26-SIMACQ-E30-0034_Cell_Phone_Repeater_Questions_Answers_V3_8132026.pdf
PDF 53 KB Posted
- Solicitation number
- N6339426Q4056
About this file
This is a Questions and Answers document addressing contractor inquiries regarding cellular infrastructure installation at two government buildings.
The document clarifies that Buildings 522 and 523 are not physically connected but have existing Single-Mode fiber strands available between them. The Government permits the contractor to run additional fiber between the buildings if necessary. Notably, the Government will accept a single centralized cellular repeater/Distributed Antenna System (DAS) serving both buildings via fiber, provided the solution is technically feasible and meets all required 4G/5G coverage and performance requirements, rather than requiring two separate cellular repeater systems for each building.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Are Buildings 522 and 523 physically connected or otherwise connected by an existing pathway suitable for fiber?
Answer: Buildings are not physically connected. There are existing Single-Mode fiber strands available between buildings 522 and 523.
Would the Government permit the contractor to run fiber between Buildings 522 and 523?
Answer: If the Contractor finds it necessary.
If technically feasible and capable of meeting all required 4G/5G coverage and performance requirements, would the Government accept a single centralized cellular repeater/DAS system serving both buildings via fiber, rather than two separate cellular repeater systems?
Answer: Yes