanged or Butt-Welding Ends for General Service MSS SP-70(2011) Gray Iron Gate Valves, Flanged and Threaded Ends
National Air and Duct Cleaners Associations (NADCA) NADCA HVAC Inspection Procedures for Assessing the Cleanliness of Commercial HVAC Systems
National Fire Protection Association (NFPA) NFPA 70 (2020) National Electric Code (NEC) NFPA 70E (2021) Standard for Electrical Safety in the Workplace NFPA 90A(2018) Standard for the Installation of Air Conditioning and Ventilating Systems
National Electrical Manufacturers Association (NEMA) NEMA ICS 6(1993; R 2016) Industrial Control and Systems: Enclosures NEMA MG 1(2016; SUPP 20162018) Motors and Generators NEMA MG 10(2017) Energy Management Guide for Selection and Use of Fixed
Frequency Medium AC Squirrel-Cage Polyphase Induction Motors NEMA MG 11(1977; R 2012) Energy Management Guide for Selection and Use of Single Phase
Motors
International Electrical Testing Associations (NETA) NETA ATS(2017) Standard for Acceptance Testing Specifications for Electrical Power Equipment and
Systems NETA MTS(2015) Standard for Maintenance Testing Specifications for Electrical Power Equipment and
Systems
Society of Automotive Engineers International (SAE) SAE AMS-STD-595A (2017) Colors Used in Government Procurement
Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA) SMACNA 1403(2008) Accepted Industry Practice for Industrial Duct Construction, 2nd Edition SMACNA 1780(2002) HVAC Systems - Testing, Adjusting and Balancing, 3rd Edition SMACNA 1819(2002) Fire, Smoke and Radiation Damper Installation Guide for HVAC Systems, 5th Edition SMACNA 1884(2003) Fibrous Glass Duct Construction Standards, 7th Edition SMACNA 1966(2005) HVAC Duct Construction Standards Metal and Flexible, 3rd Edition SMACNA 1972 CD(2012) HVAC Air Duct Leakage Test Manual - 2nd Edition
The Society for Protective Coatings (SSPC) SSPC-SP 2 (2018) Hand Tool Cleaning SSPC-SP 3 (2018) Power Tool Cleaning
Underwriter’s Laboratory (UL) UL 1 (2020) UL Standard for Safety Flexible Metal Conduit UL 6(2014) UL Standard for Electrical Rigid Metal Conduit-Steel UL 83 (2020) UL Standard for Safety Thermoplastic-Insulated Wires and Cables UL 181(2017) UL Standard for Safety Factory-Made Air Ducts and Air Connectors UL 360 (2018) UL Standard for Safety Liquid-Tight Flexible Metal Conduit UL 514B (2020) Conduit, Tubing and Cable Fittings UL 555(2006; Reprint Aug 2016) UL Standard for Safety Fire Dampers UL 1995(2015) UL Standard for Safety Heating and Cooling Equipment
Unified Facilities Criteria (UFC) UFC 1-200-01 (2020) DoD Building Code (General Building Requirements) UFC 3-410-01 (2020) Heating, Ventilating, and Air Conditioning Systems UFC 3-410-02 (2020) Direct Digital Control for HVAC and Other Building Control Systems UFC 4-010-06 (2017) Cybersecurity of Facility-Related Control Systems
United States Army Corps of Engineers (USACE) EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. Department of Defense (DoD) MIL-STD-101(2014; Rev C) Color Code for Pipelines and for Compressed Gas Cylinders
U.S. Department of Defense (DoD) Instructions (Inst.)
DoD Instr. 8500.01 (2019) Cybersecurity DoD Instr. 8510.01 (2017) Risk Management Framework for DoD Information Technology
U.S. Department Of Energy (DoE) Energy Star(1992; R 2006) Energy Star Energy Efficiency Labeling System (FEMP)
1.25 LIST OF ATTACHMENTS: The following attachments form part of this Statement of Work and are incorporated by reference:
1.25.1 Attachment 1, Site Map –PNBC (1 page);
1.25.2 Attachment 2, Contractor Production Report (1 page);
1.25.3 Attachment 3, Requirements for Contractor Lift Operations (8 pages);
1.25.4 Attachment 4, Mobile Construction Equipment Checklist (2 pages);
1.25.5 Attachment 5, Activity Hazard Analysis (3 pages);
1.25.6 Attachment 6, NSWCPD Entry screening Assessment (1 page);
1.25.7 Attachment 7, Photographs – B-77H Split System HP-3 Replacement (7 pages);
1.25.8 Attachment 8, Instrumentation Drawings – Split HP-3 DDC Schematic (1 page); and,
1.25.9 Attachment 9, Schematic Sketch 1 – Layout Drawing (1 page).
2.0 SECTION 2: DETAILED DESCRIPTION
2.1 General: Supplemental information for the following work can be found in SOW Attachment 7
(Photographs), SOW Attachment 8 (Instrumentation drawings for DDC panel), and SOW Attachment 9, (Sketch 1 – Schematic Drawing). The following SOW sections describe the demolition, equipment, installation, and start-up materials and activities defining this project.
2.2 The contractor shall Label all equipment with labels made of self-sticking, plastic film designed for permanent installation. The contractor shall review labels with TPOC for approval prior to installing on the equipment.
2.3 Demolition and Deconstruction
2.3.1 No demolition work may begin until all material related to new work in SOW Section 2 are at the work site. The contractor shall take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. The contractor shall take appropriate action to protect all personnel working in and around the project site, including below the work site.
2.3.2 The contractor shall remove and recycle all of the existing refrigerant between the existing Air-
Handling Unit (AHU) HP-3, the condenser and the existing line sets in accordance with applicable or relevant and appropriate local and Federal laws. The existing refrigerant is R-22. The contractor shall have certified technicians to handle this work.
2.3.3 The contractor shall remove and properly dispose of the existing AHU HP-3, the existing condensate drip pans, and the electrical disconnect located on top of the control house within Building 77H, marked as HP-3, 77H-7. The contractor shall demolish and save the existing Direct Digital Control (DDC) panel to be re installed as required in Section 2.5.1.4.
2.3.4 The Contractor shall remove and properly dispose of the following existing ductwork:
2.3.4.1 Demolish the supply duct between the AHU HP-3 and the ducted elbow into the control house; and
2.3.4.2 Demolish the return duct between the AHU HP-3 and the ducted elbow into the control house.
2.3.5 The contractor shall remove and properly dispose of the existing condenser and the existing lines sets between the condenser and the AHU HP-3 located on the roof of Bldg 756, marked as HP-3, 77H-7.
2.3.5.1 The contractor may save and reuse the existing condenser supports if appropriate.
2.4 Equipment and Materials
2.4.1 The contractor shall replace the existing air handling unit (Trane Model # TWE120A300EL) and supply a new Constant Volume Air Handling unit with the following specifications and salient features:
2.4.1.1 The unit shall be a ten(10) ton AC cooling split system unit rated for no less than 4,000 cubic feet per minute (cfm), complete with a heater rated at no less than five (5) KW to be used for dehumidification and minimal electric heating as needed. The AHU fan and motor shall be sized such that AHU is capable of producing the same external static pressure (after the electric heater) as existing equipment currently supplies.
2.4.1.2 The unit shall fit on the existing 8-foot by 7-foot pad on the top of the control house.
2.4.1.3 The unit shall be certified and rated in accordance with AHRI 430 and AHRI certified for cooling.
2.4.1.4 The unit shall have a dual refrigeration circuit and the unit shall utilize R-410A refrigerant.
R-22 shall not be used.
2.4.1.5 The AHU shall have an air-tight insulated casing with the casing insulation conforming to NFPA 90A. Insulation shall not be less than 1-inch thick, 1.5-pound density coated fibrous glass material having a thermal conductivity not greater than 0.23 Btu-in/hr-sf-F.
2.4.1.6 The AHU unit shall have interlaced / intertwined evaporator coils. One-hundred percent (100%) of the coils shall be leak tested at a minimum of 450 psig.
2.4.1.7 The contractor shall have the manufacturer perform a 100-percent unit run test prior to shipping the unit.
2.4.1.8 Equipment shall operate at 460-volts, 3-phase, and 60-Hz electrical supply. The AHU-fan motor shall have a service factor of at least 1.15.
2.4.1.9 The AHU unit shall be equipped with secondary stainless drip pan
(a) The Drip pan shall be a min 3-inches longer and wider than the new AHU unit.
(b) New condensate pans shall be 304 stainless steel or approved equal.
(c) The contractor shall supply the drip pan with a float type wet detector(s) to be tied into the DDC system.
(d) New condensate pans shall be piped utilizing 3/4-inch minimum PVC piping to the floor drain(s) in a similar fashion as the existing condensate drains. The drain shall include a trap.
2.4.1.10 The equipment shall be provided with an onboard controller with the following specifications and salient features:
(a) The controller shall have an on-board user interface with a minimum 2-inch by 16-inch backlit LCD display and navigation buttons. The navigation buttons shall allow the user to view status, configure, and troubleshoot the unit without additional tools.
(b) The controller shall be configured for conventional thermostat connection for control of fan, compressor 1, compressor 2, and electric heaters 1.
(c) The controller shall be compatible with Bacnet Open protocol to operate with the Gov’t current control system.
For instance, Trane Model Number TWE12044B with Symbio 700 Controller and Trane condenser unit, Model Number TTA12044D is an example of a unit that meets the salient features discussed above.
2.4.2 The contractor shall replace the existing condenser (Trane Model #TTA120) and supply a new multi-stage condenser unit with the following specifications and salient features:
2.4.2.1 The unit shall be designed to be compatible with the ten(10) ton AC split system cooling unit described in Section 2.4.1.
2.4.2.2 Equipment shall operate at 460-Volts, 3-phase, and 60-Hz electrical supply.
2.4.2.3 The unit shall be a multi-stage cooling unit without a heat pump, containing a minimum of two separate independent refrigeration circuits. The unit shall utilize R-410A refrigerant. R- 22 shall not be used.
2.4.2.4 The unit shall be capable of operating in low ambient conditions to provide year-round cooling. The condenser unit shall have head pressure control to allow for low ambient cooling through modulating control of condenser fans.
2.4.2.5 The system shall be equipped with hot-gas bypass valves and thermal expansion valves (one circuit only) unless modulating compressor are supplied.
2.4.2.6 One-hundred percent (100 percent) of the coils shall be leak tested at a minimum of 660 psig.
2.4.2.7 The contractor shall have the manufacturer perform a 100 percent unit run test prior to shipping the unit.
2.4.2.8 The unit shall be certified and rated in accordance with ASHRI standards, and certified to
UL 1995.
2.4.2.9 Condenser coil(s) shall have hail guards or similar guarding to prevent coil damage from hail and other falling debris.
For instance, a Trane condenser unit, Model Number TTA12044D is an example of a unit that meets the salient features discussed above.
2.4.3 The contractor shall provide the following refrigeration system between the condenser and AHU unit and it shall include the following items:
2.4.3.1 New line sets shall be provided to be able to connect the AHU HP-3 to the condensing unit.
The Line set shall be sized per the manufacture recommendations.
(a) The contractor may use mechanical connections instead of brazing for the copper piping with approval from the TPOC.
2.4.3.2 The liquid and suction lines shall have service valves with gauge ports.
2.4.3.3 The liquid line shall have a filter and drier.
2.4.3.4 The system shall have crankcase heaters to warm the oil in low ambient conditions.
2.4.4 The contractor shall supply new NEMA 3R disconnects for the AHU HP-3 unit and the condenser unit. Contractor shall be responsible for providing all necessary electrical work, including but not limited to: any necessary fuses, breakers, larger wiring, conduit, breakers, disconnects, power conductors, controls wiring, sensors, etc. to provide power or instrumentation to the new condenser and air handler with electric heat. Re-use of existing wiring is encouraged where possible.
2.4.5 The contractor shall furnish and supply all required ductwork, dampers, piping, insulation, wiring, valves, switches, sensors, controls, etc. and any necessary materials and ancillary components required to install and fully integrate the new AHU unit.
2.4.5.1 The contractor shall provide all metal ductwork construction, including all fittings and components, that complies with SMACNA 1966. Radius type elbows shall have a centerline radius of 1.5 times the width or diameter of the duct, unless approved by the TPOC.
2.4.5.2 Metallic Flexible Duct shall conforms to UL 181 and NFPA 90A with factory-applied insulation, vapor barrier, and end connections. This shall only be used to connect from the AHU to the duct system.
2.4.6 The contractor shall supply one (1) set of spare belts with this project for the new AHU-3.
2.4.7 The contractor shall fabricate and supply a new handrail as described in Section 2.5.1.6.
2.5 Installation of New Equipment, Ductwork, Line sets, Electrical, and Controls
2.5.1 The contractor shall install the new Air Handler unit (AHU) on top of the control house within Bldg 77H on the same housekeeping pad as the existing air handler.
2.5.1.1 Contractor shall be responsible for mounting all the new equipment, with vibration isolating mounts.
2.5.1.2 The contractor shall install the new controller to the new HP-3 Air hander unit.
2.5.1.3 The contractor shall relocate the DDC panel and install the AHU non-fused minimum
NEMA3R outdoor rated electrical disconnect to the location shown on Attachment 9. The contractor shall support these items using uni-strut secured to the floor or approved equal and shall be mounted at a height of approximately 4 feet above the floor.
(a) The contractor may reuse all existing wiring between the main breaker and the existing disconnect if acceptable per NEC for the new AHU unit. The existing main breaker is 30 amp. The contractor shall install new wiring between the new disconnect and the AHU unit. The Contractor shall run new properly sized electrical feed, as required, to the AHU to meet new electrical requirements of unit with electric heat.
(b) All electrical work shall be code compliant with NEC. Contractor shall be responsible for providing all necessary electrical work, including but not limited to: any necessary fuses, breakers, larger wiring, conduit, breakers, disconnects, power conductors, controls wiring, sensors, etc. to provide power or instrumentation to the new condenser and air handler with electric heat. Re-use of existing wiring is encouraged where possible.
2.5.1.4 The contractor shall reconnect the new AHU HP-3 drains to the existing drain location using like materials.
2.5.1.5 The contractor shall install a new approximately 15-foot long handrail similar to the existing handrails at the top of the steps from the southwest corner of the AHU to the mid rail beam.
See Attachment 7 for Photograph of existing handrail design and Attachment 9 for location of new handrail. The handrail shall be 42-inches tall with a mid-rail halfway down and a toe-board installed at the bottom. The handrail shall be epoxied bolted/bonded or approved equal to the existing roof and shall be installed to be capable of withstanding, without failure, a force of at least 200 pounds applied in a downward or outward direction within 2 inches of the top edge, at any point along the top rail. The handrails shall be installed per OSHA 1910.29 and OSHA 1926.500-1926.503. The handrails shall be painted to match the existing rails on this area.
2.5.2 The contractor shall install the new condenser on the roof of Bldg 756 in a similar fashion to the condensers for other units located in the immediate vicinity.
2.5.2.1 Contractor shall be responsible to modify, expand, or replace the existing roof supports as may be necessary to accommodate new equipment.
2.5.2.2 Contractor shall be responsible for mounting new equipment with vibration isolating mounts.
2.5.2.3 The contractor shall install a new NEMA3R outdoor rated electrical disconnect for the new compressors and mount it to the outside wall of the Bldg 77H building, similar to the other disconnects in the area.
(a) The contractor shall use conduit on all horizontal runs across the roof. Flex conduit shall be minimized to locations under 4 feet in length.
(b) The contractor may reuse all existing wiring between the main breaker and the existing disconnect if acceptable per NEC for the new condenser unit.
(c) The contractor shall provide all electrical work to power the new Condenser unit and all work shall be code compliant with NEC. Contractor shall be responsible for providing all necessary electrical work, including but not limited to: any necessary fuses, breakers, larger wiring, conduit, breakers, disconnects, power conductors, controls wiring, sensors, etc. to provide power or instrumentation to the new condenser and air handler with electric heat. Re-use of existing wiring is encouraged where possible.
2.5.2.4 The contractor shall install the new line sets between the AHU-3 and the Condensing unit utilizing the existing opening in the wall of Bldg 77H. The contractor shall minimize the length of this run as much as possible.
2.5.2.5 The conduit and lines sets shall utilize dura-block style supports on the roof to these lines, similar to the other lines on the roof.
2.5.3 The Contractor shall install ductwork to connect the new air handler to the new supply, return, and air intake duct system. The contractor shall submit for approval their proposed ductwork layout and sizing prior to the start of work. A conceptual sketch has been included as Attachment 9.
2.5.3.1 All ductwork shall be sized according to ASHRAE standards. Ductwork shall be sized for a pressure drop of 0.1” WG or less per 100’. Main duct velocity shall not exceed 1200 fpm, branch duct velocity shall not exceed 800 fpm (based on net free area).
2.5.3.2 Contractor shall provide and install new ductwork to connect the new AHU HP-3 to the existing supply ductwork on top of the control house.
2.5.3.3 The contractor shall provide and install a new Outside and Return Air Duct system with the following requirements:
(a) The new AC system shall be installed with an outside air duct(s) capable of bringing in
100 percent outside air for economizing.
(b) Contractor shall provide new outside air intake that ensures inlet velocity is no greater than 500 feet per minute (fpm) and that no moisture is carried into the HVAC ductwork.
(c) The contractor shall install the new outside Air intake so that it is routed from the Bldg
77H west side of the building through the window. Penetrating the roof is not permitted. Final outside air intake location is to be approved by NSWCPD Code Facilities. At the end of each workday, all open penetrations between Bldg 77H and the outside shall be covered.
(d) The contractor shall install the new return duct from the existing return ductwork on top of the control house to the mixing box.
(e) The contractor shall supply a new mixing box with actuated return and outside air dampers.
(f) Contactor shall install actuator operated relief dampers in the return duct. (Exhaust pressure operated relief dampers are not acceptable).
2.5.3.4 The contractor shall install all new sensors as listed in Section 2.5.4.2 in appropriate locations as agreed to by the contractor and the TPOC.
2.5.3.5 All 77H wall openings must be temporarily covered and secured at the end of every day with plywood to provide adequate physical security measures and to prevent the intrusion of rain, moisture, animals, and extreme temperatures.
2.5.3.6 All new or modified ductwork shall be externally insulated with a minimum of 1-inch thick mineral fiber type insulation. Contractor shall also repair/replace insulation on existing ductwork where damaged or disturbed (either previously or during the course of work).
2.5.3.7 All new ductwork and duct supports shall be installed according to SMACNA 1966. Do not use friction beam clamps indicated in SMACNA 1966. Attach supports only to structural framing members and concrete slabs. Where supports are required between structural framing members, provide suitable intermediate metal framing. Where C-clamps are used, provide retainer clips.
2.5.4 The Contractor shall connect the new AHU HP-3 split system with the existing facility HVAC Direct
Digital Control system (DDC). The contractor shall supply and run any required wiring, conduit, pneumatic tubing, sensors, controls, etc. from the field device to the local DDC panel leaving approx.
6-feet excess at the panel for NSWCPD Facilities personnel to connect to the DDC panel. The contractor shall label all new control wires at each end. Existing wiring may be reused if appropriate.
The contractor shall supply all new sensors to complete this work.
2.5.4.1 From AHU controller, the contractor shall run the following…