This solicitation seeks proposals for technical, process and programmatic support services for the integration of logistics products. The Naval Surface Warfare Center Philadelphia Division intends to award up to four cost-plus-fixed-fee indefinite-delivery/indefinite-quantity contracts to support code 31 with logistics, program engineering, technology systems, system engineering and business process engineering.

Key details include: Proposals are due no later than 17 May 2019. The period of performance is five one-year ordering periods. Services include program and business management support, logistics support, project and process engineering support, general engineering support, and special requirements support. The place of performance involves both on-site and off-site work, and the level of effort is specified as 140,080 hours annually. Security requirements include secret-level clearance for contractor personnel.

Amendment 0003: The purpose of Amendment 0003 is to provide NSWCPD answers to Contractor questions received in response to the subject Solicitation. The RFP closing date and time remains unchanged at 15 May 2019 4:00 p.m. EST. No further question will be received for the subject Solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Support for the Integration of Logistics Products, newest first.
File Type Posted
FINAL_AMEND_0004.pdf PDF
N64498-19-R-4041_Attachment__3_SBPCD.xlsx XLSX spreadsheet
Attachment_3_-_SBPCD.XLSX XLSX spreadsheet
31_Integration_ILS_MAC_-_DD_Form_254_04172019_(003).pdf PDF
N64498-19-R-4041_Amendment_0002.pdf PDF
N64498-19-R-4041_Amendment_0001.pdf PDF
CDRL_A004_-_Technical_Report-StudyServices_04122019.pdf PDF
N64498-19-R-4041_ILS_Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See Pages 2 through 49 for details.

1. CONTRACT ID CODE PAGE OF PAGES

J 1

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-May-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6449819R4041

X 9B. DATED (SEE ITEM 11)

11-Apr-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-May-2019

CODE

NAVAL SURFACE WARFARE CENTER PHILA

CODE 0222, AARON KOUMARAS

215-897-7750, AARON.KOUMARAS@NAVY.MIL

5001 SOUTH BROAD STREET

PHILADELPHIA PA 19112

N64498 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6449819R4041

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGES:

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0003:

(1) The purpose of Amendment 0003 is to provide NSWCPD answers to Contractor questions received in response to the subject Solicitation.

(2) The RFP closing date and time remains unchanged at 15 May 2019 4:00 p.m. EST. No further question will be received for the subject Solicitation.

(3) All other terms and conditions of the subject Solicitation remain unchanged.

NSWCPD Questions and Answers:

Question 38:

Page 98 of 122 (Section L.3.5): Would the Government please confirm that Offerors are required to submit a technical approach that addresses all 42 SOW sub-task areas (including methodologies, risks, risk mitigations, and prior risk mitigation successes), AS WELL AS corporate experience (Section L.3.3) that covers all 42 SOW sub-task areas (in the way of no more than 5 contract examples), AS WELL AS relevant past performance examples (Section L.3.7)?

Answer 38:

Offerors are instructed to provide proposals in accordance with the instructions provided within Sections L of the Solicitation.

Question 39:

Page 114 of 122, Section L, under L-209-H009 (a) under Notification of Potential Organizational Conflict(s) of Interest, the Government has not completed the OCI clause. Will the Government specify those programs of primary concern?

Answer 39:

L-209-H009 NOTIFICATION OF POTENTIAL ORGANIZATIONAL CONFLICT(S) OF INTEREST (NAVSEA) (DEC 2018) has been updated per the subject Amendment. All offerors are instructed to review the updated clause within Amendment 0003.

Question 40:

The technical and management approach shall address the Offeror’s proposed methodology for performing the requirements of the solicitation, including the SOW. The Offeror shall also identify any risks associated with the requirements of the SOW, and describe any techniques, methods, and actions that will be used by the Offeror to mitigate the risk(s).

Section L.3.5 and Section M define Volume II/Factor 3 as being comprised of four subfactors (3A, 3B, 3C, and 3D).

However, the introductory paragraph in Section L.3.5 also asks for methodology and risk information that is not

Answer 40:

Section M has been updated to include the following evaluation criteria, “The Government will evaluate the effectiveness of each Offeror's technical and management approach to perform the requirements in the solicitation. Offerors who demonstrate mature and effective management and technical processes may receive a higher rating. Offerors will also be evaluated the degree to which the proposed risk management approach appears reasonable for the proposed effort under the Statement of Work.”

All offerors are instructed to review the updated evaluation criteria within Amendment 0003.

Question 41:

Some of the labor categories use the eCRAFT code from the SCA Directory of Occupations. Is this contract covered by the Service Contract Labor Standards? If so, please provide the appropriate wage determination(s).

Answer 41:

The Service Contract Labor Standards will not be applicable for the subject Solicitation.

Question 42:

The Government provided a NTE amount for CLIN 0002 which includes materials, travel, subcontracting, and other direct costs. Will the Government provide a breakdown of the ODC NTE amount for CLIN 0002 into Materials and Travel since contractors typically apply different indirect markups to material and travel costs in accordance with accounting practices?

Answer 42:

No. There is no designated ratio / percentage for ODC Breakdown. Determinations may be decided at the Task Order level.

Question 43:

In Section A, 5. Support Costs, the Government states “For evaluation purposes, the Government will add the Offeror’s proposed indirect burden costs to the stated base support costs of $1,905,878.24 for CLIN 0002.” In Section M, Support Costs, the Government states “Offerors shall burden the pre-established NTE amount with applicable indirect cost rate loadings to arrive at its total proposed Support Costs.” Should Offerors apply indirect costs to the Support Costs or will the Government add proposed indirect costs to the Support Costs?

Answer 43:

Offerors are instructed to review Section M: Support Costs of the subject Solicitation for clarification on this question.

Question 44:

In section L.3.6.1 Small Business Commitment Document (SBPCD), it specifies the use of Attachment 3 for the formatting of the Small Business Participating Document (SBPDC). Attachment 3, Declaration of Non-Collusion Certification, contained in the Solicitation does not seem to correspond with the L.3.6.1 requirement. Can you elaborate or provide an additional document that establishes the required format and expected formulas for calculations?

Answer 44:

Solicitation N64498-19-R-4041 contains an administrative error which referred to “The Declaration of Non- Collusion Certificate” as Attachment 3. There is no requirement for the “The Declaration of Non-Collusion Certificate” and is hereby deleted from the Solicitation. The Small Business Participating Document (SBPCD) attachment was provided per Amendment 0002.

Question 45:

CDRL A005 establishes the requirement to provide a Small Business Participation Commitment Report on a semi-annual basis. Is this report in addition to reporting requirements established under FAR 52.219-9?

Answer 45:

Yes. That is correct.

Question 46:

On page 2 of the solicitation it states, “proposes to award up to four (4) Cost-Plus Fixed-Fee (CPFF) Indefinite- Delivery, Indefinite-Quantity (IDIQ) contract(s) resulting from this RFP.” This statement seems to indicate that there is reasonable expectation that two more responsible Offerors will respond, yet certified cost or pricing data is being requested. FAR 15.403-1(c)(1)(ii) states that adequate price competition is a standard for exception from certified cost or pricing data requirements if there was a reasonable expectation that two or more responsible Offerors would submit priced offers.

Answer 46:

Section L has been updated to include the following instructions to offerors, “In the absence of adequate price competition, the Contracting Officer may request additional data per FAR 15.403- 3 and as described in the solicitation provision 52.215-20, Requirements for Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data.”

All offerors are instructed to review the updated evaluation criteria within Amendment 0003.

Question 47:

Will the Government consider eliminating 252.215-7009, since it is required with the submission of certified cost or pricing data, and modifying the clause 52.215-20 to 52.215-20 Alt IV so that certified cost or pricing data is not required to be submitted with the proposal?

Answer 47:

DFARS Clause 252.215-7009 “Proposal Adequacy Checklist” has been removed from the solicitation.

Additionally, FAR Clause 52.215-20 “Requirements for Cost or Pricing Data or Information Other Than Certified Cost or Pricing Data” has been removed and replaced with DFARS Clause 252.215-7010 “Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data”.

Question 48:

In Section L.3. the table on pages 94 and 95 only states how many paper copies are to be submitted for each volume.

Can the Government verify if electronic copies are required for any other volumes besides Volume V. Factor 6 Cost Proposal?

Answer 48:

Offerors shall submit electric copies for both the Cost and Technical portions of their proposals. Additional guidance pertaining to submission of electronic copies was provided via Amendment 0002.

Question 49:

Section 3.3.4 of the solicitation requires use of an IBM-Kenexa LCMS Premier System for training products. Since some of the personnel needed to support this contract are located at the Government site, please confirm that contractors are expected to procure a license to that content management system of if entries will be made on a Government-provided and licensed system.

Answer 49:

If entries are to be made via a government NMCI seat, the contractor will not need to procure the license. The contractor will need to procure the license if accessing the system from their respective IT machine.

Question 50:

In the Level of Effort table provided on page 4 of 122 in RFP N6449819R4041, the government indicates that the key position titled “Technician, Engineering IV” has an eCRAFT Code (actually SCA Labor Category) of “30085.” However, the DOL SCA Directory of Occupations (Fifth Edition) indicates that the SCA Labor Category of “30085” is actually for “Engineering Technician V.” This can be found on page 108 of the SCA Directory of Occupations (Fifth Edition). This discrepancy is also found on page 24 of 122 under paragraph D of section 10.1.1 of the RFP.

Similarly, the government indicates that the non-key position titled “Technician, Engineering III” has an eCRAFT Code (actually SCA Labor Category) of “30084.” From the SCA Directory of Occupations, that SCA Labor Category “30084” is listed as “Engineering Technician IV.” This discrepancy is also found on page 25 of 122 under paragraph G of section 10.1.1 of the RFP.

Please provide clarification as to the exact Level of Engineering Technicians required in both instances.

Answer 50:

As a result of this amendment, all offerors are instructed to utilize the following labor categories and their respective eCRAFT Codes.

1. Technician, Engineering IV – 30084

2. Technician, Engineering III – 30083

Question 51:

On page 99 section L.3.6.1 states that the Small Business Participation Commitment Document (SBCPD) should follow the format provided in Attachment 3, however Attachment 3 is DECLARATION OF NON-COLLUSION.

Can the Government provide the Attachment that the format of the SBCPD should follow?

Answer 51:

Solicitation N64498-19-R-4041 contains an administrative error which referred to “The Declaration of Non- Collusion Certificate” as Attachment 3. There is no requirement for the “The Declaration of Non-Collusion Certificate” and is hereby deleted from the Solicitation. The Small Business Participating Document (SBPCD)

Question 52:

The solicitation is missing Section J List of Attachments. Can the Government provide Section J?

Answer 52:

All applicable attachments are been identified within the Solicitation, Amendment 0001 and Amendment 0002.

Question 53:

The FBO website page for the opportunity – Support for the Integration of Logistics Products (https://www.fbo.gov/?s=opportunity&mode=form&tab=core&id=93685110097f0b1789b79cdf8ff2d42d) indicates that the opportunity allows for electronic responses submission. But in the RFP, it states that vendors are to submit their proposals in hard copy. Would the government consider opting for electronic submissions for this opportunity?

Answer 53:

Per Section L of the subject Solicitation, e-mailed proposals are not permitted. All Offerors are instructed to submit hard copy offers in accordance with the terms and conditions of Solicitation N64498-19-R-4041.

Question 54:

The RFP states that vendors are to submit Past Performances but does not specify the number of Past Performances that are required to be submitted. Would the government consider requesting a specific the number of Past Performances that vendors are to submit?

Answer 54:

In accordance with L.3.7 VOLUME IV: FACTOR 5 – PAST PERFORMANCE, all Offerors are instructed to “List all relevant contracts performed within the last 3 years, whether completed or not, including Federal, State and Local Government and private sector contracts.”

Question 55:

The Solicitation SF-33 states that proposals are due on May 11, 2019 at 12:00PM. May 11, 2019 falls on a Saturday. Would the Government please confirm that the proposals delivery location will be open on Saturday May 11, 2019 to receive submission packages? Would the Government also provide any special instructions for delivery of submissions outside of standard work days?

Answer 55:

In accordance with Amendment 0002, the RFP closing date has been extended to 15 May 2019 4:00 p.m. EST.

Question 56:

Section L.3.6.1 Pg. 99 references SBPCD Attachment 3. Does the Government intend to issue the Small Business Participation Commitment Document (SBPCD) as it was not provided in the original RFP or Amendment 1 attachments?

Answer 56:

Solicitation N64498-19-R-4041 contains an administrative error which referred to “The Declaration of Non- Collusion Certificate” as Attachment 3. There is no requirement for the “The Declaration of Non-Collusion Certificate” and is hereby deleted from the Solicitation. The Small Business Participating Document (SBPCD)

Question 57:

Will the government please clarify if a copy of a fully executed Teaming Agreement for each small business subcontractor will suffice as a letter of commitment? If so, may we submit each small business subcontractor Teaming Agreement as an attachment to the cost proposal or will the signature page plus Exhibit A, Scope of Work, from the agreement meet the requirement?

Answer 57:

Offerors may provide a letter of commitment for each subcontractor included in their cost proposal.

Question 58:

Will the government please clarify where in the proposal Offeror should address this attachment?

Answer 58:

All Offerors are instructed to complete Attachment 1: Direct Labor Rate Substantiation Sample Format Chart and submit it along with their Cost Proposal.

Question 59:

Since Attachment 1 is intended to substantiate proposed direct labor rates, should there be a data field within Attachment 1 to provide the proposed rate?

Answer 59:

All Offers’ are instructed to complete Attachment 1 Direct Labor Rate Substantiation Sample Format Chart in it’s current format.

Question 60:

RFP Reference: L.3.8.3 Completed RFP RFP States: "This document shall be fully executed. The document shall not be embellished with any cover or binding."

Does this requirement mean Offeror should submit fully executed document (Sections A – K) as a separate stand-alone package rather than inserting into a proposal volume? Please clarify.

Answer 60:

NSWCPD is not expecting a separate stand-alone package for Sections A-K.

Question 61:

RFP Reference: Clauses Incorporated by Reference, Page 107 RFP States: 252.215-7009 Proposal Adequacy Checklist (JAN 2014) Question: Given the Government has included DFAR 252.215-7009, Proposal Adequacy Checklist (JAN 2014), in Section L, is it assumed Offerors are to include a completed checklist with their proposal? If so, will the government please specify where in the proposal the completed checklist should be included?

Answer 61:

DFARS Clause 252.215-7009 “Proposal Adequacy Checklist” has been removed from the solicitation.

Additionally, FAR Clause 52.215-20 “Requirements for Cost or Pricing Data or Information Other Than Certified Cost or Pricing Data” has been removed and replaced with DFARS Clause 252.215-7010 “Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data”.

Question 62:

RFP Reference: Attachment 3, Declaration of Non-Collusion Certification This attachment is not addressed anywhere in the RFP.

Question: Will the government please clarify if this attachment is to be completed by the Offeror and where it should be provided within the proposal?

Answer 62:

Solicitation N64498-19-R-4041 contains an administrative error which referred to “The Declaration of Non- Collusion Certificate” as Attachment 3. There is no requirement for the “The Declaration of Non-Collusion Certificate” and is hereby deleted from the Solicitation.

Question 63:

Please clarify proposal delivery requirements in reference to RFP page 1, Block 7

Answer 63:

All offerors are instructed to hand deliver their proposals to:

5001 South Broad Street Philadelphia, PA 19112-5083 Attn: Aaron Koumaras, Contract Specialist

OR, Mail their proposals to the following address:

Naval Surface Warfare Center, Philadelphia Division (NSWCPD) 1601 Langley Avenue (Building 542) Philadelphia, PA 19112-5083 Attn: Aaron Koumaras, Contract Specialist

Will the Government allow flow charts to enable organization in the presentation of the Technical and Management Approach?

Answer 64:

Offerors are permitted to submit the information/data in the format as they deem fit as long as it is in accordance with the terms and conditions of the Solicitation.

Question 65:

Since the Government is requesting that proposals be delivered by mail, will the government consider changing the due date from Monday to Tuesday or Wednesday to allow offers the ability to arrange for carrier pick-up that does not occur on the weekend?

Answer 65:

In accordance with Amendment 0002, the RFP closing date has been extended to 15 May 2019 4:00 p.m. EST.

Question 66:

The Government specifies a minimum font of Times New Roman throughout the proposal.

Will the Government consider allowing a minimum font size of 8 points for graphics and tables throughout?

Answer 66:

The font shall be Times New Roman with a font size of 12 throughout the document. The font size for text contained in embedded graphics (tables and illustrations) shall be no smaller than 8 point Times New Roman font.

Question 67:

L.2 states “The font shall be Times New Roman with a font size of 12 throughout the document.” Can Offerors use font that is larger than 12 for items such as a volume’s title page or graphics? Can Offerors use font that is smaller than 12 for items such as headers and footers?

Answer 67:

The font shall be Times New Roman with a font size of 12 throughout the document. The font size for text contained in embedded graphics (tables and illustrations) shall be no smaller than 8 point Times New Roman font.

Question 68:

The table in L.3 lists the number of originals and copies for each volume. However, this table does not list the number of electronic copies required for each volume. Can the Government clarify which volumes require electronic files to be submitted in accordance with L.2.4 INSTRUCTIONS FOR ELECTRONIC FILES?

Answer 68:

Offeror’s are instructed to provide a backup, electronic copy for all data submitted within their cost and technical proposals.

Question 69:

The RFP specifies (M.3) that Offerors will be evaluated on the realism of the proposed subcontracting commitment when compared to the information in its cost and technical proposal and its subcontracting plan. Overall small business dollar goals should be consistent from the Subcontracting Plan and SBPCD.

Small Businesses are exempt from submission of a Small Business Plan per FAR 52.219-9 “(a) This clause does not apply to small business concerns.”

Question 64

Please clarify the Government’s intent and include a copy of Attachment 3 referenced in section L.3.6.1

Answer 69:

Solicitation N64498-19-R-4041 contains an administrative error which referred to “The Declaration of Non- Collusion Certificate” as Attachment 3. There is no requirement for the “The Declaration of Non-Collusion Certificate” and is hereby deleted from the Solicitation. The Small Business Participating Document (SBPCD)

Question 70:

RFP Reference: Section B, Level of Effort RFP States: "eCRAFT Code for each Labor Category" Question: Do the eCRAFT codes in the Level of Effort chart represent Service Contract Act (SCA) Wage Determination (WD) codes? If so, please amend the solicitation so it is clear that SCA is applicable and provide the WD rates for the applicable categories in the chart.

Answer 70:

The Service Contract Labor Standards will not be applicable for the subject Solicitation.

Question 71:

Section L (Page 99 of 122), L.3.6.1- Small Business Participation Commitment references Attachment 3 as the SBPCD spreadsheet, but the Declaration of Non-Collusion Certification was attached to the RFP as Attachment

3. Would the Government please provide the SBPCD spreadsheet and clarify if the Declaration of Non-Collusion is also required and if that would be Attachment 4?

Answer 71:

Solicitation N64498-19-R-4041 contains an administrative error which referred to “The Declaration of Non- Collusion Certificate” as Attachment 3. There is no requirement for the “The Declaration of Non-Collusion Certificate” and is hereby deleted from the Solicitation. The Small Business Participating Document (SBPCD)

Question 72:

Page 61 of 122, Section H, Given the IDIQ MAC nature of the resultant contract, under H-209-H004 ORGANIZATIONAL CONFLICT OF INTEREST (NAVSEA) (DEC 2018) subparagraph (f), will the Government please verify that the limitations on future contracting will be defined by the work performed under awarded task orders of the resultant contract?

Answer 72:

As stated in Clause H-209-H004 ORGANIZATIONAL CONFLICT OF INTEREST (NAVSEA) (DEC 2018) subparagraph (f), any restrictions resulting from this clause are limited to “any system, component or services which is the subject of the work to be performed under this contract.”

Question 73:

Page 114 of 122, Section L, under L-209-H009 NOTIFICATION OF POTENTIAL ORGANIZATIONAL CONFLICT(S) OF INTEREST (NAVSEA) (DEC 2018), the Government did not complete the “fill-in” under subparagraph (a) for the related laboratories (if applicable), in support of operation of the office or any of its programs. Will the Government please verify that this field is TBD at the Prime Contract level and will be completed at the individual task order level?

Answer 73:

L-209-H009 NOTIFICATION OF POTENTIAL ORGANIZATIONAL CONFLICT(S) OF INTEREST (NAVSEA) (DEC 2018) has been updated. All offerors are instructed to review the updated clause within Amendment 0003.

(End of Text)

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following have been modified:

LEVEL OF EFFORT

Below is the Level of Effort (LOE) chart for the performance of the resultant contract(s). The LOE is based on the following labor categories and hours - per contract year:

Title eCRAFT

Code Gov’t Site

Hours Gov’t Site

OT

Cont’r Site

Hours Cont’r Site

OT

MANAGER, PROGRAM/PROJECT III* MANP3 - - 1,800 -

ENGINEER MECHICAL/ELECTRICAL III* EE3/EM3 - - 1,920 -

MANAGER, PROGRAM/PROJECT II* MANP2 - - 1,000 -

TECHNICIAN, ENINGEERING IV* 30084 - - 3,840 300

LOGISTICIAN III LGT3 - - 3,840 -

ANALYST, SUPPLY MANAGEMENT I ANM1 1,920 - 1,080 -

ANALYST, PROGRAM MANAGEMENT III ANM3 - - 3,840 -

ENGINEER II E2 7,680 - 13,760 -

ANALYST, MANAGEMENT II ANME2 3,840 - 4,160 -

LOGISTICIAN II LGT2 3,840 - 8,160 400

TECHNICIAN,ENGINEERING III 30083 6,160 - 3,840 400

ANALYST, PROGRAM MANAGEMENT 1 ANM1 6,160 - 3,840 -

LOGISTICIAN I LGT1 6,160 - 3,840 -

ENGINEER 1 E1 6,160 - 5,840 -

PROJECT ENGINEER 1 E1 4,160 3,840

CLERK, GENERAL I 1111 - - 4,000 -

DRAFTER/CAD OPERATOR III 30063 - - 6,000 300

TECHNICAL WRITER III 30463 - - 5,000 -

ARTIST, GRAPHIC 15080 - - 6,000 -

SPECIALIST, TRAINING II ST2 1,920 - 5,080 -

TOTALS 48,000 - 90,680 1,400

TOTAL LEVEL OF EFFORT 140,080 per year

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

STATEMENT OF WORK

Technical, Process and Programmatic Support for the Integration of Logistics Products

1.0 INTRODUCTION

1.0.1 BACKGROUND

Naval Surface Warfare Center Philadelphia Division (NSWCPD) is the Navy’s center for excellence for ships and ship-systems. For over one hundred (100) years, NSWCPD has provided full-spectrum research and development, testing, evaluation, in-service engineering, and fleet support organization for the Navy’s surface and under-sea vehicles. Expertise spans across more than forty (40) disciplines, from electrical and mechanical engineering to computer engineering and physics.

NSWCPD Division 30 provides program level management and leadership for logistics, and acquisition support programs and initiatives. This includes the planning, development, production, procurement, and sustainment of logistic products for Hull, Mechanical and Electrical (HM&E) systems and equipment installed on Navy’s ships, submarines, military watercraft and unmanned vehicles and coordination of Integrated Logistics Support (ILS) updates associated with life-cycle sustainment planning and execution for shipboard HM&E system and equipment.

To assist in establishing program goals – thresholds and objectives – for the minimum number of cost, schedule, and performance parameters that describes the program over its life cycle, Code 31 works closely with the logistic division and technical codes throughout NSWCPD and with new construction and in-service Program Executive Office (PEO) sponsors at NAVSEA.

1.0.2 This Contract is for non-personal services. It does not create employment rights with the U.S. Government whether actual, inherent, or implied

1.0.3 Government/Contractor Relationship

(a) The services to be delivered under this Multiple Award Contract are non-personal services and the parties recognize and agree that no employer-employee relationship exists or will exist under the Multiple Award Contract between the Government and the Contractor's personnel. Therefore, it is in the best interest of the Government to provide both parties a full understanding of their respective obligations.

(b) The Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishable badges or other visible identification for meetings with Government personnel. In addition, Contractor personnel shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence

(c) Contractor personnel under this Multiple Award Contract shall not engage in any of the inherently Governmental functions listed at FAR Subpart 7.5 or DFARS Subpart 207.5.

(d) Employee Relationship:

1) The services to be performed under this Multiple Award Contract do not require the Contractor or its personnel to exercise personal judgment and discretion on behalf of the Government. Rather the Contractor's personnel will act and exercise personal judgment and discretion on behalf of the Contractor.

2) Rules, regulations, directives, and requirements that are issued by the U. S. Navy and NSWCPD under its responsibility for good order, administration, and security are applicable to all personnel who enter a Government installation or who travel on Government transportation. This is not to be construed or interpreted to establish any degree of Government control that is inconsistent with a non-personal services contract.

(e) Inapplicability of Employee Benefits: This Multiple Award Contract does not create an employer-employee relationship. Accordingly, entitlements and benefits applicable to such relationships do not apply.

(f) Notice. It is the Contractor's, as well as the Government's, responsibility to monitor Multiple Award Contract activities and notify the Contracting Officer if the Contractor believes that the intent of this Section has been or may be violated.

1) The Contractor shall notify the Contracting Officer in writing via letter or email within three (3) calendar days from the date of any incident that the Contractor considers to constitute a violation of this Section. The notice should include the date, nature, and circumstances of the conduct; the name, function, and activity of each Government employee or Contractor official or employee involved or knowledgeable about such conduct; identify any documents or substance of any oral communication involved in the conduct; and the Contractor's estimated date when, absent a response, cost, schedule or performance will be impacted.

2) The Contracting Officer will, within five (5) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer will either:

(i) Confirm the conduct is in violation and when necessary direct the mode of further performance,

(ii) Countermand any communication regarded as a violation,

(iii) Deny that the conduct constitutes a violation and when necessary direct the mode of further performance, or

(iv) In the event the notice is inadequate to make a decision, advise the Contractor what additional information is required, and establish the date by which it should be furnished by the Contractor.

1.1 SCOPE

The Navy’s Machinery Research, Logistics and Ship Integrity Division of the Naval Surface Warfare Center Philadelphia (NSWCPD) Department 30 is responsible for providing machinery research and development, logistics and ship integrity engineering. Department 30's knowledge of machinery engineering commences at the earliest stages of shipboard equipment and component product development; continues through new ship construction; and supports In-Service engineering for ships and ship systems currently in the Fleet. Code 31 is responsible for the development, implementation, procurement and maintenance of logistic products for Hull, Mechanical and Electrical (HM&E) systems and equipment installed on U.S. Navy surface ships, aircraft carriers and submarines as well as USCG, Army, MSC and FMS program ships. It also coordinates the Integrated Logistics Support (ILS) updates associated with shipboard HM&E system and equipment alterations as well as engineering and procurement services for alteration and modernization of ship systems, in-service engineering responsibility for future and in-service systems, and training development. Code 31 supports various commands including NAVSEA, Army, MSC, USCG, PEOs, and fleet logistics, maintenance and readiness commands including the TYCOMS and RMC’s. To execute its responsibilities Code 31 requires the support in logistics, program engineering, technology systems, system engineering and business case analysis as well as business process engineering support to create an integrated approach to logistics in an effort to support the needs and demands of customers for ILS products in the most cost effective manner. As such will require support in the areas delineated in this Statement of Work (SOW) for those project areas.

2.0 APPLICABLE DOCUMENTS

2.1 GEIA-STD-0007 Logistics Product Data (www.standards.sae.org)

2.2 GEIA-HB-0007-A, Guide to Logistics Product Data (www.standards.sae.org)

2.3 NAVSEA Technical Specification 9090-600 (www.everyspec.com)

2.4 NAVSEA Technical Specification 9090-310 (www.navsea.navy.mil)

2.5 General Specification for Overhaul of Surface Ships- GSO (NAVSEA S9AA0-AB-GSO-010) (https://maintenance.navsea.navy.mil/domino/gso/gso/gso_main.asp) CAC / PKI required

2.6 CINCLANTFLT/CINCPACFLT 4790.3 Joint Fleet Maintenance Manual (JFFM)

(www.submepp.navy.mil)

2.7 NAVSEAINST 4790.8B Ships' Maintenance and Material Management (3-M) Manual (www.navsea.nay.mil)

2.8 Technical Manual Contract Requirement (TMCR), NDMS 050066-000, New Manual or Complete

Revision of HM & E Equipment Technical Manual

2.9 AECMA S1000D Standard (Specification 1000D), International Specification for Technical Publications

Utilizing a Common Source Data Base

2.10 MIL-STD-3034, Reliability Centered Maintenance (RCM) Process (www.everyspec.com)

2.11 MIL-P-24534A: Planned Maintenance Subsystem: Development of Maintenance Requirement Cards, Maintenance Index Pages, and Associated Documents

2.12 NAVSEA TS 9090-700: Ship Configuration and Logistic Support Information System

2.13 DoD Instruction 4151.22: Condition Based Maintenance Plus for Materiel Maintenance (ww.dtic.mil)

2.14 DoD 5025.1-M: DoD Directives System Procedures (www.dtic.mil)

2.15 DoD Commonality Handbook (https://acc.dau.mil/)

The Contractor shall reference and utilize the latest version available when performing tasks within this Statement of Work (SOW).

3.0. PERFORMANCE REQUIREMENTS

3.1 Program and Business Management in Support of NSWCPD Code 31

3.1.1 Participate in technical meetings and program reviews as directed by the NSWCPD Code technical managers and various naval commands and commercial companies as needed to ensure program objective completion.

3.1.2 Develop and provide status on initiatives via Plan of Actions and Milestones (POA&M).

3.1.3 Assist the Technical Program manager with development of programmatic and technical briefs, such as but not limited to program reviews, business case analysis, analysis of alternatives. These briefs will be provided mostly to US Navy commands.

3.1.4 Develop, manage, and extract programmatic and financial data for review and reporting.

3.1.5 Provide detail design, quality assurance and engineering development oversight to various projects in all stages of development of logistics elements, including initial concept to final installation and fielding alterations.

3.1.6 Generate project plans, concepts of operation, and management outlines.

3.1.7 Provide technical management of programs in various stages of progress, to include projects from development to initial fielding; Tracking projects against schedule and budget and goals, alerting the Technical Program manager of issues

3.1.8 Provide oversight to this contract for NSWCPD and ensure that deliverables maintain quality, time and cost targets.

3.2 Logistics in Support of NSWCPD Code 31

3.2.1 The Contractor will provide financial and engineering support to develop return cost analysis evaluations and package development of modernization, alteration and repair projects as competed by various Alteration Installation Teams (AIT) teams, IAW REF F (JFFM), as part of the Quality Assurance (QA) validation of ILS packages and completed alteration reports.

3.2.2 The Contractor will support development of projection AIT budgets with NSWCPD based on historical project data from various program codes and AIT sponsors, SCD, NDE, NMD data and ship programming plans and fielding schedules.

3.2.3 The Contractor will support program managers for validation of work and development and analysis of return cost data from alterations and modernization in an effort to build future year funding profiles.

3.2.4 Develop all applicable ILS support for the applicable systems IAW all applicable navy instructions and standards. Examples to include but not be limited to Allowance Parts List (APL), Planned Maintenance (PMS), technical manuals, technical manuals, training packages, one line diagrams, code registers. Provide obsolescence engineering support as needed.

3.2.5 Provide support to technical codes for alteration programs and modernization with the development of ILS certifications. Create and or modify certification packages.

3.2.6 Review and QA check all ILS and provisioning documents to and validate the program requirements.

3.2.7 The Contractor will provide RCM, FMECA and LORA analysis support for the evaluation of logistics elements for provisioning, sustainability, maintenance, and technical documentation updates.

3.2.8 Support ILS integrated product and process teams with the technical and logistics organizations of NSWCPD and Fleet asset to develop logistic product plans and artifacts to ensure systems supported by the SEA for fully life cycle supported and provisioned.

3.2.9 The Contractor will assist in the integration of ILS products; assist the government in forecasting material and providing metrics communicating current levels of readiness and sustainment pertaining to maintenance-working with the Fleet (TYCOM, RMC) and SYSCOM (NAVSEA, SURFMEPP); and provide technical analysis, recommendations, white papers, and other documents for logistics issues related to ILS life-cycle support including but not limited to sparing, tech docs and support equipment requirements as well as advanced planning and work package development

3.2.10 The Contractor will identify, characterize, track and monitor logistics milestones for Ship Availabilities;

provide status and Ship Availability planning updates to appropriate stakeholders and their organizations;

review Ship Change Documents (SCDs) for ILS impacts to readiness/sustainment and update, verify and process Technical Manuals, PMS, Provisioning, Training, EOSS, Configuration and ILS Certifications as well as provide recommendations to close gaps/deficiencies identified; recommend actions to correct deficiencies and assist in reviewing Coordinated Shipboard Allowance Lists (COSAL); participate in Advanced Planning and ILS Working Groups.

3.2.11 Provide support for the Systems Engineering Technical Authority (SETA) technical documentation and standards projects including Cumbersome Work Practice (CWP), Mishap and Safety technical response, Research and System Engineering Working Group (R&SE), Specification Improvement Board (SIB) comment and adjudication process and Affordability projects. Provide technical and program management support to include: executing the NAVSEA mishap technical response process, facilitate working group meetings, training and conferences, and conference calls. Coordinate responses to assigned Safety Inspection Reports actions to ensure shipboard system/machinery is safe for continued operations, identify risk mitigations and identify deficiencies in Technical Standards. Provide engineering and technical support to NSWCPD for development and update of revisions for NAVSEA specifications to include:

identification of changes, incorporating lessons learned, facilitating meetings, adjudicating comments, providing change pages and comment forms.

3.3 Project / Process Engineering in Support of NSWCPD Code 31

3.3.1 Provide qualified personnel to read and interpret drawings for provisioning assistance, review of items for

ILS certifications and support, as well as possible impacts to materiel readiness (such as PMS and EOSS).

3.3.2 The Contractor will maintain Availability Master Schedules for assigned Surface Ship, Submarine and Carrier Availabilities; monitor technical progress of activities; collect activity progress and completion status data from program participants; assess risks and conduct Critical Path Mappings (CPM) to prevent and or minimize availability schedule compression/or missed milestones; and analyze schedule data for conflicts, identify problem areas, solicit input from concerned activities and facilitate resolution.

3.3.3 The Contractor will be required to develop the required documents to support fielding temporary alterations

/ alterations required under SHIPMAIN entitlement process, JFMM, and FMP. The Contractor will also be required to develop any necessary installation documentation per to deploy the temporary alteration. This includes detailed POA&Ms.

3.3.4 The Contractor will review, modify, prepare or validate Front End Analysis (FEA), Job Task Analysis

(JTA) and Class and System Navy Training Systems Plans (NTSPs) and assist identification and validation of training requirements based on ILS required changes as indicated in the process review and assist in support of the Navy’s Training Planning Process Methodology (TRPPM) ensuring meeting of each milestones. Training material will be SCORM 1000D compliant, developed and maintained in licensed instance of an IBM-Kenexa LCMS Premier system.

3.3.5 Draft and review communications guidelines, processes, and standard procedures, facilitate and organize

Naval or defense-related conferences, seminars, summits meetings and effectiveness reviews, assist in the creation and implementation of a communications plan in order to inform, educate, and build support and consensus among key internal and external stakeholders.

3.3.6 Design, develop and provide graphics, products and services to effectively communicate command mission and objectives and support Department 30 sponsored activities, projects and events as well as create and update training curriculum for new division employees to introduce them to the primary processes, missions, products and services.

3.3.7 Develop training materials and projects for virtual training programs, fleet training programs (such as

SWOS). Training material will be compliant to all pertinent direction and references and shall be maintained in licensed instance of an IBM-Kenexa LCMS Premier system (CDRL A004).

3.3.8 Act as a liaison to other commands, Fleet, NAVSEA, PEO and new acquisition programs such as LCS, LPD, LPD Midlife, LHD, ORP, army watercraft, USCG vessels, MSC platforms and DDG 1000 during the integration efforts for insertion of logistics elements and products within the navy maintenance and logistics process.

3.3.9 Support the development of process improvement programs and ensure that the logistics support plan for

NSWCPD conforms to current navy and future navy programs. Support the integration of logistics products within the current environment (3M, MFOM, ICMP, PMS-SKED, NMD).

3.3.10 Support insertion of logistics elements within the navy maintenance environment (CBM, RCM, PM, CM) in an overall effort to reduce total ownership cost over the system life cycle.

3.3.11 Develop process maps and procedures to assist the technical code in the standardization of work flow, logistics support, and for the integration of logistics elements between the technical codes of NSWCPD Department 30, and navy requirements (CDRL A004).

3.3.12 Provide support to commonality programs, policy and procedure, business process re-engineering and integration efforts to the modernization process within the ISEA, public and private shipyards.

3.3.13 Develop and manage Metrics, Key Performance Indicators (KPI), related to the process so that constant improvement and efficiencies are gained within the commonality program, supporting Deep Dive data, usage data, and other metrics as developed (CDRL A004).

3.4 General Engineering in Support of NSWCPD Code 31

3.4.1 Provide material tracking and identification as needed to support technical evaluations for alteration development and program support for the technical codes.

3.4.2 Review and comment on technical documents for technical accuracy, this will include program developed documents, OEM provided documents, operational documents, training and provisioning documents to ensure that all systems are supported over their lifecycle.

3.4.3 Support knowledge management programs and processes, IPT and BRT processes as a logistics SME.

3.4.4 The Contractor will assist NSWCPD support navy, army, coast guard, military sealift command, and foreign military sales programs maintenance programs and initiatives efforts in support with development of needs and impact analysis (including ROI and TOC evaluations) and developing recommendations, briefs, formal presentations and plan of action, as well as the monitoring execution-to-plan of all maintenance initiatives.

3.4.5 The Contractor will assist NSWCPD support TYCOM and Fleet Force’s business rules, polices and mechanisms for oversight and accountability.

3.4.6 The Contractor will assist in the implementation, validation and metric analysis of a tailored training for the maintenance team, Port Engineer, Chief Test Engineer, and Quality Assurance, on subjects such as Integrated Project Team Development (IPTD) and Pre-availability training.

3.4.7 Provide support services to various ISEA and platform agents and technical codes on problem resolutions, technical evaluations, SCD development, ECP evaluation and technical feedbacks. This support will be onsite and offsite, i.e. waterfront technical support.

3.4.8 Develop technical packages of documents including CAD drawings, technical manuals, provisioning documents, and project time lines (CDRL A004).

3.4.9 The Contractor will support shipboard validation audits via planning and executing shipboard and desktop validation support to the Configuration Managers to ensure programs achieve their maintenance, readiness and sustainment, goals/objectives.

3.5 Special Requirements in Support of NSWCPD Code 31

3.5.1 In conjunction with the foregoing work, the contractor may be required to enter into task order-specific non-disclosure and/or non-compete agreements with respect to information provided by the government in order to execute tasks related to the development of future requirements.

4. DATA REQUIREMENTS

4.1 Contract Status Report (CDRL A001)

4.1.1 This report shall reflect both prime and Subcontractor data if applicable at the same level of detail.

4.1.2 The CDRL shall be delivered electronically, unless otherwise stated, and while Contractor's format is acceptable the Government's approval must be received in writing from the COR within 5 business days before formal submission.

4.2 Travel Report (CDRL A002)

4.2.1 This report shall reflect both prime and subcontractor data if applicable at the same level of detail.

4.2.2 The CDRL shall be delivered electronically, unless otherwise stated, and while Contractor’s format is acceptable, Government’s approval is required from the COR.

4.3 Contractor’s Personnel Roster (CDRL A003)

4.3.1 The CDRL shall be delivered electronically, unless otherwise stated, and while Contractor’s format is acceptable, Government’s approval is required from the COR. This report shall reflect both prime and subcontractor data if applicable at the same level of detail.

4.4 Technical Report - Study/Services (CDRL A004)

4.4.1 Provide technical reports as required. There may be a need for other specific reports, test plans, evaluation reports or documentation created as in integral part of a requirements will be specified at the time of Task Order (TO) issuance.

4.5 Small Business Participation Commitment Report (A005)

4.5.1 All Offerors (both other than small businesses and small businesses) shall comply with the requirements of this factor per Section L.3.1. In preparation of the SBPCD, please note the Minimum Quantitative Requirement (MQR) specified in Section M.

5. SECURITY REQUIREMENTS

The Contractor is responsible for completing all required Government mandated training to maintain security and network access to government sites and IT systems to include but not limited to: Antiterrorism Level 1 Awareness; DoD Cyber Awareness Challenge; Combatting Human Trafficking; Records Management in the DON: Everyone's Responsibility; Training and Readiness: The Active Shooter; Constitution Day; NAVSEA Introduction to Controlled Unclassified Information; Operations Security (OPSEC); NAVSEA Counterintelligence Training; Privacy and Personally Identifiable Information (PII) Awareness Training; and NAVSEA Physical Security training. Certificates of successful completion shall be sent to the COR and as otherwise specified in the contract.

a. In accordance with SECNAV M-5510.30 Chapters 5 and 6, all Contractor personnel that require access to Department of Navy (DON) information systems and/or work on-site are designated Non-Critical Sensitive/ IT-II positions, which require an open investigation or favorable adjudicated Tier 3 by the Vetting Risk Operations Center (VROC). Investigations should be completed using the SF-86 Form and the SF-87 finger print card. An interim clearance is granted by VROC and recorded in the Joint Personnel Adjudication System (JPAS). An open or closed investigation with a favorable adjudication is required prior to issuance of a badge providing access to NSWCPD sites and buildings.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .