RFP_N6449818R0020.pdf
PDF 521 KB Posted
- Attached to
- Production, Testing, and Delivery of Solid Waste (SW) Processing Equipment for Naval Ships Federal contract opportunity
- Solicitation number
- N64498-18-R-0020
About this file
RFP (N64498-18-R-0020) for Pulpers and Shredders.
View the file
Other files for this federal contract opportunity
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until 04:00 PM local time 18 Jul 2018
X
A X B X C X D
EX
X
G F 66 - 75
76 - 83 X H 84 - 88
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
DO-A9 1 88
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
N64498 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 25
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
26 - 32 33 - 37
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
38 - 39 40 - 45
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 46 - 49 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 50 - 51 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
52 - 64
PART II - CONTRACT CLAUSES
NAVAL SURFACE WARFARE CENTER PHILA
CODE 0231, JAMES OSULLIVAN
215-897-2518, JAMES.OSULLIVAN2@NAVY.MIL
5001 SOUTH BROAD STREET
PHILADELPHIA PA 19112
215-897-2518
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.5. DATE ISSUED
18 Jun 2018
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
N6449818R0020
Section B - Supplies or Services and Prices
NOTES
1. CONTRACT TYPE:
The Naval Surface Warfare Center, Philadelphia Division (NSWCPD) located in Philadelphia, PA proposes to award one Indefinite-Delivery, Indefinite-Quantity, Firm-Fixed-Price type Contract providing supplies as described in Section C, Statement of Work. The Contract shall have an ordering period from date of Contract award through sixty (60) months thereafter. The Period of Performance shall be from date of Contract award through sixty-six (66) months thereafter.
2. BASIS OF COMPETITION:
This is a 100% small business set-aside solicitation.
3. SINGLE AWARD:
As detailed in Section M, award will be made to the Offeror whose offer is determined to represent the best value to the Government.
4. Minimum/Maximum:
The minimum value of supplies that must be ordered from the awardee will be one (1) unit of CLINs 0001 and 0002, or if the first article testing is waived, CLINs 0003 and 0018. The minimum shall be satisfied by the issuance of the first Delivery Order issued under the resultant Contract award. The maximum value of supplies is all quantities of all CLINs.
5. SUBMISSION OF OFFERS:
As detailed in Section L of this solicitation, Offerors are required to submit a technical proposal as part of their offer. Offerors are advised of the requirements contained in Clause 52.219-8, entitled “Utilization of Small Business Concerns. Failure to comply with the instructions set forth in Section L of this Solicitation or to provide all information requested may result in the determination that the proposal is nonresponsive and ineligible for Contract award. Also, In accordance with 252.215-7010 REQUIREMENTS FOR
CERTIFIED COST OR PRICING DATA AND DATA OTHER THAN CERTIFIED COST OR PRICING
DATA, please submit Other Than Certified Cost or Pricing Data with your proposal submission in order to support your proposal.
6. Questions:
Potential offerors should ask all questions within seven (7) days of RFP release. All questions should be sent to Jim O’Sullivan:
Email: James.osullivan2@navy.mil Phone: (215) 897-2518
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Unit First Article Test Unit
Pulper System A
First Article Test of this unit satisfies the FAT requirement for all pulpers. If First Article Testing is not waived at time of award, unit that successfully passes the First Article Test will partially fulfill the quantity requirement of CLIN 0003-0007.
FOB: Destination
FFP
NET AMT
0002 1 Unit First Article Test Unit
Shredder System D
First Article Test of this unit satisfies the FAT requirement for all shredders. If First Article Testing is not waived at time of award, unit that successfully passes the First Article Test will partially fulfill the quantity requirement of CLIN 0018- 0022.
0003 4 Each Pulper, Large, System A
Mod I Large Pulper (LP) with Electrical Enclosure
To be ordered from date of award through 12 months thereafter (Year 1)
STEPLADDER PRICING
STEPLADDER NAME ITEM NO FROM QUANTITY TO QUANTITY UNIT PRICE
System A 0001 0003 1.00 2.00
3.00 4.00
0004 6 Each Pulper, Large, System A
Mod I Large Pulper (LP) with Electrical Enclosure
To be ordered from 13 months after award through 24 months thereafter (Year 2)
System A 0002 0004 1.00 2.00
5.00 6.00
0005 6 Each Pulper, Large, System A
Mod I Large Pulper (LP) with Electrical Enclosure
To be ordered from 25 months after award through 36 months thereafter (Year 3)
System A 0003 0005 1.00 2.00
0006 6 Each Pulper, Large, System A
Mod I Large Pulper (LP) with Electrical Enclosure
To be ordered from 37 months after award through 48 months thereafter (Year 4)
System A 0004 0006 1.00 2.00
0007 6 Each Pulper, Large, System A
Mod I Large Pulper (LP) with Electrical Enclosure
To be ordered from 49 months after award through 60 months thereafter (Year 5)
System A 0005 0007 1.00 2.00
0008 6 Each Pulper, Small, System B
Small Pulper (SP) with Electrical Enclosure
To be ordered from date of award through 12 months thereafter (Year 1)
System B 0006 0008 1.00 2.00
0009 4 Each Pulper, Small, System B
Small Pulper (SP) with Electrical Enclosure
To be ordered from 13 months after award through 24 months thereafter (Year 2)
System B 0007 0009 1.00 2.00
0010 4 Each Pulper, Small, System B
Small Pulper (SP) with Electrical Enclosure
To be ordered from 25 months after award through 36 months thereafter (Year 3)
System B 0008 0010 1.00 2.00
0011 4 Each Pulper, Small, System B
Small Pulper (SP) with Electrical Enclosure
To be ordered from 37 months after award through 48 months thereafter (Year 4)
System B 0009 0011 1.00 2.00
0012 4 Each Pulper, Small, System B
Small Pulper (SP) with Electrical Enclosure
To be ordered from 49 months after award through 60 months thereafter (Year 5)
System B 0010 0012 1.00 2.00
0013 4 Each MOD I Plastic Waste Shredder, System C
Mod I Plastic Waste Shredder (PS), Hard Mounted with MK II Electrical Enclosure
To be ordered from date of award through 12 months thereafter (Year 1)
System C 0011 0013 1.00 2.00
0014 6 Each MOD I Plastic Waste Shredder, System C
Mod I Plastic Waste Shredder (PS), Hard Mounted with MK II Electrical Enclosure
To be ordered from 13 months after award through 24 months thereafter (Year 2)
System C 0012 0014 1.00 2.00
0015 6 Each MOD I Plastic Waste Shredder, System C
Mod I Plastic Waste Shredder (PS), Hard Mounted with MK II Electrical Enclosure
To be ordered from 25 months after award through 36 months thereafter (Year 3)
System C 0013 0015 1.00 2.00
0016 6 Each MOD I Plastic Waste Shredder, System C
Mod I Plastic Waste Shredder (PS), Hard Mounted with MK II Electrical Enclosure
To be ordered from 37 months after award through 48 months thereafter (Year 4)
System C 0014 0016 1.00 2.00
0017 6 Each MOD I Plastic Waste Shredder, System C
Mod I Plastic Waste Shredder (PS), Hard Mounted with MK II Electrical Enclosure
To be ordered from 49 months after award through 60 months thereafter (Year 5)
System C 0015 0017 1.00 2.00
0018 4 Each MOD I M/G Shredder, System D
Mod I Metal and Glass Shredder (MGS), Hard Mounted with MK II Electrical Enclosure
To be ordered from date of award through 12 months thereafter (Year 1)
System D 0016 0018 1.00 2.00
0019 6 Each MOD I M/G Shredder, System D
Mod I Metal and Glass Shredder (MGS), Hard Mounted with MK II Electrical Enclosure
To be ordered from 13 months after award through 24 months thereafter (Year 2)
System D 0017 0019 1.00 2.00
0020 6 Each MOD I M/G Shredder, System D
Mod I Metal and Glass Shredder (MGS), Hard Mounted with MK II Electrical Enclosure
To be ordered from 25 months after award through 36 months thereafter (Year 3)
System D 0018 0020 1.00 2.00
0021 6 Each MOD I M/G Shredder, System D
Mod I Metal and Glass Shredder (MGS), Hard Mounted with MK II Electrical Enclosure
To be ordered from 37 months after award through 48 months thereafter (Year 4)
System D 0019 0021 1.00 2.00
0022 6 Each MOD I M/G Shredder, System D
Mod I Metal and Glass Shredder (MGS), Hard Mounted with MK II Electrical Enclosure
To be ordered from 49 months after award through 60 months thereafter (Year 5)
System D 0020 0022 1.00 2.00
0023 12 Each Control Valves (SP), System E
Small Pulper (SP) Control Valves
To be ordered from date of award through 12 months thereafter (Year 1)
System E 0021 0023 1.00 2.00
3.00 4.00
5.00 6.00
7.00 8.00
9.00 10.00
11.00 12.00
0024 8 Each Control Valves (SP), System E
Small Pulper (SP) Control Valves
To be ordered from 13 months after award through 24 months thereafter (Year 2)
System E 0022 0024 1.00 2.00
3.00 4.00
7.00 8.00
0025 8 Each Control Valves (SP), System E
Small Pulper (SP) Control Valves
To be ordered from 25 months after award through 36 months thereafter (Year 3)
System E 0023 0025 1.00 2.00
3.00 4.00
0026 8 Each Control Valves (SP), System E
Small Pulper (SP) Control Valves
To be ordered from 37 months after award through 48 months thereafter (Year 4)
System E 0024 0026 1.00 2.00
3.00 4.00
0027 8 Each Control Valves (SP), System E
Small Pulper (SP) Control Valves
To be ordered from 49 months after award through 60 months thereafter (Year 5)
System E 0025 0027 1.00 2.00
3.00 4.00
0028 8 Each Control Valves (LP), System F
Large Pulper (LP) Control Valves
To be ordered from date of award through 12 months thereafter (Year 1)
System F 0026 0028 1.00 2.00
3.00 4.00
0029 12 Each Control Valves (LP), System F
Large Pulper (LP) Control Valves
To be ordered from 13 months after award through 24 months thereafter (Year 2)
System F 0027 0029 1.00 2.00
3.00 4.00
0030 12 Each Control Valves (LP), System F
Large Pulper (LP) Control Valves
To be ordered from 25 months after award through 36 months thereafter (Year 3)
System F 0028 0030 1.00 2.00
3.00 4.00
5.00 6.00
7.00 8.00
0031 12 Each Control Valves (LP), System F
Large Pulper (LP) Control Valves
To be ordered from 37 months after award through 48 months thereafter (Year 4)
System F 0029 0031 1.00 2.00
3.00 4.00
5.00 6.00
7.00 8.00
0032 12 Each Control Valves (LP), System F
Large Pulper (LP) Control Valves
To be ordered from 49 months after award through 60 months thereafter (Year 5)
System F 0030 0032 1.00 2.00
3.00 4.00
5.00 6.00
7.00 8.00
0033 8 Each Electrical Enclosure (LP), System G
Large Pulper Electrical Enclosure
To be ordered from date of award through 12 months thereafter (Year 1)
System G 0031 0033 1.00 2.00
3.00 4.00
0034 8 Each Electrical Enclosure (LP), System G
Large Pulper Electrical Enclosure
To be ordered from 13 months after award through 24 months thereafter (Year 2)
System G 0032 0034 1.00 2.00
3.00 4.00
0035 8 Each Electrical Enclosure (LP), System G
Large Pulper Electrical Enclosure
To be ordered from 25 months after award through 36 months thereafter (Year 3)
System G 0033 0035 1.00 2.00
3.00 4.00
0036 8 Each Electrical Enclosure (LP), System G
Large Pulper Electrical Enclosure
To be ordered from 37 months after award through 48 months thereafter (Year 4)
System G 0034 0036 1.00 2.00
3.00 4.00
0037 8 Each Electrical Enclosure (LP), System G
Large Pulper Electrical Enclosure
To be ordered from 49 months after award through 60 months thereafter (Year 5)
System G 0035 0037 1.00 2.00
3.00 4.00
0038 8 Each Electrical Enclosure (SP), System H
Small Pulper Electrical Enclosure
To be ordered from date of award through 12 months thereafter (Year 1)
System H 0036 0038 1.00 2.00
3.00 4.00
0039 8 Each Electrical Enclosure (SP), System H
Small Pulper Electrical Enclosure
To be ordered from 13 months after award through 24 months thereafter (Year 2)
System H 0037 0039 1.00 2.00
3.00 4.00
0040 8 Each Electrical Enclosure (SP), System H
Small Pulper Electrical Enclosure
To be ordered from 25 months after award through 36 months thereafter (Year 3)
System H 0038 0040 1.00 2.00
3.00 4.00
0041 8 Each Electrical Enclosure (SP), System H
Small Pulper Electrical Enclosure
To be ordered from 37 months after award through 48 months thereafter (Year 4)
System H 0039 0041 1.00 2.00
3.00 4.00
0042 8 Each Electrical Enclosure (SP), System H
Small Pulper Electrical Enclosure
To be ordered from 49 months after award through 60 months thereafter (Year 5)
System H 0040 0042 1.00 2.00
3.00 4.00
0043 1 Lot Technical Data
Techincal Data in accordance with DD Form 1423, Contract Data Requirements List A001 - A012
0044 1 Lot Shipping
System I, Shipping
CLAUSES INCORPORATED BY FULL TEXT
HQ B-2-0004 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (DEC 1995)
(a) As part of the negotiated fixed price or total estimated amount of this contract, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $500 or less at the time of final contract closeout. The term "residual dollar amount" shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.
(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.
HQ-B-2-0009 NOTE (CDRL)
NOTE A - Offeror shall complete the "Price Group" and "Estimated Total Price" blocks of each data item on the Contract Data Requirements List(s), attached hereto.
(End of Text)
HQ B-2-0022 CONTRACT SUMMARY FOR PAYMENT OFFICE (FIXED PRICE) (FEB 1997)
This entire contract is fixed price.
Section C - Descriptions and Specifications
SOW
SECTION C DESCRIPTION AND SPECIFICATIONS
Statement of Work:
1. This contract is for the production, testing, and delivery of Solid Waste (SW) Processing equipment for naval ships. Procurement of Solid Waste Processing Equipment (Mod I Large Pulper, Small Pulper, Mod I Metal and Glass Shredder, Mod I Plastic Waste Shredder, Mod I Large Pulper Electrical Enclosure, Small Pulper Electrical Enclosure, Small Pulper Control Valves and Mod I Large Pulper Control Valves) will consist of any combination of the following equipment:
a. Equipment "A" consists of:
One (1) Mod I Large Pulper with Electrical Enclosure, with GFP provided parts listed in Section C.15.a.(2).
b. Equipment "B" consists of:
One (1) Small Pulper with Electrical Enclosure, GFP provided part listed in Section C.15.a.(3).
c. Equipment "C" consists of:
One (1) Mod I Plastics Shredder, Hard Mounted with MK II Electrical Enclosure with GFP provided part listed in section C.15.a.(4).
d. Equipment "D" consists of:
One (1) Mod I Metal and Glass Shredder, Hard Mounted with MK II Electrical Enclosure with GFP provided part listed in section C.15.a.(5).
e. Equipment “G” consists of:
One (1) Mod I Large Pulper Electrical Enclosure with GFP provided part listed in section C.15.a.(6).
f. Equipment “H” consists of:
One (1) Small Pulper Electrical Enclosure with GFP provided part listed in section C.15.a.(7).
2. Equipment A - Mod I Large Pulper (LP) with Electrical Enclosure shall be manufactured and tested in accordance with NAVSEA drawing 593-8729130 Assy 99 (Large Pulper Mod 1 Top Level Assembly), 593- 8729126 (Large Pulper Mod 1 Interface Drawing), and all drawings referenced thereon including all tiered references. See Attachment 1 for a list of the drawings of record.
3. Equipment B - Small Pulper (SP) with Electrical Enclosure shall be manufactured and tested in accordance with NAVSEA drawing 593-6960581 (Small Pulper Top Level Assembly), 593-6960580 (Small Pulper Interface Drawing), and all drawings referenced thereon including all tiered references. See Attachment 1 for a list of the drawings of record.
4. Equipment C – Mod I Plastic Waste Shredder (PS), Hard Mounted with MK II Electrical Enclosure shall be manufactured and tested in accordance with NAVSEA drawing 593-7556873 Assy 99 (Solid Waste Shredder Top
Level Assembly), 593-6960880 (Solid Waste Shredder Interface Drawing), and all drawings referenced thereon including all tiered references. See Attachment 1 for a list of the drawings of record.
5. Equipment D – Mod I Metal and Glass Shredder (MGS), Hard Mounted with MK II Electrical Enclosure shall be manufactured and tested in accordance with NAVSEA drawing 593-7556873 Assy 96 (Solid Waste Shredder Top Level Assembly), 593-6960880 (Solid Waste Shredder Interface Drawing), and all drawings referenced thereon including all tiered references. See Attachment 1 for a list of the drawings of record.
6. Equipment E – Small Pulper Control Valves shall be manufactured and tested in accordance with NAVSEA Drawing 593-6960782 Assy 99 (Small Pulper Control valve Assembly). See Attachment 1 for a list of the drawings of record.
7. Equipment F – Mod I Large Pulper Control Valves shall be manufactured and tested in accordance with NAVSEA Drawing 593-8729128 Assy 99 (Large Pulper Mod 1 Control Valve Assembly). See Attachment 1 for a list of the drawings of record.
8. Equipment G – Mod I Large Pulper Electrical Enclosure shall be manufactured and tested in accordance with NAVSEA Drawing 593-8729152 Assy 99 (Large Pulper Mod 1 Electrical Enclosure Assembly and Details). See Attachment 1 for a list of the drawings of record.
9. Equipment H – Small Pulper Electrical Enclosure shall be manufactured and tested in accordance with NAVSEA Drawing 593-6960500 Assy 98 (Pulper Electrical Control Enclosure Arrangement). See Attachment 1 for a list of the drawings of record.
10. The nameplates for Large Pulpers, Small Pulpers, Plastics Shredders, and Metal and Glass Shredders, and their electrical enclosures indicate the serial number for the component. Serial numbers shall be sequential starting with the number 1 for a component. The serial number will be comprised of four elements.
Title Position Symbol Explanation Contractor designation 1 Upper case alpha-
Character Letter designation for the Contractor to be assigned by NSWCPD-SSES at a later date.
Sequence Number 2-5 Numeric Number designation for the Contractor to be assigned by NSWCPD-SSES at a later date.
Equipment Type 6 Upper case alpha- Character
Letter designation for the equipment.
L - Large Pulper M - Metal and Glass Shredder P – Plastics Waste Shredder S - Small Pulper
Component Designation 7 Upper case alpha-character
Number designation for the component.
Q - equipment (CMU, CLCU, Shredder) E – electrical control enclosure
Examples: R0001LQ is the serial for the first Large Pulper manufactured by Contractor R. R0010PE is the tenth Plastics Waste Electrical Enclosure manufactured by Contractor R.
11. Testing shall be performed in accordance with Attachments 2 through 5 to this statement of work in addition to those tests referenced in the drawings.
12. The Contractor shall implement a quality assurance program that is in accordance with at least a tailored version of ISO 9002 (1994), Quality Systems - Model for Quality Assurance in Production and Installation identified below.
13. The following sections of ISO 9002 (1994) shall be invoked in order to meet the minimum quality assurance requirements:
4.2 Quality System
4.2.1 General
4.2.2 Quality-System Procedures
4.5 Document and Data Control
4.5.1 General
4.5.2 Document and Data Approval and Issue
4.5.3 Document and Data Changes
4.6 Purchasing
4.6.1 General
4.6.4.2 Customer Verification of Subcontracted Product
4.7 Control of Customer-Supplied Product
4.9 Process Control
4.10 Inspection and Testing
4.10.1 General
4.10.2 Receiving Inspection and Testing
4.10.3 In-Process Inspection and Testing
4.10.4 Final Inspection and Testing
4.10.5 Inspection and Test Records
4.11 Control of Inspection, Measuring, and Test Equipment
4.11.1 General
4.11.2 Control Procedure
4.12 Inspection and Test Status
4.13 Control of Nonconforming Product
4.13.1 General
4.13.2 Review and Disposition of Nonconforming Product
4.14 Corrective and Preventive Action
4.14.2 Corrective Action
4.16.1 Control of Quality Records)
14. Deliverables:
a. Hardware:
(1) Shipboard Solid Waste Processing Equipment as detailed in section C.1, the Statement of Work.
Testing of the first delivery each of Equipment A, Equipment B, Equipment C, Equipment D, Equipment E, Equipment F, Equipment G, and Equipment H shall be witnessed by the Government prior to delivery, unless the Government specifically waives this requirement for each specific piece of equipment in writing. Testing will be in accordance with Attachments 2 through 5.
(2) GFP for Mod I Large Pulper (System A): The following item will be furnished by the government to be used for each piece Large Pulper Equipment (System A) that is manufactured:
(a) Mod I Large Pulper: Allen Bradley PLC Programming Module
(b) Mod I Large Pulper: Maple Systems HMI Programming Module
(3) GFP for Small Pulper (System B): The following item will be furnished by the government to be used in each piece Small Pulper Equipment (System B) that is manufactured:
(a) Pulper PROM Chip: 593-6960500 pc #97 (programmed)
(4) GFP for MOD 1 Plastics Shredder (System C): The following item will be furnished by the government to be used in each piece MOD 1 Plastics Shredder (System C) that is manufactured:
(a) MOD I PS PROM Chip: 593-7556872 Pc #6 (programmed)
(5) GFP for Mod I Metal and Glass Shredder (System D): The following item will be furnished by the government to be used in each piece Large Pulper Equipment (System B) that is manufactured:
(a) MOD I MGS PROM Chip: 593-7556872 Pc #6 (programmed)
(6) GFP for Mod I Large Pulper Electrical Enclosure (System G): The following item will be furnished by the government to be used for each piece Large Pulper Electrical Enclosure Equipment (System G) that is manufactured:
(a) Mod I Large Pulper: Allen Bradley PLC Programming Module
(b) Mod I Large Pulper: Maple Systems HMI Programming Module
(7) GFP for Small Pulper Electrical Enclosure (System H): The following item will be furnished by the government to be used in each piece Small Pulper Electrical Enclosure Equipment (System H) that is manufactured:
(a) Pulper PROM Chip: 593-6960500 pc #97 (programmed)
15. Required Delivery Locations
The contractor will be responsible to deliver completed sets of equipment to one of the following locations:
1. NSWC STAGING AND TRANSFER FACILITY, N3454A
LEE BING
5909 THURSTON AVENUE,
SUITE 200
VIRGINIA BEACH VA 23455
(757) 494-0065
2. MARINETTE MARINE CORPORATION, UIC N40516
JOSE FERNANDEZ
1600 ELY STREET BLDG. 26
MARINETTE, WI 54153
(715) 735-9341 EXT 7153
3. C500 LCS PLATFORM MANAGER, UIC N40518
JODY, DILLON
30665 COUNTY ROAD 49 NORTH
WAREHOUSE #5 SUIT
LOXLEY, AL 36551
(703) 712-8424
4. INGALLS SHIPBUILDING, UIC N50545
LAND BASED TEST FACILITY (LBTF)
1000 JERRY ST PE HWY
PASCAGOULA, MS 39567
ATTN: RONNIE THOMAS (228) 935-3863/
KIM YAUCH (228) 769-4314
5. SUPERVISOR OF SHIPBUILDING,
CONVERSION AND REPAIR, USN
UIC Q90611
BATH IRON WORKS
GFM WAREHOUSE
1 CRESSEY RD
BRUNSWICK, ME 04011
ATTN: JOE LAMONTAGNE (207) 442-1275/
JOHN HOBSON (207) 442-1236/
ED DUCHESNEAU (207) 442-1756
HQ C-2-0026 FIRST ARTICLE (CONTRACTOR TESTING) (NAVSEA) (APR 2015)
(a) For the purpose of this contract, the "First Article" is synonymous with the terms "preproduction model(s) and "preproduction equipment".
(b) The First Article shall conform in every respect to the requirements of this contract and shall be fully tested by the Contractor to determine compliance with said requirements. The production equipment shall be manufactured with tools, material and methods that are the same as or representative of the tools, material and methods that were used to manufacture the First Article.
(c) Pursuant to paragraph (e) of the clause entitled "FIRST ARTICLE APPROVAL--CONTRACTOR TESTING" (FAR 52.209-3), the First Article may be delivered as part of the production quantity.
HQ C-1-0001 ITEM(S) A0001 – A0012 DATA REQUIREMENTS (NAVSEA) (SEP 1992)
The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423.
HQ C-2-0008 ASSIGNMENT AND USE OF NATIONAL STOCK NUMBERS (NAVSEA) (MAY 1993)
To the extent that National Stock Numbers (NSNs) or preliminary NSNs are assigned by the Government for the identification of parts, pieces, items, subassemblies or assemblies to be furnished under this contract, the Contractor shall use such NSNs or preliminary NSNs in the preparation of provisioning lists, package labels, packing lists, shipping containers and shipping documents as required by applicable specifications, standards or Data item Descriptions of the contract or as required by orders for spare and repair parts. The cognizant Government Contract Administration Office shall be responsible for providing the Contractor such NSNs or preliminary NSNs which may be assigned and which are not already in possession of the Contractor.
HQ C-2-0009 ASSIGNMENT OF SERIAL NUMBER(S) (NAVSEA) (SEP 1990)
The Contractor shall request serial number assignment, in writing, from the Cognizant Technical Program Office, with a copy to the cognizant Contract Administration Office. The request for serial number assignment shall contain the following minimum information:
(a) Contract number;
(b) Assigned line item number and description;
(c) Assigned type designation;
(d) Assigned model number;
(e) Top drawing number and ID (List of Drawings) number;
(f) Exact quantity for which serial numbers are being requested, including preproduction samples required by the contract; and
(g) National Stock Number
HQ C-2-0014 CONTRACTOR'S PROPOSAL (NAVSEA) (MAR 2001)
(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with detailed obligations to which the Contractor committed itself in Proposal _____________ dated __________ in response to NAVSEA Solicitation No. N64498-18-R-0020. .
(b) The technical volume(s) of the Contractor's proposal is incorporated by reference and hereby made subject to the provisions of the "ORDER OF PRECEDENCE" (FAR 52.215-8) clause of this contract. Under the "ORDER OF PRECEDENCE" clause, the technical volume of the Contractor's proposal referenced herein is hereby designated as item
(f) of the clause, following "the specification" in the order of precedence.
HQ C-2-0033 LIMITATION OF LIABILITY - HIGH VALUE ITEMS (NAVSEA) (JUN 1992)
The following items are subject to the clause of this contract entitled "LIMITATION OF LIABILITY--HIGH VALUE
ITEMS" (FAR 52.246-24):
1. MOD I LARGE PULPER WITH ELECTRICAL ENCLOSURE
HQ C-2-0063 USE OF NAVY SUPPORT CONTRACTOR S FOR OFFICIAL CONTRACT FILES
(NAVSEA) (APR 2004)
(a) NAVSEA may use a file room management support Contractor , hereinafter referred to as "the support Contractor ", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.
(b) The cognizant Contracting Officer will ensure that any NAVSEA Contract under which these file room management services are acquired will contain a requirement that:
The support Contractor not disclose any information;
(2) Individual employees are to be instructed by the support Contractor regarding the sensitivity of the official contract files;
(3) The support Contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,
(4) In addition to any other rights the Contractor may have, it is a third party beneficiary who has the right of direct action against the support Contractor , or any person to whom the support Contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.
(c) Execution of this contract by the Contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support Contractor for the limited purpose of executing its file room support contract responsibilities.
(d) NAVSEA may, without further notice, enter into contracts with other Contractor s for these services. Contractor s are free to enter into separate non-disclosure agreements with the file room Contractor . (Please contact Director, E Business Division for Contractor specifics.) However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.
Section D - Packaging and Marking
SECTION D Packaging and Marking
1. Packaging Requirements:
a. Introduction: The Plastic and Metal Glass Shredders, Small Pulpers and Large Pulpers, and associated electrical enclosures require packaging for physical and mechanical protection ensuring cushioning, cleanliness and preservation as defined in Standard Practice for Commercial Packaging - ASTM D3951-95. (Table 1 below is the list of references used to prepare these requirements).
b. Conditions for Consideration: The conditions to be considered include, but are not limited to:
(1) Multiple handling during transportation and in-transit storage from point of origin to ultimate user.
(2) Loading on ship deck, transfer at sea, helicopter delivery, and offshore (export) delivery to the ultimate user.
(3) Environmental exposure during shipment or during transit operations where port and warehouse facilities are limited or nonexistent.
(4) Outdoor storage in all climatic conditions for a minimum of one year.
(5) Potential static loads imposed by stacking.
c. Packaging Method: ASTM D 3951-95 defines the minimum requirements for packaging. The objective is to provide unit packaging to contain the contents and to prevent damage; and use of intermediate packaging of multiple items to enhance handling and inventory. The primary packaging is heat sealable bags and barrier material, boxes and waterproof barrier material.
(1) Heat Sealable Bags and Barrier Material:
(a) The requirement is that items preserved, wrapped, cushioned, desiccated, anchored, or shock-mounted in accordance with ASTM D395 1 - 95 shall be enclosed in a heat sealable heavy duty/high density polyethylene bag/sleeve, with low vapor transmission characteristics, that acts as a barrier material to water-vapor and grease. Shredders and Pulpers shall be packaged in the polyethylene barrier material.
(b) For machinery bolted to skids, the barrier material shall have gasketed holes to permit installation of the barrier material over, under, and around the fastener devices used to secure the packaged item. Alternatively, on skids with a solid plywood base, the barrier material shall be secured to the plywood base by nailing the barrier through wood strips and gasket material to the base, effectively forming a vapor-proof enclosure.
(c) Standard commercial practices shall apply for bag construction, styles and seam requirements.
Minimal workmanship standards are necessary to ensure pinholes, tears, cuts, splits, creases, wrinkles, folds or other imperfections do not impair usefulness of the bag.
(d) Table 1 of this specification lists the physical properties that the material shall possess.
(2) Boxes and Waterproof Barrier Material
(a) Based on the weight of the Pulpers and Shredders, the shipping containers including cushioning, anchoring, blocking, or bracing of packaged items shall be as defined in ASTM D395 1 - 95 (Boxes, Wood-Cleated, Skidded, Load-Bearing Base). For reference, when determining how a component will be packaged, use the requirements of Specification ASTM D 4169 -94 Standard Practice for Performance Testing of Shipping Containers and Systems, to ensure that the shipping units, including cushioning, anchoring, blocking or bracing, will withstand the specified environment. Testing of the packaging, however, is not required.
(3) Preservation/Protective Coatings
(a) Since the exterior surfaces of the equipment are either bare stainless steel or protected by paint, protective coatings are not required.
(b) However, a protective coating is required on both the Metal Glass and Mod I Plastics Shredder chamber cutters and spacers. For the cutter and spacers installed in the chamber, coat with SAE 40 oil after assembly; and for the spare cutters and spacers coat with cosmoline.
d. Packaging of Machinery, Controllers, and Spare Parts
(1) Both the Small and Large Pulper electrical enclosures shall be boxed separately and packaged in the same shipping container as the Pulpers.
(2) The base of the box shall be large enough to contain the footprint of the machine or parts being packaged. Additionally, a 5 1/2 inch outer edge for potential lifts is required and the base should also be skidded to accommodate handling equipment from two directions (forklift headers & voids).
(3) In general, bolting the smaller components to the base satisfies bracing requirements. The Small and Large Pulpers however, shall be placed on an oversized base and braced where required to prevent it from falling over during shipment and handling. Bolting shall be accomplished using a through-bolting method rather than lag bolting. Bolt the machinery to their bases with bolts of at least a 3/4-inch diameter size. Use washers to prevent damage to the surface of the machine and to prevent the head of the bolt from pulling through the base of the box. A support beam(s) shall be installed across the top of the inside of the box to provide additional structural support and to strengthen the box. Activated desiccant bags shall be used inside the bags to help absorb moisture.
Desiccant bags shall also be placed inside the control enclosures. A water-resistant barrier, as described in Table 1, shall be secured to the open top of the box before the lid is secured to the box sides.
(4) Spare Parts shall be crated separately (packaging selection as appropriate). Individual components within the spare parts boxes shall be sealed in bags with desiccant as described in section 3.1. If the individual part as supplied by the vendor is already in the equivalent packaging, it does not have to be repackaged. Placement of the spare parts within the containers shall be arranged to protect contents during shipment and storage. Application of cushioning material is acceptable to reduce externally and/or internally applied shock; however, the material shall not be deleterious to the desiccant.
(5) Application of cushioning material is acceptable to reduce externally and/or internally applied shock; however, the material shall not be deleterious to the desiccant.
e. Marking and Bar Coding
(1) Nomenclature to be used in marking the exterior of the shipping boxes shall be one of the following as applicable:
(a) Equipment Serial Number # , Electrical Enclosure Serial Number #
(b) Local Status Indicator Serial Number #
(c) Spare Parts Box #
(2) Shipping box markings shall in accordance with ASTM D3951-95 and MIL-STD-129 for guidance. Using MIL-STD-129 as guidance, provide specific markings: Item Identification Markings - (paragraph 4.2.2); Contract Data (paragraph 4.2.3); and Address Marking (paragraph 4.3.1) using a bar coded DD Form 1387.
(3) Shipping boxes shall include the following bar coded information using paragraph 4.5.1.2 of MIL- STD-129M as guidance: NSN/NATO Stock Number, Contract or Order Number (including call number), CAGE Code, and CLIN.
(4) Packaging boxes shall have the following additional markings where necessary: "Unbalanced Load" and "Caution: Lift by Base Only," and "To Open Remove Bottom Lag Bolts", and "Caution: This container contains desiccant", and "Do Not Stack".
(5) Labels for the repair/spare parts shall have the following information:
* Part Name
* Drawing and Piece Number or Part Number as shown in Section B
* Manufacturer’s CAGE Code
* Manufacturer’s Part Number
* Quantity in the package
* NSN/NICN Stock Number or other number identified in a Delivery Order.
System A – E: Use Equipment NIINs NIIN Large Pulper 014877424 NIIN Small Pulper 014877151 Niin MOD I Plastic Shredder LLCYB3912 NIIN Metal Glass Shredder 014709481 NIIN Control Valves 014596896
System F – J: Use System Designation (ie, F – J)
Bar coding for Onboard Repair Parts and Auxiliary Components is required.
f. Caution for the Packaging of this Equipment: the interior of this equipment and associated piping shall be dry before packaging.
g. Special precautions shall be taken to prevent any sagging or any deformation of the equipment or its components while shipping.
Table 1.
Specifications Applicable to Packaging
* Standard Practice for Commercial Packaging ASTM D 3951 - 95
* Standard Terminology of Packaging and Distribution Environments ASTM D 996-95
* Standard Practice for Performance Testing of Shipping Containers and Systems ASTM D 4169-94
* Marking Packages MIL-STD-129
Shipping Containers/Boxes: Plywood Boxes:
* Plywood grade ANSI/HPMA HP 1983, Type I, grade 3-4, interior with exterior glue, water repellent treatment.
* All wood packaging materials including crates, blocking or bracing shall be constructed from materials in accordance with International Standards for Phytosanitary Measures (ISPM) 15. In accordance with the requirements of ISPM 15, the following commercial heat treatment process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging Material (WPM).
WPM is defined as wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frames, and cleats. Packaging materials exempt from the requirements are materials that have undergone a manufacturing process such as corrugated fiberboard, plywood, particleboard, veneer, oriented strand board, and plastic. All WPM shall be constructed from Heat Treated (HT to 56 degrees Centigrade for 30 minutes) lumber and certified by an accredited agency recognized by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL:
http://www.alsc.org). Failure to comply with the requirements of this restriction may result in refusal, destruction, or treatment of materials at the point of entry.”
Sealed Bags:
* Polythene, high density, opaque-nominal thickness 0.003 to 0.004 inches.
* Oil resistance: no oil penetration through material in 7 hours.
* Water resistance: no water penetration through material or seam in 72 hours.
* Seam strength: heat sealable, static load 2 1/2 pounds for 5 min @ 73 +/- 3.5 degrees F.
* Low water vapor transmission characteristics.
* Anti-static.
Desiccant Bags:
* Newly manufactured, non-deliquescent and capable of reactivation.
* Desiccant unit adsorption capacity: The quantity of desiccant which will maintain, in equilibrium with air 25 degrees C, (bagged desiccant) 40% Relative Humidity. Calculate the quantity:
* 3.0 ounces of desiccant/cubic ft. or
* One "unit" of desiccant total sq. ft. (of barrier material) x factor of 1.6; use factor of 0.011 for sq.
inches or use factor of 17.0 for sq. meters
* Strength of desiccant container: when dropped from a height of l0ft to a concrete surface, the container (bag) shall not puncture, tear or burst or show visible signs of desiccant leaking.
* Include humidity indicator card in each container with desiccant.
Water Resistant Barrier Material: (top of primary boxes) Polythene - see Sealed Bags above
Data to be delivered by Integrated Digital Environment (IDE) or other electronic media shall be as specified in the contract.
All unclassified data to be shipped shall be prepared for shipment in accordance with best commercial practice.
Classified reports, data, and documentation shall be prepared for shipment in accordance with National Industrial Security Program Operating Manual (NISPOM), DOD 5220.22-M dated 28 February 2006 with Change 2 dated 18 May 2016.
HQ D-2-0004 IDENTIFICATION MARKING OF PARTS (NAVSEA) (NOV 1996)
Identification marking of individual parts within the systems, equipments, assemblies, subassemblies, components, groups, sets or kits, and of spare and repair parts shall be done in accordance with applicable specifications and drawings.
To the extent identification marking of such parts is not specified in applicable specifications or drawings, such marking shall be accomplished in accordance with the following:
(1) Parts shall be marked in accordance with generally accepted commercial practice.
(2) In cases where parts are so small as not to permit identification marking as provided above, such parts shall be appropriately coded so as to permit ready identification.
HQ D-2-0007 MARKING AND PACKING LIST(S) - ALTERNATE I (NAVSEA) (APR 2015)
(a) Marking. Shipments, shipping containers and palletized unit loads shall be marked in accordance with MIL-STD- 129R dated 18 February 2014.
(b) Packing List(s). A packing list (DD Form 250 Material Inspection and Receiving Report may be used) identifying the contents of each shipment, shipping container or palletized unit load shall be provided by the Contractor with each shipment in accordance with the above cited MIL-STD. When a contract line item identified under a single stock number includes an assortment of related items such as kit or set components, detached parts or accessories, installation hardware or material, the packing list(s) shall identify the assorted items.
Where DD Form 1348-1 or DD Form 1348-1A is applicable and an assortment of related items is included in the shipping container, a packing list identifying the contents shall be furnished.
(c) Master Packing List. In addition to the requirements in paragraph (b) above, a master packing list shall be prepared where more than one shipment, shipping container or palletized unit load comprise the contract line item being shipped.
The master packing list shall be attached to the number one container and so identified.
(d) Part Identification. All items within the kit, set, installation hardware or material shall be suitably segregated and identified within the unit pack(s) or shipping container by part number and/or national stock number. Refer to the above cited MIL-STD for marking of assorted (related-unrelated) items.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE
All Supplies/services will be inspected/accepted at Origin and by the Government.
CLAUSES INCORPORATED BY REFERENCE
52.246-2 Inspection Of Supplies--Fixed Price AUG 1996 52.246-16 Responsibility For Supplies APR 1984 252.246-7000 Material Inspection And Receiving Report MAR 2008
52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
(a) The Contractor shall comply with the higher-level quality standard(s) listed below:
ISO 9002 (1994), Quality Systems - Model for Quality Assurance in Production and Installation
(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph
(a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing, and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
HQ E-1-0001 INSPECTION AND ACCEPTANCE LANGUAGE FOR DATA
Inspection and acceptance of all data shall be as specified on the attached Contract Data Requirements List(s), DD Form 1423.
HQ E-1-0003 INSPECTION AND ACCEPTANCE LANGUAGE FOR F.O.B. DESTINATION DELIVERIES
Item(s) 0001 - 0042 - Inspection and acceptance shall be made at destination by a representative of the Government.
HQ E-2-0004 COST OF QUALITY DATA (NAVSEA) (MAY 1995)
Cost of Quality Data: The contractor shall maintain and use quality cost data as a management element of the quality program. The specific quality cost data to be maintained and used will be determined by the contractor.
These data shall, on request, be identified and made available for "on site" review by the Government representative.
HQ E-2-0015 QUALITY MANAGEMENT SYSTEM REQUIREMENTS (NAVSEA) (APR 2017)
Quality Management System Requirements. The Contractor shall provide and maintain a quality management system that, as a minimum, adheres to the requirements of ANSI/ISO/ASQ 9001-2015 Quality Management Systems and supplemental requirements imposed by this contract. The quality management system procedures, planning, and all other documentation and data that comprise the quality management system shall be made available to the Government for review. Existing quality documents that meet the requirements of this contract may continue to be used. The Government may perform any necessary inspections, verifications, and evaluations to ascertain conformance to requirements and the adequacy of the implementing procedures. The Contractor shall require of subcontractors a quality management system achieving control of the quality of the services and/or supplies provided. The Government reserves the right to disapprove the quality management system or portions thereof when it fails to meet the contractual requirements.
Section F - Deliveries or Performance
DELIVERY SCHEDULE
CLIN ORDERING PERIOD MAX QUANTITY DELIVERY PLACE OF PERFORMANCE
0001 From date of contract award through 12 months thereafter
1 unit First Article Testing (FAT) units are due 10 months after date of delivery order - FAT only new vendors
Contractors Facilities, IAW Section C
0002 From date of contract award through 12 months thereafter
1 unit First Article Testing (FAT) units are due 10 months after date of delivery order - FAT only new vendors
Contractors Facilities, IAW Section C
0003 From date of contract award through 12 months thereafter
4 each For each awarded delivery order, each unit due 10 months after FAT approval or if FAT is waived, 10 months after receipt of GFM
Contractors Facilities, IAW Section C
0004 From 13 months after award through 24 months thereafter
6 each For each awarded delivery order, each unit due 10 months after FAT approval or if FAT is waived, 10 months after receipt of GFM
Contractors Facilities, IAW Section C
0005 From 25 months after award through 36 months thereafter
6 each For each awarded delivery order, each unit due 10 months after FAT approval or if FAT is waived, 10 months after receipt of GFM
Contractors Facilities, IAW Section C
0006 From 37 months after award through 48 months thereafter
6 each For each awarded delivery order, each unit due 10 months after FAT approval or if FAT is waived, 10 months after receipt of GFM
Contractors Facilities, IAW Section C
0007 From 49 months after award through 60 months thereafter
6 each For each awarded delivery order, each unit due 10 months after FAT approval or if FAT is waived, 10 months after receipt of GFM
Contractors Facilities, IAW Section C
0008 From date of contract award through 12 months thereafter
6 each For each awarded delivery order, each…